PROJECT DESCRIPTION
This project will remove all apparent loose or cracked concrete areas along each cantilever walkway and deck and include the repair all balconies, cantilevers, and spalling. This project also requires exposed enforcing to be coated prior to spalling repairs, and a protective coating to be applied after repairs to walkways.
SPECIAL SCHEDULING
The facility/activity will remain in operation during the entire construction period. The Contractor shall conduct his operations so as to cause the least possible interference with normal operations of the facility/activity.
SUPERVISION
One person may fill the roles of Superintendent, Quality Control Manager, and Safety & Health Officer, if duly qualified for all three positions as defined in the project specification.