Urgency_Impact_Statement_Redacted.pdf
PDF 741 KB Posted
- Attached to
- N3904019Q0100 - Disposal Containers Federal contract opportunity
- Solicitation number
- N3904019Q0100
About this file
Signed Sole Source
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N3904019Q0100_RFQ.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JUSTIFICATION FOR URGENCY ($2,500 to $250,000)
Ref: FAR 13.106 and NAVSUP 4200.85D Chapter 5 Paragraph 2.b.(2)(b)
The service or material listed on (Document number) is urgent and advertising requirements are precluded for reasons indicated below. If the service/material is not received by the Required Delivery Date (ROD), specific damages to the Navy will result.
1. In the spaces above, provide the name of all known suppliers of the required product or service. Suggested Source(s) (complete with addresses, phone and fax numbers):
(1) American Alloy; 3808 N Sullivan Rd.; Building 11 - Suite M; Spokane, WA 99216 phone: 509-921-5794; fax : 509-893-4175
(2) ________________________ _
(3) ________________________ _
2. Brief descriptive narrative of service or material required:
Fabrication of custom disposal containers to be used for a project at the . Usage will be in the Delivery date for the containers must include sufficient time for inspection of the containers as well as time to address any deficiencies that may be found during inspection. Containers must then be shipped from
3. Required Delivery Date (RDD):_F=-e=b=r-=u=ar:...;.y--=2==8o..i.,-=2-=-0-=-19"----------------
4. Describe the resulting damages if the above required delivery date is not met. Explain why the service/material is needed and what will happen if it's not received by the RDD. (As necessary, describe the impact on overhaul/availability schedules, impact to base support, personnel safety issues, potential environmental damages, etc.) The impact should be expressed as the daily cost (labor, material, etc.) to the government for each day of delay beyond the RDD.
The RDD is selected delays in delivery will directly translate into day-for-day delays in critical-path project work at the , because we will be unable to remove the necessary items without a container into which they can be placed. This is sequential work with no parallel path. The project has stated that each day of delay results in a one million dollar cost to the government.
5. Lack of prior planning does not support urgency. Please provide a time-line beginning on the date the need was first identified and ending on the date the requisition was submitted to the Contracting Office. Why is the claimed "urgency" not the result of a lack of advanced planning?
approximately eight months of time because , and have only approximately two and a half months to obtain replacement containers.
6. Only our minimum current requirements can be purchased under conditions of urgency.
What is the minimum quantity that must be obtained by the RDD? Why can't some of the total required quantity be procured under urgency while procuring the remaining items/services through the normal procurement process?
All containers will be used within an approximate one-week time span. The entire quantity is urgent, and no portion of the order may be contracted separately through the normal contracting process.
I CERTIFY THAT STATEMENTS CHECKED ABOVE ARE COMPLETE AND
CORRECT TO THE BEST OF MY KNOWLEDGE AND DO NOT CONTAIN
CLASSIFIED INFORMATION. I UNDERSTAND THAT PROCESSING THIS
URGENCY STATEMENT COULD PRECLUDE THE FULL ADVERTISEMENT OF
THIS PROCUREMENT.
Signature IS/ Jeff Wilson Title Nuclear Engineer
Activity Portsmouth Naval Shipyard Date 12/6/2018
Contracting Officer Signatur~ ~ Date rJ/J 1 /;g
File details come from the government source that posted it.