Attachment_1_Performance_Work_Statement.pdf
PDF 5 MB Posted
- Solicitation number
- N4008419B0092
About this file
Attachment 1 Performance Work Statement
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N40084-19-B-0092_AM-0002.pdf | ||
| N40084-19-B-0092_AM-0001.pdf | ||
| Pre-Bid_Conference_Brief_19B0092.pdf | ||
| Attachment_4_Site_Visit_Request_Form.xls | XLS spreadsheet | |
| N40084-19-B-0092.pdf | ||
| Attachment_3_Pre-Bid_Inquiry_Form.xls | XLS spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
eProject No. 1599202
NAVFAC SPECIFICATION No.
SRN 12603385
DEMOLISH BUILDINGS,
BLDG. NOS. T-115, 409A, 102 and 51
FOR
COMBINED ARMS TRAINING CENTER, CAMP FUJI, JAPAN
SPECIFICATION AND DRAWINGS PREPARED BY:
NAVFAC FAR EAST, PUBLIC WORKS DEPARTMENT ATSUGI
FACILITIES ENGINEERING & ACQUISITION DIVISION
PE/PED: DATE: 18 Dec 2017
BR MGR:
DATE
NAVFAC FE PW2 DATE
For Commander, NAVFAC: DATE:
UNCLASSIFIED/FOR OFFICIAL USE ONLY
SRN12603385
PART I - THE SCHEDULE
SECTION C: DESCRIPTION/SPECIFICATIONS/WORK STATEMENT
Annex Sub-Annex Spec Item # Title
Annex 1 0100000 1 General Information
Annex 2 0200000 2 Management and Administration
Annex 15 1502000 1 General Information
Annex 15 1502000 2 Management and Administration
Annex 15 1502000 3 Recurring Work (Not Applicable)
Annex 15 1502000 4 Non-Recurring Work
0100000 – General Information Spec Item Title Description 1 General Information
1.1 Outline of Services Except where otherwise stated, the Contractor shall furnish all labor, supervision, management, tools, materials, equipment, facilities, transportation, incidental engineering, and other items necessary to provide the services outlined below and described in this Performance Work Statement (PWS) at Combined Arms Training Center (CATC) Camp Fuji, Japan under a performance-based contract that is comprised of both Recurring Work and Non-Recurring Work Items.
The PWS is organized into annexes. Annex 1 is "General Information".
Annex 2 contains the on-site project management and administration requirements. Annexes 3 through 18 contain the technical requirements.
The annex numbers are identified as 1 through 18 in the description column, but the full expanded annex numbers include seven digits (e.g., Annex 1 expanded number is 0100000 as shown in the header row at the top of this page).
Annex 1 General Information Annex 2 Management and Administration Annex 3 N/A (Not Applicable) Annex 4 N/A Annex 5 N/A Annex 6 N/A Annex 7 N/A Annex 8 N/A Annex 9 N/A Annex 10 N/A Annex 11 N/A Annex 12 N/A Annex 13 N/A Annex 14 N/A Annex 15 Facilities Support Sub Annex 1502000 Facility Investment Annex 16 N/A Annex 17 N/A Annex 18 N/A
1.2 Project Location The work shall be performed but not limited to Bldgs. T-115, 409A, 102, 51, and their vicinity area in CATC Camp Fuji.
1.3 Acquisition of
Additional Work
The Government reserves the right to acquire additional services at additional locations identified in the recurring work requirements of this contract. Additional services will be incorporated into the contract in accordance with the CHANGES clause, SECTION I or ordered under the indefinite delivery indefinite quantity provisions of the contract. Items of work not covered by this contract but within the general intent are considered in the scope of this contract.
1.4 Background Information The listed buildings will no longer be used.
See local information at following website; http://www.fuji.marines.mil/
1.5 Verification of
Workload and Conditions
Throughout the PWS, the workload data is generally referred to as being located in Section J. Section J provides data such as inventories, maps, floor plans, and tables to represent the type, quantity and location of services to be provided. However, offerors are encouraged to visit the project site during the site visit for offerors and to visit the technical library during posted hours as part of its due diligence to assess the nature
0100000 – General Information Spec Item Title Description of work and conditions under which work is to be performed.
1.6 Climate Patterns Climate patterns for Camp Fuji are typical to Gotemba city’s climate patterns that have four seasons. Refer to Japan Meteorological Agency’s website: http://www.jma.go.jp/jma/index.html
1.7 Related Information There are four types of Related Information that can be found in the Description and Related Information columns of the specification as follows:
Informational Notes as used throughout this PWS provides additional information to offerors to be used in developing a thorough understanding of the work to be performed in this contract. Any block of text marked “Informational Notes” throughout Annexes 1 through 18 is subject to this disclaimer. Offerors may not rely upon the "Informational Notes" as material representations of the Government. Information provided in "Informational Notes" does not create a contractual requirement on either party to this contract.
Clarifying Information describes client expectations in a more detailed manner than the Performance Objective and Performance standard alone.
Constraining Information describes limitations to the work performed to meet the Performance Objective and Performance Standard.
Requirement Information further describes client requirements associated with each Performance Objective.
1.8 Navy Approach to
Service Contracting
The Department of Navy (DoN) spends over $1 billion in annual obligations to meet global requirements for facility operations and maintenance provided through Facility Support Contracts (FSC) and additional billions to provide other base operations support services (OBOS). The Head of the Contracting Activity (HCA) of the Naval Facilities Engineering Command (NAVFAC) has focused increased attention on re-engineering FSC contracts in response to customer and industry feedback, budget constraints, and the impact of a variety of contracting, program management and financial management regulations.
The Navy also supports the following principles:
1.8.1 Partnering Philosophy The first principle is that the Navy views its contractors as partners and not just abstract service providers. The Navy wants its contractors to succeed because partners' success drives the Navy's successful mission completion.
Within the bounds of acquisition policy the Navy intends to work to find solutions that will be beneficial to both the Government and its partners.
1.8.2 Contractor's Knowledge The second principle is that the Navy will receive insightful management from its contractors. This management will include the knowledge, skills, authority and willingness to use contractor resources to find better ways of serving Navy clients’ strategic and operational goals and objectives. The Navy's use of performance-based objectives evidences this principle.
Although performance work statements will typically contain several levels of performance assessment, the Navy wants its contractors to exercise maximum discretion within bounds of prudent risk management to adjust processes and resources needed to reach specified objectives at the highest performance level.
1.8.3 Industry Best Practices The third principle is that the Navy will adopt industry best commercial practices and maintain state-of-the-art service delivery. It is the Navy's and contractor's responsibility as partners to reach this goal. To that end, 0100000 – General Information Spec Item Title Description the Navy's emphasis will be in evaluating performance objectives (end results).
1.9 Standard Template Key to implementing a programmatic approach is using a standard template that ensures Navy-wide consistency yet affords appropriate tailoring to meet local needs. This contract conforms to the standard template and has been tailored for this solicitation. NAVFAC intends to use this template-based approach for future service contracts. Offerors should develop an understanding of the template as part of performing due diligence in reaching an understanding of the Navy’s requirements and expectations.
The standard template contains 18 standard annexes. Annex 1 will always contain information that is relevant to the entire scope of the contract.
Annex 2 contains on-site project management and administration requirements that are relevant to the entire scope of the contract. Annexes 3 through 18 contain the technical information and requirements peculiar to that technical annex. Within each technical annex, the organization of information and requirements are also standardized. Specification item 1 will always contain General Information. Specification item 2 will always contain the management and administrative requirements. Specification item 3 will always contain the Recurring Work requirements.
Specification item 4 will always contain the Non-recurring Work requirements. Requirements and standards for higher level specification items apply to all subordinate specification items, e.g., Specification Item 4 standards apply to all Non-recurring work specification items.
Specification Item 4.1 is applicable to all 4.1 subordinate specification items. Specification Items 4.2 and 4.3 are not considered subordinate to
4.1. All costs associated with Annexes 1 and 2 and Specification items 1 and 2 must be priced and distributed within Specification Item 4 of Annexes 3 through 18.
1.10 Navy PBSA Approach The Navy’s approach to performance-based service acquisition (PBSA) includes four component parts which are:
1) performance outcomes,
2) measurable standards,
3) consideration of incentives, and
4) performance assessment plan.
1.11 Technical Proposal
Certification
The Contractor warrants that its proposal incorporated herein by reference will meet or exceed the performance objectives set forth in this contract.
0200000 – Management and Administration Table of Contents
Spec Item Title
2 Management and Administration
2.1 Definitions and Acronyms
2.2 General Information
2.2.1 Government Regular Working Hours
2.2.1.1 Observed Federal Holidays
2.2.1.2 Restriction to Contractor Working Hours
2.2.2 Wage Determinations
2.2.3 Requirements Hierarchy
2.3 General Administrative Requirements
2.3.1 Required Conferences and Meetings
2.3.2 Training for Maintenance and Operation of New and Replacement Systems and Equipment
2.3.3 Partnering
2.3.3.1 Informal Partnering
2.3.3.2 Contract Partnering Administration
2.3.3.3 Contract Partnering Session Attendees
2.3.4 Permits and Licenses
2.3.5 Insurance
2.3.5.1 Certificate of Insurance
2.3.5.2 Minimum Insurance Amounts
2.3.6 Protection of Government Property
2.3.7 Government Information Technology (IT) System
2.3.8 Directives, Instructions, and References
2.3.9 Invoicing Procedures
2.3.10 Forms
2.4 Government-Furnished Property, Materials and Services
2.4.1 Government-Furnished Facilities (GFF)
2.4.2 Government-Furnished Utilities
2.4.3 Government-Furnished Materials (GFM)
2.4.4 Government-Furnished Equipment (GFE)
2.4.5 Government-Furnished Services (GFS)
2.5 Contractor-Furnished Items
2.6 Management
2.6.1 Work Reception
2.6.2 Work Control
2.6.3 Work Schedule
2.6.4 Deliverables
2.6.5 Service Interruptions
2.6.6 NAVFAC MAXIMO
2.6.7 Quality Management System (QMS)
2.6.7.1 Quality Management (QM) Plan
2.6.7.2 Quality Inspection and Surveillance
2.6.7.3 Quality Inspection and Surveillance Report
2.6.8 Property Management Plan
2.6.9 System and Equipment Replacement
2.7 Personnel Requirements
2.7.1 Key Personnel
2.7.1.1 Project Manager (PM)
2.7.1.2 Quality Manager
2.7.1.3 Site Safety and Health Officer (SSHO)
2.7.1.4 Environmental/Energy Manager
2.7.2 Employee Requirements
2.7.2.1 Employee Certification and Training
2.7.2.2 Employee Appearance
2.7.2.3 Employee Conduct
2.7.2.4 Identification as Contractor Employee
2.7.2.5 Removal of Employees
2.7.2.6 Proof of Legal Residency
2.7.3 Enterprise-wide Contractor Manpower Reporting Application (eCMRA)
2.8 Security Requirements
2.8.1 Employee Listing
2.8.2 Vehicles
2.8.3 Passes and Badges
2.8.4 Access to Installation
2.8.4.1 NCACS Program
2.8.4.2 One-Day Passes
2.8.5 Access to Buildings
2.8.6 Access Arrangements
2.8.6.1 Escort Arrangement for Secured Areas
2.8.7 Security Clearances
2.8.8 Access to Sensitive Unclassified Information
2.8.9 Employee Status
2.9 Contractor Safety Program
2.9.1 Accident Prevention Plan (APP)
2.9.2 Activity Hazard Analysis (AHA)
2.9.3 Safety and Occupational Health (SOH) Risks and Compliance Plans
2.9.3.1 Alcohol and Drug Abuse Prevention Plan
2.9.3.2 Chemical Hazard Communication Program
2.9.3.3 Confined Space Program
2.9.3.4 Critical Lift Plan
2.9.3.5 Fall Prevention and Protection Plan
2.9.4 Crane Operations
2.9.4.1 Crane Inspections
2.9.4.2 Rigging Gear
2.9.4.3 Crane Operators
2.9.5 Accident and Damage Reporting
2.9.5.1 Accident Reporting and Notification Criteria
2.9.6 Fire Protection
2.9.7 Monthly On-Site Labor Report
2.9.8 OSHA Citations and Violations
2.9.8.1 Japanese Labor Standards Inspection Office (LSIO) Citations and Violations
2.9.9 Safety Inspections and Monitoring
2.9.10 Safety Certification
2.9.11 Safety Apparel on Jobsites
2.9.12 Emergency Medical Treatment
2.10 Environmental Management and Sustainability
2.10.1 Energy Management Program
2.10.1.1 Water Conservation Plan
2.10.1.2 Energy Efficient Products
2.10.2 Environmental Protection
2.10.2.1 ODS Requirements for Refrigerant Recycling
2.10.2.2 Non-Hazardous Waste Disposal
2.10.2.3 Hazardous Waste Disposal
2.10.2.4 Spill Prevention, Containment, and Clean-up
2.10.2.5 Hazardous Material Management
2.10.2.6 Protection of Endangered and Threatened Species (Flora and Fauna)
2.10.2.7 Noise Control
2.10.2.8 Salvage
2.10.2.9 Asbestos Containing Material (ACM)
2.10.3 Sustainable Procurement and Practices
2.10.3.1 Environmentally Preferable Products
2.10.3.2 Use of Recovered Materials
2.10.3.3 Use of Biobased Products
2.11 Disaster Preparedness
2.12 Technical Library
2.13 Warranty Management
2.14 Recurring Work Procedures
2.15 Non-recurring Work
2.15.1 Unit Priced Task (UPT) Work (Non-Negotiated)
2.15.1.1 Acceptance and Performance
2.15.1.2 Invoicing and Receiving Payment
2.15.2 Unit Priced Labor (UPL)Work (Negotiated)
2.15.2.1 Non-recurring Preparation of Proposals
2.15.2.1.1 Labor Requirements
2.15.2.1.2 Material and Equipment Requirements
2.15.2.2 Issuance of Final Task Order
2.15.3 Non-recurring ELINS
0200000 - Management and Administration Spec Item Title Description 2 Management and
Administration
2.1 Definitions and
Acronyms
Definitions and Acronyms are listed in J-0200000-01.
2.2 General Information
2.2.1 Government Regular
Working Hours The Government's regular working hours are from 0745-1630, five days per week, Monday through Friday, except observed Federal holidays.
Exceptions to the regular hours of operation are detailed in subsequent sections of this PWS. Work in certain annexes or sub-annexes require Contractor continuous operations, 24 hours a day, every day of the year including holidays. The performance of other work requirements shall be accomplished within the Government’s regular working hours unless the specific work requirement specified herein necessitates otherwise. Any other work outside Government regular working hours requires prior KO approval.
2.2.1.1 Observed Federal
Holidays
The Government observes the following holidays: New Year’s Day, Martin Luther King Jr.’s Birthday, President’s Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans’ Day, Thanksgiving Day, and Christmas Day.
2.2.1.2 Restriction to
Contractor Working Hours
If the Contractor wishes to work outside of the Government's regular working hours for the Contractor’s convenience, the Contractor shall submit a written Request to Work Outside Government’s Regular Working Hours per Section F. Excludes work to be performed during specified hours.
2.2.2 Wage Determinations Not Applicable.
2.2.3 Requirements
Hierarchy Requirements or definitions specified in each spec item of this contract apply to subordinate paragraphs. For example, requirements shown in spec item 4.1 would apply to spec items 4.1.1, 4.1.2, 4.1.2.1 and so on.
Likewise, Performance Standards specified at a lower digit level (i.e. spec item 4.1.1, 4.1.2, 4.1.2.1) apply when performance is assessed at a higher tier (i.e., spec item 4.1) based on the composite work requirements.
2.3 General Administrative
Requirements
2.3.1 Required Conferences
and Meetings
The Contractor may be required to attend administrative and coordination meetings. The Contractor shall attend meetings as requested by the Contracting Officer.
2.3.2 Training for
Maintenance and Operation of New and Replacement Systems and Equipment
When construction, renovation, or repair work is performed by means other than this contract, the Contractor shall attend Government provided training, as applicable, for maintenance and operation of new and replacement systems and equipment at no additional cost to the Government.
Upon the completion of repair and/or replacement work performed by the Contractor at each location, the Contractor shall provide “on the job site training” to the Government and/or Contractor employees to ensure all functions and operations of new equipment and system utilized for routine operation and maintenance work are fully captured and understood.
Training will be performed at no additional cost to the Government.
2.3.3 Partnering To increase the likelihood of successful performance of this contract, the Government requires cohesive partnerships with its Contractors and
0200000 - Management and Administration Spec Item Title Description subcontractors. Key stakeholders, including the supported commands who will receive services, principal individuals from NAVFAC, the performance assessment team, and representative(s) of the installation(s) will be invited to participate in the partnering process. Key members of the prime and subcontractors teams, including senior management personnel must participate. The partnership will draw on the strength of each organization in an effort to achieve quality contract services done right the first time, within the contract price, as scheduled, and without any safety mishaps.
Partnering should accomplish three goals:
- The first goal is to develop a cohesive team with common purpose, commitment and established communication processes.
- The second goal of partnering is contract specific, identifying risks and opportunities for the team to address.
- The third goal is to sustain the Partnership throughout the contract by identifying and addressing issues that affect the Partnership.
2.3.3.1 Informal Partnering The Contracting Officer shall organize the initial Partnering Meeting with key personnel of the project team, including Contractor's personnel and Government personnel. The initial session will be scheduled concurrent with the Pre-Performance Conference and held no later than 30 days after award and will be held at a Government provided facility as designated by the KO.
The Initial Informal Partnering Session will be conducted and facilitated by the Contracting Officer. The senior Government stakeholder present will lead the meeting, however, the Contractor’s PM or senior representative is encouraged to participate as co-lead.
The Partners will determine the frequency of the follow-on sessions.
2.3.3.2 Contract Partnering
Administration
Upon award, the ACO will contact the Contractor, supported command(s), Region, and Installation(s) stakeholders, and the performance assessment team to discuss implementation of partnering. A partnership agreement, The Charter, should be in place as early as possible so issues arising, even before work begins, can be resolved using the issues resolution process.
Replacement of Core Management Team members (stakeholders who attended the initial session and manage the contract work day-to-day) is discouraged since it will disrupt the synergy that has been developed. If replacement of a team member proves to be unavoidable, a follow-on partnering session must be held to officially turn the responsibilities of the position over to the new member.
The Core Management Team consisting of the attendees below must be present during the initial and all follow-on partnering sessions. These are the core mandatory attendees. Other stakeholders may attend if they desire or as recommended by the partners.
2.3.3.3 Contract Partnering
Session Attendees
The Contractor shall bring the necessary personnel to successfully partner on this contract. Asterisk indicates mandatory personnel.
President/Vice President
* Project Manager
* Quality Manager Site Safety and Health Officer
2.3.4 Permits and Licenses The Contractor shall obtain all required permits, licenses, and
0200000 - Management and Administration Spec Item Title Description authorizations to perform work under this contract and comply with all the applicable Federal, state and local laws and regulations. The Contractor shall submit copies of Permits and Licenses per Section F.
2.3.5 Insurance The Contractor shall submit a Certificate of Insurance per Section F as evidence of the existence of the following insurance coverage in amounts not less than the amounts specified below in accordance with the FAR Clause 52.228-5, INSURANCE – WORK ON A GOVERNMENT INSTALLATION. This insurance must be maintained during the performance period.
2.3.5.1 Certificate of Insurance The Certificate of Insurance shall provide for at least 30 calendar days written notice to the KO by the insurance company prior to cancellation or material change in policy coverage. Other requirements and information are contained in the aforementioned insurance clause.
2.3.5.2 Minimum Insurance
Amounts
The Contractor shall procure and maintain, during the entire period of performance under this contract, the following minimum insurance coverage:
1) Comprehensive General Liability: ¥50,000,000 per occurrence.
2) Automobile Liability: ¥20,000,000 per person, ¥50,000,000 per occurrence, ¥2,000,000 per occurrence for property damage.
3) Workers' Compensation: As required by Japanese workers' compensation and occupational disease statutes.
4) Employer's liability coverage: ¥10,000,000.
5) Other as required by Japanese law.
2.3.6 Protection of
Government Property
During execution of the work, the Contractor shall protect Government property. The Contractor shall return areas damaged as a result of negligence under this contract to their original condition at no cost to the Government.
2.3.7 Government
Information Technology (IT) System
Not Applicable
2.3.8 Directives, Instructions, and References
Department of Defense (DoD), Secretary of the Navy (SECNAV), Chief of Naval Operations (OPNAV), and other applicable Directives, Instructions, and References are listed in J-0200000-03. The Contractor shall comply with the most current version of directives, instructions, and references including versions published during the term of the contract.
2.3.9 Invoicing Procedures Refer to Section G for invoicing instructions and J-0200000- 05 for Invoice Form sample.
2.3.10 Forms Forms referenced in this Annex, e.g. accident reporting, and damage reporting are included among the Forms in J-0200000-05.
2.4 Government-Furnished
Property, Materials and Services
In accordance with FAR 52.245, GOVERNMENT PROPERTY and NAVFAC Clause 5252.245-9300, GOVERNMENT-FURNISHED PROPERTY, MATERIALS AND SERVICES, and the following paragraphs, the Government will furnish or make available to the Contractor certain Government-owned facilities, utilities, materials, equipment and services for use in connection with this contract as stated below.
0200000 - Management and Administration Spec Item Title Description
A list of Government Furnished Property, Materials, and Services is provided in J-0200000-06.
2.4.1 Government-Furnished
Facilities (GFF)
Refer to J-0200000-06.
2.4.2 Government-Furnished
Utilities
Refer to J-0200000-06.
2.4.3 Government-Furnished
Materials (GFM)
None.
2.4.4 Government-Furnished
Equipment (GFE)
None.
2.4.5 Government-Furnished
Services (GFS)
None.
2.5 Contractor-Furnished
Items
Except for items identified as Government Furnished, the Contractor shall provide all equipment, materials, parts, supplies, components, and facilities to perform the requirements of this contract. The KO may inspect Contractor-furnished items for adequacy and compliance with contract requirements. Inadequate or unsafe items shall be removed and replaced by the Contractor at no cost to the Government. Materials containing asbestos, lead, and polychlorinated biphenyls (PCBs) shall not be brought onsite. Energy efficient tools and equipment shall be used when available. The KO may at any time require Samples, Safety Data Sheets (SDS) or Manufacturer’s Data Cut Sheets of Materials used in this contract.
2.6 Management The Contractor shall manage the total work effort associated with the services required herein to meet the performance objectives and standards.
Such management includes but is not limited to planning, scheduling, cost accounting, report preparation, establishing and maintaining records, and quality assurance. The Contractor shall provide a staff with the necessary management expertise to ensure performance objectives and standards are met.
2.6.1 Work Reception The Contractor shall provide the capability to receive, prioritize, correspond, and respond to service orders and task orders during Government regular working hours and provide a point of contact at a local or toll free number who can perform the above function during other than Government regular working hours, twenty-four (24) hours, Monday through Sunday, seven (7) days a week throughout the contract period, including federal holidays.
Submit work reception information per Section F.
2.6.2 Work Control The Contractor shall implement all necessary work control procedures to ensure timely accomplishment of work requirements, as well as to permit tracking and reporting of work in progress. The Contractor shall plan and schedule work to assure material, labor, and equipment are available to complete work requirements within the specified time limits and in conformance with the quality standards established herein. Verbal scheduling and work status updates shall be provided when requested by the KO. A status update of any item of work must be provided within two
(2) hours of the inquiry during regular working hours, and by 0945 hours the following work day for inquiries after regular working hours.
It is the Contractor’s full responsibility to coordinate with and notify affected tenants/organizations/commands of the work schedule and system interruption duration even if the Government organization did the
0200000 - Management and Administration Spec Item Title Description schedule notice. The Contractor shall maintain good and professional communication with them all the time.
Prior to any work, the Contractor shall notify activities and customers of the exact work schedule and duration of interruption of each system.
Notification deadline will be specified by the KO.
Customers and maintenance personnel shall be provided with appropriate updated information about equipment and systems.
2.6.3 Work Schedule The Contractor's work shall not interfere with normal Government business. In those cases where some interference is unavoidable, the Contractor shall minimize the impact and effects of the interference. The Contractor shall provide advance access of all of its work schedules to the Government. The Contractor shall notify the KO of any difficulty in scheduling work due to Government controls.
The Contractor will be required to provide close coordination with all concerning activities for establishment of work schedule and for successful work performance.
Non-Recurring Work Schedule: Immediately after receipt of task order(s), and prior to starting the work (at least five (5) working days in advance;
confirm with KO) all work schedules for non-recurring work shall be submitted to and shall be approved by the KO and customer per Section F.
Work Outside Regular Working Hours, and Its Request: If the Contractor desires to carry on work outside of the station's regular working hours, he shall submit, no later than fifteen (15) calendar days prior to the requested date, a written application giving the specific dates, hours, location, type of work to be performed, contract number, and project title to the KO for approval consideration. Depending on the scale of the work, the Contractor may have to submit the request much earlier than the fifteen
(15) calendar days prior to the requested date. The Contractor, therefore, well in advance, shall consult with the KO for its schedule. Service order work of emergency or urgent nature will not need this request.
2.6.4 Deliverables Records and reports are specified in Section C and listed as deliverables in Section F. The Contractor shall submit accurate and complete documents within the required timeframes as specified in Section F.
Government acceptance of deliverables will not relieve the Contractor of the responsibility for any error or omission which may exist in the deliverable, as the Contractor is responsible for all requirements of this contract.
The deliverables’ format, even once approved, will be subject to change during the contract period at no additional cost to the Government in order to capture information that may be utilized in future planning for the Government.
2.6.5 Service Interruptions If any utilities or other services (including but not limited to road, fire lane, fire protection systems and other systems) must be discontinued (even temporarily) due to scheduled contract work, the Contractor shall notify the KO, affected tenants, and customers in accordance with local procedures. The Contractor shall request in writing a minimum of fifteen
(15) calendar days prior to the desired work date per Section F. As soon
0200000 - Management and Administration Spec Item Title Description as the request is approved by the KO/Security/Fire Dept or other Department, notify the affected tenants, and customers of the outage or closure. Depending on the scale of the work, the Contractor may have to submit the request much earlier than the fifteen (15) calendar days prior to the requested date. The Contractor, therefore, well in advance, shall consult with the KO for its schedule.
If the discontinued service is due to an emergency breakdown the Contractor shall notify the KO, affected tenants and customers as soon as practicable.
2.6.6 NAVFAC MAXIMO MAXIMO is the Computerized Maintenance Management System (CMMS) used by the Government for work order history, asset management, and condition assessment. The Contractor shall provide all required data for NAVFAC MAXIMO as identified below:
As soon as the Contractor completes installation of new equipment, the Contractor shall fill out and submit per Section F an ICAP Inventory List or UICAP Inventory List which will be utilized by the Government for CMMS. Refer to J-0200000-05 for ICAP inventory list blank form.
2.6.7 Quality Management
System (QMS)
The Contractor shall establish and maintain a complete QMS program in accordance with the provisions specified herein. The Contractor’s QMS program shall provide an effective and efficient means of identifying and correcting problems throughout the entire scope of operations. The Contractor's QMS program shall address:
Accurate documentation of work processes, procedures, and output measures.
A systematic procedure for assessing compliance with performance objectives and standards.
Accurate documentation of quality inspections and surveillance conducted throughout the execution of work.
Assessment-driven corrective actions and process adjustments as appropriate in a timely manner.
2.6.7.1 Quality Management
(QM) Plan
The Contractor shall develop and submit a QM Plan per Section F. The QM Plan shall describe the QMS methodology and approaches used under this contract. If any changes are made during the period of performance, submit to the KO a revised QM Plan for acceptance.
The Contractor’s QM Plan shall include, at a minimum, the following:
• Policy and objectives of Quality Management System (QMS)
• Quality organization o List of personnel o Responsibilities & lines of authority o Training and qualifications
• Approach to assuring quality of services provided and conformance with performance objectives and standards
• Methods and procedures for effective planning, operation and control of processes and performance of work
• Procedures for inspection and surveillance of services o Scheduling and performance of inspection and surveillance o Measurement, data collection and analysis o Corrective action, preventive action, and continuous improvement
0200000 - Management and Administration Spec Item Title Description o Oversight of subcontracted work
• Documentation and records management
• Communication with government (customers)
2.6.7.2 Quality Inspection and
Surveillance
The Contractor shall establish and maintain an inspection and surveillance system in accordance with the FAR Clause 52.246-4, INSPECTION OF SERVICES – FIXED PRICE, to ensure that the work performed conforms to the contract requirements. The Contractor shall document and maintain a file of all scheduled and performed inspections and surveillances, inspection and surveillance results, and dates and details of corrective and preventive actions. The quality inspection and surveillance file shall be the property of the Government and made available during the Government’s regular working hours. The file shall be turned over to the KO within five calendar days of termination of the contract as indicated in Section F.
2.6.7.3 Quality Inspection and
Surveillance Report
The Contractor shall submit a copy of the Contractor Quality Inspection and Surveillance Report per Section F. The Contractor Quality Inspection and Surveillance Report shall include a summary and results of the quality inspection and surveillance events performed and assessment-driven corrective actions and process adjustments during the previous month.
The Government may adjust the frequency of the submittal based on the Contractor’s quality of performance.
2.6.8 Property Management
Plan
The Contractor shall establish and maintain a plan that meets the contract clause requirements of Specification Item 2.4, Government-Furnished Property, Materials and Services, of this Annex. This plan shall identify the Contractor’s policies, procedures, and practices in receiving and performing physical inventories, repairing and maintaining, preserving and protecting, and reporting the disposition of accepted government property in its possession. The Property Management Plan shall be submitted per Section F.
2.6.9 System and Equipment
Replacement
The Contractor shall maintain the integrity and performance of existing energy saving, water conservation or other sustainability design features of systems and equipment in the performance of repair and replacement work. Except where otherwise specified, replacement components shall be of the same model/style or equivalent as the component being replaced.
Substitutes for replacement components must be accepted by the KO prior to use. The KO will furnish available information for the existing systems and equipment.
2.7 Personnel
Requirements
The Contractor shall comply with the personnel requirements stated below.
The Contractor will not be allowed to bring any employees aboard United States Forces, Japan (USFJ) installations and areas from countries listed in under USFJ Instruction 31-204 (Designated Third Country Nationals.)
2.7.1 Key Personnel The Contractor shall submit a List of Key Personnel and Qualifications per Section F. The Contractor shall provide any additional information requested by the KO necessary to certify their qualifications.
Key personnel shall be able to speak, read and comprehend English to the extent that they can perform the contract requirements and comply with installation emergency procedures or an interpreter shall be made available at no additional cost to the Government.
The Contractor shall submit an Organizational Chart per Section F
0200000 - Management and Administration Spec Item Title Description showing lines of authority of the key personnel for this contract. The chart shall include names of personnel and their position title in this contract. As a minimum, include the PM, Quality Manager, SSHO, and who they will report directly to for this contract. The key personnel shall be revised as applicable for the contract.
Any potential replacement of departing key personnel shall be subject to the acceptance of the Government.
One person cannot share all the positions of these key personnel.
2.7.1.1 Project Manager (PM) The Contractor shall provide a PM and designated alternate, as applicable, who has the have full authority to act for the Contractor on all contract matters relating to this contract. The PM or alternate shall be available on-site within two hours after the Government’s request. The PM, including alternate shall be an employee of the prime contractor. Sub-contractor employees cannot assume PM or alternate PM position.
The PM shall have at least three years of experience in managing a workforce providing services on contracts of similar size, scope and complexity.
2.7.1.2 Quality Manager The Contractor shall provide a Quality Manager or designated alternate and shall be on-site during the Government's regular working hours when the Contractor is performing work and shall be available on-site within two hours after the Government’s regular working hours. The Quality Manager must report directly to a senior corporate official and shall not report directly to the Project Manager.
The Quality Manager shall have fulfilled the following pre-requisite training and experiences before being hired as the Quality Manager under this contract:
The Quality Manager shall have at least three years of experience in preparing and enforcing QMS programs on contracts of similar size, scope and complexity. The Quality Manager may be the same person as the
SSHO.
2.7.1.3 Site Safety and Health
Officer (SSHO)
The SSHO must meet the requirements of EM 385-1-1 Section 1 and ensure that the requirements of 29 CFR 1926.16 are met for the project.
Provide a Safety oversight team that includes a minimum of one Competent Person at each project site to function as the Site Safety and Health Officer (SSHO). The SSHO or an equally-qualified Designated Representative/alternate shall be on-site at all times when work is being performed to implement and administer the Contractor's safety program and government-accepted Accident Prevention Plan. The SSHO's training, experience, and qualifications shall be as required by EM 385-1-1 paragraph 01.A.17, entitled SITE SAFETY AND HEALTH OFFICER (SSHO), and all associated sub-paragraphs.
A Competent Person shall be provided for all of the hazards identified in the Contractor's Safety and Health Program in accordance with the accepted Accident Prevention Plan, and shall be on-site at all times when the work that presents the hazards associated with their professional expertise is being performed. Provide the credentials of the Competent Persons(s) to the Contracting Officer for acceptance in consultation with the Safety Office.
The Contractor shall provide a SSHO whose primary duty and responsibility is to prepare and enforce the Contractor’s safety program on this contract. The SSHO shall have fulfilled the following pre-requisite training and experiences before being hired as the SSHO under this contract:
The SSHO shall have completed five (5) years of satisfactory experience in preparing and enforcing safety programs on contracts of similar size and complexity in the past or three (3) years experience if he possesses a Certified Safety Professional (CSP) or safety and health degree. The SSHO shall have completed the OSHA 30-hour construction safety class or equivalent and maintain competency through 24 hours of formal safety and health related coursework every four (4) years. The SSHO may be the same person as the project manager but shall have fulfilled the pre-requisite qualification and experience.
Note: Host Nation Safety training will be considered to the equivalent 30 hour OSHA Construction safety class training requirement. The Japan Construction Occupational Safety and Health Association (JCOSHA) provides' the construction safety course "Kouji Shunin", or "Course for Construction Site Managers", which is an acceptable equivalent to the 30- Hour OSHA Construction Safety Course mentioned above. Completion of this training will fulfill the requirements of the above. This training can be viewed at the JCOSHA website http://www.kensaibou.or.jp, or http://www.kensaibou.or.jp/english.
These training courses have five (5) years of validated date. The SSHO shall maintain renewal of certificates. Information of the SSHO refresher course can be viewed at the website below:
http://www.kensaibou.or.jp/seminar/information.aspx?LevelId=107
2.7.1.4 Energy Manager The Contractor shall provide an Environmental/Energy Manager whose duty and responsibility is to ensure Contractor operations adhere to the goals and policies of the Environmental Management System, the Installation Energy Plan, and other specified Sustainability requirements affecting this contract. The Environmental/Energy Manager shall develop, implement and monitor environmental strategies, policies and programs that promote sustainable development and examine the contract activities to establish where improvements can be made and ensure compliance with environmental legislation and energy policy.
The Environmental/Energy Manager shall have a minimum two years experience with environmental procedures similar to those of this contract;
familiarity with Environmental Management Systems (EMSs); and knowledge of environmental regulations and federal energy laws and policy (including energy and water reduction requirements and renewable energy requirements) that are applicable to operations similar to those of this contract.
2.7.2 Employee
Requirements
The Contractor shall provide experienced, qualified, and capable personnel to perform the work in this contract. Personnel shall be fully knowledgeable of all safety, environmental, and energy requirements associated with the work they perform. Personnel shall speak, read, and comprehend English to the extent that they can perform the contract requirements and comply with installation emergency procedures, or the
0200000 - Management and Administration Spec Item Title Description
Contractor shall provide interpreter for them at no additional cost to the Government.
2.7.2.1 Employee Certification
and Training
The Contractor shall maintain personnel certification, training, and licensing records for employee requirements specified herein and within all technical annexes/sub-annexes. Certification, training, and licensing records shall be kept current and on file for the duration of the contract including all option periods. Records shall be made available for Government review within four (4) hours of request.
2.7.2.2 Employee Appearance The Contractor shall ensure that all employees present a professional appearance that is appropriate for their position. The KO reserves the right to determine the acceptability of any clothing worn. All Contractor/subcontractor employees working under this contract shall be identified by a distinctive nameplate, emblem, or patch attached in a prominent place on an outer garment. Employee identification shall not be substituted for station required passes or badges.
2.7.2.3 Employee Conduct Contractor employees shall conduct themselves in a proper, efficient, courteous and businesslike manner.
2.7.2.4 Identification as
Contractor Employee
Contractor employees shall identify themselves as Contractor personnel by introducing themselves or being introduced as Contractor personnel and displaying distinguishing badges or other visible identification for meetings with Government personnel. All Contractor employees shall appropriately identify themselves as contractor employees in telephone conversations and in formal and informal written correspondence.
2.7.2.5 Removal of Employees The Contractor shall remove from the site any individual whose continued employment is deemed by the KO to be contrary to the public interest or inconsistent with the best interests of National Security.
2.7.2.6 Proof of Legal
Residency
No employee or representative of the Contractor will be admitted to the site of work unless satisfactory Proof of Japanese citizenship or Proof of Legal Residency within Japan is furnished per Section F.
2.7.3 Enterprise-wide
Contractor Manpower Reporting Application (eCMRA)
The Contractor shall report all contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: https://doncmra.nmci.navy.mil.
Per Section F, reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk, linked at https://doncmra.nmci.navy.mil.
2.8 Security Requirements The Contractor shall comply with all Federal, state, and local security statutes, regulations, and requirements. The Contractor shall become acquainted with and comply with all Government regulations as posted, or as requested by the KO when required to enter a Government site. The Contractor shall ensure that all security/entrance clearances are obtained.
a. The Contractor shall comply with all activity security requirements. Upon request, the Contractor shall submit the name and address of each employee performing work under this contract and shall have the employees fill out questionnaires and other forms required for security.
0200000 - Management and Administration Spec Item Title Description
b. Neither the Contractor nor any of his employees shall disclose or cause to be disseminated any information concerning the operations of the activity which could result in or increase the likelihood of the possibility of a breach of the activity's security or interrupt the continuity of its operations.
c. Disclosure of information to any person not entitled to receive it, or failure to safeguard any classified information that may come to the Contractor or any person under his control, may subject the Contractor, his agents or employees to criminal liability under Title 18, Sections 793 and 798 of the United States Code.
d. All inquiries, comments or complaints arising from any matter observed, experienced, or learned as a result of or in connection with the performance of this contract, the resolution of which may require the dissemination of official information shall be directed to the KO.
e. Deviations from or violations of any of the provisions of this paragraph will, in addition to all other criminal and civil remedies provided by law, subject the Contractor to immediate termination for default and/or the individuals involved to a withdrawal of the Government's acceptance and approval of employment.
2.8.1 Employee Listing The Contractor shall maintain a current Employee List and submit per Section F. The list shall include the following;
1) employee’s name
2) date of birth
3) place of birth
4) citizenship (if not Japanese, attach a copy of passport)
5) address
6) supervisor
7) company, and
8) level of security clearance
After receipt of the names and obtaining of security clearances, the Pass Office at CATC Camp Fuji Security Office will issue a Contractor's pass and/or badge to each person on the list. No personnel will be permitted on the site without a valid pass and/or badge. When within the confines of the CATC Camp Fuji personnel shall have their passes and/or badges immediately available and shall produce them for identification purposes when requested by security authorities. When an employee leaves the Contractor's service, the employee's pass and badge shall be returned immediately to the Contracting Officer. Passes and/or badges issued to Contractor employees shall not negate the requirement for employee identification required in the “IDENTIFICATION OF CONTRACTOR EMPLOYEES” item. Submit a copy of picture ID per employee.
2.8.2 Vehicles Prior to the start of on-site work, and as changes are made thereafter, the Contractor shall submit a list of vehicles to be utilized during the project to the KO and shall include the following information for each vehicle:
1) Make
2) Year
3) Type
0200000 - Management and Administration Spec Item Title Description
4) License Number
5) Insurance (both compulsory and voluntary insurance original copy will be required for vehicle pass registration. Voluntary insurance certificate document may be acceptable if it is not a copy.)
6) Policy Number
7) Expiration Date of Insurance
8) For Rental Vehicle; Rental Contract Certificate Document
9) Vehicles with installed cameras shall ensure recording capability is disabled prior to entering the installation.
The Contractor shall request vehicle passes per Section F.
Decals shall be placed inside each of the Contractor's vehicles in a manner and size that is clearly visible. All vehicles shall display a valid license plate. Vehicles shall meet all other requirement of local regulations, such as safety standards and exhaust gas regulations, and shall carry proof of insurance, safety inspection record and registration.
The Contractor’s vehicles used for this contract shall have a company name displayed on each side of the Contractor's vehicles or shall have contractor’s nameplate or similar item by which the Government can identify the vehicle’s purpose. The company name displayed and nameplate or similar item shall be in a manner and size that is clearly visible.
2.8.3 Passes and Badges All Contractor employees shall obtain the required employee and vehicle passes. The Government will issue them without charge. Each employee shall carry the Government issued pass (and badge, if issued, over the front of the outer clothing) at all times. When an employee leaves the Contractor's service, the employee's Passes and Badges shall be returned within ten (10) calendar days as indicated in Section F.
Badges, passes or decals missing or lost and the circumstances surrounding them shall be reported immediately to the source of issue.
Upon termination, expiration, completion of contract, or when no longer…