Revision 1 12/8/2020
REPLACE PIVS FOR BLDG. 155 ORDNANCE WAREHOUSE, & BLDG. 143 FRC
SAFETY
MCAS CHERRY POINT, NORTH CAROLINA 28533-0006
WORK ORDER #6781991
1.1. GENERAL INTENTION
Replace a total of two (2) PIVs at Bldg. 155, & 143.
1.2. LOCATION
Bldg. 155, Ordnance General Purpose Warehouse, A St. and
Cleveland Dr. Bldg. 143, FRC- East Safety Office, A St. &
Beachey Rd.
1.3. DETAILED REQUIREMENTS
This project consists of replacing two (2) PIVs at two separate locations inside MCAS Cherry Point. This project requires that all fire protection replacement work performed under the scope of this contract shall be performed in accordance with the requirements set forth by the National Fire Protection
Association, NFPA for PIV installation and as indicated.
The contractor shall coordinate all construction site preparations and scheduling for this project with the building managers at each location through the Contracting Officer’s
Representative. The Contracting Officer’s Representative shall provide a schedule of the two PIVs that are being replaced to
Cherry Point Fire Department and Public Works Dept. for outage procedure requirements. The contractor shall be responsible for providing the schedule. If any assistance is needed for isolating any of the PIVs under the scope of this contract, the contractor shall submit a service request to Public Works Dept.
in a timely manner that meets the contractor provided scheduling requirements. The contractor shall have all utilities clearly marked prior to the start of this project.
All digging under the scope of this contract shall be performed with the use of a properly sized trench box.
Dig down to an approximate depth(s) of 8ft. and remove the
PIV(s) and discard off base. (The PIV at Bldg. 155 currently has a concrete pipe/barrier in place around the PIV and will need to be discarded off base. It is not required to replace the concrete pipe/barrier). (The PIV at Bldg. 143 will require demoing approximately 100 sq.ft. of 6” thick concrete sidewalk
Revised 12/8/2020
(to include the existing truncated dome mat) (see the enclosure for a general location of concrete sidewalk demo) and approximately 40 sq.ft. of 4” thick asphalt from the road/crosswalk, and discarding off base. A new sidewalk shall be poured to match the dimensions of the existing sidewalk. All sidewalk slopes shall slope away from any the road. To prevent water puddling, the running slope shall be no greater than 5%, and the cross slope shall be a minimum of 1% and no greater than 2%. An under laying compacted gravel base of 6 inches shall be applied and the top of the compacted gravel base grade shall meet the required thickness of new concrete of 6”. Pour and finish new concrete (3500 psi). All expansion joints shall be the same distance apart as the existing. All edges of the sidewalk shall be edged smooth. The broom finish of the sidewalk shall match the existing, and there shall be no track marks left from the edging trowels or the expansion joint groover. Once the new concrete sidewalk is cured, install a new like in kind truncated dome mat in the same location as the existing, per the manufactures instructions. Lay new asphalt in the area affected by the repairs. An under laying compacted gravel base shall be applied and the top of the compacted gravel base grade shall meet the required thickness of new asphalt of 4”. The new asphalt shall be laid smooth and match the surrounded grade. Re-paint the white line(s) of Beachey Rd.
in the area affected by this PIV replacement with pavement paint that matches the current existing color/material. Re-paint the entire adjacent crosswalks that crosses Mackerel
Rd./parallel with Beachey Rd. and the crosswalk that crosses
Beachey Rd. to match the current existing ladder design with white pavement paint consisting of epoxy material embedded with reflective glass beads, per the manufactures instructions. The existing railroad crossing sign currently placed next to the
PIV shall be preserved for re-installment. The contractor shall place a temporary railroad crossing sign at this site during the entire duration of this PIV replacement. [The government gives permission to the contractor to utilize the existing railroad crossing sign for temporary use for this PIV replacement].
Replace the PIV(s) with new, like in kind or better PIVs per the manufactures specifications. Install PIVs in accordance with AWWA C600 for PIV installation and as indicated. Make and assemble joints as specified for making and assembling the same type joints between pipe and fittings. Provide metal harness as specified under pipe anchorage requirements for the respective pipeline material to which PIV(s) is attached. Use appropriate couplings, retaining rings/gaskets with grip rings, pipe clamps, seals, & bolt packages. Upon any cases where a single
PIV is unable to be isolated, it will be acceptable to maintain an outage until concrete restraints can be cured.
Perform water leak tests on each newly installed PIV per the manufacture’s recommended instructions to ensure there are no water leaks. The contractor shall be responsible for the repairs of any water leaks that may be present from the task of this project.
Backfill the excavated trench 12” above the fire main using a base course of #57 washed stone. The contractor shall ensure the #57 washed stone is compacted properly around the ductile iron pipe repair. Cover with GEO fabric, and fill the trench with existing material to cover and level the trench. The excavated area shall be compacted and level with the existing grade.
Lay new sod where the grass was effected from the PIV replacements. The contractor shall be responsible for maintenance of the newly installed sod to include watering the areas 2 times per week for 4 weeks.
Any discrepancies beyond this scope of work shall be reported to the Contracting Officer’s Representative.
After Inspection and approval, the contractor shall turn all required warranty paperwork into the Contracting Officers
Representative.
1.4. SPECIAL SCHEDULING REQUIREMENTS
Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.
Specific items of work to which this requirement applies include:
New PIVs, fittings/associated hardware, excavator, trench box, #57 washed stone, GEO fabric, compactor, concrete forms & concrete, asphalt, pavement paint, and sod.
Bldgs. 155, and 143 will remain in operation during the entire construction period. The Contractor must conduct operations so as to cause the least possible interference with normal operations of the activity.
Permission to interrupt any activity roads, railroads, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption and in accordance with section 1.10.
The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the construction schedule each factor which constitutes a potential interruption to operations.
1.5. CONTRACTOR ACCESS AND USE OF PREMISES
DBIDS has gone live at MCAS Cherry Point. In order to reduce wait time when exchanging your RapidGate credential, it is highly recommended each applicant pre-register at https://dbids-global.dmdc.mil/enroll#!/
Non-DoD cardholding visitors to Marine Corps Installations with a driver's license or ID issued by a state that is not compliant with the Real ID Act of 2005 will now need to provide an alternate form of acceptable identification to gain entry, or be escorted by an authorized patron of the air station.
North Carolina now issues REAL ID compliant driver’s licenses, but many drivers have yet to be issued the new license. Drivers may get a North Carolina REAL ID driver's license at any NCDMV driver's license office.
The Act established minimum security standards for license issuance and production and prohibits Federal agencies from accepting driver's licenses and identification cards from states not meeting the Act's minimum standards.
In absence of a compliant state issued driver's license or ID, one of the following federally approved forms of identification must also be provided in addition to the non-compliant driver's license or ID:
1. U.S. Passport
2. U.S. Passport Card
3. U.S. Coast Guard Merchant Mariner Card
4. Personal Identity Verification (PIV) Card
5. Personal Identity Verification - Interoperable (PIV-I)
6. U.S. State Department Driver's License
7. Veteran's Health Identification Card (Issued by the U.S.
Department of Veterans Affairs)
8. U.S. Permanent Resident Card (Form I-551) https://dbids-global.dmdc.mil/enroll#!/
9. U.S. Certificate of Naturalization or Certificate of Citizenship (Form N-550)
10. Department of Homeland Security Employment Authorization Document (Form I-766)
1.5.1 ACTIVITY REGULATIONS
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark
Contractor equipment for identification.
1.5.1.1 SUBCONTRACTORS AND PERSONNEL CONTRACTS
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.5.1.2 ADDITIONAL PERSONNEL REQUIREMENTS
This section intentionally left out.
1.5.1.2.1 GENERAL CONSTRUCTION
General construction of this project must be performed by U.S.
firms using U.S. citizens. General construction includes construction activities such as building site work, utilities, foundations, structure, and enclosure or shell, including doors, windows and façade work.
1.5.1.2.2 FINISH WORK
1.5.1.2.3 ELECTRONIC SECURITY SYSTEMS EQUIPMENT
1.5.1.3 INSTALLATION ACCESS
Obtain access to Navy and Marine Corps installations through participation in the Defense Biometrics Identification System
(DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy Commercial Access
Control System (NCACS), are available at https://www.cnic.navy.mil/om/dbids.html. No fees are associated with obtaining a DBIDS credential.
Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor
Control Office to access an installation.
1.5.1.3.1 REGISTRATION FOR DBIDS
Registration for DBIDS is available at https://www.cnic.navy.mil/om/dbids.html. Procedure includes:
a. Present a letter or official award document (i.e. DD Form 1155 or SF 1442) from the Contracting Officer that provides the purpose for access to the Base Visitor Control Center representative.
b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.
c. Provide completed SECNAV FORM 5512/1 to the Base Visitor Control Center representative to obtain a background check.
This form is available for download at https://www.cnic.navy.mil/om/dbids.html.
d. Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, finger prints, base restriction and several other assessments.
e. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.
1.5.1.3.2 DBIDS ELIGIBILITY REQUIREMENTS
Throughout the length of the contract, the Contractor employee must continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
https://www.cnic.navy.mil/om/dbids.html
An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification. The Government is the final authority.
1.5.1.3.3 DBIDS NOTIFICATION REQUIREMENTS
Immediately report instances of lost or stolen badges to the
Contracting Officer.
Immediately collect DBIDS credentials and notify the
Contracting Officer in writing under the following circumstances:
1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.
2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the Installation or anyone therein.
1.5.1.3.4 ONE-DAY PASSES
Personnel applying for One-Day passes at the Base Visitor
Control Office are subject to daily mandatory vehicle inspection, and will have limited access to the installation.
The Government is not responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.
1.5.1.4 NO SMOKING POLICY
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.5.2 WORKING HOURS
Regular working hours shall consist of an 8 1/2 hour period normally between the hours of 7:00 am to 3:30 pm, Monday through Friday, excluding Government holidays.
1.5.3 WORK OUTSIDE REGULAR HOURS
Work outside regular working hours requires Contracting Officer approval. Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the
Contracting Officer may approve work outside regular hours.
During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting
Officer. Make utility cutovers after normal working hours or on
Saturdays, Sundays, and Government holidays unless directed otherwise.
1.5.4 EXCLUSIONARY PERIOD
1.5.5 OCCUPIED BUILDING[S]
The Contractor shall be working around existing buildings which are occupied. Do not enter the building(s) without prior approval of the Contracting Officer.
The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
The Government will remove and relocate other Government property in the areas of the building(s) scheduled to receive work.
1.5.6 UTILITY CUTOVERS AND INTERRUPTIONS
Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays.
Conform to procedures required in the paragraph "Work Outside
Regular Hours".
Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, and compressed air are considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular
Hours".
Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.
1.6 SECURITY REQUIREMENTS
1.6.1 STATION REGULATIONS
No employee or representative of the contractor will be admitted to the work site without an Identification Badge or is specifically authorized admittance to the work site by the
FEAD, Facilities Engineering & Acquisition Division.
IMPORTANT NOTE: FEAD personnel (Construction Managers, Engineers/Architects, Engineering Technicians, Contract
Specialists, or Contract Surveillance Representatives) will not receive, process, re-transmit or otherwise handle IN ANY WAY
Personally Identifiable Information.
1.6.2 CONTRACTOR ACCESS TO MCAS CHERRY POINT AND OUTLYING AREAS
Documentation requirements for granting access to MCAS Cherry
Point for commercial and contract employers and employees. This document is an aid in meeting ASO 5560.6A requirements and is not a substitute for the order.
The Pass & Identification Office at Building 251 will issue credentials to authorized contractors. Sub-Contractors and suppliers must coordinate through the Prime-Contractor:
Criminal Activity. In accordance with ASO 5560.6A, the below list of criminal activities within an applicant's record are considered not in the best interest of the Marine Corps and will be grounds for automatic denial of access aboard the
Installation:
a. Conviction of any felony offense.
b. Conviction of any misdemeanor offense, which was the result of a plea bargain of a felony offense.
c. Conviction of any offense involving a weapon.
d. Conviction of any drug offense involving manufacturing or trafficking.
e. More than one misdemeanor conviction of drug related offenses over the applicant's lifetime or one misdemeanor drug related offense within the last five years.
f. Conviction of any assault charge.
g. Conviction of any offense involving theft or larceny.
h. Conviction of any offense of domestic violence.
i. Conviction of any offense related to the abuse/neglect of a child.
j. Conviction of any sexual in nature related offense or registration as a sex offender.
k. Commission of any grievous criminal offense/misconduct while aboard any Federal installation, including blatant disregard for rules and regulations of the Installation, but excluding minor traffic offenses.
l. Other than Honorable, Bad Conduct, and Dishonorable discharges from the U.S. Military.
m. Those identified as undocumented citizens.
n. Those on the National Terrorist Watch List.
o. Any individual who attempts to hide or purposely fails to disclose all past criminal history during the vetting process.
p. Any individual that the Provost Marshal's Office determines to present a risk to the security and safety of the Installation and whose access is deemed not in the best interest of the Marine Corps.
q. Any individual who has been debarred from the Installation by the Installation Commander or is currently listed as debarred from any other Federal installation.
r. Any individual with an outstanding warrant for their arrest or apprehension.
s. Any individual with a pending criminal court case that, if convicted, would result in access denial in accordance with the criteria listed above.
1.6.3 FLIGHTLINE SECURITY REQUIREMENTS
Work involved under this contract is in the Flightline Security
Area. No employee or representative of the Contractor will be admitted to the work site unless they (1) are specifically authorized admittance by the FEAD, and (2) have a security badge. The Contractor shall obtain clearance and flightline security badges for all personnel required to be on the project site prior to performing any work. The Contractor shall submit a written request for security badges to the FEAD and to Pass &
ID. Each employee will be required to go to PASS & ID at
Building 251 to obtain his security badge with flightline access. A limited number of Contractor vehicles will be allowed access to the site of work subject to meeting regular Station access requirements. No personal vehicles will be allowed behind the security fence. Parking of vehicles shall be restricted to the immediate project site as determined by the
FEAD. The security badges issued under this contract are valid for this specific project and are not transferable to another project.
1.6.4 STAGING AREA
The contractor staging area will be (PM to coordinate). Amount of material on site shall be kept to a minimum and shall only be material that is pertinent to the work currently being performed. All stockpiling of equipment and materials shall be closely coordinated with the Government and shall not disrupt activities at the site.
1.7 MINIMUM INSURANCE REQUIREMENTS
Furnish a list of contract personnel of the Contractor and subcontractors including addresses and telephone number for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in the previous lists.
1.8 SUPERVISION
The complexity of this project will require one person to fill the roles of the Superintendent, QC, and SSHO.
1.9 SUBMITTALS
The following items shall have submittals delivered to the COR for approval by the government prior to the commencement of site work.
PIVs for Bldgs. 155, 143, & pavement paint.
1.10 PLANNED OUTAGES AND SERVICE DISRUPTIONS
Planned outages and service disruptions are requested by the contractor for approval to the COR when necessary to facilitate and/or accomplish contract work. Affected services include utilities (steam, water, waste water, and electrical service), communications (telephone, network, industrial control systems, and fire/security alarm systems) fire protection equipment, infrastructure, railroads, and road closures. Disruption of these services cannot be allowed without written approval of the government.
The contractor is required to: 1) Request the outage in writing. 2) Demonstrate sufficient contingency preparedness in the event that service cannot be restored due to a failure in accomplishment of contract work.
All outages require Contractor’s written request fifteen (15) days prior to commencement of such work. The request shall be submitted to the COR with the date, time, duration, and scope of the outage.
As supporting documentation for the request, the contractor is require to submit a contingency plan for all reasonably foreseen risks related to the contractor’s performance of the work that would impact disrupted services in excess of the approved outage. This plan must demonstrate the following at a minimum.
1. Understanding of key personnel and communications methods to include phone numbers.
2. Analysis of reasonable risks during the contract work that would impact disrupted services in excess of the approved outage.
3. An effective recovery plan to restore minimum essential services in the event of these risks materializing.
4. Requested government support.
The government will similarly produce risk-based contingency plans for restoration of essential services caused by reasonably foreseen factors that are not related to the performance of the contract. In these cases, the government may request the contractor make additional preparations to support essential and high risk services. Such requests are considered within the scope of this contract but will be priced and negotiated via modification as conditions warrant.
Approvals will be issued by the Public Works Officer or his/her designee and transmitted via the contracting officer’s representative.
1.11 GOVERNMENTAL SAFETY REQUIREMENTS
Use appropriate personnel protective equipment such as safety glasses, hard hats, hearing protection, protective clothing, and gloves.
All current North Carolina Buildings Codes, Fire Codes, Statues, NEC, OSHA Safety Codes, and U.S. Army Corps of
Engineer’s Safety and Health Requirements Manual, EM 385-1-1 shall be strictly enforced.
An accident prevention plan in accordance with the EM 385-1-1 is required.
The contractor is responsible for any required permits.
1.12 EXECUTION
If during the course of the work, conditions are encountered which are not covered in the contract or are different from conditions that would be reasonably anticipated, the contractor shall immediately notify the Contracting Officer. If such conditions are hazardous or the continuation of work would cause a hazardous condition to develop, the contractor shall stop work and proceed as directed by the Contracting Officer as directed by provisions contained in other sections of this specification. This may include modifications to, or the development of a new, Health and Safety Plan for this project, and alternate or additional appropriate abatement procedures.
LOCATION OF BLDG. 155
LOCATION OF BLDG. 143
CONCRETE SIDEWALK DEMO