ATTACHMENT A_ 1722311_X132_SOW.pdf
PDF 1 MB Posted
- Attached to
- X-132 100 Ton Roof Top Chiller Replacement
- Solicitation number
- N4008524R2722
About this file
This document is a Statement of Work (SOW) for a project to replace the 125-ton roof top chiller with a 100-ton air cooled chiller serving the HVAC equipment for Building X-132 at the Naval Station in Norfolk, Virginia.
The key requirements include: performing the work in accordance with industry standards and government requirements; providing all required submittals; conducting a site visit prior to preparing the bid; providing new materials per manufacturer's instructions; properly disposing of demolished materials; coordinating work between disciplines to prevent conflicts; and obtaining required permits for "Hot Work". The contractor must also provide electrical support for the chiller replacement. Required submittals include shop drawings, product data, samples, and manufacturer's instructions. The government will review and approve the submittals. The project is part of a larger federal contract opportunity solicited under Solicitation Number N4008524R2722 to replace the 100-ton roof top chiller for Building X-132 at the Naval Station in Norfolk.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Work Order (eProjects) No:
X-132 at
Naval Station, Norfolk, Virginia
Bob Gladney, P.E.
PWD Norfolk, Facilities Engineering and Acquisition Division Rev. 5.7.10
Executable Scope eProjects Work Order Number: 1722311 Building: X-132, Naval Station Norfolk Project Title: Replace Roof Top Chiller Customer: Tony Skinner, JECC Scope By: Bob Gladney, P.E.
Date: April 15, 2024
Overview:
Replace the 125 ton Roof Top Chiller with a 100 ton air cooled chiller serving JECC spaces HVAC equipment of Building X-132, located at Naval Station, Norfolk, VA.
Contractor Requirements:
1. Perform work in accordance with the following industry standards and government requirements, (attached):
a. ASHRAE Standard 135 BACnet™ A Data Communication Protocol for Building Automation and Control Networks
b. International Code (IMC) latest edition
c. NFPA 70 National Electric Code, Latest edition.
2. Generate and provide all submittals in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES as applicable. (attached)
3. Perform a thorough site visit before preparing bid for any work associated with this project.
4. Provide all materials new, unless specifically noted as existing or provided by the government.
5. Provide and install all required materials in accordance with manufacturer’s written instructions.
6. Contractor is responsible for proper disposal of all unused and demolished.
7. Any potential issues observed during the Pre-Award walk-through that may conflict with these documents must be brought to the attention of the Contracting Officer.
8. Work must be accomplished in and around areas which will remain in operation.
Accordingly, measures shall be taken to avoid interference with the operational work routine.
9. Provide protection for existing conduit, light fixtures, pipes, furniture, finishes and other building accoutrements to remain during work.
10. Where existing components to remain are damaged due to demolition or new construction required by these documents, Contractor must repair the damaged item(s) with new materials to match the adjacent material, texture, and color.
11. Shore all demolition as required to maintain a safe and controlled work environment.
12. Refer to all instructions provided by the other engineering disciplines or trades.
13. Provide equipment ground wire when installed with feeders and branch circuits.
14. Coordinate work between all disciplines prior to fabrication and installation to prevent conflicts. Notify the Contracting Officer, in writing, where conflicts are discovered prior to construction and before beginning work in these areas. Contractor must rectify conflicts that arise due to lack of coordination at no cost to the government.
15. Submit and obtain a written permit from the Fire Division prior to performing “Hot
Work” (welding, cutting, etc.) or operating other flame-producing / spark-producing devices. Provide at least two (2) twenty (20) pound 4A:20 BC rated extinguishers for normal “Hot Work”. All extinguishers must be current inspection tagged, approved safety pin, and tamper resistant seal. When starting work in the facility, require that all personnel familiarize themselves with the location of the nearest fire alarm boxes and place in memory the emergency Fire Division phone number. Any fire, no matter how small, must be immediately reported to the Fire Division.
16. Notify the Contracting Officer, in writing, when the contract work is complete for an inspection to be performed by this office. Contract will not be considered complete until a satisfactory record of inspection is granted.
Work must be completed as listed below:
REPLACE ROOF TOP CHILLER, according to the Scope of Work listed on Project Drawings, attached.
ELECTRICAL SUPPORT
1. Provide electrical support for the following:
a. Lock-out and tag-out.
b. Locate existing and/or provide power circuits required for a complete and working system in strict accordance with the equipment manufacturer’s written instructions. Comply with The National Electric Code, NFPA 70.
Required submittals from Contractor for Government review and approval:
Provide submittals as required by the attached drawings.
Attachments:
1. Specification Section 01 33 00 SUBMITTAL PROCEDURES
2. Project Drawings M-101 & M-701
Attachment 1:
UFGS SECTION 01 33 00
SUBMITTAL PROCEDURES
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
08/18
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 Submittal Descriptions (SD)
1.1.2 Approving Authority
1.1.3 Work
1.2 SUBMITTALS
1.3 SUBMITTAL CLASSIFICATION
1.3.1 Government Approved (G)
1.3.2 For Information Only
1.4 FORWARDING SUBMITTALS REQUIRING GOVERNMENT APPROVAL
1.4.1 O&M Data
1.5 PREPARATION
1.5.1 Transmittal Form
1.5.2 Identifying Submittals
1.5.3 Submittal Format
1.5.3.1 Format of SD-01 Preconstruction Submittals
1.5.3.2 Format for SD-02 Shop Drawings
1.5.3.2.1 Drawing Identification
1.5.3.3 Format of SD-03 Product Data
1.5.3.3.1 Product Information
1.5.3.3.2 Standards
1.5.3.3.3 Data Submission
1.5.3.4 Format of SD-04 Samples
1.5.3.4.1 Sample Characteristics
1.5.3.4.2 Sample Incorporation
1.5.3.4.3 Comparison Sample
1.5.3.5 Format of SD-05 Design Data
1.5.3.6 Format of SD-06 Test Reports
1.5.3.7 Format of SD-07 Certificates
1.5.3.8 Format of SD-08 Manufacturer's Instructions
1.5.3.8.1 Standards
1.5.3.9 Format of SD-09 Manufacturer's Field Reports
1.5.3.10 Format of SD-11 Closeout Submittals
1.5.4 Source Drawings for Shop Drawings
1.5.4.1 Source Drawings
1.5.4.2 Terms and Conditions
1.5.5 Electronic File Format
1.6 QUANTITY OF SUBMITTALS
1.6.1 Number of SD-01 Preconstruction Submittal Copies
1.6.2 Number of SD-04 Samples
1.7 INFORMATION ONLY SUBMITTALS
1.8 PROJECT SUBMITTAL REGISTER
1.8.1 Submittal Management
1.8.2 Preconstruction Use of Submittal Register
1.8.3 Contractor Use of Submittal Register
SECTION 01 33 00 Page 1
1.8.4 Approving Authority Use of Submittal Register
1.8.5 Action Codes
1.8.5.1 Government Review Action Codes
1.8.6 Delivery of Copies
1.9 VARIATIONS
1.9.1 Considering Variations
1.9.2 Proposing Variations
1.9.3 Warranting that Variations are Compatible
1.10 SCHEDULING
1.10.1 Reviewing, Certifying, and Approving Authority
1.10.2 Constraints
1.10.3 QC Organization Responsibilities
1.11 GOVERNMENT APPROVING AUTHORITY
1.11.1 Review Notations
1.12 DISAPPROVED SUBMITTALS
1.13 APPROVED SUBMITTALS
1.14 APPROVED SAMPLES
PART 2 PRODUCTS
PART 3 EXECUTION
ATTACHMENTS:
Appendix A - Submittal Register
-- End of Section Table of Contents --
SECTION 01 33 00 Page 2
SECTION 01 33 00
SUBMITTAL PROCEDURES
08/18
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 Submittal Descriptions (SD)
Submittal requirements are specified in the technical sections. Examples and descriptions of submittals identified by the Submittal Description (SD) numbers and titles follow:
SD-01 Preconstruction Submittals
Submittals that are required prior to or commencing with the start of work on site.
For Government approved division 01 preconstruction submittals that are required prior to or commencing with the start of work shall be submitted within 30 calendar days of contract award unless specified elsewhere in the specifications. For contractor approved division 01 submittals that are required prior to or commencing with the start of work shall be submitted within 45 calendar days of contract award unless specified elsewhere in the specifications.
Preconstruction Submittals include schedules and a tabular list of locations, features, and other pertinent information regarding products, materials, equipment, or components to be used in the work.
Certificates Of Insurance
Surety Bonds
List Of Proposed Subcontractors
List Of Proposed Products
Baseline Network Analysis Schedule (NAS)
Submittal Register
Schedule Of Prices Or Earned Value Report
Accident Prevention Plan
Work Plan
SECTION 01 33 00 Page 3
Quality Control (QC) plan
SD-02
SD-02 Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.
Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.
Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.
Samples of warranty language when the contract requires extended product warranties.
SD-05 Design Data
Design calculations, mix designs, analyses or other data pertaining to a part of work.
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.
Report that includes findings of a test required to be performed on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report that includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports
Daily logs and checklists
Final acceptance test and operational test procedure
SD-10 Operation and Maintenance Data
Data provided by the manufacturer, or the system provider, including
SECTION 01 33 00 Page 4 manufacturer's help and product line documentation, necessary to maintain and install equipment, for operating and maintenance use by facility personnel.
Data required by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.
Data incorporated in an operations and maintenance manual or control system.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).
Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
1.1.2 Approving Authority
Office or designated person authorized to approve the submittal.
1.1.3 Work
As used in this section, on-site and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction. In exception, excludes work to produce SD-01 submittals.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor QC approval.
Submit the following in accordance with this section.
SD-01 Preconstruction Submittals
Submittal Register; G
1.3 SUBMITTAL CLASSIFICATION
1.3.1 Government Approved (G)
Government approval is required for extensions of design, critical materials, variations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Government.
Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, submittals are considered to be "shop drawings."
1.3.2 For Information Only
Submittals not requiring Government approval will be for information
SECTION 01 33 00 Page 5 only. Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are not considered to be "shop drawings."
1.4 FORWARDING SUBMITTALS REQUIRING GOVERNMENT APPROVAL
As soon as practicable after award of contract, and before procurement or fabrication, forward to the Commander, NAVFAC MIDLANT Naval Station Norfolk, Public Works Dept. submittals required in the technical sections of this specification, including shop drawings, product data and samples.
In addition, forward a copy of the submittals to the Contracting Officer.
1.4.1 O&M Data
Submit data specified for a given item within 30 calendar days after the item is delivered to the contract site.
In the event the Contractor fails to deliver O&M data within the time limits specified, the Contracting Officer may withhold from progress payments 50 percent of the price of the items to which such O&M data apply.
1.5 PREPARATION
1.5.1 Transmittal Form
Transmit each submittal, except sample installations and sample panels to the office of the approving authority using the transmittal form prescribed by the Contracting Officer. Include all information prescribed by the transmittal form and required in paragraph IDENTIFYING SUBMITTALS.
Use the submittal transmittal forms to record actions regarding samples.
1.5.2 Identifying Submittals
The Contractor's Quality Control Manager must prepare, review and stamp submittals, including those provided by a subcontractor, before submittal to the Government.
Identify submittals, except sample installations and sample panels, with the following information permanently adhered to or noted on each separate component of each submittal and noted on transmittal form. Mark each copy of each submittal identically, with the following:
a. Project title and location
b. Construction contract number
c. Dates of the drawings and revisions
d. Name, address, and telephone number of Subcontractor, supplier, manufacturer, and any other Subcontractor associated with the submittal.
e. Section number of the specification by which submittal is required
f. Submittal description (SD) number of each component of submittal
g. For a resubmission, add alphabetic suffix on submittal description, for example, submittal 18 would become 18A, to indicate resubmission
SECTION 01 33 00 Page 6
h. Product identification and location in project.
1.5.3 Submittal Format
1.5.3.1 Format of SD-01 Preconstruction Submittals
When the submittal includes a document that is to be used in the project, or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.
Provide data in the unit of measure used in the contract documents.
1.5.3.2 Format for SD-02 Shop Drawings
Provide shop drawings not less than 8 1/2 by 11 inches nor more than 30 by 42 inches, except for full-size patterns or templates. Prepare drawings to accurate size, with scale indicated, unless another form is required.
Ensure drawings are suitable for reproduction and of a quality to produce clear, distinct lines and letters, with dark lines on a white background.
a. Include the nameplate data, size, and capacity on drawings. Also include applicable federal, military, industry, and technical society publication references.
b. Dimension drawings, except diagrams and schematic drawings. Prepare drawings demonstrating interface with other trades to scale. Use the same unit of measure for shop drawings as indicated on the contract drawings. Identify materials and products for work shown.
Submit an electronic copy of drawings in PDF format.
1.5.3.2.1 Drawing Identification
Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to information required in paragraph
IDENTIFYING SUBMITTALS.
Number drawings in a logical sequence. Each drawing is to bear the number of the submittal in a uniform location next to the title block. Place the Government contract number in the margin, immediately below the title block, for each drawing.
1.5.3.3 Format of SD-03 Product Data
Present product data submittals for each section. Include a table of contents, listing the page and catalog item numbers for product data.
Indicate, by prominent notation, each product that is being submitted;
indicate the specification section number and paragraph number to which it pertains.
1.5.3.3.1 Product Information
Supplement product data with material prepared for the project to satisfy the submittal requirements where product data does not exist. Identify this material as developed specifically for the project, with information and format as required for submission of SD-07 Certificates.
SECTION 01 33 00 Page 7
Provide product data in units used in the Contract documents. Where product data are included in preprinted catalogs with another unit, submit the dimensions in contract document units, on a separate sheet.
1.5.3.3.2 Standards
Where equipment or materials are specified to conform to industry or technical-society reference standards of such organizations as the American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), or Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing organization, competent to perform testing, and approved by the Contracting Officer. State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.
1.5.3.3.3 Data Submission
Collect required data submittals for each specific material, product, unit of work, or system into a single submittal that is marked for choices, options, and portions applicable to the submittal. Mark each copy of the product data identically. Partial submittals will not be accepted for expedition of the construction effort.
Submit the manufacturer's instructions before installation.
1.5.3.4 Format of SD-04 Samples
1.5.3.4.1 Sample Characteristics
Furnish samples in the following sizes, unless otherwise specified or unless the manufacturer has prepackaged samples of approximately the same size as specified:
a. Sample of Equipment or Device: Full size.
b. Sample of Materials Less Than 2 by 3 inches: Built up to 8 1/2 by 11 inches.
c. Sample of Materials Exceeding 8 1/2 by 11 inches: Cut down to 8 1/2 by 11 inches and adequate to indicate color, texture, and material variations.
d. Sample of Linear Devices or Materials: 10 inch length or length to be supplied, if less than 10 inches. Examples of linear devices or materials are conduit and handrails.
e. Sample Volume of Nonsolid Materials: Pint. Examples of nonsolid materials are sand and paint.
f. Color Selection Samples: 2 by 4 inches. Where samples are specified for selection of color, finish, pattern, or texture, submit the full set of available choices for the material or product specified. Sizes and quantities of samples are to represent their respective standard
SECTION 01 33 00 Page 8 unit.
g. Sample Panel: 4 by 4 feet.
h. Sample Installation: 100 square feet.
1.5.3.4.2 Sample Incorporation
Reusable Samples: Incorporate returned samples into work only if so specified or indicated. Incorporated samples are to be in undamaged condition at the time of use.
Recording of Sample Installation: Note and preserve the notation of any area constituting a sample installation, but remove the notation at the final clean-up of the project.
1.5.3.4.3 Comparison Sample
Samples Showing Range of Variation: Where variations in color, finish, pattern, or texture are unavoidable due to nature of the materials, submit sets of samples of not less than three units showing extremes and middle of range. Mark each unit to describe its relation to the range of the variation.
1.5.3.5 Format of SD-05 Design Data
Provide design data and certificates on 8 1/2 by 11 inch paper.
1.5.3.6 Format of SD-06 Test Reports
By prominent notation, indicate each report in the submittal. Indicate the specification number and paragraph number to which each report pertains.
1.5.3.7 Format of SD-07 Certificates
Provide design data and certificates on 8 1/2 by 11 inch paper.
1.5.3.8 Format of SD-08 Manufacturer's Instructions
Present manufacturer's instructions submittals for each section. Include the manufacturer's name, trade name, place of manufacture, and catalog model or number on product data. Also include applicable federal, military, industry, and technical-society publication references. If supplemental information is needed to clarify the manufacturer's data, submit it as specified for SD-07 Certificates.
Submit the manufacturer's instructions before installation.
1.5.3.8.1 Standards
Where equipment or materials are specified to conform to industry or technical-society reference standards of such organizations as the American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), or Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance. In lieu of the label or listing, submit a certificate from an independent testing
SECTION 01 33 00 Page 9 organization, competent to perform testing, and approved by the Contracting Officer. State on the certificate that the item has been tested in accordance with the specified organization's test methods and that the item complies with the specified organization's reference standard.
1.5.3.9 Format of SD-09 Manufacturer's Field Reports
By prominent notation, indicate each report in the submittal. Indicate the specification number and paragraph number to which each report pertains.
1.5.3.10 Format of SD-11 Closeout Submittals
When the submittal includes a document that is to be used in the project or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document.
Provide data in the unit of measure used in the contract documents.
1.5.4 Source Drawings for Shop Drawings
1.5.4.1 Source Drawings
The entire set of source drawing files (DWG) will not be provided to the Contractor. Request the specific Drawing Number for the preparation of shop drawings. Only those drawings requested to prepare shop drawings will be provided. These drawings are provided only after award.
1.5.4.2 Terms and Conditions
Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse is at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor must make no claim, and waives to the fullest extent permitted by law any claim or cause of action of any nature against the Government, its agents, or its subconsultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities, or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These electronic source drawing files are not construction documents.
Differences may exist between the source drawing files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic source drawing files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. The Contractor is responsible for determining if any conflict exists. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished source drawing files, the signed and sealed construction documents govern. Use of these source drawing files does not relieve the Contractor of the duty to fully comply with the contract documents, including and without limitation the need to check, confirm and coordinate the work of all contractors for the project. If the Contractor uses, duplicates or modifies these electronic source drawing files for use in producing construction data related to
SECTION 01 33 00 Page 10 this contract, remove all previous indication of ownership (seals, logos, signatures, initials and dates).
1.5.5 Electronic File Format
Provide submittals in electronic format, with the exception of material samples required for SD-04 Samples items. Compile the submittal file as a single, complete document, to include the Transmittal Form described within. Name the electronic submittal file specifically according to its contents, and coordinate the file naming convention with the Contracting Officer. Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer. Generate PDF files from original documents with bookmarks so that the text included in the PDF file is searchable and can be copied. If documents are scanned, optical character resolution (OCR) routines are required. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature or a scan of a signature.
E-mail electronic submittal documents smaller than 10MB to an e-mail address as directed by the Contracting Officer. Provide electronic documents over 10 MB on an optical disc or through an electronic file sharing system such as the AMRDEC SAFE Web Application located at the following website: https://safe.amrdec.army.mil/safe/.
1.6 QUANTITY OF SUBMITTALS
1.6.1 Number of SD-01 Preconstruction Submittal Copies
Unless otherwise specified, submit electronic copies of administrative submittals.
1.6.2 Number of SD-04 Samples
a. Submit one set of samples showing the range of variation, of each required item.
b. Submit one sample panel or provide one sample installation where directed. Include components listed in the technical section or as directed.
c. Submit one sample installation, where directed.
d. Submit one sample of nonsolid materials.
1.7 INFORMATION ONLY SUBMITTALS
Submittals without a "G" designation must be certified by the QC manager and submitted to the Contracting Officer for information-only. Approval of the Contracting Officer is not required on information only submittals. The Contracting Officer will mark "receipt acknowledged" on submittals for information and will return only the transmittal cover sheet to the Contractor. Normally, submittals for information only will not be returned. However, the Government reserves the right to return unsatisfactory submittals and require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from
SECTION 01 33 00 Page 11 requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
1.8 PROJECT SUBMITTAL REGISTER
A sample Project Submittal Register showing items of equipment and materials for when submittals are required by the specifications is provided as "Appendix A - Submittal Register."
1.8.1 Submittal Management
Prepare and maintain a submittal register, as the work progresses. Do not change data that is output in columns (c), (d), (e), and (f) as delivered by Government; retain data that is output in columns (a), (g), (h), and
(i) as approved. As an attachment, provide a submittal register showing items of equipment and materials for which submittals are required by the specifications. This list may not be all-inclusive and additional submittals may be required.
Column (c): Lists specification section in which submittal is required.
Column (d): Lists each submittal description (SD Number. and type, e.g., SD-02 Shop Drawings) required in each specification section.
Column (e): Lists one principal paragraph in each specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting the project requirements.
Column (f): Lists the approving authority for each submittal.
Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns and all dates on which submittals are received by and returned by the Government.
1.8.2 Preconstruction Use of Submittal Register
Submit the submittal register. Include the QC plan and the project schedule. Verify that all submittals required for the project are listed and add missing submittals. Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule:
Column (a) Activity Number: Activity number from the project schedule.
Column (g) Contractor Submit Date: Scheduled date for the approving authority to receive submittals.
Column (h) Contractor Approval Date: Date that Contractor needs approval of submittal.
Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.
SECTION 01 33 00 Page 12
1.8.3 Contractor Use of Submittal Register
Update the following fields with each submittal throughout the contract.
Column (b) Transmittal Number: List of consecutive, Contractor-assigned numbers.
Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.
Column (l) Date submittal transmitted.
Column (q) Date approval was received.
1.8.4 Approving Authority Use of Submittal Register
Update the following fields:
Column (b) Transmittal Number: List of consecutive, Contractor-assigned numbers.
Column (l) Date submittal was received.
Column (m) through (p) Dates of review actions.
Column (q) Date of return to Contractor.
1.8.5 Action Codes
1.8.5.1 Government Review Action Codes
"A" - "Approved as submitted"
"AN" - "Approved as noted"
"RR" - "Disapproved as submitted"; "Completed"
"NR" - "Not Reviewed"
"RA" - "Receipt Acknowledged"
1.8.6 Delivery of Copies
Submit an updated electronic copy of the submittal register to the Contracting Officer with each invoice request. Provide an updated Submittal Register monthly regardless of whether an invoice is submitted.
1.9 VARIATIONS
Variations from contract requirements require Contracting Officer approval pursuant to contract Clause FAR 52.236-21 Specifications and Drawings for Construction, and will be considered where advantageous to the Government.
1.9.1 Considering Variations
Discussion of variations with the Contracting Officer before submission will help ensure that functional and quality requirements are met and
SECTION 01 33 00 Page 13 minimize rejections and resubmittals.
Specifically point out variations from contract requirements in a variation submittal. Failure to point out variations may cause the Government to require rejection and removal of such work at no additional cost to the Government.
1.9.2 Proposing Variations
Specifically point out variations from contract requirements in a variation submittal. Failure to point out variations may cause the Government to require rejection and removal of such work at no additional cost to the Government.
1.9.3 Warranting that Variations are Compatible
When delivering a variation for approval, the Contractor warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.10 SCHEDULING
Schedule and submit concurrently product data and shop drawings covering component items forming a system or items that are interrelated. Submit pertinent certifications at the same time. No delay damages or time extensions will be allowed for time lost in late submittals. Allow an additional 10 working days for review and approval of submittals for refrigeration and HVAC control systems.
a. Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. The Contractor is responsible for additional time required for Government reviews resulting from required resubmittals. The review period for each resubmittal is the same as for the initial submittal.
b. Submittals required by the contract documents are listed on the submittal register. If a submittal is listed in the submittal register but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but that have been omitted from the register or marked "N/A."
c. Resubmit the submittal register and annotate it monthly with actual submission and approval dates. When all items on the register have been fully approved, no further resubmittal is required.
Contracting Officer review will be completed within 15 working days after the date of submission.
SECTION 01 33 00 Page 14
e. For submittals requiring review by a Government fire protection engineer, allow a review period, beginning when the Government receives the submittal from the QC organization, of 20 working days for return of the submittal to the Contractor.
1.10.1 Reviewing, Certifying, and Approving Authority
The QC Manager is responsible for reviewing all submittals and certifying that they are in compliance with contract requirements. The approving authority on submittals is the QC Manager unless otherwise specified. At each "Submittal" paragraph in individual specification sections, a notation "G" following a submittal item indicates that the Contracting Officer is the approving authority for that submittal item. Provide an additional copy of the submittal to the Government Approving authority
1.10.2 Constraints
Conform to provisions of this section, unless explicitly stated otherwise for submittals listed or specified in this contract.
Submit complete submittals for each definable feature of the work. At the same time, submit components of definable features that are interrelated as a system.
When acceptability of a submittal is dependent on conditions, items, or materials included in separate subsequent submittals, the submittal will be returned without review.
Approval of a separate material, product, or component does not imply approval of the assembly in which the item functions.
1.10.3 QC Organization Responsibilities
a. Review submittals for conformance with project design concepts and compliance with contract documents.
b. Process submittals based on the approving authority indicated in the submittal register.
(1) When the QC manager is the approving authority, take appropriate action on the submittal from the possible actions defined in paragraph APPROVED SUBMITTALS.
(2) When the Contracting Officer is the approving authority or when variation has been proposed, forward the submittal to the Government, along with a certifying statement, or return the submittal marked "not reviewed" or "revise and resubmit" as appropriate. The QC organization's review of the submittal determines the appropriate action.
c. Ensure that material is clearly legible.
d. Stamp each sheet of each submittal with a QC certifying statement or an approving statement, except that data submitted in a bound volume or on one sheet printed on two sides may be stamped on the front of the first sheet only.
(1) When the approving authority is the Contracting Officer, the QC organization will certify submittals forwarded to the Contracting
SECTION 01 33 00 Page 15
Officer with the following certifying statement:
"I hereby certify that the (equipment) (material) (article) shown and marked in this submittal is that proposed to be incorporated is in compliance with the contract drawings and specification, can be installed in the allocated spaces, and is submitted for Government approval.
Certified by Submittal Reviewer _____________________, Date _______ (Signature when applicable)
Certified by QC Manager _____________________________, Date ______" (Signature)
(2) When approving authority is the QC manager, the QC manager will use the following approval statement when returning submittals to the Contractor as "Approved" or "Approved as Noted."
"I hereby certify that the (material) (equipment) (article) shown and marked in this submittal and proposed to be incorporated is in compliance with the contract drawings and specification, can be installed in the allocated spaces, and is approved for use.
Certified by Submittal Reviewer ______________________, Date ______ (Signature when applicable)
Approved by QC Manager _______________________________, Date _____" (Signature)
e. Sign the certifying statement or approval statement. The QC organization member designated in the approved QC plan is the person signing certifying statements. The use of original ink for signatures is required. Stamped signatures are not acceptable.
f. Update the submittal register as submittal actions occur, and maintain the submittal register at the project site until final acceptance of all work by the Contracting Officer.
g. Retain a copy of approved submittals and approved samples at the project site.
h. For "S" submittals, provide a copy of the approved submittal to the Government Approving authority.
1.11 GOVERNMENT APPROVING AUTHORITY
When the approving authority is the Contracting Officer, the Government will:
a. Note the date on which the submittal was received from the QC manager.
b. Review submittals for approval within the scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
c. Identify returned submittals with one of the actions defined in paragraph REVIEW NOTATIONS and with comments and markings appropriate for the action indicated.
SECTION 01 33 00 Page 16
Upon completion of review of submittals requiring Government approval, stamp and date submittals. Electronic copies of the submittal will be retained by the Contracting Officer and electronic copies of the submittal will be returned to the Contractor.
1.11.1 Review Notations
Submittals will be returned to the Contractor with the following notations:
a. Submittals marked "approved" or "accepted" authorize proceeding with the work covered.
b. Submittals marked "approved as noted" or "approved, except as noted, resubmittal not required," authorize proceeding with the work covered provided that the Contractor takes no exception to the corrections.
c. Submittals marked "not approved," "disapproved," or "revise and resubmit" indicate incomplete submittal or noncompliance with the contract requirements or design concept. Resubmit with appropriate changes. Do not proceed with work for this item until the resubmittal is approved.
d. Submittals marked "not reviewed" indicate that the submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.
e. Submittals marked "receipt acknowledged" indicate that submittals have been received by the Government. This applies only to "information-only submittals" as previously defined.
1.12 DISAPPROVED SUBMITTALS
Make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications, give notice to the Contracting Officer as required under the FAR clause titled CHANGES. The Contractor is responsible for the dimensions and design of connection details and the construction of work. Failure to point out variations may cause the Government to require rejection and removal of such work at the Contractor's expense.
If changes are necessary to submittals, make such revisions and resubmit in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
1.13 APPROVED SUBMITTALS
The Contracting Officer's approval of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing, and other information are satisfactory.
Approval or acceptance by the Government for a submittal does not relieve the Contractor of the responsibility for meeting the contract requirements or for any error that may exist, because under the Quality Control (QC)
SECTION 01 33 00 Page 17 requirements of this contract, the Contractor is responsible for ensuring information contained with in each submittal accurately conforms with the requirements of the contract documents.
After submittals have been approved or accepted by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
1.14 APPROVED SAMPLES
Approval of a sample is only for the characteristics or use named in such approval and is not be construed to change or modify any contract requirements. Before submitting samples, provide assurance that the materials or equipment will be available in quantities required in the project. No change or substitution will be permitted after a sample has been approved.
Match the approved samples for materials and equipment incorporated in the work. If requested, approved samples, including those that may be damaged in testing, will be returned to the Contractor, at its expense, upon completion of the contract. Unapproved samples will also be returned to the Contractor at its expense, if so requested.
Failure of any materials to pass the specified tests will be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make as that material. The Government reserves the right to disapprove any material or equipment that has previously proved unsatisfactory in service.
Samples of various materials or equipment delivered on the site or in place may be taken by the Contracting Officer for testing. Samples failing to meet contract requirements will automatically void previous approvals. Replace such materials or equipment to meet contract requirements.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
SECTION 01 33 00 Page 18
Attachment 2:
Drawings
M-101
N A
V A
L
FA
C
IL
IT
IE
S E
N G
IN
E
E R
IN
G
C O
M M
A N
D
M
ID
-A
TL
A N
TI
C
B
LD
G . X
-1
R E
P
LA
C E
R O
O
FT
O P
C H
IL
LE
R
M-701
A
V A
L
FA
C
IL
IT
IE
S E
N G
IN
E
E R
IN
G
C O
M M
A N
D
M
ID
-A
TL
A N
TI
C
B
LD
G . X
-1
R E
P
LA
C E
R O
O
FT
O P
C H
IL
LE
R
S-001
A
VY
P
U B
LI
C
W O
R K
S C
E N
TE
R
R E
P A
IR
S
A N
D R
E N
O
VA
TI
O
S
TO
B U
IL
D
IN
G
X -1
S-101
A
VY
P
U B
LI
C
W O
R K
S C
E N
TE
R
R E
P A
IR
S
A N
D R
E N
O
VA
TI
O
S
TO
B U
IL
D
IN
G
X -1
| X-132 - Steel Platform at Roof - 2003.pdf |
| G-001 |
| G-002 |
| H-101 |
| H-102 |
| H-103 |
| H-104 |
| H-105 |
| H-106 |
| H-107 |
| AD-101 |
| AD-102 |
| AD-103 |
| AD-104 |
| AD-105 |
| PD-101 |
| MD-101 |
| MD-102 |
| MD-103 |
| MD-104 |
| ED-101 |
| ED-102 |
| ED-103 |
| A-001 |
| A-101 |
| A-102 |
| A-103 |
| A-104 |
| A-105 |
| A-106 |
| A-107 |
| A-108 |
| A-109 |
| A-110 |
| A-301 |
| A-401 |
| A-402 |
| A-403 |
| A-404 |
| A-405 |
| A-406 |
| A-407 |
| A-408 |
| A-501 |
| A-502 |
| A-503 |
| A-504 |
| A-505 |
| A-506 |
| A-507 |
| A-508 |
| A-601 |
| A-602 |
| A-603 |
| A-604 |
| A-701 |
| S-001 |
| S-101 |
| P-001 |
| P-401 |
| P-402 |
| F-101 |
| M-001 |
| M-101 |
| M-102 |
| M-103 |
| M-104 |
| M-301 |
| M-401 |
| M-501 |
| M-502 |
| M-601 |
| M-701 |
| M-702 |
| E-001 |
| E-101 |
| E-102 |
| E-103 |
| E-104 |
| E-105 |
| E-106 |
| E-107 |
| E-108 |
| E-109 |
| E-401 |
| E-402 |
| E-501 |
| E-502 |
| E-503 |
| E-504 |
| E-505 |
| E-601 |
| E-602 |
| E-603 |
| X132-1722311-M-101.pdf |
| Sheets and Views |
| M-101 |
| X132-1722311-M-701.pdf |
| Sheets and Views |
| M-701 |