This is a continuation sheet for a federal contract attachment specifying requirements for manufacturing a work platform (RF-2204). The document requires the manufacture and inspection of one work platform unit in accordance with drawing "WORK PLATFORM_2370-2204 – 6134V600.PDF." The contractor must deliver a Certificate of Compliance as documentation per Exhibit A Sequence A002.
Quality assurance and testing requirements are substantial. Before proof load testing, the contractor must complete visual certification, GO/NOGO gage checks, and penetrant testing per Exhibit A Sequences A002AA, A002AB, and A002AC. After proof load testing is successfully completed, the contractor must perform visual certification and penetrant testing inspection of each lift block per Exhibit A Sequences A002AD and A002AE. Material Safety Data Sheets must be provided per Exhibit A Sequence A003. Following satisfactory completion of the load and proof testing, items must be permanently marked according to the drawing specifications and statement of required tests. The packaging and marking requirements are contingent upon successful test completion.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQ DOC NO. - 6134V600 ATTACHMENT 1
CONTINUATION SHEET CONTRACT NO. - _______________ PAGE 1 OF 1
NAME OF OFFER OR/CONTRACTOR
1 WORK PLATFORM (RF-2204) 1 EA
C. DESCRIPTION/SPECIFICATIONS
C.1. MANUFACTURE WORK PLATFORM (RF-2204)
C.1.1. MANUFACTURE AND INSPECT IN ACCORDANCE WITH
DRAWING “WORK PLATFORM_2370-2204 – 6134V600.PDF”.
C.3. DATA REQUIREMENTS PER EXHIBIT A (DD-1423) & ATTCHMENT #1
C.3.1 CERTIFICATE OF COMPLIANCE; EXHIBIT A SEQUENCE A002.
C.3.2 BEFORE PROOF LOAD TEST - VISUAL CERTIFICATION, GO/NO-
GO GAGE CHECK AND PENETRANT TESTING, EXHIBIT A SEQUENCES
A002AA, A002AB AND A002AC.
C.3.3 AFTER PROOF LOAD TEST - VISUAL CERTIFICATION AND PT
INSPECTION OF EACH LIFT BLOCK, EXHIBIT A SEQUENCES A002AD
AND A002AE.
C.4. MATERIAL SAFETY DATA SHEETS, EXHIBIT A SEQUENCE A003.
D. PACKING/PACKAGING/MARKINGS:
D.1 FOLLOWING SATISFACTORY COMPLETION OF LOAD/PROOF TEST,
PERMANENTLY MARK ITEMS AS REQUIRED PER DRAWING AND
STATEMENT OF REQUIRED TESTS.
ITEM # SUPPLIES/SERVICES QTY U/I