This is a justification memorandum for use of other than full and open competition for an acquisition under the Simplified Acquisition Threshold. The document authorizes a single-source procurement for an ASCO 7000 automatic transfer switch (ATS), ASCO catalogue number J07ATB030400N5XP, rated for 480V/400A and housed in a NEMA 4X stainless steel outdoor-rated enclosure. The required delivery date is July 1, 2026.
The contracting officer has determined that brand name justification applies to this procurement. The ASCO 7000 ATS is required as a direct replacement part for units being installed to support the DD2 Complex facility and serves as a critical spare part. The specific make and model is the standard switch used throughout the Shipyard for emergency power applications, with electrical production shops trained exclusively on this unit and engineering procedures written to interface with it. Substituting an alternative product would necessitate additional training, reworking of engineered procedures, and cause operational delays. The justification was certified by Brendan Kennedy on March 5, 2026, and approved by Contracting Officer Dayna O'Brien on March 23, 2026.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N3904026Q5451_ QA.pdf | ||
| N3904026Q5451_ Combined Synopsis.pdf | ||
| N3904026Q5451_ Attachment 1- SOW.pdf | ||
| N3904026Q5451_ Attachment 2- OPSEC.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(This is only applicable to acquisitions under the Simplified Acquisition Threshold. Acquisition using FAR Subpart 13.5 shall follow the special documentation requirements at FAR 13.501.)
USE OF OTHER THAN FULL AND OPEN COMPETITION FOR AN ACQUISITION
UNDER THE SIMPLIFIED ACQUISITION THRESHOLD
I. BACKGROUND:
1. FAR 13.106-1(b)(1)(i) states for purchases not exceeding the simplified acquisition threshold, Contracting Officers may solicit from one source if the Contracting Officer determines that the circumstances of the contract action deem only one source reasonably available (e.g., urgency, exclusive licensing agreements, brand-name or industrial mobilization).
2. As required by FAR 13.106-3(b)(3)(i), this memorandum explains the absence of competition for this acquisition, as only one source will be solicited for this requirement (or for a portion of the requirement) and the requirement is not expected to exceed the simplified acquisition threshold.
II. DESCRIPTION OF ITEM OR SERVICE:
Provide a description of the item or service required, to include its intended use, the name of the required source or brand name, and the required delivery date/period of performance.
Item is an ASCO 7000 automatic transfer switch (ATS) with bypass and isolation capability.
ATS is ASCO catalogue # J07ATB030400N5XP and is rated for 480V / 400A and is contained in a NEMA 4X stainless steel outdoor rated enclosure. RDD is 7/1/2026
III. THE DETERMINATION FOR USE OF OTHER THAN FULL AND OPEN
COMPETITION IS BASED ON THE FOLLOWING (select all that apply):
A. ___ ONLY ONE RESPONSIBLE SOURCE (select all that apply):
1. ___ RESTRICTIVE RIGHTS. The source has established proprietary rights, limited rights in data, patent rights, copyrights or secret processes in the item or service required.
Explain what rights are restricted, why the restrictive rights make the required item or service available from only one source, and why another company could not satisfy the Government’s need.
2. ___ EXCLUSIVE LICENSING AGREEMENTS. The item or service is only available from the Original Equipment Manufacturer (OEM), or there is only one authorized distributor or technical representative for the OEM.
Identify the OEM and explain the circumstances surrounding why the item or service is only available from the OEM.
OR
Identify the distributor(s)/authorized technical representative(s) for the item or service. Provide evidence of the exclusive licensing agreement as an attachment to this document. NOTE: If there is more than one distributor/authorized technical representative for an OEM part, then Part B, BRAND NAME SOLE SOURCE, is applicable, and Part A, ONLY ONE RESPONSIBLE SOURCE, should be left blank).
3. ___ OTHER REASONS. Other reason not identified above. Provide details on mission impact if requirement is not solicited from only one source.
B. _X_ BRAND NAME. Item required must be a brand name product, or feature of a product, particular to one manufacturer. Discuss why you are precluding consideration of a product manufactured by another company. Describe how the particular brand name, product, or feature is essential to the Government’s requirements and why a “brand name or equal” purchase description cannot be used (see FAR 11.104). Describe how market research indicates other companies’ similar products or products lacking the particular feature do not meet, or cannot be modified to meet, the agency’s needs.
The requested ASCO 7000 automatic transfer switch (ATS) with the specified part number and stated accessory package is required for this application due to it being a direct replacement part for the ATS units that will be installed to support the DD2 Complex facility. This ATS has been identified as a critical spare part and is required to be on-hand once the facility is online. This particular make and model of transfer switch is used throughout the Shipyard and is the standard switch used in emergency power applications. Due to this, the electrical production shops are trained on this specific unit and the engineering procedures they follow are written to interface with this specific unit.
Changing from the ASCO 7000 ATS in this application would cause detriment to the production personnel who interface with the switch and cause the need for additional training and reworking of engineered procedures. This re-engineering would cause excess effort and delays and is not desirable.
C. ___UNUSUAL AND COMPELLING URGENCY. The supplies or services are of such unusual and compelling urgency that the Government would be seriously injured unless the agency is permitted to limit the number of sources from which it solicits bids or proposals.
Urgent requirements are supplies or services that will result in a work stoppage, or are mission critical and the routine processing time would result in injury to the Government. The determination that the procurement for the above item/service is an urgent and compelling requirement is based on the following:
1. Date on which the requirement was first identified:
2. Required delivery date/period of performance:
File details come from the government source that posted it. Updated .