N39040Q6134V600 Exhibit A_Work Platform.pdf

PDF 91 KB Posted

Attached to
Work Platform; Nuc Requirement for Portsmouth Naval Shipyard
Solicitation number
N39040Q6134V600
Issued by

About this file

This is a Contract Data Requirements List (CDRL) documented on DD Form 1423 for Contract N39040Q6134V600 covering a Work Platform (RF-2204) system/item.

The CDRL specifies seven data submission requirements, all of which are one-time submissions (O-TIME frequency) required to be delivered with material. All submissions must include a Certificate of Compliance (COC) with a quantity of one per item and be distributed to Code 410 via WAWF (Wide Area Workflow). The technical office responsible is 2370.1, and all data submissions require DD 250 documentation marked as "SD" (Source Data). The specific requirements include: (1) Certificate of Compliance per contract paragraph C.3.1.; (2) Visual Certification before proof load test per C.3.2.; (3) Go/No-Go assessment before proof load test per C.3.2.; (4) Penetrant Testing before proof load test per C.3.2.; (5) Visual Certification after proof load test per C.3.3.; (6) Penetrant Testing after proof load test per C.3.3.; and (7) Material Safety Data Sheets for applicable materials per C.4. The document was prepared by Matthew Wurtz (Employee ID 49556) on 6/25/2026 and requires approval signature and date, which remain blank on the current version.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT N39040Q6134V600

EXHIBIT A

(ADP DD FORM 1423 (MECHANIZED EQUIVALENT) PER DAR CLAUSE 16-815)

CONTRACT DATA REQUIREMENTS LIST

SYSTEM/ITEM: WORK PLATFORM (RF-2204)

CATEGORY ____________

ITEM NO CONTRACTOR

01 SEQ NO A002

02 DATA DESC CERTIFICATE OF COMPLIANCE

03 SUBTITLE

04 DID NUMBER PER ATTACHMENT 1 TO EXHIBIT A

05 CONTRACT REF PARA. C.3.1.

06 TECH OFFICE 2370.1

07 DD 250 REQ SD

08 APP CODE

09 IAC INPUT

10 FREQUENCY O-TIME; SUBMIT ONE COC PER ITEM

11 AS OF DATE

12 DATE 1ST SUBM WITH MATERIAL

13 DATE SUB SUBM

14 DISTRIBUTION 0_-_N/A________/(1) - Code 410 VIA WAWF

15 TOTAL 1 __

16 REMARKS 1 SUBMITTAL; QTY (1) COC

SEQ. NO.:

PREPARED BY _/s/ Matthew Wurtz 49556____________________________

DATE__6/25/2026 _______

APPROVED BY _______________________________ _________________

DATE__________________

DD FORM 1423

01 SEQ NO A002AA

02 DATA DESC VISUAL CERT

03 SUBTITLE BEFORE PROOF LOAD TEST

04 DID NUMBER PER ATTACHMENT 1 TO EXHIBIT A

05 CONTRACT REF PARA. C.3.2.

06 TECH OFFICE 2370.1

07 DD 250 REQ SD

08 APP CODE

09 IAC INPUT

10 FREQUENCY O-TIME; SUBMIT ONE COC PER ITEM

11 AS OF DATE

12 DATE 1ST SUBM WITH MATERIAL

13 DATE SUB SUBM

14 DISTRIBUTION 0_-_N/A________/(1) - Code 410 VIA WAWF

APPROVED BY _______________________________ _________________

01 SEQ NO A002AB

02 DATA DESC GO/NO-GO

03 SUBTITLE BEFORE PROOF LOAD TEST

04 DID NUMBER PER ATTACHMENT 1 TO EXHIBIT A

05 CONTRACT REF PARA. C.3.2.

06 TECH OFFICE 2370.1

07 DD 250 REQ SD

08 APP CODE

09 IAC INPUT

10 FREQUENCY O-TIME; SUBMIT ONE COC PER ITEM

11 AS OF DATE

12 DATE 1ST SUBM WITH MATERIAL

13 DATE SUB SUBM

14 DISTRIBUTION 0_-_N/A________/(1) - Code 410 VIA WAWF

APPROVED BY _______________________________ _________________

01 SEQ NO A002AC

02 DATA DESC PENETRANT TESTING

03 SUBTITLE BEFORE PROOF LOAD TEST

04 DID NUMBER PER ATTACHMENT 1 TO EXHIBIT A

05 CONTRACT REF PARA. C.3.2.

06 TECH OFFICE 2370.1

07 DD 250 REQ SD

08 APP CODE

09 IAC INPUT

10 FREQUENCY O-TIME; SUBMIT ONE COC PER ITEM

11 AS OF DATE

12 DATE 1ST SUBM WITH MATERIAL

13 DATE SUB SUBM

14 DISTRIBUTION 0_-_N/A________/(1) - Code 410 VIA WAWF

APPROVED BY _______________________________ _________________

01 SEQ NO A002AD

02 DATA DESC VISUAL CERT

03 SUBTITLE AFTER PROOF LOAD TEST

04 DID NUMBER PER ATTACHMENT 1 TO EXHIBIT A

05 CONTRACT REF PARA. C.3.3.

06 TECH OFFICE 2370.1

07 DD 250 REQ SD

08 APP CODE

09 IAC INPUT

10 FREQUENCY O-TIME; SUBMIT ONE COC PER ITEM

11 AS OF DATE

12 DATE 1ST SUBM WITH MATERIAL

13 DATE SUB SUBM

14 DISTRIBUTION 0_-_N/A________/(1) - Code 410 VIA WAWF

APPROVED BY _______________________________ _________________

01 SEQ NO A002AE

02 DATA DESC PENETRANT TESTING

03 SUBTITLE AFTER PROOF LOAD TEST

04 DID NUMBER PER ATTACHMENT 1 TO EXHIBIT A

05 CONTRACT REF PARA. C.3.3.

06 TECH OFFICE 2370.1

07 DD 250 REQ SD

08 APP CODE

09 IAC INPUT

10 FREQUENCY O-TIME; SUBMIT ONE COC PER ITEM

11 AS OF DATE

12 DATE 1ST SUBM WITH MATERIAL

13 DATE SUB SUBM

14 DISTRIBUTION 0_-_N/A________/(1) - Code 410 VIA WAWF

APPROVED BY _______________________________ _________________

01 SEQ NO A003

02 DATA DESC MATERIAL SAFETY DATA SHEETS

03 SUBTITLE FOR APPLICABLE MATERIALS

04 DID NUMBER PER ATTACHMENT 1 TO EXHIBIT A

05 CONTRACT REF PARA. C.4.

06 TECH OFFICE 2370.1

07 DD 250 REQ SD

08 APP CODE

09 IAC INPUT

10 FREQUENCY O-TIME; SUBMIT ONE COC PER ITEM

11 AS OF DATE

12 DATE 1ST SUBM WITH MATERIAL

13 DATE SUB SUBM

14 DISTRIBUTION 0_-_N/A________/(1) - Code 410 VIA WAWF

APPROVED BY _______________________________ _________________

File details come from the government source that posted it. Updated .