22B2507 Amendment 0002.pdf
PDF 172 KB Posted
- Solicitation number
- N4008522B2507
About this file
This solicitation notice seeks bids for a regional indefinite delivery indefinite quantity roofing repair and replacement contract at various government sites in the greater Hampton Roads, Virginia area. The contract will have a base year and four option years, not to exceed 60 months total. The minimum guarantee is $5,000 to be issued via task order, covering the full contract term.
The work includes locating and repairing roof leaks, removing and replacing single-ply, modified bitumen, asphalt shingle, standing seam metal and Transite roofing systems. Limited demolition, repair and replacement of associated elements like siding and copings is also included. The contractor must furnish all labor, materials, equipment and management for task order work. One contract will be awarded as a small business set-aside for NAICS code 238160, with a size standard of $16.5M. Bids are due by the date specified in block 13A of the SF1442 form.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 22B2507 Amendment 0001.pdf | ||
| 22B2507 HR Roofing IDIQ IFB.pdf | ||
| Attachment D- Pre-Proposal Inquiry (PPI) Form.xlsx | XLSX spreadsheet | |
| Attachment A- Hampton Roads Roofing IDIQ.pdf | ||
| Attachment C - PIEE Vendor Access Instructions.pdf | ||
| Attachment B- ELINs Hampton Roads Roofing IDIQ Contract.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this Amendment is to provide responses to the Pre-Proposal Inquiries (PPIs).
SEE SF 30 BLOCK 14 CONTINUATION PAGE
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 09-Aug-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008522B2507
X 9B. DATED (SEE ITEM 11)
14-Jul-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
08-Aug-2022
CODE
NAVFACSYSCOM MID-ATLANTIC
CONTRACTING CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008522B2507
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0002
The purpose of this amendment is to provide the following:
1. Response to Pre-Proposal Inquiries (PPIs)
Solicitation: N40085-22-B-2507
PPI # Reference Question Response
Page
Section Paragraph
1 6 00 21 13 1.2 General
Overview of Contract
4 The government states "The Government contemplates that one contract will be awarded for this solicitation." Can the government please clarify if there is a opportunity for multiple awardees on this contract or is the government committed to only award one contract for the entire IDIQ?
Refer to 01 11 00 Summary of Work, Part 1 General, 1.2.1 Project Description - The Government contemplates one contract award with six administration offices resulting from this solicitation."
The Contract will be awarded as stated.
2 7 2 1 It is our understanding that basis of award shall be determined solely from pricing for base year and options. The roofing material market is very volatile and increasing monthly. For bidding purposes, are contractors to predict future increases for bid options (year 2,3,4,5), or are contractors to bid current pricing and government be prepared to make adjustments later via contract mods, etc?
In accordance with 52.222-30 Construction Wage Rate Requirements-- Price Adjustment under Clauses Incorporated by Reference, no future adjustments in contract price(s) are to be made. All bids shall include pricing for the base year and all option years as per the
IFB.
3 7 2 1 Due to the volatile material market, can government include FAR 16.203 'Economic Price Adjustment Clasue' into this contract?
This would be the only accurate way to receive competitive bids.
No, bid per IFB.
4 7 2 1 Due to the large amount of line items per option to provide pricing for, will government condsider granting an extension to the 8/16 bid date to ensure contractors have an adequate amount of time to firmly and accurately price out each item?
No, bid per IFB.
5 Attach ment B
A020 A020AA "Non pre-priced work (including material at contractor's bare cost also includes special equipment rental at contractor's bare cost)($150,000 shall remain as bid price)" - Can government further clarify what this means? Is this a $150,000 allowance for rental equipment needed by contractor to perform each line tiem unit cost?
The purpose of this line item is for work not included or covered by pre-priced items which includes the associated cost defined in Attachement B - "Description Of Contract Requirements" - "Scope Of Work"
6 Attach ment B
Is contractor to include mobilization costs for each individual line item?
Refer to Attachement B - "Description Of Contract Requirements" - "Scope Of Work" for clarification on what should be inclusive for each line item.
7 Attach ment B
A020 Can government further identify the intenstion and meaning of " Non pre-priced work, labor, and command interest work? Is this for contractor to take immediate action in the event of an emergency?
Refer to Attachement B - "Description Of Contract Requirements" - "Statement Of Work For Line Items" Column for 020AA, 020AB, and 020AC for further clarification of 020 - "Non Pre-Pried work, Labor, and Command Interest Work"
8 44 52.228-1 C Section 52.228-1 states that the Bid Guarantee shall be 20% of the bid price or $3M, whichever is less however the government has not released a Seed Project for this solicitation.
Is the Bid Guarantee 20% of the minimum 5,000 or of some other value?
Bid per clause 52.228-1 using the total bid price amount for the base year and all option years.
9 17 01 57 19 Temporary
Environmental Controls
3.3.1, 3.3.2 With regard to 3.3 Protection of Cultural Resources, these sections refer to drawings that depict existing archaeological and historical resources. However, no drawings were provided in the bid package. Can those be sent for review to aid in providing the correct scope and cost estimates?
Any applicable drawings will be provided after award to the awardee.
10 7 2. Basis of Award
1 Given the current climate of prices, the difficulty in this market is to gauge the actual price of building materials, shipping, and the cost of labor. Are the prices for line items we are proposing considered fixed (similar to the GSA schedule), or will they be used as the basis for an award?
Yes, prices for line items are Firm Fixed- Price.
11 N/A General Question
N/A Will Subcontractor experience be evaluated and considered?
Refer to the General Requirements, bid per
IFB.
12 N/A General Question
N/A How often will work orders be provided at the task order level? Is there an expectation of 3-5 per month?
Task orders will be issued as required in accordance with the terms of the contract.
13 N/A General Question/
IDIQ
N/A Will there only be one IDIQ awardee? Yes, the Contract will be awarded as stated.
Refer to 01 11 00 Summary of Work, Part 1 General, 1.2.1 Project Description - The Government contemplates one contract award with six administration offices resulting from this solicitation."
14 N/A General Question/ Due Date
N/A Considering the number of questions asked and when answers are provided, would the Government consider extending this opportunity to ensure that offerors have time to submit a compliant offer?
No, bid per IFB.
15 N/A General Question
N/A Can the government confirm that there are no font, spacing or page number requirements for any of the contractor-created attachments in the bid package?
Confirmed, bid per IFB.
(End of Summary of Changes)