This document is an Amendment of Solicitation (Standard Form 30) for a pool shell surface renovation project at Camp Lejeune, North Carolina. The amendment (Amendment 0001) for solicitation N40085-23-R-0406 provides clarifications and answers to six key contractor questions about the project scope. Key details include replacing deck tiles (to be flush with existing surface), replacing all pool inlets, outlets, and main drain covers, adding 2x2 tile under the bulkhead for future repairs, and cleaning/preparing all surfaces. The government confirms that loose items will be removed and stored by the end user, and that approximately 20% of light bulbs will be replaced. The solicitation remains open with proposals due on August 18, 2025 at 2:00 PM EDT, and the amendment must be acknowledged with proposal submission to avoid potential rejection.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICIATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 11)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

1 2

AMENDMENT NO. 0001 8/14/25 23-0406

N40085

NAVFAC Mid-Atlantic Resident Officer in Charge of Construction 1107 A Birch Street Camp Lejeune, NC 28547-2521

See Item 6

✘ N40085-25-R-9015

07/29/25

23-0406, AS4400 POOL SHELL SURFACE

Amendment 0001, Questions and Answers

The time and date for receipt of proposals remains August 18, 2025 at 02:00 PM EDT.

This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of a proposal.

See Continuation Page(s)

N40085-23-R-0406 Amendment 0001

CONTINUATION SHEET

1. QUESTION: Sheet D3 indicates areas of replacement tile. Deck tiles are not currently recessed into the concrete deck, please confirm the intent is for the deck tile for depth markers and safety tiles to be chipped out and recessed into the pool concrete deck.

1. ANSWER: A2, 1., Correct the intent is to have the new tile depth markers and safety tile flush with the existing surface, chipping, grinding and or sawing for the new thickness of the tile to be flush with the existing surface.

2. QUESTION: Sheet P1 indicates cost to replace all inlets and outlets, please confirm that the main drain covers are to be included within the scope as they are of age for needing to be replaced. Please also confirm that the scope of work does NOT include replacement of any gutter grating.

2. ANSWER: P1, NOTES: Intent is to replace all inlets and outlets include all fixtures, COVERS and grills. The plug and cover opening by reinstallation of screens, grills; is for protection of the inlet and outlet only from damage of fasteners and location till new covers, screens, grills are put in place. The gutter grates are not in contract to replace.

3. QUESTION: Regarding the bulkhead in the pool, the bulkhead needs to be supported during the emptying of the pool, it is suggested to lower water of the pool, install a white 2x2 non-skid tile under the current location of the bulkhead, then refill the pool and sift bulkhead over the newly installed tile. This will allow for easier cleaning and for a safety time during replastering activities.

3. ANSWER: Contactor shall add 2x2 tile the with and length of bulkhead for future repairs or resurface of pool, cost will be cheaper than removing and reinstalling of bulkhead, with less damage to property and personnel.

4. QUESTION: Please confirm that all loose items around pool will be removed, stored, and reinstalled by government/end user?

4. ANSWER: Correct, user responsibility see: SPECIAL SCHEDULING AND ACCESS Mr.

Reed, Mr. Reed can be reached at 1-910-449-5605

5. QUESTION: Sheet E1 notes to include cost of 20% of lights to be replaced. Please confirm this intended for lights bulbs only, and not including replacing any light niches. Is there any existing information on the brand/type of lights to confirm equal lights being provided.

5. ANSWER: E1 NOTES The intent is to replace any bulbs that are not working after removal and reinstallation, the government understands that the light bulbs and trim would have to be removed for the protection of lights during the hydro blasting, contractor shall confirm the wires are sealed from leaking.

6. QUESTION: Please confirm if in the scope of work should be a wipe down and cleaning of stainless-steel surfaces of gutter.

6. ANSWER: T2, SURFACE PREPARATION, 1. Leave clean building materials and equipment with all damaged surfaces corrected. Correct, the intent is to have all surfaces cleaned before reinstalling