RM12-1896 Dry Dock 4 Renovations 16 Oct 2018 Industry Day Event - Synopsis
BOTTOM LINE UP FRONT:
NAVFAC government is seeking industry feedback for project RM12-1896 - Dry Dock 4 Renovations at Norfolk Naval Shipyard in Portsmouth, Virginia. The project includes:
Installation of temporary cofferdam to support construction
Construction of new caisson and repair of caisson seat
Structural repairs to dry dock floors and walls (includes pinning the dry dock floor via micropiling)
Repair of dry dock utility systems (includes: potable water, fire protection, salt water, sewer, oily waste, steam, electrical, and communication systems)
Renovation of pump well mechanical and electrical systems and architectural features (includes installation of three (3) 85,000 gallons per minute vertical mixed flow dewatering pumps)
The estimated range of construction cost for this project is $100-$250 million.
This will be an excellent opportunity for contractors with NAICS codes 237990 and similar construction experience to learn more about this upcoming project and meet the design team.
Please arrive by 1300 at the Portsmouth Renaissance Hotel, 425 Water Street, Portsmouth VA
23704. Due to security restrictions, a site visit will not be included as part of this event. During the presentation, the design team will provide a virtual walkthrough of the project environment.
Please contact the Contracting Officer, Mr. Philip Cole, for more information at philip.j.cole@navy.mil.
AGENDA:
October 16th, 2018 Portsmouth Renaissance Hotel, 425 Water St, Portsmouth, VA 23704
1300-1305 Introduction ………………….…….…Michelle Gooden, NAVFAC Contract Specialist
1305-1320 Opening Remarks …...CDR Ben Wainwright, NAVFAC PWD Portsmouth PWO and
Mr. Robert Fogel, NAVSEA Nuclear Equipment & Facilities Manager
1320-1420 Project Presentation – Technical………Ben Slaughter, NAVFAC Project Manager;
David Cortinas, Moffatt & Nichol Project Manager; and Moffatt & Nichol/Burns & McDonnell JV
Project Team
1420-1435 ………………...….………………….……………………………………………...…. Break
1435-1505 Project Presentation – Acquisition……………Michelle Gooden, NAVFAC Contract
Specialist
1505-1600 Q&A Session….NAVFAC and Moffatt & Nichol/Burns & McDonnell JV Project Team
GENERAL OVERVIEW
Dry Dock 4 is located at the Norfolk Naval Shipyard in Portsmouth, Virginia. The dry dock, constructed in 1919, supports repairing, overhauling, and modernizing ships and submarines.
The dry dock is approximately 1,012’ long, 144’ wide at coping level, and 51’ deep. The existing walls and floors are primarily unreinforced concrete. The existing caisson seat is granite blocks, and the caisson is of the older hydrometer style. Due to its age, Dry Dock 4 is in need of renovations to meet Navy certification requirements.
Figure 1 - Project Location
The RM12-1896 project includes, but is not limited to:
Demolition of existing caisson and caisson seat.
Construction of a temporary cofferdam.
Construction of new flood-through caisson and caisson seat. (Figure 2)
Pinning the dry dock floor with the installation of micropiles. (Figure 5)
Removal of up to 36” of concrete from the floor and 24” of concrete from the wall of the dry dock. (Figure 5) o Concrete removal program shall include provisions to repair leaking cracks.
Installation of precast concrete panels along dry dock walls. The top section of the wall will include an integral utility trench and extended coping wall to provide flood protection.
(Figure 4, 5)
Construction of a new dry dock floor with an integral trench drainage system. (Figure 3)
Filling of obsolete tunnels with flowable fill or self-consolidating concrete.
Relocation of dry dock utilities into proposed utility trench. Utilities include but are not limited to: compressed air, sanitary sewer, steam, potable water, fire protection, salt water, and oily waste. Note that electrical ductbanks will be located outside of the utility trench.
Renovation of electrical system that services Dry Dock 4.
o Includes, but not limited to: Pad mounted transformer and switch, jumper stations, ductbanks and associated cabling, turtlebacks, and lighting.
Renovation of telecommunication system that services Dry Dock 4.
Renovation of all pumpwell mechanical, electrical, fire alarm, and telecommunication systems, including (Figure 6):
o Main dewatering pumps
Three pumps with a proposed flow rate of 85,000 gpm per pump o Drainage pumps
Three pumps with a proposed flow rate of 5,000 gpm per pump o Sump Pumps
Two pumps with a proposed flow rate of 300 gpm per pump o HVAC o Lighting o Controls o Electrical infrastructure
Reconstruction of pumpwell roof system to meet a design flood elevation of 106. (Figure
6)
Renovation of pumpwell operations deck to provide a more functional layout and to meet life safety requirements.
The project’s contract will include a base and option. The base contract, referred to as
Phase 1, will consist of the temporary cofferdam and new caisson. Phase 1 award is planned for September 2019. Phase 2 will consist of all other work. Phase 2 award is planned for February 2020.
NOTE: All exhibits and figures included in this synopsis are preliminary and subject to change. They are not to be used for bidding or construction purposes.
Intentionally Blank – Proceed to Next Page
Figure 2 - Dry Dock 4 - Flood-through caisson - proposed
Figure 3 - Dry Dock Plan View - Proposed
Figure 4 - Dry Dock Wall Section - Proposed
Figure 5 - Dry Dock 4 - Wall Section - Proposed
Figure 6 - Dry Dock 4 pump well roof renovation - Proposed