Section F – Management and Administration Deliverables Summary
This document is Section F of a federal contract (N4008526R0200) detailing the deliverables and performance requirements for Management and Administration (Section 0200000) and Facility Investment (Section 1502000). The contract establishes comprehensive submission requirements for administrative, operational, safety, environmental, and facility-related documentation throughout the contract performance period.
Under Section 0200000, the contractor must submit numerous management and administrative deliverables to the Contracting Officer (KO) and Contracting Officer's Representative (COR). Key submissions include Plans of Action and Milestones (within 15 calendar days prior to contract start), Quality Management Plans (within 15 calendar days prior to start), Work Schedules (monthly, with 10 days' advance notice), Scheduling and Work Status Updates (weekly with 30-minute response requirement during working hours), and Employee Lists (within 15 calendar days prior to start and within 7 days of changes). Security-related deliverables require submission to the Command Security Manager and include OF-306 Declaration for Federal Employment and Digital Fingerprints (prior to work commencement) and personnel access lists for Government IT systems (within 15 calendar days prior to start). Critical incident notifications must be reported immediately upon discovery during working hours or by 0800 the following work day for after-hours discoveries. Safety documentation includes Accident Prevention Plans, Activity Hazard Analysis, OSHA compliance reports (within 48 hours of citation receipt), and monthly labor reports submitted the first work day of each month. Environmental deliverables encompass spill notifications (within 15 minutes to Regional Dispatch Center and within 24 hours to KO/COR) and Asbestos Containing Material notifications (verbal within one hour and written within 24 hours). Additional recurring submissions include Service Contract Reporting (by October 31 annually), Property Management Plans (within 45 calendar days after award), and Technical Library Table of Contents (within 15 calendar days after contract start).
Section 1502000 addresses Facility Investment deliverables required monthly and annually, including Service Order Summary Reports, Preventive Maintenance Program Plans, Inspection and Certification Program reports, and Monthly PM Work Schedules (all submitted the first work day of each month or five work days prior to month beginning). All deliverables require one copy submission to the KO unless otherwise specified, with distribution frequency ranging from "as required" to monthly, annually, or one-time submissions at contract initiation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N4008526R0200.pdf | ||
| N4008526R0200 _ PPQ.docx | DOCX document | |
| N4008526R0200 _ Section J.pdf | ||
| Wage_Determination2015-5799_Rev34_8-22-26.pdf | ||
| N4008526R0200 _ PPI.docx | DOCX document | |
| N4008526R0200 _ ELINS.xlsx | XLSX spreadsheet | |
| N4008526R0200 _ Section C.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N4008526R0200_Section F
SECTION F – 0200000 - MANAGEMENT AND ADMINSTRATION
Section F 0200000 Deliveries or Performance
DELIVERABLES
Spec Item
Form Attachment
Number
Deliverable
Title
Date (s) of
Submission
Distribution
Frequency
Original
Copies (including original)
2.2.1.2 N/A Request to Work
Outside Government’s Regular Working Hours
At least seven calendar days prior to requested day.
KO and
COR
1 As required
2.3.4 N/A Permits and
Licenses
Before work commences and as requested by the KO.
KO and
COR
1 As specified
2.3.5 N/A Certificate of
Insurance
Within 15 calendar days prior to contract start.
KO and
COR
1 As specified
2.3.5 N/A Written Notice of
cancellation or material change in policy coverage
At least 30 calendar days prior to cancellation or material change in policy coverage
KO and
COR
1 As required
2.6.1 N/A Plans of Action
and Milestones (POA&Ms)
Within 15 calendar days prior to contract start and within seven calendar days of changes.
KO,
COR,
and
Command Security Manager
1 As required
2.6.1 N/A Cybersecurity
Incident
Immediately upon discovery during regular working hours and by 0800 the following work day for discoveries after regular working hours
KO,
COR,
and
Comma nd
Security Manage r
1 As required
Section F 0200000
Deliveries or Performance
Form Attachme nt
Frequen cy
(includin g original)
2.6.4 N/A Scheduling and
Work Status Updates
Weekly, within 30 minutes of the inquiry during regular working hours, and by 08:00 the following work day for inquiries after regular working hours
KO and
COR
1 As Specified
2.6.4 N/A Work
Schedules
Within 15 calendar days prior to contract start, 10 days prior to the beginning of the month in which services are scheduled to be performance, and within two calendar days of changes.
COR 1 Monthly
2.6.5 N/A Notification of
any Difficulty in Scheduling Work
By the end of each workday
KO and
COR
1 As required
2.6.6 N/A Status of
Deliverables
Within 30 minutes of the inquiry during regular working hours, and by 0800 the following work day for inquiries after regular working hours
KO and
COR
Form Attachme
(includin g original)
2.6.7 N/A Service
Interruptions
At least five working days in advance
KO and
COR
1 As required
2.6.9.1 N/A Quality
Management Plan
Within 15 calendar days prior to contract start.
KO and
COR
1 As specified
2.6.9.1 N/A Revised Quality
Management Plan
Within seven calendar days of changes.
KO and
COR
1 As specified
2.6.9.2 N/A QC Inspection
File
Within five calendar days of completion/ termination of the contract.
KO and
COR
1 As specified
2.6.9.3 N/A Contractor
Quality Inspection and Surveillance Report
First work day of each month.
KO and
COR
1 Monthly
2.6.10 N/A Property
Management Plan
Within 45 calendar days after award.
KO and
COR
1 As specified
2.7.1 N/A List of Key
Personnel and Qualifications
Within 15 calendar days prior to contract start
KO and
COR
1 As specified
2.7.1 N/A Organizational
Chart
Within 15 calendar days prior to contract start
KO and
COR
1 As specified
2.7.2.6 N/A Proof of Legal
Residency
Prior to be admitted to site of work.
KO and
COR
specified
Form Attachme
(includin g original)
2.7.3 N/A Service
Contract Reporting
(SCR)
No later than 31 October
KO and
COR
1 Annually for labor executed during the period of performa nce during each
Governm ent fiscal year (FY)
2.8.1 N/A Employee List Within 15
calendar days prior to contract start and within seven calendar days of changes.
KO and
COR
1 As required
2.8.8 N/A OF-306
Declaration for Federal Employment and Digital Fingerprints
Prior to commencemen t of work
KO,
COR,
and
Security Manager
1 As required
2.8.9 N/A List of
personnel requiring access to and the justification for their access to Government IT, OT, and FRCS
Within 15 calendar days prior to contract start and within seven calendar days of changes.
KO,
COR,
and
Security Manager
Form Attachme
(includin g original)
2.9.2 N/A Accident
Prevention Plan
Within 15 calendar days prior to contract start and within seven calendar days of changes.
KO and
COR
1 As specified
2.9.3 N/A Activity Hazard
Analysis
Together with the Accident Prevention Plan and within seven calendar days of and changes.
KO and
COR
1 As specified
2.9.4 N/A Compliance
Plans, Programs, and Procedures
Together with the Accident Prevention Plan and within seven calendar days of and changes.
KO and
COR
1 As specified
2.9.4.7 N/A Control of
Hazardous Energy (lockout/tagout)
Within 30 calendar days after annual inspection.
KO and
COR
1 Annually
2.9.8 N/A Monthly On-
Site Labor Report
First work day of each month.
KO and
COR
1 Monthly
2.9.9 N/A OSHA
Citations and Violations Corrective Action Report
Within 48 hours after receiving a citation.
KO and
COR
1 As required
2.9.10 N/A Safety
Inspection and Monitoring Report
Upon request. KO and
COR
Form Attachme
(includin g original)
2.9.11 N/A Safety
Certifications
Within 15 calendar days prior to contract start and as old certifications, expire.
KO and
COR
1 As specified
2.10 N/A EMS Goals and
Policy Measurement Information
Upon request. KO and
COR
1 As required
2.10.2 N/A Environmental
Protection Plan
Within 15 calendar days prior to contract start and within seven calendar days of changes.
KO and
COR
1 As specified
2.10.2.7 N/A Fuel and
hazardous substance spill notification
Within 15 minutes of discovery
Regional Dispatch Center
1 As required
2.10.2.7 N/A Fuel and
hazardous substance spill notification
As soon as possible but not more 24 hours of discovery
KO and
COR
1 As required
2.10.2.7 N/A Fuel and
hazardous substance spill report
Within 48 hours of discovery
KO and
COR
Form Attachme
(includin g original)
2.10.2.8 N/A Emergency
Planning and Community Right-To-Know Act (EPCRA) Report
Within 15 calendar days prior to contract start and not less than 10 working days prior to planned use of hazardous material.
KO and
COR
1 As specified
2.10.2.8 J-0200000-
Contractor Hazardous Material Inventory Log
Within 15 calendar days after the end of each calendar year and at termination of the contract.
KO and
COR
1 Annually
2.10.2.12 N/A Asbestos
Containing Material
(ACM)
Verbally notify the KO and COR within one hour and follow-up with written Notification within 24 hours
KO and
COR
1 As specified
2.10.3 N/A Sustainable
Procurement and Practices Plan
Within 15 calendar days prior to contract start and within 15 calendar days after exercised option periods.
KO and
COR
1 Annually
2.10.3 N/A Sustainable
Delivery of Services Report
Within five calendar days after each contract period.
KO and
COR
1 Annually
Form Attachme
(includin g original)
2.10.3.2 N/A Recovered
Material Certification
As specified KO and
COR
1 When a product containin g recovered materials is equal to or better than the original and could be used.
2.11 N/A Mission
Essential Contractor Services Plan
Within 15 calendar days prior to contract start and within seven calendar days of changes.
KO and
COR
1 As Required
2.11 N/A Mission
Critical/Mission Essential Personnel
Within 15 calendar days prior to contract start and within seven calendar days of changes.
KO and
COR
1 As specified
2.12 N/A Technical
Library Table of Contents
Within 15 calendar days after contract start and within seven calendar days of changes
KO and
COR
1 As specified
2.14.1 Recurring Work
Proposals
Within five calendar days following receipt of request
KO and
COR
Form Attachme
(includin g original)
2.14.2 N/A Notification to
the Government for Work Above the Recurring Work Limitations and Rough Order of Magnitude
Within two hours of identification
KO and
COR
1 As required
2.15.1.1 N/A Non-Recurring
Work Quantities Ordered via FedMall
By the fifth day of the following month
KO and
COR
1 Monthly
2.15.2.1 N/A Non-Recurring
Work Proposals
Within two working days following receipt of request
KO 1 As
SECTION F - 1502000
FACILITY INVESTMENT - DELIVERIES OR PERFORMANCE
Number of Form Copies
Annex/ Attachment Date (s) of Original/ (including Spec Item Number Deliverable Title Submission Copies original) Frequency 1502000/ N/A Certification and Within 15 days KO 1 Once for
2.2.1 Licenses after award or as initial
requested by the submittal, then KO as requested
1502000/ N/A Service Order First work day of KO 2 Monthly
3.1 Summary Report each month
1502000/ N/A Preventive 30 calendar days KO 2 Annually
3.2 Maintenance after contract
Program Plan award 1502000/ N/A Monthly PM Work Five work days KO 1 Monthly
3.2 Schedule prior to the
beginning of each month
1502000/ N/A Inspection, Testing, First work day of KO 2 Monthly
3.3 and Certification each month
Program Summary Report
1502000/ N/A Inspection, Testing First work day of KO 2 Monthly
3.3 and Certification each month
Schedule and Equipment Certifications