This document is an Industry Day presentation by Naval Facilities Engineering Systems Command (NAVFAC) Mid-Atlantic for a design-build renovation project at Naval Station Norfolk. The project will establish a Fleet Legal Services Complex (FLSC) in Building SP-17, involving partial demolition, renovation of the center portion, and new permanent modular construction. The project offers a base bid and three additive options ranging from 52,000 to 110,000 square feet, with an estimated construction cost between $100 million and $250 million.
The proposed facility will serve as the primary legal support center for the U.S. Navy Second Fleet in the Hampton Roads area, accommodating various legal service units including Region Legal Service Office, Navy-Marine Corps Trial Judiciary, Defense Services Office, and Victim's Legal Counsel Program. The project is a Navy Pilot Project requiring prefabricated modular construction, with new modules to be located within the existing building footprint except for circulation spaces. The Industry Day is scheduled for March 18, 2025, from 1:00-2:30 PM, with interested contractors required to RSVP to Kristy Gerrek by March 17, 2025.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Industry Day Attendance List.pdf | ||
| RM24-3467 Renovate SP17 Fleet Legal Industry Day Flyer.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Renovate SP17 for Fleet Legal Services
RM24-3467
Naval Station Norfolk, Norfolk VA
INDUSTRY DAY
18 March 2025
1300-1430
AGENDA
Time Action Presenter
1300 Opening Remarks/Introductions NAVFAC Contracting
1305 Ground Rules and Goals NAVFAC Contracting
1310 Project Presentation NAVFAC Design Team
1400 Questions NAVFAC Contracting
1430 Adjourn
INTRODUCTIONS
• Philip Cole, Contracting Officer, NAVFAC Mid-Atlantic
• Kristy Gerrek, Contract Specialist, NAVFAC Mid-Atlantic
• Robert Brown, Project Manager, NAVFAC Mid-Atlantic
• Anthony Wilkins, Design Manager, NAVFAC Mid-Atlantic
• Christine Carlson, Associate VP, Principle; Project Manager, AECOM
• Kristi Guilfoyle, Project Manager, AECOM
• Bill Clendenin, Project Director, AECOM
GROUND RULES
• This meeting is informational and for planning purposes only.
• This is not a Request For Proposal (RFP). Discussions today will not be evaluated in response to any future requests for proposals.
• Do not provide the Government with proprietary information, trade secrets, or any other information deemed source selection sensitive, or information that you do not want disseminated to the public.
• Effort that any contractor/entity expends on this effort is at its own time, risk, and expense.
• Hold all questions until the end of the presentation.
• Everything you see today is a DRAFT and is subject to change.
INDUSTRY DAY GOALS
• Notify the Industry of the upcoming solicitation for the RM24-3467 Renovate SP17 for Fleet Legal Services, Naval Station Norfolk, Virginia.
• Inform Industry of the scope and possible construction challenges for the project.
• Solicit private sector input to help shape the project procurement.
PROJECT PRESENTATION
NAVFAC / AECOM
PROJECT LOCATION
Norfolk Naval Station
SP-17 Building Site
• Total Area:
• Base Bid: 51,487 SF
• Base Bid + Option 1: 65,525 SF
• Base Bid + Option 1&2: 75,382 SF
• Base Bid + Option 1, 2, 3: 109,348 SF
• 406 Parking Spaces + 20 Motorcycle Spaces outside the perimeter
• ICD/ICS 705, Marine Corps level II, and JPO security requirements
BASE BID SITE PLAN
EXISTING FLOOR PLANS
SP-17 BASE BID + OPTIONS
SPACE STACKING DIAGRAM
Integrating Remaining Element of SP-17 with New Construction (Base Bid + Options 1, 2 and 3)
MASSING STUDY
RENOVATION OF EXISTING TO REMAIN EXTERIOR
RESTORATION OF EXISTING TO REMAIN EXTERIOR
BUILDING FOOTPRINT CONSTRAINTS
PROJECT CONSTRUCTION METHODOLOGY TYPES
PROJECT CONSTRUCTION METHODOLOGY TYPES
Modular Construction
Building elements constructed off-site, in whole or in part, in a controlled environment and assembled on-site.
PROJECT CONSTRUCTION METHODOLOGY TYPES
Examples of permanent Modular construction
• Modular units partially finished in a factory
• Interior walls and finishes to be completed by general contractor on site
Open “Shell” Modules
PROJECT CONSTRUCTION METHODOLOGY TYPES
Examples of permanent Modular construction
• Interior of modular units are fully finished in a factory
• Exterior finish applied on site
Closed “Finished Box” Modules
Base bid:
first floor plan
Base bid:
second floor plan
Base bid + option 1:
First floor plan
Base bid + option 1:
Base bid + option 1 & 2:
Base bid + option 1 & 2:
Base bid + option 1, 2 & 3:
Base bid + option 1, 2 & 3:
ANY QUESTIONS?
Any additional questions can be submitted in writing to: