This is a Combined Synopsis/Solicitation Notice and Request for Quotation (RFQ) issued by Portsmouth Naval Shipyard for the procurement of membranes and mockup bases.

The solicitation (N39040Q6036V238) requests quotes for three primary items: 90 units of thin membranes manufactured per drawing 149D1555, Rev. L, PC-21; 90 units of thick membranes manufactured per drawing 149D1555, Rev. L, PC-22; and 90 units of 18-inch mockup bases manufactured per drawing 149D1555, Rev. L, PC-16. All items require freight costs to be included in pricing, and vendors must submit accompanying data requirements including certificates of compliance, dimensional inspections, and material safety data sheets. The required delivery date is January 1, 2027, with performance at Portsmouth Naval Shipyard in Kittery, Maine. This is a small business set-aside acquisition under NAICS code 322710 (Machine Shops) with a size standard of 500 employees. Quotes are due by April 29, 2026, at 8:00 AM ET and must be submitted via email to Sarashea.thibodeau.civ@us.navy.mil. All vendors must be registered in the System for Award Management (SAM). Award will be made to the lowest price technically acceptable quote based on technical acceptability, adherence to schedule, and price. Vendors must complete the RFQ form with all highlighted fields, provide technical documentation demonstrating compliance with specifications, and acknowledge acceptance of all terms and conditions or face rejection.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COMBINED SYNOPSIS/SOLICITATION NOTICE:

Requirement Title: Membranes; Thick and Thin & Mockup Base

Solicitation Number: N39040Q6036V238

Response Deadline: 04/29/2026

POC: Sarashea Thibodeau; Sarashea.thibodeau.civ@us.navy.mil ; 207-438-3874

GENERAL INFORMATION:

1. This is a combined synopsis/solicitation for commercial products or commercial services prepared in accordance with the format in subpart 12.6, as supplemented with additional information included in this notice.

This announcement constitutes the only solicitation; proposals are being requested and a written solicitation will not be issued Paper copies of this solicitation will not be available. This combined synopsis/solicitation SHALL be posted on SAM.gov.

2. This solicitation documents and incorporates provisions and clauses in effect through FAC 2026-01 and DFARS Change Notice 2025-1110. It is the responsibility of the contractor to be familiar with the applicable clauses and provisions. The clauses may be accessed in full text at these addresses:

https://www.acquisition.gov/browse/index/far and http://www.acq.osd.mil/dpap/dars/change_notices.html.

3. This solicitation is being issues as a(n): Request For Quotation (RFQ)

4. This acquisition is for: Small Business Set-Aside

5. North American Industry Classification System Code (NAICS): 322710; Machine Shops

6. The size standard is: 500 (# of Employees)

REQUIREMENT INFORMATION:

The Portsmouth Naval Shipyard requests responses from sources capable of providing the following:

• Required Delivery Date: 01/01/2027

• Place of Performance: Portsmouth Naval Shipyard, Kittery Maine, 03904

METHOD OF PROPOSAL SUBMISSION:

Offers shall be emailed. All responsible sources may submit a quote which shall be considered by the agency.

System for Award Management (SAM): Vendors must be registered in the SAM database to be considered for award. Registration is free and can be completed on-line at http://www.sam.gov/.

mailto:.civ@us.navy.mil https://www.acquisition.gov/browse/index/far http://www.acq.osd.mil/dpap/dars/change_notices.html http://www.sam.gov/

REQUEST FOR QUOTATION

N39040Q6036V238

THIS IS NOT AN ORDER

PLEASE PROVIDE DELIVERED PRICES, AVAILABILITY, AND PRICE SOURCE WITH QUOTE

REFERENCE # N39040Q6036V238 DUE DATE: 04/29/2026 08:00 AM ET

From: Portsmouth Naval Shipyard Your company info:

Sarashea.thibodeau.civ@us.navy.mil Name:

Contracting, Code 410 POC:

Kittery, ME 03904 (P) PHONE: 207-438-3874 Email:

Cage Code:

BUSINESS SIZE (circle one): SMALL LARGE PAYMENT TERMS ______%______DAYS

MOBILIZATION TIME: _________ARO PRICES DERIVED FROM (CHECK ONE)

F.O.B. DESTINATION, Y____N____ ___COMMERCIAL PRICE LIST DATED

IF NO, SHIPPING COST__________. ___INTERNAL PRICE LIST DATED

___OTHER ( PLEASE EXPLAIN )

Please indicate your preferred payment method by checking one of the options below. Payment options available are WAWF and GCPC: Government Commercial Purchase Card (up to $100,000). Please ensure that you register for WAWF (www.wawftraining.com) GCPC_____ WAWF (Wide Area Workflow) _____

*Please note that purchase card orders are not paid up front. Once material is received, a Government cardholder may be contacted for purchase card information.

_X__ If checked, to be awarded on an “All or None” basis, and CPARS evaluation procedures apply.

YOUR SIGNATURE___________________________________DATE________________________

ITEM DESCRIPTION QTY Unit Price Total

0001 THIN MEMBRANE:

MANUFACTURED IAW DWG

149D1555, REV. L, PC-21

In Accordance with Attachments

Include Freight Costs in CLIN 0001

90 EA.

0002 Data Requirements for CLIN 0001

1 SET Not Separately Priced

0002AA SEQUENCE A002AA:

CERTIFICATE OF COMPLIANCE

INFO ONLY Not Separately Priced

0002AA SEQUENCE A002AA:

DIMENSIONAL INSPECTION;

LIP

INFO ONLY Not Separately Priced

0003 THICK MEMBRANE:

149D1555, REV. L, PC-22

mailto:.civ@us.navy.mil http://www.wawftraining.com/

Include Freight Costs in CLIN 0002

0004 Data Requirements for CLIN 0003

0004AA SEQUENCE A002AA:

CERTIFICATE OF COMPLIANCE

INFO ONLY Not Separately Priced

0004AB

SEQUENCE A002AB:

DIMENSIONAL INSPECTION;

LIP

INFO ONLY Not Separately Priced

0004AC SEQUENCE A005:

MATERIAL SAFETY DATA

SHEETS

INFO ONLY Not Separately Priced

0005 18-INCH MOCKUP BASE:

149D1555, REV. L, PC-16

Include Freight Costs in CLIN 0005

0006 Data Requirements for CLIN 0005

0006AA SEQUENCE A002AA:

CERTIFICATE OF COMPLIANCE

INFO ONLY Not Separately Priced

0006AB SEQUENCE A002AB:

LIQUID PENETRANT (PT)

INSPECTION

INFO ONLY Not Separately Priced

0006AC SEQUENCE A003:

MATERIAL SAFETY DATA

SHEETS

INFO ONLY Not Separately Priced

• Required Delivery Date: 01/01/2027

• Place of performance is: Portsmouth Naval Shipyard, Kittery Maine, 03904

• For evaluation purposes, please provide any applicable procedures and technical information. If no information is provided, your quotation may be determined to be unresponsive.

• Award may be made on the basis of adherence to the schedule and/or soonest mobilization.

• Please provide published commercial labor rates and breakdown of total prices, if applicable, for Price Justification purposes.

• See Below for Detailed Statement of Work and Applicable Clauses.

ALL OFFERS SHALL INCLUDE THIS FORM FILLED OUT IN ITS ENTIRETY (HIGHLIGHTED YELLOW

FIELDS ARE REQUIRED).

CLAUSES:

Responsibility and Inspection: unless otherwise specified in the order, the supplier is responsible for the performance of all inspection requirements and quality control. The following FAR provisions and clauses are applicable to this procurement:

52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements—Representation

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements

52.204-7 System for Award Management 52.204-13 System for Award Management Maintenance

52.204-19 Incorporation by Reference of Representations and Certifications

52.204-22 Alternative Line Item Proposal 52.207-1 Notice of Standard Competition 52.209-1 Qualification Requirements

52.209-2 Prohibition on Contracting with Inverted Domestic Corporations—Representation

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations

52.209-11 Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law

52.210-1 Market Research 52.211-8 Time of Delivery

52.212-1 Instructions to Offerors—Commercial Products and Commercial Services

52.212-2 Evaluation—Commercial Products and Commercial Services

52.212-3 Offeror Representations and Certifications—Commercial Products and Commercial Services

52.212-4 Contract Terms and Conditions—Commercial Products and Commercial Services

52.213-4 Terms and Conditions—Simplified Acquisitions (Other Than Commercial Products and Commercial Services)

52.219-1 Small Business Program Representations 52.219-6 Notice of Total Small Business Set-Aside

52.219-28 Post-Award Small Business Program Rerepresentation

52.222-3 Convict Labor

52.222-19 Child Labor—Cooperation with Authorities and Remedies

52.222-50 Combating Trafficking in Persons 52.223-3 Hazardous Material Identification & Material Safety Data 52.226-7 Drug Free Workplace

52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving

52.227-3 Patent Indemnity

52.232-33 Payment by Electronic Funds Transfer—System for Award Management

52.232-36 Payment by Third Party 52.232-39 Unenforceability of Unauthorized Obligations

52.232-40 Providing Accelerated Payments to Small Business Subcontractors

52.233-3 Protest after Award 52.233-4 Applicable Law for Breach of Contract Claim 52.246-1 Contractor Inspection Requirements 52.246-2 Inspection of Supplies—Fixed-Price:

Inspection of Supplies-Fixed-Price (Aug 1996)

(a) Definition. "Supplies," as used in this clause, includes but is not limited to raw materials, components, intermediate assemblies, end products, and lots of supplies.

(b) The Contractor shall provide and maintain an inspection system acceptable to the Government covering supplies under this contract and shall tender to the Government for acceptance only supplies that have been inspected in accordance with the inspection system and have been found by the Contractor to be in conformity with contract requirements. As part of the system, the Contractor shall prepare records evidencing all inspections made under the system and the outcome. These records shall be kept complete and made available to the Government during contract performance and for as long afterwards as the contract requires.

The Government may perform reviews and evaluations as reasonably necessary to ascertain compliance with this paragraph. These reviews and evaluations shall be conducted in a manner that will not unduly delay the contract work. The right of review, whether exercised or not, does not relieve the Contractor of the obligations under the contract.

(c) The Government has the right to inspect and test all supplies called for by the contract, to the extent practicable, at all places and times, including the period of manufacture, and in any event before acceptance. The Government shall perform inspections and tests in a manner that will not unduly delay the work. The Government assumes no contractual obligation to perform any inspection and test for the benefit of the Contractor unless specifically set forth elsewhere in this contract.

(d) If the Government performs inspection or test on the premises of the Contractor or a subcontractor, the Contractor shall furnish, and shall require subcontractors to furnish, at no increase in contract price, all reasonable facilities and assistance for the safe and convenient performance of these duties. Except as otherwise provided in the contract, the Government shall bear the expense of Government inspections or tests made at other than the Contractor’s or subcontractor’s premises; provided, that in case of rejection, the Government shall not be liable for any reduction in the value of inspection or test samples.

(e) (1) When supplies are not ready at the time specified by the Contractor for inspection or test, the Contracting Officer may charge to the Contractor the additional cost of inspection or test.

(2) The Contracting Officer may also charge the Contractor for any additional cost of inspection or test when prior rejection makes reinspection or retest necessary.

(f) The Government has the right either to reject or to require correction of nonconforming supplies. Supplies are nonconforming when they are defective in material or workmanship or are otherwise not in conformity with contract requirements. The Government may reject nonconforming supplies with or without disposition instructions.

(g) The Contractor shall remove supplies rejected or required to be corrected. However, the Contracting Officer may require or permit correction in place, promptly after notice, by and at the expense of the Contractor. The Contractor shall not tender for acceptance corrected or rejected supplies without disclosing the former rejection or requirement for correction, and, when required, shall disclose the corrective action taken.

(h) If the Contractor fails to promptly remove, replace, or correct rejected supplies that are required to be removed or to be replaced or corrected, the Government may either (1)by contract or otherwise, remove, replace, or correct the supplies and charge the cost to the Contractor or (2) terminate the contract for default. Unless the Contractor corrects or replaces the supplies within the delivery schedule, the Contracting Officer may require their delivery and make an equitable price reduction. Failure to agree to a price reduction shall be a dispute.

(i) (1) If this contract provides for the performance of Government quality assurance at source, and if requested by the Government, the Contractor shall furnish advance notification of the time-

(i) When Contractor inspection or tests will be performed in accordance with the terms and conditions of the contract; and

(ii) When the supplies will be ready for Government inspection.

(2) The Government’s request shall specify the period and method of the advance notification and the Government representative to whom it shall be furnished. Requests shall not require more than 2 workdays of advance notification if the Government representative is in residence in the Contractor’s plant, nor more than 7 workdays in other instances.

(j) The Government shall accept or reject supplies as promptly as practicable after delivery, unless otherwise provided in the contract. Government failure to inspect and accept or reject the supplies shall not relieve the Contractor from responsibility, nor impose liability on the Government, for nonconforming supplies.

(k) Inspections and tests by the Government do not relieve the Contractor of responsibility for defects or other failures to meet contract requirements discovered before acceptance.

Acceptance shall be conclusive, except for latent defects, fraud, gross mistakes amounting to fraud, or as otherwise provided in the contract.

(l) If acceptance is not conclusive for any of the reasons in paragraph (k) hereof, the Government, in addition to any other rights and remedies provided by law, or under other provisions of this contract, shall have the right to require the Contractor (1)at no increase in contract price, to correct or replace the defective or nonconforming supplies at the original point of delivery or at the Contractor’s plant at the Contracting Officer’s election, and in accordance with a reasonable delivery schedule as may be agreed upon between the Contractor and the Contracting Officer; provided, that the Contracting Officer may require a reduction in contract price if the Contractor fails to meet such delivery schedule, or (2) within a reasonable time after receipt by the Contractor of notice of defects or nonconformance, to repay such portion of the contract as is equitable under the circumstances if the Contracting Officer elects not to require correction or replacement. When supplies are returned to the Contractor, the Contractor shall bear the transportation cost from the original point of delivery to the Contractor’s plant and return to the original point when that point is not the Contractor’s plant.

If the Contractor fails to perform or act as required in paragraph (l)(1) or (l)(2) of this clause and does not cure such failure within a period of 10 days (or such longer period as the Contracting Officer may authorize in writing) after receipt of notice from the Contracting Officer specifying such failure, the Government shall have the right by contract or otherwise to replace or correct such supplies and charge to the Contractor the cost occasioned the Government thereby.

(End of clause) 52.246-15 Certificate of Conformance

52.247-34 F.o.b. Destination

52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form)

52.252-1 Solicitation Provisions Incorporated by Reference

52.252-2 Clauses Incorporated by Reference 52.252-6 Authorized Deviations in Clauses 52.253-1 Computer Generated Forms

Additional DFARS contract terms and conditions applicable to this procurement are:

252.203-7000 Requirements Relating to Compensation of Former DoD Officials

252.203-7002 Requirement to Inform Employees of Whistleblower Rights

252.204-7003 Control of Government Personnel Work Product

252.204-7009 Limitations on the Use or Disclosure of Third-Party Contractor Reported Cyber Incident Information

252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting

252.204-7014 Limitations on the Use or Disclosure of Information by Litigation Support Contractors

252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support

252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services

252.204-7024 Notice on the use of the Supplier Performance Risk System

252.206-7000 Domestic Source Restriction 252.211-7003 Item Unique Identification and Valuation 252.223-7001 Hazard Warning Labels 252.223-7008 Prohibition of Hexavalent Chromium

252.232-7003 Electronic Submission of Payment Requests and Receiving Reports

252.232-7006 Wide Area WorkFlow Payment Instructions 252.232-7010 Levies on Contract Payments 252.243-7001 Pricing of Contract Modifications

252.244-7000 Subcontracts for Commercial Products or Commercial Services

252.246-7004 Safety of Facilities, Infrastructure, and Equipment for Military Operations

252.247-7023 Transportation of Supplies by Sea--Basic

C-202-H001 Additional Definitions--Basic (Navsea) (Oct 2018)

C-204-H001 Use Of Navy Support Contractors For Official Contract Files (Navsea) (Oct 2018)

C-204-H002 Implementation Of Enhanced Security Controls On Select Defense Industrial Base Partner Networks (Navsea) (Jan 2020)

C-211-H018 Approval By The Government (Navsea) (Jan 2019)

C-215-H002 Contractor Proposal Navsea) (Oct 2018)

C-217-H001 Provisioned Items Order--Basic (Navsea) (Oct 2018)

C-223-H003 EXCLUSION OF MERCURY (NAVSEA) (MAR 2019)

C-223-N002 Restrictions On Use Of Yellow Material (Navsea) (Oct 2018)

C-227-H003 PROTECTION OF NAVAL NUCLEAR PROPULSION INFORMATION (NAVSEA) (OCT

2018)

C-227-H006 DATA REQUIREMENTS (NAVSEA) (OCT 2018)

C-246-H002 GOVERNMENT USE OF CONTRACTOR'S INSPECTION EQUIPMENT (NAVSEA) (OCT

2018)

C-247-H001 Permits And Responsibilities (Navsea) (Dec 2018)

D-211-H001 PACKAGING OF DATA (NAVSEA) (FEB 2022)

D-223-W001 EXPLOSIVE OR HAZARDOUS MATERIALS--PACKAGING & LABELING (NAVSEA)

(OCT 2018)

D-247-H002 Packaging Of Supplies--Basic (Navsea) (Dec 2020)

D-247-W001 Prohibited Packing Materials (Navsea) (Oct 2018)

E-246-H013 INSPECTION AND ACCEPTANCE OF DATA (NAVSEA) (OCT 2018)

E-246-H019 Inspection And Acceptance Of Ptd (Navsea) (Oct 2018)

E-246-H022 Inspection And Test Records (Navsea) (Jan 2019)

E-246-W002 Certificate Of Compliance (Navsea) (Oct 2018)

E-246-W004 Procurement Quality Assurance Inspection And Acceptance (Navsea) (Oct 2018)

F-211-W001 Partial Deliveries (Navsea) (Oct 2018)

F-242-H001 Contractor Notice Regarding Late Delivery (Navsea) (Oct 2018)

F-247-H001 DELIVERY OF DATA (NAVSEA) (OCT 2018)

F-247-N002 Instructions For Deliveries To The Portsmouth Naval Shipyard (Navsea) (Mar 2019)

G-232-H002 Payment Instructions (Navsea) (Feb 2024)

G-232-H005 Supplemental Instructions Regarding Invoicing (Navsea) (Jan 2019)

G-242-H001 Government Contract Administration Points-Of-Contact And Responsibilities (Navsea) (Oct 2023)

G-242-H002 Hours Of Operation And Holiday Schedule (Navsea) (Jul 2021)

H-246-H001 CALIBRATION SYSTEM REQUIREMENTS (NAVSEA) (FEB 2023)

52.212-1 Instructions to Offerors--Commercial Items

I. GENERAL

In addition to FAR 52.212-1, “Instructions to Offerors – Commercial Items” and any other Instructions contained elsewhere in this solicitation, the following information is provided:

Objections to any of the terms and conditions of the RFQ will constitute a deficiency which will make the offer unacceptable.

IMPORTANT NOTES:

1. Vendors shall respond to all requirements of the solicitation document. Vendors are cautioned not to alter the solicitation.

2. Initial quotes and any modifications thereto are to be submitted to the Contracting Office on or before the closing dated time cited elsewhere in this Request for Quote.

3. Responses should be submitted via email only

4. Please review all specifications carefully.

II. CONTENT OF QUOTE

• RFQ pricing and information pages completed by the vendor.

• Technical Submission to include:

o Submission of technical information demonstrating compliance with the specifications, including, but not limited to:

Brochures pertaining to the pieces of equipment being quoted, to include, but not limited to: pictures of the equipment, and technical specifications of the equipment including model/series unit demonstrating compliance with the PWS and specifications. These should be readily identified by the item ID number.

The details of any/all exceptions taken to the specification.

The completion and submission of the above items will constitute a quote and will be considered the vendor’s unconditional assent to the terms and conditions of this solicitation and any attachments and/or exhibits hereto. An objection to any of the terms and conditions of the solicitation will constitute a deficiency which will make the offer unacceptable. Potential contractors will be screened for contractor responsibility in accordance with FAR Subpart 9.1.

52.212-2, Evaluation - Commercial Items is applicable to this procurement.

The Government will award a contract resulting from this solicitation to the responsible vendor whose quote conforming to the solicitation will be most advantageous to the Government, price and other factors considered. The contract will be awarded to the vendor with the Lowest Price Technically Acceptable. Quotes will be evaluated based on the following criteria:

- Technical Acceptability (Must meet specifications and document capabilities)

- Adherence to Schedule (Award may be made based on delivery and ability to meet the requested schedule)

- Price (Lowest Price Technically Acceptable, after adherence to other factors)

Vendors will be required to submit a quote that will be evaluated in accordance with the specifications provided in the solicitation, FAR 52.212-1 Instruction to Offerors. Failure to include pricing for all line items shall be cause for rejection of the quote for all line items.

Technical:

Please provide documentation demonstrating your capabilities in fulfilling the SOW.

Technical Evaluation Ratings Rating Description Acceptable Submission clearly meets the minimum requirements of the solicitation Unacceptable Submission does not clearly meet the minimum requirements of the solicitation

If the technical submittal is determined “Unacceptable”, it renders the entire quote technically unacceptable. Technical submissions that do not meet the minimum requirements will be rated as “Unacceptable” and will no longer be considered for further competition or award.

Schedule:

Please confirm availability for requested period of performance. If your company is unavailable for the requested period, please provide earliest available start. Please provide your best and fastest schedule. Award may be made to the vendor who can provide the soonest execution.

Price:

The Price will be evaluated as Lowest Price Technically Acceptable, however, the Contracting Officer reserves the right to award based on ability to meet the required schedule.

******* END OF REQUEST FOR QUOTE *******