AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICIATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 11)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

N40085‐24‐R‐2652 Amendment 0003

Con nua on Sheet

Document, Section Question

CLNC 41 22 13.15 BRIDGE CRANE

OVERHEAD ELEC UNDER RUNNING

TROLLEY,Page 34, Paragraph 3.3

ERECTION AND INSTALLATION

DOES THE GOVERNMENT REQUIRE THE CRANE SYSTEM TO BE INSTALLED

USING NAVFAC P307 TRAINED PERSONNEL TO ENSURE ALL GOVERNMENT

REQUIREMENTS ARE MET?

Answer: Correct

24‐0400 1047 Bridge Crane ‐ SOW;

Specifications: Page 6, Specifications

CAN THE GOVERNMENT PROVIDE THE CONCRETE PSI AND THICKNESS OF

FLOOR WHERE CRANE SYSTEM IS TO BE INSTALLED?

Answer: See a achment: 1047 S DRAWING BOAT SHOP AND ATTACHMENT:

12739701 N6 BOAT SHOP

DRAWING SHOP 6” CONCRETE, NO psi DATA FOUND.

24‐0400 1047 Bridge Crane ‐ SOW;

Specifications: Page 6, Specifications

JUST TO VERIFY DOES THE GOVERNMENT DESIRE THE CRANE SYSTEM AND

HOIST TO MEET ALL REQUIREMENTS OF THE NAVCRANECENINST 11450.2A?

Answer: Correct

Combined DIV 01 specs small projects, Page 24/235, Section 01 31 50 Part 1.1 Submittals, SD‐11 Closeout Submittals AND Section 41 22 13.15 page 11 ‐ 14/39, Section 1.6 Quality Assurance

DOES THE GOVERNMENT DESIRE THE CRANE PROVIDER/INSTALLER

PROVIDE ALL NAVY PRODUCT SUBMITTALS, CERTIFICATES, LOAD TEST, NDT,

MISR, CCIR, BRAKE SPECIFICATIONS AS PART OF INSTALLATION?

Answer: Correct

CLNC 41 22 13.15 BRIDGE CRANE

OVERHEAD ELEC UNDER RUNNING

TROLLEY, page 36/39, Paragraph 3.4.5 Load Tests AND page 35/39 Section

3.4.2 Operational Tests

DOES THE GOVERNMENT REQUIRE THE CRANE PROVIDER/INSTALLER TO

PROVIDE LOAD TEST WEIGHTS AND NAVFAC CERTIFIED LOAD TEST

DIRECTOR TO PERFORM LOAD TESTING IAW THE NAVFAC P307 AS PART OF

THE INSTALLATION?

Answer: Correct

CLNC 41 22 13.15 BRIDGE CRANE

OVERHEAD ELEC UNDER RUNNING

TROLLEY, page 39/39, paragraph 3.8

FINAL ACCEPTANCE

WILL THE CRANE PROVIDER/INSTALLER BE REQUIRED TO CORRECT ALL

ITEMS THAT DO NOT MEET THE UFGS 41 SERIES SPEC REQUIREMENT PRIOR

TO CRANE ACCEPTANCE?

Answer: Correct

24‐0400 1047 Bridge Crane ‐ SOW;

Specifications: Page 6, Specifications

CAN THE FREESTANDING CRANE SYSTEM BE BRACED BACK TO THE

BUILDING TO STABILIZE AND REDUCE MOMENT OF INERTIA IF NEEDED?

Answer: Correct

24‐0400 1047 Bridge Crane ‐ SOW;

Specifications: Page 6, Specifications

ARE PE STAMPED ENGINEERING DRAWINGS REQUIRED ON CRANE RUNWAY

AND BRIDGE?

N40085‐24‐R‐2652 Amendment 0003

Con nua on Sheet

Answer: Correct

N/A

WILL THE GOVERNMENT PROVIDE A CLEAR UNOBSTRUCTED WORK SPACE

DURING INSTALLATION?

Answer: Correct, unit shall remove all obstacles in Contractor way, Contactor shall be responsible for the securing the bay area during the dura on of contract.

CLNC Section 41 22 13.15 page 39/39, paragraph 3.8 FINAL ACCEPTANCE

WILL THE GOVERNMENT HAVE THE BASE CRANE CERTIFYING OFFICIAL AT

ACCEPTANCE AND LOAD TESTING TO ENSURE THE CRANE IS IAW WITH THE

NAVCRANECENINST 11450.2A?

Answer: Contractors responsibility to no fy Base Crane Cer fier.

2. All other terms and condi ons remain unchanged.

24-0400 Amend 0003
Untitled
Untitled

24-0400 SF30 Continuation Page Amend 0003

IDCode:
Page: 1
Pages: 2
AmendNo: AMENDMENT NO. 0003
EffDate: 4/18/24
ReqNo:
ProjNo: 24-0400
IssCode: N40085
IssuedBy: NAVFAC Mid-Atlantic

Resident Officer in Charge of Construction 1107A Birch Street Camp Lejeune, NC 28547-2521

AdmCode:
AdminBy: See Item 6
ContName:
ContStrt:
ContCnty:
ContSt:
ContZIP:
Code:
FacCode:
SolChgYs: Yes
SolChgNo: Off
SolAmdNo: N40085-24-R-2652
AmendDate: 3-13-24
ModNo:
ModDate:
NoCopies: 1
Amended: Yes
OffrExt: Off
OffrNoEx: No
ApprData:
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: 24-0400, 1047 Bridge Crane

Amendment 0003, Answer Requests for information

This amendment should be acknowledged when your proposal is submitted. Failure to acknowledge the amendment may constitute grounds for rejection of a proposal.