Replace Sewage Pump
Solicitation number
N4008524R2734
Issued by

About this file

This document is a Scope of Work (SOW) for a federal contract opportunity to replace two sewage pumps in Building #3400 at the Joint Expeditionary Base Little Creek/Fort Story in Virginia Beach, Virginia.

The key details are:

  • The contract will require the contractor to provide supervision, labor, material, and equipment to replace two sewage pumps, sump pump, controls, piping, and electrical connections in Building #3400.
  • The contract completion date is 270 calendar days from award.
  • Hazardous materials like asbestos and lead may be present and must be managed accordingly.
  • The contractor must submit various plans and reports for government approval, including an Accident Prevention Plan, Quality Control Plan, Construction Schedule, and Equipment Inventory Form.
  • The contract is only open to contractors on the NAVFAC Mid-Atlantic Multiple Award Construction Contract (MACC) ML-C00077.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BUILDING #3400 – REPLACE SWEAGE PUMPS eProjects WO#: 1816607

JEB LITTLE CREEK, VIRGINIA BEACH, VIRGINIA

SCOPE OF WORK 7 May 2024 Page 1 of 17

***UNCLASSIFIED***

BUILDING #3400

REPLACE SWEAGE PUMPS

At the

Joint Expeditionary Base Little Creek/Fort Story, Virginia Beach, Virginia

PREPARED BY:

NAVFAC MID-ATLANTIC, PWD Little Creek/Fort Story, FEAD FSC PRL23, JEB Little Creek, 1450 Gator Boulevard, Building 3165, Room 148 Virginia Beach, Virginia 23459-8616

PREPARER(S):

FEAD ET: Adam McBride

SUBMITTED BY:

Facilities Support Contracts Branch Head:

Chris Spelce Date: 5/7/24

APPROVED BY:

PRL1 Facilities Management Division Director: Craig Machmer

SCOPE OF WORK 7 May 2024 Page 2 of 17

1. POINTS OF CONTACT:

FEAD Contracting Officer: Kate Dinneen, 757-462-5347 FEAD Contract Specialist in charge: TBD FEAD Engineering Technician: TBD Facility Maintenance Specialist (FMS): Lavern Rushin, 757-462-5366 Activity POC (if applicable): Rick Czymbor, 757-462-5427

2. GENERAL:

2.1 The Contractor shall provide supervision, labor, material and equipment required to perform all work for the following project: replace TWO sewage pumps in Bldg. 3400. All work shall be done in a manner to provide a complete, usable and finished end product. See paragraph “7. WORK REQUIREMENTS” for an expanded and detailed scope of work.

2.2 The Contractor shall comply with the requirements of the most current Contract as prescribed by the Contracting Officer for use on this contract.

2.3 A Pre-Proposal site meeting shall be held at the project site to review and discuss the scope of work and assess existing field conditions, prior to Award of this Task Order. The Contractor and his key personnel involved with the project shall attend with the Government. Coordinate/schedule the date and time with the Contracting Officer’s approval.

2.4 Existing reference drawing CD’s may be available upon request. Reference drawings shall be used for informational purposes only, and may not accurately reflect current as-built conditions. The Contractor must not solely rely on the reference drawings to determine existing conditions, but must field verify all existing conditions pertinent to the project.

2.5 All work shall be performed in accordance with, but not limited to, standard industry practices, applicable local, state and federal codes, laws and regulations, and the Unified Facilities Criteria (UFC’s).

2.6 FOR PROJECTS INVOLVING LESS THAN 10,000 SQUARE FEET OF LAND DISTURBANCE,

OR WHEN NO LAND DISTURBANCE PROPOSED BUT POTENTIAL FOR STORMWATER

POLLUTION STILL PRESENT (I.E. Painting, Service Connections, Minor building renovations, hazardous material abatement etc.): The contractor must utilize best management practices to ensure materials (Paints, Solvents, Petroleum Products, Trash, Sediment...Etc.)

associated with this activity do NOT become a pollutant in storm water runoff. The Contractor shall keep a spill kit on hand in case of any equipment failure, hydraulic line break, etc. if heavy equipment will be used for this project. No discharges to the sanitary sewer system, storm system or surface waters are permitted without prior coordination with, and approval from the Water Program Manager! Concrete mixing and/or pouring must be done in a way to prevent entry to storm water conveyances or surface waters. Notify NAVFAC EV-Environmental immediately of any spills (anything other than storm water) to the storm system as well as any spills to any sewer system since notifications will need to be made to the regulatory authorities within 24 hours of discovery.

2.7 Supervision: Have a Supervisor fluent in English on the job site during working hours at all times.

The Supervisor shall be a United States Citizen or a Documented Legal Resident of the United States of America.

2.8 Equipment Inventory Form: The Contractor shall submit an Equipment Inventory Form for existing equipment to be demolished/removed, or for new equipment to be provided under this

SCOPE OF WORK 7 May 2024 Page 3 of 17 contract. The Equipment Inventory Form shall be completely filled-out and provided for each piece of equipment as stated in “PART 8 – ATTACHMENTS, EQUIPMENT LISTING”. Further clarification on the equipment types shall also be discussed at the PAK or Pre-Construction Meetings, or as directed by the Contracting Officer.

-Submit all Equipment Inventory Forms to the Contracting Officer, prior to demolition of the existing equipment and prior to installation of the new equipment. (See PART 8 – ATTACHMENTS for the Equipment Inventory Form to utilize).

3. SPECIAL SCHEDULING REQUIREMENTS/WORK PROCEDURES:

3.1 The project Contract Completion Date (CCD) shall be 270 calendar days from Award of this Task

Order.

3.2 UTILITIES LOCATION AND VERIFICATION (Exterior): Prior to digging, the appropriate digging permit must be obtained. All underground utilities in the work area must be positively identified by a private utility locating service in addition to any station locating service and coordinated with the station utility department, prior to any digging. Any markings made during the utility investigation must be maintained throughout the contract. The Contractor must physically verify underground utility locations by hand digging using wood or fiberglass handled tools when any adjacent construction work is expected to come within three feet of the underground system. Digging within 2 feet of a known utility must not be performed by means of mechanical equipment; hand digging shall be used. If construction is parallel to an existing utility expose the utility by hand digging every 100 feet if parallel within 5 feet of the excavation.

3.3 UTILITIES LOCATION AND VERIFICATION (Interior): Utilities located within concrete slabs or pier structures, bridges, and the like, are extremely difficult to identify due to the reinforcing steel used in the construction of these structures. Whenever contract work involves concrete chipping, saw cutting, or core drilling, the existing utility location must be coordinated with station utility departments in addition to a private locating service. Outages to isolate utility systems must be used in circumstances where utilities are unable to be positively identified. The use of historical reference drawings does not alleviate the contractor from meeting this requirement. The contractor must perform positive identification and locating of existing utilities prior to any concrete chipping, saw cutting or core drilling of any kind.

3.4 The contractor shall utilize existing isolation valves (if available and usable/pressure holding) and other types of non-destructive system(s) isolation to minimize the draining of potable water, chilled water, condenser water, heating water piping systems to provide the necessary system connections and disconnections. All water drained from existing systems shall be captured and containerized for sampling. Prior to any discharges, the Contractor shall submit the Water Test Report(s) to the JEB Little Creek/Fort Story Waste Water Manager (through the Contracting Officer) for determination and documentation of disposal method(s). The test report submittal(s) shall include an estimate of volume (gallons) and date of scheduled discharge(s). The contractor shall provide the disposal of all drained water in accordance with all applicable federal, state and local regulations. POC: Roger White, (757) 462-5361.

3.5 In the event that hazardous waste is generated, the hazardous waste program manager must be contacted for the appropriate guidance. In addition, any movement of soil/fill material outside of project boundaries, meaning both soil brought onsite and soil from the site relocated to other areas, must be coordinated with the hazardous waste program manager to ensure environmental compliance. POC: Roger White, (757) 462-5361.

3.6 Pre-Outage Coordination Meeting:

SCOPE OF WORK 7 May 2024 Page 4 of 17

Apply for utility outages at least 15 days in advance to the Contracting Officer. As a minimum, the request must include the location of outage, utilities being affected, duration of outage and any necessary sketches. Any/all utility outage requests must be approved by the Contracting Officer prior to starting the work. Once approved, and prior to beginning work on the utility system requiring shut down, attend a pre-outage coordination meeting with the Contracting Officer to review scope of work and the lock-out/tag-out procedures for worker protection. No work will be performed on energized electrical circuits unless proof is provided that no other means exist.

3.7 Control of Hazardous Energy (Lock-out/Tag-out):

Provide and operate a Hazardous Energy Control Program (HECP) in accordance with EM 385-1- 1 Section 12, 29 CFR 1910.333, 29 CFR 1915.89, and paragraph HAZARDOUS ENERGY

CONTROL PROGRAM (HECP).

3.8 In general terms, demolition work and the use of word “demolish”, shall include the removal and effective management and disposal of existing construction and or structures. Contractor shall take care to prevent damage to existing utilities and construction that are not scheduled for demolition.

If damage occurs, the Contractor shall make repairs, or replacement with new, to the satisfaction of the Contracting Officer and at no cost to the Government. Selling of demolished or salvaged materials and equipment on government properties is prohibited.

3.9 Work Hours: The Contractor’s normal working hours shall be between 0700 to 1630, Monday through Friday, excluding Federal Holidays and other days specifically designated by the Contracting Officer. Advance approval from the Contracting Officer is required for contractor personnel to work outside of normal working hours. Any/all Contractor’s requests to work outside of normal working hours must be given to the Contracting Officer in a form of a written request, occurring no less than 5 calendar days prior to such work, to allow for appropriate approvals and inspections process. The written request must include as a minimum, the specific dates, hours, location, type of work performed, and contract personnel performing the work. Based on the written request, the Contracting Officer, at his discretion, may approve or disapprove the work outside of normal working hours.

3.16 Access to construction work areas shall be limited to the Contractor’s personnel, or other approved personnel as designated by the Contracting Officer. Construction work areas shall have complete and secure separation from adjacent occupied areas, as approved and directed by the Contracting Officer and Activity’s Security Officer.

3.17 Passes and Badges: All Contractor employees, including subcontractors, and subcontractors’ employees, suppliers, and suppliers’ employees shall be required to comply with the Installation Security Requirements regarding personnel, vehicle, equipment, security passes/badges and access to the jobsite. Nothing in the contract shall be construed in any way to limit the authority of the Commanding Officer to prescribe new, or to enforce existing security regulations governing the admission or exclusion of persons and the conduct of persons while aboard the station, including but not limited to, the rights of search of all persons or vehicles aboard the station. All Contractor employees/subcontractors shall have current and valid government issued Contractor Base Access Passes and Badges, in order to perform work under this contract.

Coordinate with the Contracting Officer for other specific security and access requirements.

a) Access to Buildings/ Occupied Buildings: The Contractor may work in or around existing occupied buildings. It shall be the Contractor’s responsibility, through the Contracting Officer, to obtain access to building and facilities and arrange for them to be opened and closed. Do not enter the building(s) without prior approval of the Contracting Officer. The existing buildings and their contents shall be kept secure at all times. Provide temporary closures as

SCOPE OF WORK 7 May 2024 Page 5 of 17 required to maintain security. Contract personnel will not be permitted in security-regulated buildings or areas unless cleared by the Security Officer.

b) Passes and Badges: Contractor employees and representatives performing work under this contract are required to be either United States Citizens or Documented Legal Residents, status of which, MUST be verified/confirmed by the Prime Contractor. All Contractor employees shall obtain the required employee and vehicle passes/badges. Each employee shall wear the government issued badge, AT ALL TIMES, over the front of the outer clothing for awareness and visibility. Failure to obtain government issued security and base access passes/badges shall result in the revocation of the Prime Contractor’s Base Access Contractor Passes/Badges, at the sole discretion of the Contracting Officer and/or the Installation Security Officer. The Prime Contractor is totally responsible to instruct/verify/confirm that all employees and subcontractors obtain valid/approved government issued passes and badges. Any work stoppage or work delays caused by the Contractor/Subcontractor’s failure to comply with obtaining appropriate passes/badges or other Security compliance shall not be a cause for contract performance time extension. The Contractor shall be responsible for immediately turning in all terminated employee’s badges to the Pass and ID issuing office.

3.18 To minimize downtime for the area, construction activities may not start until the Contractor provides confirmation of receipt of all new products and materials necessary to complete the work, prior to start of construction.

4. SAFETY:

4.1 The Contractor shall comply with the most current edition of EM-385-1-1.

4.2 The Contractor shall submit the Accident Prevention Plan (APP). Submit within 3 days from issuance of this Task Order, and obtain approval prior to start of any construction activities. Field work may not begin until the APP is accepted by the Contracting Officer.

4.3 Before beginning each activity, task or Definable Feature of Work (DFOW) involving a type of work presenting hazards not experienced in previous project operations, or where a new work crew or subcontractor is to perform the work, the Contractor(s) performing that work activity must prepare an Activity Hazard Analysis (AHA). AHAs must be developed by the Prime Contractor, subcontractor, or supplier performing the work, and provided for Prime Contractor review and approval before submitting to the Contracting Officer Representative, COR. AHAs must be signed by the SSHO, Superintendent, QC Manager and the subcontractor Foreman performing the work.

Format the AHA in accordance with EM 385-1-1, Section 1 or as directed by the COR. Submit the AHA for review at least 15 working days prior to the start of each activity task, or DFOW. The Government reserves the right to require the Contractor to revise and resubmit the AHA if it fails to effectively identify the work sequences, specific anticipated hazards, site conditions, equipment, materials, personnel and the control measures to be implemented.

4.4 Provide Competent Persons in accordance with EM 385-1-1 and herein. Competent Persons for high risk activities include confined space, cranes and rigging, excavation/trenching, fall protection, and electrical work. The CP for these activities must be designated in writing, and meet the requirements for the specific activity (i.e. competent person, fall protection). Provide the credentials of the Competent Persons(s) to the Contracting Officer for information in consultation with the Safety Office.

4.5 All hot work and hot work permits shall conform to EM-385-1-1 and any local policies. Hot work permits must be attained from JEB Little Creek/Fort Story Fire Dept. (757-462-4445) prior to performing activities which generate or have the potential to generate, heat, sparks, or open flames, SCOPE OF WORK 7 May 2024 Page 6 of 17 such as abrasive blasting burning, brazing, cutting, grinding, powder-actuated tools, hot riveting, soldering, thawing activities, welding, or any similar operation capable of initiating fires or explosions.

5. HAZARDOUS MATERIALS DISCLOSURE STATEMENT(S):

5.1 Asbestos and Lead test reports are not available for Building 3400 prior to issuance of this Task

Order. However, since the building was built prior to 1978 timeframe, (actual 1952), it is anticipated that hazardous materials could be present within the area of work. The Contractor must avoid disturbing any hazardous materials to the fullest extent possible while being able to accomplish the work. If hazardous materials are encountered and disturbed, the Contractor must adhere to the requirements as stated in the subsequent paragraphs below.

5.2 For repair, remodeling, or minor construction and demolition, the Contractor may be required to work in areas that have, but not limited to, flooring, walls, ceilings, insulation, roofing materials and paints etc. etc., that may have asbestos or lead paints, or PCB and/or other hazardous materials requiring abatement and/or management according to applicable National and Local Environmental Protection laws and regulations. For work in soil excavation and other exterior construction etc., the Contractor may be required to work with contaminated material involving abatement or management of these contaminated materials. However, if during the performance of the work the Contractor encounters hazardous substances not known prior to issuance of this Task Order; the Contractor shall immediately stop work and inform the Contracting Officer for direction. In no instance shall the Contractor perform the work involving the hazardous material without notifying and receiving approval from the Contracting Officer for direction.

5.1.1 Asbestos Containing Materials (For projects that require disturbance or removal): Asbestos containing materials shall be removed, transported and managed in accordance with the following regulations: 29 CFR 1926.1101, and 40 CFR 61-Subpart M.

Category I & II Nonfriable Asbestos: Disturbance, demolition/removal of Category I & II nonfriable asbestos containing materials (approved to be left in place during the work) shall be performed in accordance with 40 CFR 61-Subpart M.

5.1.2 Paint Containing Lead, Cadmium and Chromium (For projects that require disturbance or removal): Work which requires the disturbance or removal of paint that has been determined to contain all or any of the following: lead, cadmium and chromium, shall be performed in accordance with 29 CFR 1926.62, 29 CFR 1926.1126 and 29 CFR 1926.1127.

5.1.3 Other Hazardous Materials (For projects that require disturbance or removal): Work which requires the disturbance or removal of any of the following: mercury and LLR Components, and PCB’s, shall be performed in accordance with 29 CFR 1910.1000, 10 CFR 20, 40 CFR 273, and

40 CFR 761.

5.2 Hazardous Materials Reports: In the event that work involves hazardous materials, provide the following reports:

5.2.1 Daily Reports: Notify the Contracting Officer of work involving hazardous materials abatement and removal, including quantities involved, on daily reports.

5.2.2 Hazardous Material Inventory Report: The Contractor shall provide a list of all hazardous materials used on the site.

SCOPE OF WORK 7 May 2024 Page 7 of 17

6. SUBMITTALS:

6.1 The Contractor shall submit the following for government approval, prior to the start of any construction activities and throughout the construction process:

6.1.1 Manufacturer’s Product Data: Submit manufacturer’s written detailed product data cut sheets, with instructions for installation, adjustment, cleaning and maintenance instructions.

6.1.2 Testing Plan

6.1.3 Manufacturer Product Specification

6.1.4 Manufacturer Start Up Report

6.1.5 Equipment Inventory Form

6.1.6 Demolition and Construction Debris Report

6.1.7 Lock Out/Tag Out Procedures

6.1.8 Accident Prevention Plan (APP)

6.1.9 Quality Control Plan (QCP)

6.1.10 Construction Schedule

6.1.11 Schedule of Values

SCOPE OF WORK 7 May 2024 Page 8 of 17

7. WORK REQUIREMENTS:

7.1 Provide supervision, labor, material, and equipment as required to perform the following work, and must be done in a manner to provide a complete, usable, and finished end product to replace TWO sewage pumps and associated controls in building 3400.

7.2 Remove existing sewage pumps (two), piping and piping accessories within the drywell. Remove and replace sump pump and controls. See sheet MD101. Remove flow meter and save for reinstallation. Provide and install all new pumps (two) and all piping to adapt for new pumps. See schedule on M101 for all pumps requirements.

7.3 Remove associated sewage pump electrical connections and controls. See Sheet ED101. Provide new conduit and conductor from pump motors to starter control panel and panel board. See sheet E101.

7.4 Provide new controls that meet the requirements outlined on Sheet MI701. Disconnect and reconnect flow meter. Reconnect all existing warning lights and horn. Replace exterior light/s and horn if required. Test all controls and safeties for proper operation and communication with existing SCADA transmitter.

7.5 Provide up to 4 hours of owner/operating training for Public Works personnel. Coordinate training time through COR and production division of PW.

7.6 All information here-in is for reference only. The Contractor must FIELD VERIFY all existing conditions, prior to fabrication and placing orders for any new items/equipment. The Contractor must take sole ownership/cost responsibilities for re-work or re-ordering any new items/equipment provided that does not fit or function properly within existing conditions.

7.7 The contractor shall dispose of all existing demolished/removed materials off base and will completely clean up job site after work is performed. Maintain daily site clean-up at the end of every workday during the entirety of the construction period, to prevent any hazard potential. Disposal shall be in accordance with all existing Local, State, Federal and NAVFAC MIDLANT EV rules and regulations.

SCOPE OF WORK 7 May 2024 Page 9 of 17

8. ATTACHMENTS (following the Scope of Work):

8.1 Location Map

SCOPE OF WORK 7 May 2024 Page 10 of 17

8.2 Photographs

Figure 1 – Dry Well From Above Figure 2 - Controls

Figure 3 – Wet to Dry Well Penetration Figure 4 – Wet to Dry Well Penetration

SCOPE OF WORK 7 May 2024 Page 11 of 17

Figure 5 – Discharge Header

Figure 6 – Discharge Header Figure 7 – Sewage Pump

SCOPE OF WORK 7 May 2024 Page 12 of 17

8.3 Equipment Inventory Form

SCOPE OF WORK 7 May 2024 Page 13 of 17

8.4 Floor Plans and Elevation Sketches.

SCOPE OF WORK 7 May 2024 Page 14 of 17

SCOPE OF WORK 7 May 2024 Page 15 of 17

SCOPE OF WORK 7 May 2024 Page 16 of 17

SCOPE OF WORK 7 May 2024 Page 17 of 17

**End of SCOPE OF WORK**