Summary of ECI Industry Day Presentation for P271 E-130J Project
This document is an Early Contractor Involvement (ECI) Industry Day presentation held on August 28, 2026, for the P-271 E-130J Main Operating and Training Base project at Marine Corps Air Station Cherry Point, North Carolina. The project objective is to provide operating and training infrastructure to support the TACAMO mission transition from E-6B to E-130J airframes for approximately 1,000 personnel across five tenants operating 11 aircraft. The scope encompasses over 600,000 square feet of new construction and renovation, including a 220,000 SF three-bay aircraft maintenance hangar with overhead bridge cranes and administrative offices; a 77,000 SF training facility featuring a 200-seat auditorium, operational flight trainers, and weapon systems trainers; a 100,000 SF Mobile Support Unit (MSU) warehouse with vehicle storage and maintenance capabilities; a 48,000 SF logistics warehouse; renovation of Building 244 (25,000 SF) for maintenance training; airfield improvements including a five-spot parking apron and complete upgrade to Taxiway Foxtrot (4,400 linear feet); and significant utility and roadway improvements spanning 2.5 miles (water, electrical, communications, sanitary sewer, stormwater, and natural gas).
The procurement strategy employs Design-Bid-Build with Early Contractor Involvement across three separate DBB packages (Taxiway Improvements, Roads & Utilities, and Site & Facilities), with government preference for one combined procurement exceeding $1 billion. The acquisition will use a two-segment approach: Segment 1 (ECI Preconstruction Services) with RFP in October 2026, proposals due November 2026, and award in January 2027, where up to three contractors will be selected through best-value tradeoff with non-price factors significantly more important than price; Segment 2 (Construction) with RFP in Early Spring 2028, proposals due Late Spring 2028, award Summer 2028, and construction completion by Summer 2032. Only contractors selected for Segment 1 will be prequalified for Segment 2 construction proposals. Funding is through Military Construction appropriations. Selection factors for Segment 1 emphasize corporate experience in preconstruction services, preconstruction services approach, safety, and past performance. The government solicits industry input on combining versus separating packages, implementing technical-qualifications-only evaluation for Segment 1, schedule compression strategies, and labor capacity solutions for the influx of work at Cherry Point.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| P271 Industry Day Roster.xlsx | XLSX spreadsheet | |
| P271 Industry Day Flyer.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P271 E-130J Main Operating and Training Base Marine Corps Air Station (MCAS) Cherry Point, NC
ECI Industry Day 28 August 2026
Controlled by: DON Controlled by: NAVFAC MID-LANT
DIST/LIMDIS: FEDCON
POC: Judah Emory 757-994-5691 1
AGENDA
1000 Agenda and Ground Rules – NAVFAC ML Contracting 1010 Opening Remarks - NAVFAC ML Commanding Officer 1020 Project Presentation - Technical NAVFAC ML Design Team 1100 Procurement Overview – NAVFAC ML Contracting 1115 Questions - NAVFAC ML Contracting 1200 Adjourn
INTRODUCTIONS
• CAPT Dean Allen, Commanding Officer, NAVFAC Mid-Atlantic
• Kim Kahler, Chief of the Contracting Office, NAVFAC Mid-Atlantic
• Philip Cole, Contracting Officer, NAVFAC Mid-Atlantic
• Brittany Cristelli, Contract Specialist, NAVFAC Mid-Atlantic
• Kevin Ball, Project Manager, NAVFAC Mid-Atlantic
• Judah Emory, Project Manager, NAVFAC Mid-Atlantic
• Amani Elamin, Design Manager, NAVFAC Mid-Atlantic
GROUND RULES
• This meeting is informational and for planning purposes only.
• This is not a Request For Proposal (RFP). Discussions today will not be evaluated in response to any future requests for proposals.
• Do not provide the Government with proprietary information, trade secrets, or any other information deemed source selection sensitive, or information that you do not want disseminated to the public.
• Effort that any contractor/entity expends on this effort is at its own time, risk, and expense.
• Hold all questions until the end of the presentation.
• Everything you see today is a DRAFT and is subject to change.
OPENING REMARKS
NAVFAC Mid-Atlantic Commanding Officer CAPT Dean Allen
INDUSTRY DAY GOALS
• Notify the Industry of the upcoming Early Contractor Involvement (ECI) solicitation for the P-271 E-130J Squadron Training Campus, Marine Corps Air Station (MCAS), Cherry Point, NC.
• Inform Industry of the scope, timeline, and possible construction challenges for the project.
• Solicit private sector input to help shape the project procurement.
PROJECT PRESENTATION
PROJECT HIGHLIGHTS
• Project Objective: Provide operating and training base infrastructure on the east coast to support Take
Charge and Move Out (TACAMO) mission transition from E-6B airframe to E-130J Phoenix II.
• Scope Elements:
• ~1,000 personnel across (5) tenants
• (11) aircraft
• Hangar (~220,000 SF) – (3) bay O/I level maintenance hangar with standard maintenance and administrative spaces plus reel shop, propeller shop, and mission ops command & control center
• Hangar Apron/Ancillary Components – (5) aircraft apron spots, (2) Ground Support Equipment
(GSE) sheds, mobile support unit canopy, HAZMAT storage, and antenna pads
• Training Building (~77,000 SF) – (3) operational flight trainers, (3) weapon systems trainers, (3) reel trainers, (2) cockpit trainers, supporting trainer classrooms, 200 PN auditorium, (4) 12-person classrooms, (4) 25-person classrooms, (2) 40-person classrooms, and TWS command offices
• Mobile Support Unit (MSU) Building (~100, 000 SF) – indoor vehicle storage for up to 31 semi-trucks with trailers, (3) bay auto vehicle maintenance shop, public works shop, high bay storage, security and command offices
• Warehouse Building (~48,000 SF) – (3) bay GSE shop, (1) loading dock, shipping/receiving, staging area, small/oversized parts storage, propeller and engine assembly storage
• Maintenance Training CNATT (~25,000 SF) – proposed renovation of various rooms in B244 to house trainers, classrooms, and support spaces
• Unaccompanied Housing – 256 PN capacity, single E4 and below (will be part of a future OTA barracks procurement package)
• Widening a portion of Roosevelt Avenue and Access Road and significant utility upgrades (water, sanitary, electrical and communications infrastructure
• Complete upgrade to Taxiway Foxtrot including pavement, shoulders and airfield lighting
P-271 EAST COAST COMPOUND OVERVIEW
Version 4.5 9
N
SITE AND FACILITIES (MAIN CAMPUS)
Version 4.5 10
3 BAY HANGAR
Version 4.5 11
• 220,000 SF
• 3 Bay Layout with overhead bridge cranes
• Enclosed within a secure perimeter
• 2 levels of administrative offices
• 1 secure space
HANGAR & TRAINING FACILITY SITE PLAN
AIRFIELD PARKING APRON
Version 4.5 13
• 5 Spot Aircraft Parking Apron
• Heavy Duty Concrete
Construction
• Utilities
• Enclosed within the Hangar
Secure perimeter
TRAINING FACILITY
Version 4.5 14
• 77,00 SF Facility
• Features a 200-seat auditorium
• Includes high-bay operational spaces
• 1 Secure Space
LOGISTICS WAREHOUSE FACILITY SITE PLAN
LOGISTICS WAREHOUSE FACILITY
Version 4.5 16
• 48,000 SF Multipurpose Logistics Facility
• Sited for proximity to the Hangar for safe transport of parts
MSU-X WAREHOUSE FACILITY SITE PLAN
MSU-X WAREHOUSE FACILITY
Version 4.5 18
• 100,000 SF Warehouse Facility
• Supports Customer logistics and maintenance needs
• Pull-Through covered storage for tractor trailers
• Heavy duty concrete apron
• Enclosed within a secure perimeter
ROADS AND UTILITIES IMPROVEMENTS
ROADS & UTILITIES SCOPE
• Upgrade 2.5 Miles of Roadway
• New Travel Lanes
• New Turn Lanes
• Pedestrian Bridges
• Culvert Crossings
• New Water Tower
• Upgrade Utilities
• Electrical
• Communication
• Water
• Sanitary Sewer
• Stormwater
• Natural Gas
• Full Depth Replacement
• 4,400 linear feet of pavement improvements
• Taxiway Realignment
• Stormwater Improvements
• Lighting Improvements
TAXIWAY FOXTROT IMPROVEMENTS
N
CNATT RENOVATION
• Renovate BLDG 244
• 25,000 SF of renovated classroom spaces
• Supports technical and maintenance training
• Replacement of HVAC System
• Leverages existing assets to control cost
SUMMARY OF REQUIREMENTS & KEY FIGURES
• Total New Construction & Renovation: Over 600,000 SF
• Key Facilities:
• 3-Bay Aircraft Hangar
• Training & Admin Building
• Vehicle Storage and Maintenance Facility
• General Supply Warehouse
• CNATT Renovation
• Critical Infrastructure:
• Runway/Taxiway Reconstruction
• 5-Spot Parking Apron
• Utility and Roadway improvements (~2.5 miles)
Norfolk Naval Station
PROCUREMENT STRATEGY
• Magnitude of Construction: Over $1B
• Three (3) DBB packages
• Package #1: Taxiway Improvements
• Package #2: Roads & Utilities
• Package #3: Site & Facilities
• Each package has a separate DOR.
• Design-Bid-Build with Early Contractor Involvement
• Full and Open Competition
• Two segments to the procurement process
• Segment 1 – ECI Preconstruction Services
• Best value tradeoff process
• Up to 3 contractors will be selected for preconstruction service efforts.
• Segment 2: Construction Services
• Best value tradeoff process
• Only the contractors selected for Segment 1 will be prequalified to proposed on the construction. Note: Government may elect to not include all awardees of the ECI in Segment 2 based on performance and involvement during Segment 1.
EARLY CONTRACTOR INVOLVEMENT
• Design work already under contract. Expect to be at 35% when ECI contracts are awarded.
• Contractors will work collaboratively with DORs and the Government team to improve overall project delivery.
• Preconstruction services will generally include:
• Reviewing and evaluating the design documents at specified stages to identify potential constructability challenges and risks.
• Provide value-engineering style recommendations and alternative ideas to improve the final product considering cost and schedule.
• Advising on efficient construction means and methods.
• Providing construction cost information.
• Identifying construction cost and schedule risks and mitigation recommendations.
• DORs maintains responsibility for the quality and engineering compliance for design
• Ensure design does not inhibit use of efficient construction means and methods and to develop design solutions that avoid constructability challenges and minimize cost and schedule risks.
• Careful consideration to avoid revealing and confidential business and proprietary information.
PROCUREMENT TIMELINE
• Segment 1 – ECI Preconstruction Services
• RFP: October 2026
• Proposals Due: November 2026
• Award: January 2027
• Segment 2 – Construction
• RFP: Early Spring 2028
• Proposals Due: Late Spring 2028
• Award: Summer 2028
• Construction Complete: Summer 2032
• Funding: Military Construction
Note: Dates and acquisition strategy are still in refinement, and subject to change. Source selection evaluation factors will be specifically defined in each solicitation.
SELECTION FACTORS
• Segment 1 – ECI Preconstruction Services
• Best value tradeoff process
• Non-price significantly more important than price
• Non-price
• Corporate Experience (preconstruction services and construction), Preconstruction Services Approach, Safety, Past Performance
• Price for Preconstruction Services
• Segment 2 – Construction
• Best value tradeoff process with prequalified offerors from Segment 1
• Non-price approximately equal to price
• Non-Price
• Evaluation ratings from Segment 1 carry over to Segment 2
• Technical Approach, Schedule, and Small Business Utilization and
Particpation
• Price for Construction
QUESTIONS TO INDUSTRY
• Should all 3 packages be combined into 1 ECI procurement or should the 3 packages each be their own separate ECI procurement?
• With one procurement, all construction work will be awarded to a single prime contractor responsible for delivering the program in its entirety.
• With three separate packages, construction work could be awarded to 3 separate contractors. However, there is nothing that prevents the same prime contractor receiving all or a combination of the awards.
• Government preference is 1 single procurement.
• What are your opinions on Segment 1 being based on technical qualifications only and offerors are all given the same price?
• What are ways to compress the schedule?
• With the influx of work at Cherry Point, how would you address labor capacity?
ADDITIONAL QUESTIONS OR FEEDBACK
• Any additional questions can be submitted in writing to: philip.j.cole.civ@us.navy.mil
• If you are interested in scheduling a one-on-one discussion via MS Teams or phone call, please submit requests to philip.j.cole.civ@us.navy.mil