About this file

Section F – Management and Administration Deliverables Summary

This document is Section F of a federal contract (N4008526R0200) detailing the deliverables and performance requirements for Management and Administration (Section 0200000) and Facility Investment (Section 1502000). The contract establishes comprehensive submission requirements for administrative, operational, safety, environmental, and facility-related documentation throughout the contract performance period.

Under Section 0200000, the contractor must submit numerous management and administrative deliverables to the Contracting Officer (KO) and Contracting Officer's Representative (COR). Key submissions include Plans of Action and Milestones (within 15 calendar days prior to contract start), Quality Management Plans (within 15 calendar days prior to start), Work Schedules (monthly, with 10 days' advance notice), Scheduling and Work Status Updates (weekly with 30-minute response requirement during working hours), and Employee Lists (within 15 calendar days prior to start and within 7 days of changes). Security-related deliverables require submission to the Command Security Manager and include OF-306 Declaration for Federal Employment and Digital Fingerprints (prior to work commencement) and personnel access lists for Government IT systems (within 15 calendar days prior to start). Critical incident notifications must be reported immediately upon discovery during working hours or by 0800 the following work day for after-hours discoveries. Safety documentation includes Accident Prevention Plans, Activity Hazard Analysis, OSHA compliance reports (within 48 hours of citation receipt), and monthly labor reports submitted the first work day of each month. Environmental deliverables encompass spill notifications (within 15 minutes to Regional Dispatch Center and within 24 hours to KO/COR) and Asbestos Containing Material notifications (verbal within one hour and written within 24 hours). Additional recurring submissions include Service Contract Reporting (by October 31 annually), Property Management Plans (within 45 calendar days after award), and Technical Library Table of Contents (within 15 calendar days after contract start).

Section 1502000 addresses Facility Investment deliverables required monthly and annually, including Service Order Summary Reports, Preventive Maintenance Program Plans, Inspection and Certification Program reports, and Monthly PM Work Schedules (all submitted the first work day of each month or five work days prior to month beginning). All deliverables require one copy submission to the KO unless otherwise specified, with distribution frequency ranging from "as required" to monthly, annually, or one-time submissions at contract initiation.

View the file

Other files

File Type Posted
N4008526R0200.pdf PDF
N4008526R0200 _ PPQ.docx DOCX document
N4008526R0200 _ Section J.pdf PDF
Wage_Determination2015-5799_Rev34_8-22-26.pdf PDF
N4008526R0200 _ PPI.docx DOCX document
N4008526R0200 _ ELINS.xlsx XLSX spreadsheet
N4008526R0200 _ Section C.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N4008526R0200_Section F

SECTION F – 0200000 - MANAGEMENT AND ADMINSTRATION

Section F 0200000 Deliveries or Performance

DELIVERABLES

Spec Item

Form Attachment

Number

Deliverable

Title

Date (s) of

Submission

Distribution

Frequency

Original

Copies (including original)

2.2.1.2 N/A Request to Work

Outside Government’s Regular Working Hours

At least seven calendar days prior to requested day.

KO and

COR

1 As required

2.3.4 N/A Permits and

Licenses

Before work commences and as requested by the KO.

KO and

COR

1 As specified

2.3.5 N/A Certificate of

Insurance

Within 15 calendar days prior to contract start.

KO and

COR

1 As specified

2.3.5 N/A Written Notice of

cancellation or material change in policy coverage

At least 30 calendar days prior to cancellation or material change in policy coverage

KO and

COR

1 As required

2.6.1 N/A Plans of Action

and Milestones (POA&Ms)

Within 15 calendar days prior to contract start and within seven calendar days of changes.

KO,

COR,

and

Command Security Manager

1 As required

2.6.1 N/A Cybersecurity

Incident

Immediately upon discovery during regular working hours and by 0800 the following work day for discoveries after regular working hours

KO,

COR,

and

Comma nd

Security Manage r

1 As required

Section F 0200000

Deliveries or Performance

Form Attachme nt

Frequen cy

(includin g original)

2.6.4 N/A Scheduling and

Work Status Updates

Weekly, within 30 minutes of the inquiry during regular working hours, and by 08:00 the following work day for inquiries after regular working hours

KO and

COR

1 As Specified

2.6.4 N/A Work

Schedules

Within 15 calendar days prior to contract start, 10 days prior to the beginning of the month in which services are scheduled to be performance, and within two calendar days of changes.

COR 1 Monthly

2.6.5 N/A Notification of

any Difficulty in Scheduling Work

By the end of each workday

KO and

COR

1 As required

2.6.6 N/A Status of

Deliverables

Within 30 minutes of the inquiry during regular working hours, and by 0800 the following work day for inquiries after regular working hours

KO and

COR

Form Attachme

(includin g original)

2.6.7 N/A Service

Interruptions

At least five working days in advance

KO and

COR

1 As required

2.6.9.1 N/A Quality

Management Plan

Within 15 calendar days prior to contract start.

KO and

COR

1 As specified

2.6.9.1 N/A Revised Quality

Management Plan

Within seven calendar days of changes.

KO and

COR

1 As specified

2.6.9.2 N/A QC Inspection

File

Within five calendar days of completion/ termination of the contract.

KO and

COR

1 As specified

2.6.9.3 N/A Contractor

Quality Inspection and Surveillance Report

First work day of each month.

KO and

COR

1 Monthly

2.6.10 N/A Property

Management Plan

Within 45 calendar days after award.

KO and

COR

1 As specified

2.7.1 N/A List of Key

Personnel and Qualifications

Within 15 calendar days prior to contract start

KO and

COR

1 As specified

2.7.1 N/A Organizational

Chart

Within 15 calendar days prior to contract start

KO and

COR

1 As specified

2.7.2.6 N/A Proof of Legal

Residency

Prior to be admitted to site of work.

KO and

COR

specified

Form Attachme

(includin g original)

2.7.3 N/A Service

Contract Reporting

(SCR)

No later than 31 October

KO and

COR

1 Annually for labor executed during the period of performa nce during each

Governm ent fiscal year (FY)

2.8.1 N/A Employee List Within 15

calendar days prior to contract start and within seven calendar days of changes.

KO and

COR

1 As required

2.8.8 N/A OF-306

Declaration for Federal Employment and Digital Fingerprints

Prior to commencemen t of work

KO,

COR,

and

Security Manager

1 As required

2.8.9 N/A List of

personnel requiring access to and the justification for their access to Government IT, OT, and FRCS

Within 15 calendar days prior to contract start and within seven calendar days of changes.

KO,

COR,

and

Security Manager

Form Attachme

(includin g original)

2.9.2 N/A Accident

Prevention Plan

Within 15 calendar days prior to contract start and within seven calendar days of changes.

KO and

COR

1 As specified

2.9.3 N/A Activity Hazard

Analysis

Together with the Accident Prevention Plan and within seven calendar days of and changes.

KO and

COR

1 As specified

2.9.4 N/A Compliance

Plans, Programs, and Procedures

Together with the Accident Prevention Plan and within seven calendar days of and changes.

KO and

COR

1 As specified

2.9.4.7 N/A Control of

Hazardous Energy (lockout/tagout)

Within 30 calendar days after annual inspection.

KO and

COR

1 Annually

2.9.8 N/A Monthly On-

Site Labor Report

First work day of each month.

KO and

COR

1 Monthly

2.9.9 N/A OSHA

Citations and Violations Corrective Action Report

Within 48 hours after receiving a citation.

KO and

COR

1 As required

2.9.10 N/A Safety

Inspection and Monitoring Report

Upon request. KO and

COR

Form Attachme

(includin g original)

2.9.11 N/A Safety

Certifications

Within 15 calendar days prior to contract start and as old certifications, expire.

KO and

COR

1 As specified

2.10 N/A EMS Goals and

Policy Measurement Information

Upon request. KO and

COR

1 As required

2.10.2 N/A Environmental

Protection Plan

Within 15 calendar days prior to contract start and within seven calendar days of changes.

KO and

COR

1 As specified

2.10.2.7 N/A Fuel and

hazardous substance spill notification

Within 15 minutes of discovery

Regional Dispatch Center

1 As required

2.10.2.7 N/A Fuel and

hazardous substance spill notification

As soon as possible but not more 24 hours of discovery

KO and

COR

1 As required

2.10.2.7 N/A Fuel and

hazardous substance spill report

Within 48 hours of discovery

KO and

COR

Form Attachme

(includin g original)

2.10.2.8 N/A Emergency

Planning and Community Right-To-Know Act (EPCRA) Report

Within 15 calendar days prior to contract start and not less than 10 working days prior to planned use of hazardous material.

KO and

COR

1 As specified

2.10.2.8 J-0200000-

Contractor Hazardous Material Inventory Log

Within 15 calendar days after the end of each calendar year and at termination of the contract.

KO and

COR

1 Annually

2.10.2.12 N/A Asbestos

Containing Material

(ACM)

Verbally notify the KO and COR within one hour and follow-up with written Notification within 24 hours

KO and

COR

1 As specified

2.10.3 N/A Sustainable

Procurement and Practices Plan

Within 15 calendar days prior to contract start and within 15 calendar days after exercised option periods.

KO and

COR

1 Annually

2.10.3 N/A Sustainable

Delivery of Services Report

Within five calendar days after each contract period.

KO and

COR

1 Annually

Form Attachme

(includin g original)

2.10.3.2 N/A Recovered

Material Certification

As specified KO and

COR

1 When a product containin g recovered materials is equal to or better than the original and could be used.

2.11 N/A Mission

Essential Contractor Services Plan

Within 15 calendar days prior to contract start and within seven calendar days of changes.

KO and

COR

1 As Required

2.11 N/A Mission

Critical/Mission Essential Personnel

Within 15 calendar days prior to contract start and within seven calendar days of changes.

KO and

COR

1 As specified

2.12 N/A Technical

Library Table of Contents

Within 15 calendar days after contract start and within seven calendar days of changes

KO and

COR

1 As specified

2.14.1 Recurring Work

Proposals

Within five calendar days following receipt of request

KO and

COR

Form Attachme

(includin g original)

2.14.2 N/A Notification to

the Government for Work Above the Recurring Work Limitations and Rough Order of Magnitude

Within two hours of identification

KO and

COR

1 As required

2.15.1.1 N/A Non-Recurring

Work Quantities Ordered via FedMall

By the fifth day of the following month

KO and

COR

1 Monthly

2.15.2.1 N/A Non-Recurring

Work Proposals

Within two working days following receipt of request

KO 1 As

SECTION F - 1502000

FACILITY INVESTMENT - DELIVERIES OR PERFORMANCE

Number of Form Copies

Annex/ Attachment Date (s) of Original/ (including Spec Item Number Deliverable Title Submission Copies original) Frequency 1502000/ N/A Certification and Within 15 days KO 1 Once for

2.2.1 Licenses after award or as initial

requested by the submittal, then KO as requested

1502000/ N/A Service Order First work day of KO 2 Monthly

3.1 Summary Report each month

1502000/ N/A Preventive 30 calendar days KO 2 Annually

3.2 Maintenance after contract

Program Plan award 1502000/ N/A Monthly PM Work Five work days KO 1 Monthly

3.2 Schedule prior to the

beginning of each month

1502000/ N/A Inspection, Testing, First work day of KO 2 Monthly

3.3 and Certification each month

Program Summary Report

1502000/ N/A Inspection, Testing First work day of KO 2 Monthly

3.3 and Certification each month

Schedule and Equipment Certifications