19-0411_Boat_Power_Pedestals_SBB344-SOW.pdf
PDF 121 KB Posted
- Attached to
- Boat Power Pedestals SBB344
- Solicitation number
- N40085-19-R-8100
About this file
Statement of work
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend0002.pdf | ||
| Amend0001.pdf | ||
| 19-0411_Boat_Power_Pedestals_SBB344-Sketch.pdf | ||
| RFP_198100.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT#:
PROJECT#: 19M003MZ
MACC #: 19-0411
MAXIMO#: 4880742
TITLE: SBB344 BOAT POWER PEDESTALS
ATTACHMENTS: (a) Sketch
SCOPE OF WORK: The contractor shall provide all material, labor, equipment and supervision required to accomplish the following:
General description – Install electrical service and receptacles for boat power at SBB344
Clinton Street in the Courthouse Bay area aboard Marine Corps Base Camp Lejeune, North Carolina.
ELECTRICAL WORK:
CONSTRUCTION:
New Electrical Service-
1. Install 100 amp 240/120 volt single phase MCB NEMA 3R panel on the existing pole with the camera equipment. The panel shall be labeled Panel BP.
2. Install 1 ½ inch rigid metal conduit (RMC) and weather head with 3ea #1 awg
THHN/THWN conductors up the pole leaving 3ft of free conductor at weather head for termination. Grounding and bonding shall be in accordance with Article
250 of NFPA 70 (NEC).
3. Install 6ea 4” x 4” treated posts at the indicated locations.
4. Install 6ea ½ inch RMC from Panel BP to the 4” x 4” posts and terminate in a single gang FD box.
5. Install 3ea #10 THHN/THWN conductors from Panel BP to the FD boxes. Install
30 amp 125 volt NEMA L5-30 receptacle with HBL77CM74WO marine cover.
6. Install 6ea 30 amp single pole circuit breakers as indicated.
7. Terminate all conductors, label electrical equipment, and update panel directories as required.
Existing Electrical Service-
1. Install 2ea 4” x 4” treated posts at the indicated locations.
2. Install 2ea ½ inch RMC from Panel BP to the 4” x 4” posts and terminate in a single gang FD box.
3. Install 3ea #10 THHN/THWN conductors from electrical panel to the FD boxes.
Install 30 amp 125 volt NEMA L5-30 receptacle with HBL77CM74WO marine cover.
4. Install 2ea 30 amp single pole circuit breakers.
5. Terminate all conductors, label electrical equipment, and update panel directories as required.
GENERAL REQUIREMENTS: None Identified
SUBMITTALS: None Identified
SPECIAL SCHEDULING AND ACCESS: Mr. Brandon Blakley shall be the point of contact for access to the site, brandon.blakley.ctr@navy.mil phone- (910) 440-6282.
SPECIAL CONDITIONS: None Identified
HAZARDOUS MATERIALS: None Identified
ENVIRONMENTAL REQUIREMENTS: None Identified mailto:brandon.blakley.ctr@navy.mil