Amnd 0001 20R4067 FINAL.pdf

PDF 499 KB Posted

Attached to
Design-Bid-Build FLO - Perimeter and Interior Fence Damage Repair - MCAS & OLFS
Solicitation number
N4008520R4067
Issued by

View the file

Other files

File Type Posted
Master PPI Form Template.xls XLS spreadsheet
6970349 SpecsAsOne.pdf PDF
RFP Perimeter and Interior Fence Damage Repair - MCAS_OLFS.pdf PDF
6970349 DrawingsAsOne.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICAITON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICIATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 11)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPIRATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

DBB FLO Perimeter and Interior Fence Damage Repair Solicitation N4008520R4067

Marine Corps Air Station Cherry Point, North Carolina Amendment 0001

Block 14. DESCRIPTION OF AMENDMENT (cont.)

A. The following provides the Government’s responses to preaward inquiries:

REFERENCE

Page Section Para.

QUESTION GOVERNMENT RESPONSE

CS903 Plans Detail shows rails in the middle of the panel. Can the rails be removed, or does it need to be crash rated What rating? What is the spacing of the pickets? Ameristar offers 3" or 1-7/16".

Per Government direction provided during design, decorative fence does not need to be crash-rated. Middle rails may be removed as long as the fence meets the requirements of UFC

4-022-03, MCO 5530.14A, and

ASTM F2814. Top and bottom rails are required. Spacing of the pickets shall be specified by the manufacturer. Current spacing is approximately 3” between pickets.

Does the ornamental fence need to match existing?

The design intent is to closely match the existing ornamental fencing. It should be noted that the existing ornamental fencing (along NC-101 in the vicinity of Cunningham Gate) contains reinforcing cable and is crash-rated. The new ornamental fencing does not need to be crash-rated, but should match in style and general dimensions (height, post spacing, picket spacing, picket appearance, color, etc.).

B. All other contract terms and conditions remain unchanged.

Amnd 0001 20R4067
Untitled
Untitled

Pg2 Amnd 0001 20R4067

IDCode:
Page: 1
Pages: 2
AmendNo: AMENDMENT NO. 0001
EffDate: 04/16/20
ReqNo:
ProjNo: 1634279
IssCode: ACQ1
IssuedBy: NAVAL FACILITIES ENGINEERING COMMAND, MID-ATLANTIC

9742 MARYLAND AVENUE

NORFOLK, VA 23511-3095

AdmCode:
AdminBy: See Item 6
ContName:
ContStrt:
ContCnty:
ContSt:
ContZIP:
Code:
FacCode:
SolChgYs: Yes
SolChgNo: Off
SolAmdNo: N4008520R4067
AmendDate: 03/19/20
ModNo:
ModDate:
NoCopies: 1
Amended: Yes
OffrExt: Off
OffrNoEx: No
ApprData:
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript:

N4008520R4067 FLO Perimeter and Interior Fence Damage Repair - MCAS & OLFS

The date and the hour for the receipt of proposals is remains 23 April 2020 no later than 2:00 pm (EDT).

See continuation page(s).

SignName:
SignTitl:
ContDate:
CoName:
CoTitle:
CODate: