2 Coefficient Contractor Estimate Worksheet.xlsx

XLSX spreadsheet 14 KB Posted

Attached to
NRDE GENERAL CONSTRUCTION IDIQ JOC FOR PAX/IH/DAHL
Solicitation number
N4008022R0042
Issued by

View the file

Other files

File Type Posted
ATTACHMENT 4-Teaming Consent F.docx DOCX document
ATTACHMENT 5-RFI Form F.docx DOCX document
ATTACHMENT 2 - Safety Data Sheet F.docx DOCX document
ATTACHMENT 1 - Project Data Sheet F.docx DOCX document
ATTACHMENT 3-Past Performance Questionnaire F.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRE-PRICED COEFFICIENT

PRE-PRICED COSTSMATERIALSLABOREQUIPMENTAMOUNT
PRE-PRICED COEFFICIENT
RS MEANS BARE COST (PRESUMED ANNUAL AMOUNT)$6,300,000.00$3,500,000.00$200,000.00$10,000,000.00
WORKER'S COMP INSURANCE$0.00
AVERAGE FIXED LABOR OVERHEAD$0.00
PROJECT OVERHEAD PRE-PRICED$0.00
MATERIAL MARKUP$0.00
EQUIPMENT MARKUP$0.00
SUBTOTAL$0.00
GENERAL AND ADMINISTRATIVE$0.00
PROFIT$0.00
TOTAL$0.00
COEFFICIENT FACTOR (TOTAL DIVIDED BY PRESUMED ANNUAL AMOUNT)0
RS MEANS BARE COST ADJUSTMENT (PRODUCTION/DISCOUNT - FACTOR)0.9
PRE-PRICED COEFFICIENT0.9

NON PRE-PRICED COEFFICIENT

PRE-PRICED COSTSMATERIALSLABOREQUIPMENTAMOUNT
NON PRE-PRICED COEFFICIENT
NON PRE-PRICED BARE COSTS (PRESUMED ANNUAL AMOUNT)$630,000.00$350,000.00$20,000.00$1,000,000.00
WORKER'S COMP INSURANCE$0.00
AVERAGE FIXED LABOR OVERHEAD$0.00
PROJECT OVERHEAD NON PRE-PRICED$0.00
MATERIAL MARKUP$0.00
EQUIPMENT MARKUP$0.00
SUBTOTAL$0.00
GENERAL AND ADMINISTRATIVE$0.00
PROFIT$0.00
TOTAL$0.00
COEFFICIENT FACTOR (TOTAL DIVIDED BY BARE COST)0.000
NON-PRE-PRICED BARE COST ADJUSTMENT (PRODUCTION/DISCOUNT - FACTOR)1
NON PRE-PRICED COEFFICIENT1

File details come from the government source that posted it. Updated .