PPIs (1-5)- NNSY Horizontal Lifeline Inspection.xlsx
XLSX spreadsheet 22 KB Posted
- Solicitation number
- N4008522Q2510
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0001.pdf | ||
| Building Reports.pdf | ||
| N4008522Q2510 RFQ.pdf | ||
| Pre-Proposal Inquiry Form.xlsx | XLSX spreadsheet | |
| ODP Badge Spreadsheet.xlsx | XLSX spreadsheet | |
| SECNAV 5512 1 form.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| PRE-BID QUESTIONS | |||
| NNSY Horizontal Lifelines Inspection, N4008522Q2510 | |||
| # | Question | Date Submitted | Gov't Response |
| 1 | Please describe the difference between the “New” versus “Old” set of Horizontal Lifelines listed in SOW Item #1 | 4/21/22 | The difference is the way they were anchored on each column and at the end points as apposed to the new system installed now. The new system also allows the inspector to use a sala cable attachment on the lanyard that will let them pass through each connection point while inspecting the rail rather than unhooking their safety belt hook at each point. The old style cable system does not have that availability. |
| 2 | Are all of the lifelines in this RFQ currently being inspected annually? | 4/21/22 | The liflines have been annually inspected. |
| 3 | On SOW Page 3, Contractor Item #3 – it describes some items for ‘testing’ and some items for ‘checking’. Please provide testing protocol to be followed for any testing to be completed. Also, please verify that ‘checking’ simply implies visual and/or tightening checks with no NDT required. | 4/21/22 | The lifelines need to Recertified according to the SOW. |
| 4 | It is understood that aerial lifts may be required on some of the buildings, but other buildings would be accessed via ladders and/or the crane itself. Can you please structure the bid form to simply remove aerial lifts from the base bid, and add them as a separate ‘allowance’ that may or may not be needed to ensure base bids are on equal scope? | 4/21/22 | The Contractor's Proposal to include all equipment to complete the task. |
| 5 | Please supply the list of horizontal lifelines associated with the cranes from the Crane & Rail group as discussed during the walkdown. | 4/21/22 | The life lines were list per building in the SOW. |