GPOL_Clean _Inspect_and_Repairs_POL_Facilities _NAS_Pensacola_PART_2-6.pdf
PDF 2 MB Posted
- Solicitation number
- N39430-14-R-1405
About this file
Seed Project Clean Inspect Repairs POL Facilities at NAS Pensacola FL Parts 2-6. 05 Mar 2014
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N39430-14-R-1405_Amendment_0003.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CLEAN, INSPECT, REPAIR
POL FACILITIES
at the
NAVAL AIR STATION PENSACOLA
PENSACOLA, FL
5 MAR 2014
Table of Contents
Part 1 – Contract Forms and Conditions
Part 2 – Project Program Task Order Specific Requirements
Part 3 – Project Program
1. Project Description
2. Project Objectives
3. Site Analysis
4. Building Requirements
5. Room Requirements
6. Engineering System Requirements
Part 4 – Performance Technical Specifications Per Basic MACC Contract
Part 5 – Prescriptive Technical Specifications
Part 6 – Attachments
1. Performance Assessment Plan Form
2. Permit Record of Decision Form
3. Tank Summary Sheets
4. Inspection Checklist
5. Automated Tank Gauge (ATG) Installation Guidance
6. Excavation Permit Form NASPNCLAINST 11010.3
7. Project Certification Report Minimum Requirements
CLEAN, INSPECT, REPAIR
POL FACILITIES
at
NAVAL AIR STATION PENSACOLA
PENSACOLA, FL
PART 2 DIVISION 01
SPECIFICATIONS
SPECIFICATIONS BY:
NAVFAC EXWC
POL FACILITIES ENGINEERING
1100 23RD AVENUE
PORT HUENEME, CALIFORNIA 93043
5 MAR 2014
Page Intentionally Blank
Clean Inspect Repair POL Facilities NAS Pensacola
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00.05 20 WORK RESTRICTIONS FOR DESIGN-BUILD
01 20 00.05 20 PRICE AND PAYMENT PROCEDURES FOR DESIGN-BUILD
01 30 00.05 20 ADMINISTRATIVE REQUIREMENTS FOR DESIGN-BUILD
01 31 19.05 20 POST AWARD MEETINGS
01 32 17.05 20 NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD
01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES
01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES
01 35 26.05 20 GOVERNMENT SAFETY REQUIREMENTS FOR DESIGN-BUILD
01 35 29.13 HEALTH, SAFETY, AND EMERGENCY RESPONSE PROCEDURES FOR
CONTAMINATED SITES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.05 20 DESIGN AND CONSTRUCTION QUALITY CONTROL
01 50 00.05 20 TEMPORARY FACILITIES AND CONTROLS FOR DESIGN-BUILD
01 57 19.00 20 TEMPORARY ENVIRONMENTAL CONTROLS
01 74 19.05 20 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT FOR
DESIGN-BUILD
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION 01 11 00
SUMMARY OF WORK
08/11
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN PETROLEUM INSTITUTE (API)
API Std 653 (2009; Addendum 1 2010; Addendum 2 2012) Tank Inspection, Repair, Alteration, and Reconstruction
ASTM INTERNATIONAL (ASTM)
ASTM E2114 (2008) Standard Terminology for Sustainability Relative to the Performance of Buildings
1.2 DEFINITIONS
Definitions pertaining to sustainable development are as defined in ASTM E2114 and as specified.
a. "Environmentally preferable products" have a lesser or reduced effect on the environment in comparison to conventional products and services. This comparison may consider raw materials acquisition, production, manufacturing, packaging, distribution, reuse, operation, maintenance, or disposal of the product.
b. "Indoor environmental quality" is the physical characteristics of the building interior that impact occupants, including air quality, illumination, acoustics, occupant control, thermal comfort, daylighting, and views.
c. "Operational performance" is the functional behavior of the building as a whole or of the building components.
d. "Sustainability" is the balance of environmental, economic, and societal considerations.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals shall be in accordance with Sections 01 33 10.05 20 and 01 33 00.05 20 DESIGN/CONSTRUCTION SUBMITTAL PROCEDURES.
SECTION 01 11 00 Page 1
1.4 WORK COVERED BY CONTRACT DOCUMENTS
1.4.1 Project Description
The work includes aviation fuel storage tank cleaning, inspection pursuant to API Std 653, repair and incidental related work.
1.4.2 Location
The work shall be located at the Naval Air Station Pensacola. Work will take place at two distinct locations which are separated by an estimated three miles. The locations are the bulk fuel storage site and the ready fuel site. The exact locations will be shown by the Contracting Officer.
1.5 PROJECT ENVIRONMENTAL GOALS
Contractor shall distribute copies of the Environmental Goals to each subcontractor and the Contracting Officer. The overall goal for design, construction, and operation is to clean, inspect, and repair the fuel storage tanks in a manner that meets the functional program needs and incorporates the principles of sustainability. Specifically:
a. Preserve and restore the site ecosystem and biodiversity; avoid site degradation and erosion. Minimize offsite environmental impact.
b. Use the minimum amount of energy, water, and materials feasible to meet the design intent. Select energy and water efficient equipment and strategies.
c. Use environmentally preferable products and decrease toxicity level of materials used.
d. Use renewable energy and material resources.
e. Optimize operational performance (through commissioning efforts) in order to ensure energy efficient equipment operates as intended.
Consider the durability, maintainability, and flexibility of building systems.
f. Manage construction site and storage of materials to ensure no negative impact on the indoor environmental quality of the building.
g. Reduce construction waste through reuse, recycling, and supplier take-back.
1.5.1 Independent Verification
1.6 OCCUPANCY OF PREMISES
Fuel facilities at NAS Pensacola will remain in service during performance of work under this Contract.
Before work is started, the Contractor shall provide a schedule to the Contracting Officer with an acceptable sequence of tank inspection and repair, procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
SECTION 01 11 00 Page 2
1.7 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.8 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation by contacting the Contracting Officer 15 calendar days in advance.
1.8.1 Notification Prior to Excavation
Notify the Contracting Officer at least 15 days prior to starting excavation work.
1.9 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged shall remain the property of the Government.
The salvaged property shall be segregated, itemized, delivered, and off-loaded at the Government designated storage area located within 5 miles of the construction site.
Contractor shall maintain property control records for material or equipment designated as salvage. Contractor's system of property control may be used if approved by the Contracting Officer. Contractor shall be responsible for storage and protection of salvaged materials and equipment until disposition by the Contracting Officer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 3
SECTION 01 14 00.05 20
WORK RESTRICTIONS FOR DESIGN-BUILD
01/12
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN PETROLEUM INSTITUTE (API)
API RP 2219 (2005; R 2012; 3rd Ed) Safe Operation of Vacuum Trucks in Petroleum Service
1.2 SUBMITTALS
The use of a "G" following a submittal indicates that a Government approval action is required. Submit the following in accordance with Section 01 33
10.05 20 DESIGN SUBMITTAL PROCEDURES and Section 01 33 00.05 20
CONSTRUCTION SUBMITTAL PROCEDURES.
SD-01 Preconstruction Submittals
List of contact personnel; G
Visit Access Request for NAVSUP FLC Areas; G
1.3 SPECIAL SCHEDULING REQUIREMENTS
a. No more than two fuel tanks shall be removed from service at the same time. However, of those two, no more than one of the ready fuel tanks (Tanks 5 and 6) can be out of service at the same time. Return a fuel tank to service before removing the next fuel tank from service. Submit written request to the Contracting Officer 60-days in advance for permission to remove a tank from service.
b. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work. Specific items of work to which this requirement applies include:
(1) Removal of remaining fuel from fuel tanks: Government will drain each tank until pump loses suction. Contractor will assist Government with the removal of remaining usable fuel. Estimate the quantity of remaining usable fuel per the Usable Fuel Quantity Table. Assistance includes personnel, clean conveyance and transportation equipment (tank truck minimum size 8,000 gallon), and proper handling of aviation fuel. Vacuum truck equipment shall comply with API RP 2219 Safe Operation of Vacuum Trucks in Petroleum Service. Usable fuel can be placed into another
SECTION 01 14 00.05 20 Page 1 storage facility on Base. Site operator will provide the capability to test product to determine usability prior to being placed into another tank. Assist with the fuel quality test.
Usable Fuel Quantity Table
Tank No Fac No NomCap (BBL) Rem Usable Fuel (Gal)
1 3914 42,500 10,000
2 3915 42,500 10,000
3 3916 42,500 10,000
4 3917 42,500 10,000
5 3919 3000 2,000
6 3920 3000 2,000
(2) Removal, characterization, and disposal of off-spec fuel, sludge, sediment, rinsate, and deleterious material which remains after usable fuel (if any) has been removed is the responsibility of Contractor and is pursuant to requirements and quantities specified in Section 33 65 00.
Disposal is off-Base. Disposition of this material shall be pursuant to 01 74 19.05 20.
c. Site fuel operations will remain in service during the entire construction period. Conduct activity under this RFP so as to cause the least possible interference with normal operations of the Site.
d. Permission to interrupt any Activity roads, railroads, and/or utility service shall be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
e. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations.
Identify on the construction schedule each factor which constitutes a potential interruption to operations.
f. Permission to remove a fuel storage tank from service shall be requested in writing a minimum of 60 calendar days prior to the desired date of interruption.
The following conditions apply:
(1) No more than two fuel tanks can be out of service at a time. No more than one ready fuel tank (Tanks 5 and 6) can be out of service at the same time.
g. SPAWAR Access: Provide access to SPAWAR personnel to remove and reinstall gauging during tank repairs. The Contractor will be required to coordinate their efforts with the SPAWAR to facilitate joint use of tank access and spaces during the removal and reinstallation of tank gauging.
Add time windows for SPAWAR activities into the construction schedule.
SECTION 01 14 00.05 20 Page 2
h. After a tank inspection, provide Contracting Officer with preliminary results. Do not start tank or coating repairs until authorized by the NTR. Plan in advance the sequence of actions required to start repair work after an inspection to avoid interruption of site work. Provide sufficient level of detail on construction schedule required in 01 32 17.05 20to demonstrate compliance with this requirement.
1.4 CONTRACTOR ACCESS AND USE OF PREMISES
1.4.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats , safety shoes, and other appropriate PPE in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Do not enter Installation flight line. The Contractor's equipment shall be conspicuously marked for identification.
1.4.1.1 Subcontractors and Personnel Contacts
Furnish a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.4.1.2 Identification Badges
Application for and use of badges will be as directed. Obtain access to the installation by participating in the Navy Commercial Access Control System (NCACS) or by obtaining passes each day from the Base Pass and Identification Office. Costs for obtaining passes through the NCACS are the responsibility of the Contractor. One-day passes, issued through the Base Pass and Identification Office will be furnished without charge. Furnish a completed EMPLOYMENT ELIGIBILITY VERIFICATION (DHS FORM I-9) form for all personnel requesting badges. This form is available at http://www.uscis.gov/portal/site/uscis by searching or selecting Employment Verification (Form I-9). Immediately report instances of lost or stolen badges to the Contracting Officer.
a. NCACS Program: NCACS is a program in which Contractor personnel who enroll, and are approved, are subsequently granted access to the installation for a period up to one year, or the length of the contract, whichever is less, and are not required to obtain a new pass from the Base Pass and Identification Office for each visit. The Government performs background screening and credentialing. Throughout the year the Contractor employee must continue to meet background screening standards. Periodic background screenings are conducted to verify continued NCACS participation and installation access privileges. Under the NCACS program, no commercial vehicle inspection is required, other than for Random Anti-Terrorism Measures (RAM) or in the case of an elevation of Force Protection Conditions (FPCON).
Information on costs and requirements to participate and enroll in NCACS is available at http://www.rapidgate.com/vendors/how-to-enroll or by calling 1-877-727-4342. Contractors should be aware that the costs incurred to obtain NCACS credentials, or costs related to any means of access to a Navy Installation, are not reimbursable. Any time invested, SECTION 01 14 00.05 20 Page 3 or price(s) paid, for obtaining NCACS credentials will not be compensated in any way or approved as a direct cost of any contract with the Department of the Navy.
b. One-Day Passes: If Contractor chooses not to participate in NCACS, the Contractor's personnel will have to obtain daily passes, be subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government will not be responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the NCACS.
1.4.1.3 Additional Badge Requirements
Identification badges will be issued to the Contractor and his employees in accordance with the Naval Air Station Security Regulations. A copy of the security regulations may be obtained from the security office. All badges must be returned or accounted for to the department of Public Safety's Pass and Identification Office upon expiration of the badge or contract, or termination of the employee.
A portion of the work will take place within the perimeter of the flight line and enclosed within electronic access gates. Workers shall be vetted and are required to request and acquire unescorted access to the perimeter area required to accomplish work in this RFP. Government will not provide site escorts. Access to the flight line is not required by work in this contract. Under no circumstances are contractor personnel or equipment to encroach on Installation flight line.
1.4.1.4 Employee List
The Contractor shall provide to the Contracting officer, in writing, the names of two designated representatives authorized to request personnel and vehicle passes for employees and subcontractor's employees prior to commencement of work under this contract. The Contractor shall adhere to the Installation requirements in obtaining access to the Naval Air Station complex for the life of the contract.
1.4.1.5 Personnel Entry Approval
Failure to obtain entry approval will not affect the contract price or time of completion.
1.4.2 Entry to Radiologically Controlled Areas
Contractor personnel shall not, under any circumstances, enter a radiologically controlled area or cross any posted radiological boundary.
This paragraph applies to all phases of contract work. Radiation areas shall be posted with signs consistent with OSHA requirements. Ensure that employees are familiar with the radiation signs and symbols.
Should contract workers encounter radiological postings and/or boundaries which appear to limit their ability to access or carry out their intended work, they shall notify their contract administrator for resolution of the problem.
1.4.2.1 Radioactive Materials and Equipment
All testing equipment, containing a radioactive source, shall be operated in accordance with an approved radioactive equipment plan. This plan shall
SECTION 01 14 00.05 20 Page 4 be submitted to the Contracting Officer and approved by the Radiation Officer, prior to bringing the equipment on-Base. This plan shall include:
a. The name and type of equipment.
b. The type and size of radiation source.
c. The dates and locations of the equipment's usage.
d. The radiological controls that the Contractor will use while operating the equipment.
A different radioactive equipment plan will be required for each different type of equipment, type of radioactive source, or size of radioactive source. A data sheet of for each piece of new radioactive equipment shall be submitted to the Contracting Officer to forward to the Installation Radiation Safety Officer. The data sheet shall contain the following information:
a. Name of equipment.
b. Name and address of equipment manufacturer.
c. Type and size of radiation source.
d. The location of the installed radioactive equipment (i.e. building no., floor, code/shop area).
1.4.3 Working Hours
Regular working hours shall consist of an 8 1/2 hour period established by the Contracting Officer, between 7 a.m. and 3:30 p.m., Monday through Friday, excluding Government holidays.
1.4.4 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer.
1.4.5 Occupied and Existing Buildings
The Contractor shall be working in and around existing fuel facilities which are in active fuel service. Do not interupt or impair fuel service without prior approval of the Contracting Officer.
The existing fuel facilities and their contents shall be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
1.4.6 Utility Cutovers and Interruptions
a. Utility cutovers and interruptions might be required to take place after normal working hours or on Saturdays, Sundays, and Government holidays. Request fuel service interruptions in advance from the
SECTION 01 14 00.05 20 Page 5
Contracting Officer. Conform to procedures required in the paragraph "Work Outside Regular Hours."
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, fire suppression system, fuel pipeline,and fuel tank shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours."
d. Operation of Station Utilities: The Contractor shall not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, fuel, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor shall notify the Contracting Officer giving reasonable advance notice when such operation is required.
1.4.6.1 Location of Underground Utilities
Obtain digging permits prior to start of excavation by requesting permission from the Installation at least 15 calendar days in advance on a fully completed form NASPNCLAINST 11010.3. Scan the construction site with electromagnetic or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities or utilities encased in pier structures are discovered. Verify the elevations of existing piping, utilities, and any type of underground or encased obstruction not indicated to be specified or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed.
a. Notification Prior to Excavation: Notify the Contracting Officer at least 15 days prior to starting excavation work.
1.4.7 Air Operations Obstruction Evaluation
For any activity in which equipment will be used to lift or raise material, FAA approval might be required. Request an Obstruction Evaluation from the Air Operations Department Obstruction Evaluation Coordinator during the design phase of the contract. POC will be provided by the Contracting Officer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 14 00.05 20 Page 6
SECTION 01 20 00.05 20
PRICE AND PAYMENT PROCEDURES FOR DESIGN-BUILD
01/12
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP-1110-1-8
(2009) Construction Equipment Ownership and Operating Expense Schedule, Vol 1-12
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section 01 33
10.05 20 DESIGN SUBMITTAL PROCEDURES and Section 01 33 00.05 20
CONSTRUCTION SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Schedule of Prices ; G
1.3 SCHEDULE OF PRICES
1.3.1 Data Required
Within 15 calendar days of notice of award, prepare and deliver to the Contracting Officer a Schedule of Prices (construction contract) as directed by the Contracting Officer. Provide a detailed breakdown of the contract price, giving quantities for each of the various kinds of work, unit prices, and extended prices. Costs shall be summarized and totals provided for each construction category.
1.3.2 Schedule Instructions
Payments will not be made until the Schedule of Prices has been submitted to and accepted by the Contracting Officer. For design phase progress payment(s), the Schedule of Prices or Earned Value Report from the Cost Loaded CPM shall include detailed design activities and general (summarized) approach for the construction phase(s) of the project. The Schedule of Prices or Earned Value Report shall be fully developed with detailed construction line items as design progresses. The complete design
SECTION 01 20 00.05 20 Page 1 and construction Schedule of Prices or Earned Value Report shall be submitted and accepted prior to starting construction work.
For Fast-Tracked or Critical Path Submittals of construction projects, the Schedule of Prices shall include detailed design and construction line items for each fast-tracked/ critical path phase(s), submitted to and accepted by the Contracting Officer during the Post Award Kickoff Meetings and confirmed prior to starting construction work in that phase.
Additionally, the Schedule of Prices shall be separated as follows:
a. Primary Facility/s Cost Breakdown:
Defined as work on the primary facility/s out to the 1.5 m (5 foot) line.
Work out to the 1.5 m (5 foot) line shall include construction encompassed within a theoretical line 1.5 m (5 foot) from the face of exterior walls or tank shell, and shall include attendant construction that may extend beyond the 1.5 m (5 foot) line.
b. Supporting Facilities Cost Breakdown:
Defined as site work, including incidental work, outside the 1.5 m (5 foot) line.
1.4 CONTRACT MODIFICATIONS
In conjunction with the Contract Clause "DFARS 252.236-7000, Modification Proposals-Price Breakdown," and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, equipment use rates shall be based upon the applicable provisions of the EP-1110-1-8.
1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.5.1 Content of Invoice
Requests for payment will be processed in accordance with the Contract.
Clause FAR 52.232-27, Prompt Payment Construction Contracts and FAR 52.232-5, Payments Under Fixed-Price Construction Contracts. The Requests for payment shall include the documents listed below:
a. The Contractor's invoice, on NAVFAC Form 7300/30 furnished by the Government, showing in summary form, the basis for arriving at the amount of the invoice. Form 7300/30 shall include certification by Quality Control (QC) Manager as required by the contract.
b. The Estimate for Voucher/ Contract Performance Statement on NAVFAC Form 7300/31 furnished by the Government, showing in detail: the estimated cost, percentage of completion, and value of completed performance for each of the construction categories stated in this contract. Contract Performance Statement shall be reviewed with Government QA representative for concurrence prior to invoice submission in WAWF.
c. Updated Project Schedule and reports required by the contract
d. Contractor Safety Self Evaluation Checklist
e. Other supporting documents as requested
f. Updated copy of submittal register.
SECTION 01 20 00.05 20 Page 2
g. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies.
h. Monthly Work-hour report
i. Solid Waste Disposal Report
1.5.2 Submission of Invoices
If NFAS Clause 5252.232-9301 is included in the contract, the documents listed in paragraph titled " Content of Invoice" above shall be provided in their entirety as an attachment in Wide Area Work Flow (WAWF) for each invoice submitted. The maximum size of each WAWF attachment is two megabytes, but there are no limits on the number of attachments. If a document cannot be attached in WAWF due to system or size restriction it shall be provided as instructed by the Contracting Officer. All other paper invoices shall be forwarded with specific marking on the envelope. This marking shall be in the front lower left hand corner, in large letters, "INVOICES - ENCLOSED."
Monthly invoices and supporting forms for work performed through the anniversary award date of the contract shall be submitted to the Contracting Officer within 5 calendar days of the date of invoice For example, contract award date is the 7th of the month, the date of each monthly invoice shall be the 7th and the invoice shall be submitted by the 12th of the month.
1.5.3 Final Invoice
a. A final invoice shall be accompanied by the certification required by DFARS 252.247.7023 TRANSPORTATION OF SUPPLIES BY SEA, and the Contractor's Final Release. If the Contractor is incorporated, the Final Release shall contain the corporate seal. An officer of the corporation shall sign and the corporate secretary shall certify the Final Release.
b. For final invoices being submitted via WAWF, the original Contractor's Final Release Form and required certification of Transportation of Supplies by Sea must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release Form and required certification of Transportation of Supplies by Sea has been confirmed by the Contracting Officer, the Contractor shall then submit final invoice and attach a copy of the Final Release Form and required certification of Transportation of Supplies by Sea in WAWF.
c. Final invoices not accompanied by the Contractor's Final Release and required certification of Transportation of Supplies by Sea will be considered incomplete and will be returned to the Contractor.
1.6 PAYMENTS TO THE CONTRACTOR
Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.
1.6.1 Obligation of Government Payments
The obligation of the Government to make payments required under the
SECTION 01 20 00.05 20 Page 3 provisions of this contract will, at the discretion of the Contracting Officer, be subject to reductions and/or suspensions permitted under the FAR and agency regulations including the following in accordance with "FAR 32.503-6:
a. Reasonable deductions due to defects in material or workmanship;
b. Claims which the Government may have against the Contractor under or in connection with this contract;
c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and
d. Failure to provide up to date record drawings not current as stated in Contract Clause "NFAS 5252.236-9310, Record Drawings."
1.6.2 Payment for Onsite and Offsite Materials
Progress payments may be made to the contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:
a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.
b. Materials delivered on the site but not installed, including completed preparatory work, and off-site materials to be considered for progress payment shall be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples of materials acceptable for payment consideration include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings, precast/prestressed concrete products, plastic lumber (e.g., fender piles/curbs) and high-voltage electrical cable. Materials not acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.
c. Materials to be considered for progress payment prior to installation shall be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with Schedule of Prices requirement of this contract. Requests for progress payment consideration for such items shall be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 have been met.
d. Materials are adequately insured and protected from theft and exposure.
e. Provide a written consent from the surety company with each payment request for offsite materials.
f. Materials to be considered for progress payments prior to installation shall be stored insuitable locations subject to written approval of the Contracting Officer. Materials onsite are to be secure, protected from theft, and clearly marked with Contractor's name and 24-hour contact information.
PART 2 PRODUCTS
Not used.
SECTION 01 20 00.05 20 Page 4
PART 3 EXECUTION
Not used.
SECTION 01 20 00.05 20 Page 5
SECTION 01 30 00.05 20
ADMINISTRATIVE REQUIREMENTS FOR DESIGN-BUILD
03/13
PART 1 GENERAL
1.1 SUBMITTALS
The use of a "G" following a submittal indicates that a Government approval action is required. Submit the following in accordance with Section 01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES and Section 01 33 00.05 20
CONSTRUCTION SUBMITTAL PROCEDURES.
SD-01 Preconstruction Submittals
Insurance
1.2 MINIMUM INSURANCE REQUIREMENTS
Procure and maintain during the entire period of performance under this contract the following minimum insurance coverage:
a. Comprehensive general liability: $500,000 per occurrence
b. Automobile liability: $200,000 per person, $500,000 per occurrence for bodily injury, $20,000 per occurrence for property damage
c. Workmen's compensation as required by Federal and State workers' compensation and occupational disease laws.
d. Employer's liability coverage of $100,000, except in States where workers compensation may not be written by private carriers,
e. Others as required by the State.
Refer to UFGS section 01 33 00.05 20, CONSTRUCTION SUBMITTAL PROCEDURES for typical preconstruction submittals similar to insurance.
1.3 CONTRACTOR PERSONNEL REQUIREMENTS
1.3.1 Subcontractor Special Requirements
1.3.1.1 Asbestos Containing Material
All contract requirements of PART 4, F20 SELECTIVE BUILDING DEMOLITION, assigned to the Private Qualified Person (PQP) shall be accomplished directly by a first tier subcontractor.
1.3.1.2 COATING SUBCONTRACTOR
All contract requirements of coating work required by Section 09 97 13.15 shall be accomplished directly by a first tier subcontractor. No coating
SECTION 01 30 00.05 20 Page 1 work required by Section 09 97 13.15 shall be accomplished by a second tier subcontractor.
1.3.1.3 Qualified Testing Organization
All contract requirements of work required to be performed by a Qualified Testing Organization in PART 4, D50 ELECTRICAL and G40 SITE ELECTRICAL UTILITIES, shall be accomplished directly by a first tier subcontractor.
No work to be performed by a Qualified Testing Organization, required by PART 4, D50 and G40 shall be accomplished by a second tier subcontractor.
1.4 SUPERVISION
Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, the Quality Control (QC) representative shall also have fluent English communication skills.
1.5 SUPERVISION
Provide at least one (1) qualified Project Manager and one (1) on-site Project Superintendent/Site Manager per project capable of reading, writing, and conversing fluently in the English language. The Project Manager must have a minimum 10 years experience as a Project Manager on projects with similar type, size, and complexity. The Project Superintendent/Site Manager must have a minimum of 10 years experience as a Superintendent on projects similar in type, size, and complexity.
In addition to the above experience requirements, the Project Manager and on-site Project Superintendent shall complete the course entitled "Construction Quality Management for Contractors" prior to the start of construction.
The Project Manager in this context shall mean the individual with the responsibility for the overall management of the project and the Project Superintendent shall mean the individual with the responsibility for quality and production. Both the Project Manager and Project Superintendent are subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders shall be made the subject of claim for extension of time for excess costs or damages by the Contractor.
Approval of Project Manager and on-site Project Superintendent is required prior to start of construction. Provide resumes for the proposed Project Manager and on-site Project Superintendent describing their experience with references and qualifications to the Contracting Officer for approval. The Contracting Officer reserves the right to interview the proposed Project Manager and on-site Project Superintendent at any time in order to verify the submitted qualifications.
1.6 CLEANUP
Leave premises "broom clean." Clean interior and exterior glass surfaces exposed to view; remove temporary labels, stains and foreign substances;
polish transparent and glossy surfaces; vacuum carpeted and soft surfaces.
Clean equipment and fixtures to a sanitary condition. Replace filters of
SECTION 01 30 00.05 20 Page 2 operating equipment. Clean debris from roofs, gutters, downspouts and drainage systems. Sweep paved areas and rake clean landscaped areas.
Remove waste and surplus materials, rubbish and construction facilities from the site.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 30 00.05 20 Page 3
SECTION 01 31 19.05 20
POST AWARD MEETINGS
06/13
PART 1 GENERAL
1.1 SUMMARY
This document includes post-award requirements for project kickoff and subsequent design and preconstruction meetings.
1.2 SUBMITTALS
The use of a "G" following a submittal indicates that a Government approval action is required. Submit the following in accordance with Section 01 33
10.05 20 DESIGN SUBMITTAL PROCEDURES.
SD-01 Preconstruction Submittals
Design Submittal Packaging Proposal; G
Project Schedule; G
Performance Assessment Plan (PAP); G
1.3 POST AWARD KICKOFF MEETING
The Post Award Kickoff (PAK) meeting is made up of Contract Administration, Concept Design Presentation/Design Development or Concept Design Workshop (CDW), Partnering, and Scheduling. If mutually beneficial to the Contractor and the Government, these four elements may be addressed in a single meeting..
1.3.1 PAK Meeting Schedule and Location
Within 35 calendar days after contract award, and prior to commencing work, meet with the Contracting Officer for the PAK meeting(s). The meeting shall be located at a specific time and place to be determined by the Contracting Officer.
1.3.2 PAK Meeting Outcomes
The meeting(s) outcomes are:
a. Integrate the Contractor and all client representatives into the project team.
b. Achieve consensus from the project team on any issues and concerns with the Contractor's technical proposal and the User's functional requirements. Confirm the design is within the project budget.
SECTION 01 31 19.05 20 Page 1
c. Establish and explain policies and procedures for completion of a successful proect.
d. Establish clear lines of communication and points of contact for Government and Contractor team members.
e. Establish project design schedule, design submittal packaging, and preliminary construction schedule in accordance with Secton 01 32 17.05 20 NETWORK ANALYSIS SCHEDULE (NAS) FOR DESIGN-BUILD. Discuss design milestones and events that will be included in the Quality Control Communication Plan.
f. Establish clear expectations and schedules for tank removal from service, tank return to service, lockout tagout, and roles/responsibilities during out of service periods.
g. Establish procedure for submittal reviews, Contractor's resolution to comments, and Government's role in review of packages.
1.3.3 PAK Meeting Contractor Attendees
The following Contractor key personnel shall attend the PAK: Project Engineer,Engineer-of-Record (DOR),, Project Engineer, DQC/QC Manager,.
Optional attendees include: Principal, Assistant Project Manager, major subcontractors and specialized supplemental QC personnel.
1.3.4 Contract Administration
Contract administration roles and responsibilities will be addressed.
1.3.5 Partnering
To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, Contractor and its Subcontractors. Key Personnel from the Supported Command, End User (who will occupy the facility), NAVFAC (Echelon III and/or IV), Navy Region/Installation, Contractor and Subcontractors and the Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project without any safety mishaps, conforming to the Contract, within budget and on schedule.
Information on the Partnering Process and a list of Key and Optional personnel who should attend the Partnering meeting are available from the Contracting Officer.
INFORMAL PARTNERING: The Contracting Officer shall organize the Partnering Sessions with key personnel of the project team, including Contractor's personnel and Government personnel.
The Initial Informal Partnering session should be a part of the DB Post Award Kickoff (PAK) . Partnering sessions should be held at a location agreed to by the Contracting Officer and the Contractor (typically a conference room provided by the PWD FEAD/ROICC office or the Contractor).
The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by Contracting Officer.
SECTION 01 31 19.05 20 Page 2
The Partners will determine the frequency of the follow-on sessions.
1.3.6 Performance Assessment Plan (PAP)
The Performance Assessment Plan (PAP) shall be used to document design innovation and budget management, provide performance feedback to the Contractor, and as a basis for interim and final evaluations in the Construction Contractor Appraisal System (CCASS) on-line database.
It is the intent of the Government to establish the PAP based on tangible, measurable indicators of outstanding contractor performance, and on commitments made in the Contractor's proposal. The initial PAP may be found on the NAVFAC Design-Build Request for Proposal Website in RFP PART 6 Attachments. Review and finalize the initial PAP during the Partnering Session. During the initial Partnering Session, the Government, the Contractor, the Designer-of-Record, and the Client will establish the PAP.
Following the establishment of the PAP, the Contractor will present it, with his input, for update and discussion at projects meetings which discuss project performance. Submit an updated PAP on a monthly basis with the invoice for that period as a minimum.
1.3.7 Project Schedule
Provide in accordance with Section 01 32 17.05 20 NETWORK ANALYSIS SCHEDUL
ES (NAS) FOR DESIGN-BUILD.
1.4 DESIGN QUALITY ASSURANCE MEETINGS
After Government Quality Assurance (QA) of each Design Submittal has been completed, meet with the Government for a one-day conference to discuss review comments for the specific design submittal.
Provide consolidated copies of all Government comments with annotations of Contractor's action beside them. Notify the Contracting Officer in writing within five (5) days after receipt of Government's comments if the Contractor disagrees with comments technically or interprets comments to exceed the requirements of the contract.
1.4.1 Design QA Meeting Attendees
The following Contractor key personnel shall attend the design QA meetings: Project Engineer, QC Manager, Commissioning Authority, and Contractor's Design Staff (engineering disciplines related to topics to be discussed).
1.4.2 Design QA Meeting Location
Meetings shall be located at the office of the Contracting Officer's QA Team or may be conducted at other locations or by other electronic means if mutually acceptable to all parties.
1.4.3 Minimum Design QA Meeting Agenda
Address all Government comments that are unresolved and present clarification or supporting information requested by the Contracting Officer's QA team during the previous meeting.
SECTION 01 31 19.05 20 Page 3
1.5 PRECONSTRUCTION MEETING
Meet with the Contracting Officer to discuss construction items of concern to the Government and the Contractor such as outages, storage, trailer location, disposal of construction debris, and safety, at a location to be determined by the Contracting Officer. The Preconstruction meeting may take place with the PAK meeting or at any time prior to mobilization and before any construction work begins.
1.6 RECURRING MEETINGS
1.6.1 Quality Control and Production Meetings
Quality Control and Production Meetings in accordance with Section 01 45
00.05 20 DESIGN AND CONSTRUCTION QUALITY CONTROL.
1.6.2 Safety Meetings
Safety Meetings in accordance with Section 01 35 26.05 20 GOVERNMENT
SAFTETY REQUIREMENTS FOR DESIGN-BUILD.
1.7 FACILITY TURNOVER PLANNING MEETINGS
Key personnel will meet to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start the turnover process at the PAK Meeting. The Contracting Officer's Representative will lead the meetings and guide the discussions based on an agenda provided by the Government. The Facility Turnover effort shall include the following:
a. PAK Meeting
1. Contracting Officer's Technical Representative (COTR) will provide the NRZ Checklist and the Contractor, Client, and NAVFAC Representatives will compare Contractor's schedule to NRZ Checklist to ensure all Contractor Checklist Items are included in the schedule and to discuss the scheduling impact of Client and NAVFAC Checklist Items.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
SECTION 01 31 19.05 20 Page 4
SECTION 01 32 17.05 20
NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD
2/13
PART 1 GENERAL
1.1 DESCRIPTION
The Contractor is responsible for scheduling all design, procurement and construction. A single schedule shall logically incorporate all design and construction for the entire project. Unless otherwise indicated, the contractor may begin construction when design is signed, stamped and submitted to the Government via the Contractor's quality control organization.
If Government approval is required for any portion of a final signed and sealed design package prior to construction, that review time shall be included in the schedule. The schedule shall also include times for procurement, Contractor quality control and construction, acceptance testing and training. Refer to Specification Section 01 33 00.05 20 Construction Submittal Procedures to determine if any items require Government approval prior to construction; if any are required, that submittal review time shall be included in the schedule.
The schedule is a tool to manage the project, both for Contractor and Government activities. It will also be used to measure progress and to evaluate time extensions. If cost-loaded, it will provide the basis for progress payments.
The Contractor shall use the Critical Path Method (CPM) and the Precedence Diagram Method (PDM) to satisfy time and cost applications. For consistency, when scheduling software terminology is used in this specification, the terms in Primavera's scheduling programs are used.
1.2 SUBMITTALS
The use of a "G" following a submittal indicates that a Government approval action is required. Submit the following in accordance with Section 01 33
10.05 20 DESIGN SUBMITTAL PROCEDURES and Section 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES, except as modified in this contract.
SD-01 Preconstruction Submittals
Qualifications; G
Design Baseline Network Analysis Schedule Package; G
Construction Baseline Network Analysis Schedule Package; G
SD-07 Certificates
Monthly Network Analysis Schedule Updates; G
SECTION 01 32 17.05 20 Page 1
SD-11 Closeout Submittals
As-Built Schedule; G
1.3 SCHEDULE ACCEPTANCE PRIOR TO START OF WORK
Government review comments on the Contractor's schedule(s) shall not relieve the Contractor from compliance with requirements of the Contract Documents.
The Design Baseline Network Analysis Schedule (NAS) shall be submitted and presented to the Government at the PAK Meeting. The acceptance of a Design Baseline NAS is a condition precedent to processing Contractor's pay request(s) for design activities/items of work.
Only bonds shall be paid prior to acceptance of the Design Baseline Network Analysis Schedule (NAS).
The most current updated design schedule shall accompany each design submittal.
The Contracting Officer and Contractor shall participate in a preliminary meeting(s) to discuss the proposed schedule and requirements of this section prior to the Contractor preparing the Construction Baseline Network Analysis Schedule.
The acceptance of a Construction Baseline NAS is a condition precedent to:
1. The Contractor starting work on the construction stage(s) of the contract, or removal of the first fuel tank from service.
2. Processing Contractor's pay request(s) for construction activities/items of work.
3. Review of any schedule updates
Submittal of the Baseline Network Analysis Schedules, and subsequent schedule updates, shall be understood to be the Contractor's certification that the submitted schedule meets all of the requirements of the Contract Documents, represents the Contractor's plan on how the work shall be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced (as-built logic).
1.4 SOFTWARE
Project schedules must be prepared and maintained using Primavera P3, Primavera SureTrak, or Microsoft Project as directed by the Contracting Officer. Save files in Microsoft Project compatible with the Government's version of the scheduling program. Importing data into P3/SureTrak/current mandated scheduling program using data conversion techniques or third party software will be cause for rejection of the submitted schedule.
1.5 QUALIFICATIONS
The designated Scheduler for the project shall have prepared and maintained at least 3 previous schedules of similar size and complexity of this contract using SureTrak/P3 or Microsoft Project. A resume outlining the qualifications of the Scheduler shall be submitted for acceptance to the
SECTION 01 32 17.05 20 Page 2
Contracting…