Maintenance and Repair of Track and Rail at Portsmouth Naval Shipyard, Kittery, Maine
Solicitation number
N4008518R9509
Issued by

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CODE

(Hour)

PAGE(S)

until local time

X

A X B X C

D

EX

X G F 156 - 161

162 - 174 X H 175 - 182 jeannette.vincent@navy.mil

RATING PAGE OF PAGES

7. ISSUED BY

(Date)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)

Prescribed by GSA FAR (48 CFR) 53.214(c)

DO-C2 1 182

(If other than Item 7)

15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO

AND

ADDRESS

SIGN OFFER (Type or print)

OF

OFFEROR

AMENDMENT NO. DATE

15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS

IS DIFFERENT FROM ABOVE - ENTER

SUCH ADDRESS IN SCHEDULE.

18. OFFER DATE

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

2. CONTRACT NO.

N40085 8. ADDRESS OFFER TO

See Item 7

9. Sealed offers in original and copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in

CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.

10. FOR INFORMATION

CALL:

A. NAME (NO COLLECT CALLS)

JEANNETTE L. VINCENT (207) 438-4619

11. TABLE OF CONTENTS

SOLICITATION/ CONTRACT FORM

SUPPLIES OR SERVICES AND PRICES/ COSTS

1 - 2 3 - 12

X I CONTRACT CLAUSES

DESCRIPTION/ SPECS./ WORK STATEMENT X

PACKAGING AND MARKING

13 - 55 J LIST OF ATTACHMENTS

INSPECTION AND ACCEPTANCE

DELIVERIES OR PERFORMANCE

56 - 59 60 - 65

X K

REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTS OF OFFERORS

CONTRACT ADMINISTRATION DATA 66 - 69 X

SPECIAL CONTRACT REQUIREMENTS

OFFER (Must be fully completed by offeror) 70 - 71 X M

L INSTRS., CONDS., AND NOTICES TO OFFERORS

EVALUATION FACTORS FOR AWARD

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments

AMENDMENT NO. DATE

to the SOLICITATION for offerors and related documents numbered and dated):

FACILITY

12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period

SOLICITATION, OFFER AND AWARD

X

(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)

PART I - THE SCHEDULE

26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE

EMAIL:TEL: (Signature of Contracting Officer)

CODE CODE

B. TELEPHONE (Include area code) C. E-MAIL ADDRESS

AWARD (To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE

PART IV - REPRESENTATIONS AND INSTRUCTIONS

PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

72 - 97

PART II - CONTRACT CLAUSES

NAVFAC MID ATLANTIC

PWD MAINE - FEAD PORTSMOUTH

PORTSMOUTH NAVAL SHIPYARD

BLDG 59

PORTSMOUTH NH 03801-2032

FAX:

TEL:

FAX:

TEL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

98 - 155

6. REQUISITION/PURCHASE NO.

ACQR5312185

5. DATE ISSUED

10 Apr 2018

4. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

[ X ]

3. SOLICITATION NO.

N4008518R9509

N4008518R9509

Section A - Solicitation/Contract Form

SECTION A

COMMANDER

NAVAL FACILITIES ENGINEERING COMMAND (NAVFAC)

MID-ATLANTIC ACQUISITIONS OFFICE

9324 VIRGINIA AVE, BLDG Z-140, ROOM 116

NAVAL STATION NORFOLK, VA 23511

NAVFAC RFP NUMBER: N4008518R9509

MAINTENANCE AND REPAIRS OF TRACK AND RAIL AT

PORTSMOUTH NAVAL SHIPYARD, KITTERY, MAINE.

NOTICE: PROPOSALS ARE DUE BY 2:00 PM (EST) ON 10 May 2018

Proposals are to be submitted to the office listed below:

Naval Facilities Engineering Command, Public Works Department Maine Attn: Jeannette Vincent Bldg. 59 Portsmouth Naval Shipyard Portsmouth, NH 03804-5000

All inquiries concerning any phase of the specification shall be made to Jeannette Vincent via email at jeannette.vincent@navy.mil.

Section B - Supplies or Services and Prices

SECTION B

B.1 Contract Title: Maintenance and Repair of Track and Rails at Portsmouth Naval Shipyard (PNSY), Kittery, Maine

B.2 Type of Contract: This is a combination Firm-Fixed-Price and Indefinite Delivery/ Indefinite Quantity (IDIQ) service type contract as noted in Section L, Instructions, Conditions, and Notice to Bidders.

B.3 Minimum Guarantee: The Firm-Fixed-Price portion, of the base year only, is the minimum guarantee for this contract. It can be paid in either the base year or over the entire term of the contract.

B.4 Set-Aside: None.

B.5 NAICS Code: The NAICS code assigned to this procurement is 237990 with a small business size standard of $36,500,000.00. Refer to System for Award Management (SAM) at https://www.sam.gov/portal/SAM (FAR 52.219-1-Small Business Program Representations (October 2014)).

B.6 Wage Determination: Service Contract Act and Construction Contract Wage Rate Requirements are included in this solicitation. Refer to Section J, Attachments.

B.7 Bid Guarantee/Bonding Requirements: There are no bid guarantee/bonding requirements for this procurement.

B.8 Contract Term: This contract contains provisions for a Base Period with four (4) Option Periods, not to exceed a total of sixty (60) months. See Section I, Contract Clauses, 52.217-9, Option to Extend the Term of the Contract (March 2000). In the option periods, the Government may adjust the prices, if applicable, based on new Department of Labor Wage Determination.

B.9 Period of Performance: The period of performance will be determined at the time of award.

B.10 Point of Contract: The preaward point of contract for this project award is Jeannette Vincent at 207-438-4619.

Please forward any questions regarding this project in writing to jeannette.vincent@navy.mil.

B.11 Site Visit: Refer to FAR 52.237-1, for Site Visit

1. Date and Time – Thursday, 19 April, 2018; 1:00PM Local Time.

2. Site Visit Location: Various Track and Rail locations at Portsmouth Naval Shipyard, Kittery, ME

3. Pre site Visit Requirements: Visitor requests must be emailed to jeannette.vincent@navy.mil

All visitors that do not have access to the base OR access to the CIA must submit the following information no later than Monday, 16 April 2018 to the persons listed above:

First name, last name, middle initial State of Residence Driver’s Licence # Date of Birth US Citizenship (Y or N)

On the day of the site visit, all visitors who submitted their information following instructions in the section above, will meet at Kittery Lions Club located at 117 State Rd, Kittery, ME 03904 (off the base) and be picked up by the PWD-ME Site Visit Team. Transportation will leave at 12:45PM Local Time.

All visitors must be U.S. citizens. Citizenship will be confirmed prior to leaving the location mentioned above on the day of the site visit. See document which has been uploaded separately and titled “List of Identity Proofing Documents” for guidance on approved documents for proving citizenship.

For those with base and CIA access, you can meet the site visit team at the bus stop at the south end of Building 59 at 1:00PM, however, please submit names of those attending to help with coordination of site visit.

4. Contact information:

Contract Specialist: Jeannette Vincent 207-438-4619

B.12

B.13 Evaluation of Proposals: Proposers shall submit a lump sum price for Section B, CLINs 0001 through 0010 and unit prices for Exhibit A through Exhibit E, referenced in Section J. For purposes of evaluating offers for award, the Government will utilize the pricing submitted for the base year and all option periods. Refer to Section M, FAR 52.217-5, Evaluation of Options (JUL1990).

In order to permit efficient competition, the Navy will utilize the following methodology: Proposals will initially be screened for price and placed in order of price (lowest to highest price). The Navy will then evaluate the technical factors of the three

(3) lowest‐priced proposals. The Navy will make award to the lowest‐priced, technically acceptable proposal from among the three (3) lowest‐priced proposals.

However, the Navy, at its sole discretion, reserves the right to increase the number of proposals it will review under this methodology. Accordingly, under this methodology, the technical factors of some proposals may not be evaluated by the Navy. If discussions are deemed necessary by the Contracting Officer, all proposals will be evaluated (both technical and price) for the purpose of establishing a competitive range. Offerors MUST be evaluated as technically ACCEPTABLE under factors 1, 2, 3 and 4 in order to be considered technically acceptable overall.

An overall non-price factors rating must be at least “ACCEPTABLE” in order to be eligible for award. An “UNACCEPTABLE” rating in any factor results in the overall non-price factors proposal being rated “UNACCEPTABLE” unless corrected through discussions. An overall non-price factors rating of “UNACCEPTABLE” makes a proposal ineligible for award.

B.14 Contract Line Items and Sub-Line Items:

a. Offerors shall enter unit prices and amounts for Contract Line Items (CLINs) and Exhibit Line Items (ELINs), as indicated in the schedules.

b. In the event there is a difference between the unit price and the extended total amount, the unit price will be held to be the intended offer and the total of the CLIN, SLIN, and ELINs will be recomputed accordingly.

The CLIN, which included this SLIN, will also be recomputed to take into account the changes in the contract SLINs or ELINs. If the Offeror provides a total amount for a CLIN, SLIN, or ELIN, but fails to enter the unit price, the total amount divided by the CLIN, SLIN, or ELIN quantity will be held to be the intended unit price.

c. The schedule of Recurring Work (CLINs 0001, 0003, 0005, 0007, and 0009) and the schedule of Non- Recurring Work (CLINs 0002, 0004, 0006, 0008, and 0010) will be used as the basis for deductions in accordance with NFAS 5252.246-9303, “Consequences of Contractor’s Failure to Perform Required Services.”

B.15 Indefinite Quantity Individual Contract Line Item Quantities: Once the estimated quantities for individual line items shown on the schedule have been ordered, additional quantities may be ordered as long as the overall not-to-exceed (NTE) amount of the contract per year is not exceeded and the Contractor agrees by signing the task order.

B.16 Unit Price Adjustments in Option Periods: This contract incorporates the Service Contract Labor Standards statute (SCLS) and Construction Contract Wage Rate Requirements . The Wage Determinations incorporated in Section J is for the Base Period performance period only. The latest Wage Determination available at the time for each option exercise will be incorporated into the contract and the unit prices will be adjusted in accordance with FAR 52.222-43, Fair Labor Standards Act and Service Contract Labor Standards – Price Adjustment and 52.222-32 Construction Wage Rsate Requirements- Price Ajustment (Actual Method). The contractor warrants, by submission of his bid/offer, that the bid/offer price does not include any contingency for future wage increases.

B.17 Unit Prices for Labor:

a. A portion of the work included in the scope of this contract cannot be identified in advance in sufficient detail to be included in the Firm-Fixed-Price portion or as a Unit Price Task in the Indefinite Quantity portion of the contract. Labor for this work will be ordered under the "Emergency or Urgent Service Orders" part in Section C and paid for based on unit prices for labor bid by the Contractor listed in the Schedule of Indefinite Quantity work, Line Item 0002.

b. Estimated hours in the Schedule are a forecast of future requirements. These estimated hours are for performing "Emergency or Urgent Service Orders" accomplished in the time period shown.

The Contractor shall enter, in the unit price bid space, the unit price for performing composite labor. The composite labor price shall include all direct and indirect costs associated with performing an hour of work.

The composite labor price should be the Contractor's hourly craft wage adjusted to allow for the offerors work force productivity (i.e., the Contractor's estimate of how its’ work force will perform in relation to the Means Facilities Cost Data and/or the Engineered Performance Standards). The Composite Labor Rate shall include all costs for preparation of the cost proposal, job preparation, travel, pre- expended bin materials and supplies, ordering and stockpiling job material, additional material handling, items of equipment necessary to perform work (i.e. bucket truck, lifting equipment, staging, etc.), equipment set up time, lift time, craft delay allowance, profit, tools, equipment, field and home office overhead, clerical support, supervision, inspection, fees, taxes, licenses, bonds, permits, insurance, etc.

B.18 Period of Performance – Less than One Year: Offers shall be submitted for the performance of work for a period of one year. The contractor is cautioned to recognize that the initial term of the contract may be for a period of less than one year in accordance with the “Term of Contract” clause in Section F. In the event that the period of performance is less than one year, the Government will reduce the individual line item quantities to reflect the contract term and no other adjustments to the pro-rated contract price will be made.

B.1 B.16 Government Purchase Card: Indefinite Quantity work may be ordered at the prices offered by two ways: 1) by the issuing activity using a DD Form 1155 “Order for Supplies and Services” or 2) by an authorized Government user via a Government Purchase Card (GPC). When receiving GPC orders against Section B, the contractor shall provide the supplies and services at the offered price without additional markup or handling fee.

B.17 Contractor Support of Electronic Facilities Support Contracting (e-FSC): This procurement allows for the use of FedMall (formerly DoD EMALL) for issuing orders. Refer to Section H, Special Contract Requirements.

B.18 Contractor’s Payment Schedule: Contractors are required to submit a Contractor’s Payment Schedule with the proposal. Refer to Section L, Contractor’s Payment Schedule.

B.19 Incorporation of Technical Proposal:

a. The contractor’s technical proposal, including revisions and amendments made prior to contract award and a copy of which is in the possession of both parties, will be incorporated into this contract upon award by reference with the same force and effect as if set forth in full text. All contractor personnel shall meet or exceed the qualification standards, experience levels, and trade backgrounds set forth in the technical proposal.

b. In the event of an inconsistency between the provisions of this contract and the technical proposal, the inconsistency shall be resolved by giving precedence in the following order: (i) the contract (excluding the technical proposal), and then (ii) the technical proposal.

B.20 Request for Proposals (RFP) Information/Clarification Questions: Contractors are required to review the entire solicitation package before submitting questions. All questions must be submitted at least ten (10) daysbefore proposals are due (30 APRIL 2018 NLT than 3pm local) by e-mail to jeannette.vincent@navy.mil. This is the most efficient way to ensure all questions are answered in a timely manner.

B.21 RFP Files: Solicitations are posted to the Navy Electronic Commerce Online (NECO) website (https://www.neco.navy.mil) as mandated by our Agency. By necessity, these files are protected to prevent unauthorized editing.

It is the sole responsibility of the offeror to obtain the RFP files, along with any amendments from this website.

Unprotected editable file copies of the RFP documents, including Word, Excel and/or .pdf files (Adobe Acrobat files) will not be provided. Please plan accordingly.

B.22 Solicitation: This solicitation incorporates by reference a Performance Work Statement (PWS) developed by using NAVFAC performance-based specifications. The PWS consists of Annexes 1, 2, and 15. The contractor will be required to meet the specifications in those Annexes as if they were set forth in Section C. All changes to this solicitation will be issued via amendment and posted on the NECO website.

B.23 Notice to Offerors:

Offerors are required to submit both Section B, Bid Schedule, and Section J, Exhibit Line Item Numbers (ELINs), with their offer. The total of the CLIN is equal to the sum of the ELINs as shown below:

CLINs ELINs 0001 A001 – A003 0002 A701 – A706 0003 B001 – B003 0004 B701 – B706 0005 C001 – C003 0006 C701 – C706 0007 D001 – D003 0008 D701 – D706 0009 E001 – E003 0010 E701 – E706

B.17 Proposal Delivery:

NOTICE TO PROPOSER:

Defense Biometric Identification System (DBIDS):

Access to Installation: All Contractor personnel shall obtain access to the installation through enrollment and registration into the Defense Biometric Identification System (DBIDS).

The Contractor shall provide the KO with the name of their designated Service Contractor Administrator (SCA) for enrollment in DBIDS. Once enrolled, the Contractor must provide the DBIDS Registrar with an approved employee list and then direct their employees to register into DBIDS.

DBIDS Program: DBIDS is an enterprise identity management and perimeter installation access control solution in which Contractor personnel who enroll, and are approved, are subsequently granted access to the installation for a period up to three years, or the length of the contract, whichever is less, and are not required to obtain a new pass from the Base Pass and Identification Office for each visit. There are no fees associated with obtaining a DBIDS credential.

The Government performs background screening and credentialing. Throughout the year the Contractor employee must continue to meet background screening standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.

DBIDS Credentials: Contractor employees shall furnish a completed copy of the SECNAV 5512/1 form to obtain the required background check and visit the local Navy Installation Visitor Control Center to obtain a DBIDS credential once approved. The SECNAV 5512/1 form and additional information about DBIDS can be found at: https://www.cnic.navy.mil/om/dbids.html.

The Contractor may initiate the adjudication process when a background screen failure results in disqualification from participation in DBIDS and the Contractor employees do not agree with the reason for disqualification. The Contractor may also apply for a waiver when a background screening failure results in disqualification from participation in DBIDS. The Commanding Officer will be the final waiver determination authority.

The Contractor shall immediately collect employee DBIDS credentials and notify the KO in writing:

(1) That an employee has departed the company without having properly returned or surrendered their DBIDS credentials.

(2) That there is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the installation or anyone therein.

DBIDS Paper Passes: In the event that a visitor, vendor, or Contractor employee elects not to participate in DBIDS, the individual will be issued DBIDS paper pass from the Base Pass and Identification Office in order to access to the installation. The time standard for the validity of a pass to access an installation will be not more than thirty (30) days and may be further restricted based on local policy or by Federal, DOD, Navy, and CNIC guidance.

The Government will not be responsible for any cost or lost time associated with obtaining paper passes or added vetting or inspections incurred by non-participants in the DBIDS credentialing process

The Contractor shall obtain the required employee badges and vehicle passes from the Government at its own expense, or daily passes at no additional cost. Each employee shall wear the Government issued badge over the front of the outer clothing. When an employee leaves the Contractor's service, the employee's Passes and Badges shall be returned within five (5) calendar days.

Be advised by this notice that the level of security at various Navy Installations may change at any time. As the level of security heightens, the amount of time required to gain access to all Navy Installations also increases.

Submitting Your Proposal

Proposals that are sent via the United States Postal Service or a commercial carrier, such as Federal Express, shall be addressed to:

PWD MAINE Acquisition Attn: Jeannette Vincent BLDG. 59 Portsmouth Naval Shipyard Portsmouth, NH 03804-5000

Proposals that are hand carried shall be delivered to Acquisition, 1st Floor Bldg. 59, Portsmouth Naval Shipyard, Kittery, Maine.

ITEM NO SUPPLIES/SERVICES MAX

QUANTITY

UNIT UNIT PRICE MAX AMOUNT

0001 UNDEFINED Each Base Year Recurring Services

FFP

Recurring Services - Base Year FOB: Destination

PURCHASE REQUEST NUMBER: ACQR5312185

MAX

NET AMT

UNIT UNIT PRICE MAX AMOUNT

0002 UNDEFINED Each Base year - Non-Recurring Services

FFP

Non-Recurring Services - Base year

UNIT UNIT PRICE MAX AMOUNT

0003 UNDEFINED Each OPTION 1st Option Year - Recurring Services

FFP

Recurring Services - 1st Option

UNIT UNIT PRICE MAX AMOUNT

0004 UNDEFINED Each OPTION 1st Option Year- Non-recurring Service

FFP

Non-Recurring Services- 1st Option year

UNIT UNIT PRICE MAX AMOUNT

0005 UNDEFINED Each OPTION 2nd Option Year- Recurring Services

FFP

Recurring Services - 2nd option year

UNIT UNIT PRICE MAX AMOUNT

0006 UNDEFINED Each OPTION 2nd Option Year - Non-Recurring Servicex

FFP

Non-Recurring Services - 2nd Option year

UNIT UNIT PRICE MAX AMOUNT

0007 UNDEFINED Each OPTION 3rd Option Year - Recurring Services

FFP

Recurring Services - 3rd Option Year

UNIT UNIT PRICE MAX AMOUNT

0008 UNDEFINED Each OPTION 3rd Option - Non-Recurring Services

FFP

Non-Recurring Services - 3rd Option Year

UNIT UNIT PRICE MAX AMOUNT

0009 UNDEFINED Each OPTION 4th Option Year - Recurring Services

FFP

Recurring Services - 4th Option Year

UNIT UNIT PRICE MAX AMOUNT

0010 UNDEFINED Each OPTION 4th Option Year – Non- Recurring Service

FFP

Non- Recurring Services - 4th Option Year

Section C - Descriptions and Specifications

DESCRIPTION & SPECIFICATIONS

C.2 REPORTING REQUIREMENTS. A detailed report allocating value of work/quantities performed by Contract Line Items (CLINs)/Sub-Line Items (SLINs) identified in the schedule and any accompanying Exhibits with Exhibit Line Item Numbers (ELINs) is to be submitted monthly, including all Firm-Fixed-Price (FFP) and Indefinite Quantity (IQ) Work items completed. The Contracting Officer shall be notified when 75% of any IQ Line Item (CLIN/SLIN/ELIN) is reached.

C.3 GOVERNMENT PURCHASE CARD PROGRAM. The contractor shall accept orders placed by authorized Government Purchase Card (GPC) users. The GPC is a purchasing instrument issued through a commercial bank to a Government Agency to facilitate micro purchases. A micro purchase is any order for supplies or services of $3,500.00 or less, or order for construction services of $2,000.00 or less. The Contractor processes micro purchases under the GPC program exactly as they would process a charge by an individual using a personal credit card.

a. Limitation of GPC Pricing for IQ Work: The Contractor shall be required to offer IQ pre-priced line item services to authorized Government personnel when they are ordering the work directly via the GPC Program. The Contractor shall be required to offer the pre-priced IQ line item services at the same prices in accordance with the schedule of pricing information, Section B, and Exhibits (if any). Contractor is responsible for tracking quantities and reporting total used each month and year to date to the Contracting Officer by the fifth day of each month. See Section H for additional details.

C.4 ADDITIONAL REPORTING REQUIREMENTS.

Enterprise-wide Contractor Manpower Reporting Application (ECMRA). The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: https://doncmra.dmdc.osd.mil.

Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk, linked at https://doncmra.dmdc.osd.mil.

ANNEX 010000

0100000 – General Information Spec Item Title Description 1 General Information

1.1 Outline of Services Except where otherwise stated, the Contractor shall furnish all labor, supervision, management, tools, materials, equipment, facilities, transportation, incidental engineering, and other items necessary to provide the services outlined below and described in this Performance Work Statement (PWS) at Portsmouth Naval Shipyard, Kittery, Maine, under a performance-based contract that is comprised of both Recurring Work and Non-Recurring Work Items.

The PWS is organized into annexes. Annex 1 “General Information”.

Annex 2 contains the on-site project management and administration requirements. Annexes 3 through 18 contain the technical requirements.

The annex numbers are identified as 1 through 18 in the description column, but the full expanded annex numbers include seven digits (e.g., Annex 1 expanded number is 0100000 as shown in the header row at the top of this page).

Annex 1 General Information Annex 2 Management and Administration Annex 3 Command and Staff - N/A Annex 4 Public Safety - N/A Annex 5 Air Operations - N/A Annex 6 Port Operations - N/A Annex 7 Ordnance - N/A Annex 8 Range Operations - N/A Annex 9 Health Care Support - N/A Annex 10 Supply - N/A Annex 11 Personnel Support - N/A Annex 12 Morale, Welfare and Recreation Support - N/A Annex 13 Galley - N/A Annex 14 Housing - N/A Annex 15 Facilities Support 1502000 Facilities Investment Annex 16 Utilities - N/A Annex 17 Base Support Vehicles and Equipment - N/A Annex 18 Environmental – N/A

1.2 Project Location Portsmouth Naval Shipyard (PNSY), Kittery, Maine.

1.3 Acquisition of

Additional Work

The Government reserves the right to acquire additional track maintenance services at additional locations in addition to the services and locations identified in the recurring work requirements of this contract. Additional services will be incorporated into the contract in accordance with the CHANGES clause, SECTION I or ordered under the indefinite delivery indefinite quantity provisions of the contract. Items of work not covered by this contract but within the general intent are considered in the scope of this contract.

1.4 Background Information Portsmouth Naval Shipyard is located in Kittery, Maine. It is beside the Piscataqua River, which forms the boundary between Maine and New Hampshire and provides access to the Atlantic Ocean. It is an industrial facility primarily responsible to overhaul submarines.

Spec Item Title Description

1.5 Verification of

Workload and Conditions

Throughout the PWS, the workload data is generally referred to as being located in Section J. Section J provides data such as inventories, maps, floor plans, and tables to represent the type, quantity and location of services to be provided. However, offerors are encouraged to visit the project site during the site visit for offerors and to visit the technical library during posted hours as part of its due diligence to assess the nature of work and conditions under which work is to be performed.

1.6 Climate Patterns Southern Maine has a long winter and a moderate summer. Temperatures along the coast, particularly in the winter, tend to be milder than those inland.

Generally, winter temperatures may range from a high of 31° F to a low of 10° F and summer temperatures may range a high of 85° F to a low of 60° F. However, winter temperatures may remain below zero for extended periods and summer temperatures may exceed 90° F

1.7 Related Information There are four types of Related Information that can be found in the Description and Related Information columns of the specification as follows:

Informational Notes as used throughout this PWS provides additional information to offerors to be used in developing a thorough understanding of the work to be performed in this contract. Any block of text marked “Informational Notes” throughout Annexes 1 through 18 is subject to this disclaimer. Offerors may not rely upon the "Informational Notes" as material representations of the Government.

Information provided in "Informational Notes" does not create a contractual requirement on either party to this contract.

Clarifying Information describes client expectations in a more detailed manner than the Performance Objective and Performance standard alone.

Constraining Information describes limitations to the work performed to meet the Performance Objective and Performance Standard.

Requirement Information further describes client requirements associated with each Performance Objective.

1.8 Navy Approach to

Service Contracting

The Department of Navy (DoN) spends over $1 billion in annual obligations to meet global requirements for facility operations and maintenance provided through Facility Support Contracts (FSC) and additional billions to provide other base operations support services (OBOS). The Head of the Contracting Activity (HCA) of the Naval Facilities Engineering Command (NAVFAC) has focused increased attention on re-engineering FSC contracts in response to customer and industry feedback, budget constraints, and the impact of a variety of contracting, program management and financial management regulations.

The Navy also supports the following principles:

1.8.1 Partnering Philosophy The first principle is that the Navy views its contractors as partners and not just abstract service providers. The Navy wants its contractors to succeed because partners' success drives the Navy's successful mission completion.

Within the bounds of acquisition policy the Navy intends to work to find solutions that will be beneficial to both the Government and its partners.

1.8.2 Contractor's Knowledge The second principle is that the Navy will receive insightful management from its contractors. This management will include the knowledge, skills, authority and willingness to use contractor resources to find better ways of serving Navy clients’ strategic and operational goals and objectives. The Navy's use of performance-based objectives evidences this principle.

Although performance work statements will typically contain several levels of performance assessment, the Navy wants its contractors to exercise maximum discretion within bounds of prudent risk management to adjust processes and resources needed to reach specified objectives at the highest performance level.

1.8.3 Industry Best Practices The third principle is that the Navy will adopt industry best commercial practices and maintain state-of-the-art service delivery. It is the Navy's and contractor's responsibility as partners to reach this goal. To that end, the Navy's emphasis will be in evaluating performance objectives (end results).

1.9 Standard Template Key to implementing a programmatic approach is using a standard template that ensures Navy-wide consistency yet affords appropriate tailoring to meet local needs. This contract conforms to the standard template and has been tailored for this solicitation. NAVFAC intends to use this template-based approach for future service contracts. Offerors should develop an understanding of the template as part of performing due diligence in reaching an understanding of the Navy’s requirements and expectations.

The standard template contains 18 standard annexes. Annex 1 will always contain information that is relevant to the entire scope of the contract.

Annex 2 contains on-site project management and administration requirements that are relevant to the entire scope of the contract. Annexes 3 through 18 contain the technical information and requirements peculiar to that technical annex. Within each technical annex, the organization of information and requirements are also standardized. Specification item 1 will always contain General Information. Specification item 2 will always contain the management and administrative requirements. Specification item 3 will always contain the Recurring Work requirements.

Specification item 4 will always contain the Non-recurring Work requirements. Requirements and standards for higher level specification items apply to all subordinate specification items, e.g., Specification Item 3 standards apply to all recurring work specification items. Specification Item 3.1 is applicable to all 3.1 subordinate specification items.

Specification Items 3.2 and 3.3 are not considered subordinate to 3.1. All costs associated with Annexes 1 and 2 and Specification items 1 and 2 must be priced and distributed within Specification Item 3 of Annexes 3 through 18.

1.10 Navy PBSA Approach The Navy’s approach to performance-based service acquisition (PBSA) includes four component parts which are 1) performance outcomes, 2) measurable standards, 3) consideration of incentives, and 4) performance assessment plan.

1.11 Technical Proposal

Certification

The Contractor warrants that its proposal incorporated herein by reference will meet or exceed the performance objectives set forth in this contract.

ANNEX 0200000

0200000 – Management and Administration Table of Contents

Spec Item Title

2 Management and Administration

2.1 Definitions and Acronyms

2.2 General Information

2.2.1 Government Regular Working Hours

2.2.1.1 Observed Federal Holidays

2.2.1.2 Restriction to Contractor Working Hours

2.2.2 Wage Determinations

2.2.3 Requirements Hierarchy

2.2.4 PNSY Station Regulations

2.2.5 PNSY Crane Operation and Maintenance

2.3 General Administrative Requirements

2.3.1 Required Conferences and Meetings

2.3.2 Training for Maintenance and Operation of New and Replacement Systems and Equipment

2.3.3 Partnering

2.3.3.1 Informal Partnering

2.3.3.2 Contract Partnering Administration

2.3.3.3 Contract Partnering Session Attendees

2.3.4 Permits and Licenses

2.3.5 Insurance

2.3.5.1 Certificate of Insurance

2.3.5.2 Minimum Insurance Amounts

2.3.6 Protection of Government Property

2.3.7 Government Information Technology (IT) System

2.3.8 Directives, Instructions, and References

2.3.9 Invoicing Procedures

2.3.10 Forms

2.4 Government-Furnished Property, Materials and Services

2.4.1 Government-Furnished Facilities (GFF)

2.4.2 Government-Furnished Utilities

2.4.3 Government-Furnished Materials (GFM)

2.4.4 Government-Furnished Equipment (GFE)

2.4.5 Government-Furnished Services (GFS)

2.5 Contractor Furnished Items

2.6 Management

2.6.1 Work Reception

2.6.2 Work Control

2.6.3 Work Schedule

2.6.4 Deliverables

2.6.5 Service Interruptions

2.6.6 Government’s Computerized Maintenance Management Systems (CMMS)

2.6.7 Quality Management System (QMS)

2.6.7.1 Quality Management (QM) Plan

2.6.7.2 Quality Inspection and Surveillance

2.6.7.3 Quality Inspection and Surveillance Report

2.6.8 Property Management Plan

2.6.9 System and Equipment Replacement

2.7 Personnel Requirements

2.7.1 Key Personnel

2.7.1.1 Project Manager (PM)

2.7.1.2 Quality Manager

2.7.1.3 Site Safety and Health Officer (SSHO)

2.7.1.4 Environmental/Energy Manager

2.7.2 Employee Requirements

2.7.2.1 Employee Certification and Training

2.7.2.2 Employee Appearance

2.7.2.3 Employee Conduct

2.7.2.4 Identification as Contractor Employee

2.7.2.5 Removal of Employees

2.7.2.6 Proof of Legal Residency

2.7.3 Enterprise-wide Contractor Manpower Reporting Application (eCMRA)

2.8 Security Requirements

2.8.1 Employee Listing

2.8.2 Vehicles

2.8.3 Passes and Badges

2.8.4 Access to Installation

2.8.4.1 DBIDS Program

2.8.4.2 DBIDS Credentials

2.8.4.3 DBIDS Paper Passes

2.8.5 Access to Buildings

2.8.6 Access Arrangements

2.8.6.1 Escort Arrangement for Secured Areas

2.8.7 Security Clearances

2.8.8 Access to Sensitive Unclassified Information

2.8.9 Employee Status

2.9 Contractor Safety Program

2.9.1 Accident Prevention Plan (APP)

2.9.2 Activity Hazard Analysis (AHA)

2.9.3 Safety and Occupational Health (SOH) Risks and Compliance Plans

2.9.3.1 Alcohol and Drug Abuse Prevention Plan

2.9.3.2 Chemical Hazard Communication Program

2.9.3.3 Confined Space Program

2.9.3.4 Critical Lift Plan

2.9.4 Crane Operations

2.9.4.1 Crane Inspections

2.9.4.2 Rigging Gear

2.9.4.3 Crane Operators

2.9.5 Accident and Damage Reporting

2.9.5.1 Accident Reporting and Notification Criteria

2.9.6 Fire Protection

2.9.7 Monthly On-Site Labor Report

2.9.8 OSHA Citations and Violations

2.9.9 Safety Inspections and Monitoring

2.9.10 Safety Certification

2.9.11 Safety Apparel on Jobsites

2.9.12 Emergency Medical Treatment

2.10 Environmental Management and Sustainability

2.10.1 Energy Management Plan

2.10.1.1 Water Conservation Plan

2.10.1.2 Energy Efficient Products

2.10.2 Environmental Protection

2.10.2.1 N/A

2.10.2.2 Non-Hazardous Waste Disposal

2.10.2.3 Hazardous Waste Disposal

2.10.2.4 Spill Prevention, Containment, and Clean-up

2.10.2.5 Hazardous Material Management

2.10.2.6 Protection of Endangered and Threatened Species (Flora and Fauna)

2.10.2.7 Noise Control

2.10.2.8 Salvage

2.10.2.9 Asbestos Containing Material (ACM)

2.10.3 Sustainable Procurement and Practices

2.10.3.1 Environmentally Preferable Products

2.10.3.2 Use of Recovered Materials

2.10.3.3 Use of Bio based Products

2.11 Disaster Preparedness

2.12 Technical Library

2.13 Warranty Management

2.14 Recurring Work Procedures

2.14.1 Notification to the Government for Work Above the Recurring Work Limitations

2.14.2 Recurring Work Exhibit Line Item Numbers (ELINs)

2.15 Non-recurring Work

2.15.1 Unit Priced Task (UPT) Work (Non-Negotiated)

2.15.1.1 Acceptance and Performance

2.15.1.2 Invoicing and Receiving Payment

2.15.2 Unit Priced Labor (UPL)Work (Negotiated)

2.15.2.1 Non-recurring Preparation of Proposals

2.15.2.1.1 Labor Requirements

2.15.2.1.2 Material and Equipment Requirements

2.15.2.2 Issuance of Final Task Order

2.15.3 Non-recurring ELINS

0200000 - Management and Administration

2 Management and

Administration

2.1 Definitions and

Acronyms

Definitions and Acronyms are listed in J-0200000-01.

2.2 General Information

2.2.1 Government Regular

Working Hours Regular working hours are from:

7:00 AM – 4:00 PM

Day Shift: Various – 7:00 AM – 4:00 PM Second Shift: 3:00 PM - 11:30 PM

Five days per week, Monday through Friday, except observed Federal holidays. Work in certain annexes or sub-annexes may require Contractor continuous operations, 24 hours a day, every day of the year including holidays. The performance of other work requirements shall be accomplished within the Contract’s Office regular working hours unless the specific work requirement specified herein necessitates otherwise.

Any other work outside Contract’s Office regular working hours requires prior COR approval.

2.2.1.1 Observed Federal

Holidays

The Government observes the following holidays: New Year’s Day, Martin Luther King Jr.’s Birthday, President’s Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans’ Day, Thanksgiving Day, and Christmas Day.

2.2.1.2 Restriction to

Contractor Working Hours

If the Contractor wishes to work outside of the Government's regular working hours for the Contractor’s convenience, the Contractor shall submit a written Request to Work Outside Government’s Regular Working Hours to the COR for approval at least seven calendar days prior to requested day. Excludes work to be performed during specified hours.

2.2.2 Wage Determinations Wage Determinations are included in J-0200000-02.

2.2.3 Requirements

Hierarchy Requirements or definitions specified in each spec item of this contract apply to subordinate paragraphs. For example, requirements shown in spec item 3.1 would apply to spec items 3.1.1, 3.1.2, 3.1.2.1 and so on.

Likewise, Performance Standards specified at a lower digit level (i.e. spec item 3.1.1, 3.1.2, 3.1.2.1) apply when performance is assessed at a higher tier (i.e., spec item 3.1) based on the composite work requirements.

2.2.4 PNSY Station

Regulations

Refer to Attachment J-0200000-03 PNSY STATION REGULATIONS

2.2.5 PNSY Crane Operation

and Maintenance

Refer to Attachment J-0200000-07 PNSY Contractor Crane.docx

2.3 General Administrative

Requirements

2.3.1 Required Conferences

and Meetings

The Contractor may be required to attend administrative and coordination meetings, pre-performance conferences, performance assessment board meetings, partnering sessions, etc., as scheduled by the COR.

2.3.2 Training for

Maintenance and Operation of New and Replacement Systems and Equipment

Maintenance of new and replacement systems and equipment, e.g., When construction, renovation, or repair work is performed by means other than this contract, the Contractor shall attend Government provided training, as applicable, for maintenance and operation of new and replacement systems and equipment at no additional cost to the Government.

2.3.3 Partnering The Contracting Officer shall organize the initial Partnering Meeting with key personnel of the project team, including Contractor's personnel and Government personnel. The initial session will be scheduled concurrent with the Pre-Performance Conference and held no later than 30 days after award and will be held at a Government provided facility as designated by the COR.

The Initial Informal Partnering Session will be conducted and facilitated using electronic media (video and accompanying forms) provided by Contracting Officer. The senior Government stakeholder present will lead the meeting, however, the Contractor’s PM or senior representative is encouraged to participate as co-lead.

The Partners will determine the frequency of the follow-on sessions.

2.3.3.1 Informal Partnering The Contracting Officer shall organize the initial Partnering Meeting with key personnel of the project team, including Contractor's personnel and Government personnel. The initial session will be scheduled concurrent with the Pre-Performance Conference and held no later than 30 days after award and will be held at a Government provided facility as designated by the COR.

The Initial Informal Partnering Session will be conducted and facilitated using electronic media (video and accompanying forms) provided by Contracting Officer. The senior Government stakeholder present will lead the meeting, however, the Contractor’s PM or senior representative is encouraged to participate as co-lead.

The Partners will determine the frequency of the follow-on sessions.

2.3.3.2 Contract Partnering

Administration

Upon award, the ACO will contact the Contractor, supported command(s), Region, and Installation(s) stakeholders, and the performance assessment team to discuss implementation of partnering. A partnership agreement, The Charter, should be in place as early as possible so issues arising, even before work begins, can be resolved using the issues resolution process.

Replacement of Core Management Team members (stakeholders who attended the initial session and manage the contract work day-to-day) is discouraged since it will disrupt the synergy that has been developed. If replacement of a team member proves to be unavoidable, a follow-on partnering session must be held to officially turn the responsibilities of the position over to the new member.

The Core Management Team consisting of the attendees below must be present during the initial and all follow-on partnering sessions. These are the core mandatory attendees. Other stakeholders may attend if they desire or as recommended by the partners.

2.3.3.3 Contract Partnering

Session Attendees

The Contractor shall bring the necessary personnel to successfully partner on this contract. Asterisk indicates mandatory personnel.

President/Vice President

* Project Manager

* Quality Manager Site Safety and Health Officer

2.3.4 Permits and Licenses The Contractor shall obtain all required permits, licenses, and authorizations to perform work under this contract and comply with all the applicable Federal, state and local laws and regulations. The Contractor shall submit copies of Permits and Licenses per Section F.

2.3.5 Insurance The Contractor shall submit a Certificate of Insurance per Section F as evidence of the existence of the following insurance coverage in amounts not less than the amounts specified below in accordance with the FAR Clause 52.228-5, INSURANCE – WORK ON A GOVERNMENT INSTALLATION. This insurance must be maintained during the performance period.

2.3.5.1 Certificate of Insurance The Certificate of Insurance shall provide for at least 30 calendar days written notice to the KO by the insurance company prior to cancellation or material change in policy coverage. Other requirements and information are contained in the aforementioned insurance clause.

2.3.5.2 Minimum Insurance

Amounts

Comprehensive General Liability: $500,000 per occurrence

Automobile Liability: $200,000 per person, $500,000 per occurrence, $20,000 per occurrence for property damage

Workmen's Compensation: As required by Federal and State worker's compensation and occupational disease statutes

Employer's Liability coverage: $100,000, except in states where worker's compensation may not be written by private carriers

Other as required by State Law

2.3.6 Protection of

Government Property

During execution of the work, the Contractor shall protect Government property. The Contractor shall return areas damaged as a result of negligence under this contract to their original condition at no cost to the Government.

2.3.7 Government

Information Technology (IT) System

N/A

2.3.8 Directives, Instruction, and References

Refer to Invoice Form in J-0200000-04.

2.3.9 Invoicing Procedures Refer to Section G for invoicing instructions. Refer to Invoice Form in J- 0200000-05.

2.3.10 Forms Forms referenced in this Annex, e.g. accident reporting, and damage reporting are included among the Forms in J-0200000-06.

2.4 Government-Furnished

Property, Materials and Services

In accordance with FAR 52.245, GOVERNMENT PROPERTY and NAVFAC Clause 5252.245-9300, GOVERNMENT-FURNISHED PROPERTY, MATERIALS AND SERVICES, and the following paragraphs, the Government will furnish or make available to the Contractor certain Government-owned facilities, utilities, materials, and equipment for use in connection with this contract.

2.4.1 Government-Furnished

Facilities (GFF)

None

2.4.2 Government-Furnished

Utilities

The Government will furnish water and electricity at existing outlets required for the work to be performed under the contract at no cost to the Contractor. Information concerning the location of existing outlets may be secured from the COR. The Contractor shall provide and maintain, at its expense, the necessary service lines from the existing Government outlets to the work site. Provide and maintain backflow prevention devices on connections to domestic water lines and electrical transformer provisions on connections to electric lines. Meet all Federal, State, local, and activity codes and regulations for backflow prevention devices and electrical transformer provisions. Services required by the Contractor, for which there are no available Government outlets, shall be provided by the Contractor at no cost to the Government. Telephone services are available for on-base, contract-related business only. Telephone services for off-base calls shall be arranged and paid for by the Contractor.

2.4.3 Government-Furnished

Materials (GFM)

None

2.4.4 Government-Furnished

Equipment (GFE)

None

2.4.5 Government-Furnished

Services (GFS)

None

2.5 Contractor-Furnished

Items

Except for items identified as Government Furnished, the Contractor shall provide all equipment, materials, parts, supplies, components, and facilities to perform the requirements of this contract. The COR may inspect Contractor-furnished items for adequacy and compliance with contract requirements. Inadequate or unsafe items shall be removed and replaced by the Contractor at no cost to the Government. Materials containing asbestos, lead, and polychlorinated biphenyls (PCBs) shall not be brought onsite. Energy efficient tools and equipment shall be used when available. The COR may at any time require Samples, Safety Data Sheets (SDS) or Manufacturer’s Data Cut Sheets of Materials used in this contract.

2.6 Management The Contractor shall manage the total work effort associated with the services required herein to meet the performance objectives and standards.

Such management includes but is not limited to planning, scheduling, cost accounting, report preparation, establishing and maintaining records, and quality assurance. The Contractor shall provide a staff with the necessary management expertise to ensure performance objectives and standards are met.

2.6.1 Work Reception The Contractor shall establish a work reception function with the capability to receive, correspond, and respond to task orders.

2.6.2 Work Control The Contractor shall implement all necessary work control procedures to ensure timely accomplishment of work requirements, as well as to permit tracking and reporting of work in progress.