Sources Sought Project Data Form.docx
DOCX document 19 KB Posted
- Attached to
- NSN, FY25/26 MAINTENANCE DREDGING
- Solicitation number
- N4008525R0054
About this file
This Sources Sought Project Data Form is part of a market research effort for maintenance dredging services at Naval Station Norfolk, Virginia. The Naval Facilities Engineering Systems Command (NAVFAC) Mid-Atlantic is seeking eligible small businesses, specifically service-disabled veteran-owned small businesses (SDVOSB), HUB-Zone certified, 8(a), women-owned small businesses (WOSB), and small businesses to perform construction services for dredging projects.
The procurement involves maintenance dredging at multiple pier locations to maintain Atlantic Fleet readiness, with an anticipated contract value between $5-10 million and an award date of September 2025. Interested firms must submit up to five relevant construction projects demonstrating experience with bucket dredging and barge transportation of dredge spoils, with projects required to have a final construction cost of at least $20 million and be completed within the last 10 years. The NAICS code is 237990, with a small business size standard of $39.5 million, and the solicitation will include a requirement that the winning firm perform at least 15% of the contract work with its own employees. Responses are due by 2:00 PM local time on July 11, 2025, and must be submitted electronically to Jake Busila.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sources Sought Contractor Information Form.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOURCES SOUGHT – CONSTRUCTION EXPERIENCE PROJECT DATA FORM
For N4008525R0054 Maintenance Dredging, Norfolk Naval Station, Norfolk, Virginia
Use this form (one per project) to provide supporting information that demonstrates project experience relevant to the subject announcement. Submit up to five (5) projects. Please limit response to two pages per project.
| 1. |
| Contractor Name: |
| 2. | ||||
| Project No. (check one): | ||||
| |_| - 1 | |_| - 2 | |_| - 3 | |_| - 4 | |_| - 5 |
| 3. |
| Contract Number: |
| Delivery/Task Order No.: |
| Project Number: |
| Title: |
| Location: |
| 4. |
| Award Date (mm/dd/yy): |
| 5. |
| Final Contract Price: |
| $ |
| Completion Date (mm/dd/yy): |
| (includes all options and mods) |
| Project is % complete (as of submission due date) |
| This is the |_| total project |_| subcontract price. |
| 6. | ||
| Type of work: | ||
| |_| New Construction | |_| Repair | |_| Renovation |
| 7. |
| Customer/Owner Name: |
| Point of Contact Name/Title: (person with project knowledge) |
| POC Phone Number: |
| POC Email Address: |
| 8. | |
| Were you the Prime contractor for this project? | |
| |_| Yes | |_| No |
| Were you a subcontractor for this project? | |
| |_| Yes | |_| No |
| If subcontractor, who was the Prime contractor? |
| 9. |
| Type of Contract (check all that apply): |
|_| Design-Build |_| Design-Bid-Build (fully designed project)
| |_| Other (explain): |
| If Design-Build, provide the following information: |
| |_| Design accomplished in-house |
| Lead design firm name: |
| Years working together: |
| Address: |
10. Provide a detailed description of the project:
11. Percentage of work you self-performed on this project: %.
Provide a detailed description of the work your firm self-performed on this project:
Form may be expanded. Please DO NOT change content of the form.