N3319124R0033 Attach 1 PTS.pdf
PDF 20 MB Posted
- Solicitation number
- N3319124R0033
About this file
This document is an attachment titled "N3319124R0033 Attach 1 PTS.pdf" related to Solicitation Number N3319124R0033 for the design and construction of a Maritime Center of Excellence (MCOE) in Bizerte, Tunisia.
The solicitation is issued by the Department of the Navy, Naval Facilities Engineering Command. It requires the design and construction of the MCOE facility, including site preparation, utilities, infrastructure, and all associated work. The project has a total not-to-exceed value of $37,200,000. The contract type is Design-Build, with a Guaranteed Maximum Price. Responses to the solicitation are due by July 6, 2023, and the anticipated award date is September 28, 2023. The project includes small business and HUBZone set-asides. No incumbent contractor information is provided.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Maritime Center of Excellence (MCOE) Phase I
– BPC 333 Cases Bizerte, Tunisia
WON: 1807573
WORK ORDER NO. 1807573
Request For Proposal (RFP) Design-Build
‘Scope of Work’
PROJECT TITLE: Maritime Center of Excellence (MCOE) Phase I - BPC 333 Cases
At
Tunisia Navy Base, Bizerte, Tunisia
FINAL
May 28th, 2024
PREPARED BY:
NAVFAC EURAFCENT
Expeditionary Business Line (EXBL)
Viale Porto 51 Aeroporto Capodichino 80144, Napoli, IT
Project Manager: Morgan Danner, R.A.
APPROVED BY:
NAVFAC EURAFCENT EX: Fredelix Menez, P.E.
Review Date: May 27, 2024
Bizerte, Tunisia
WON: 1807573
Table of Contents PROJECT TITLE: Maritime Center of Excellence (MCOE) Phase I - BPC 333 Cases
1. PROJECT OVERVIEW
1.1 PROJECT LOCATION
1.2 DESIGN-BUILD CONTRACT
1.2.1 Acronyms
1.2.2 Sustainable Design
1.2.3 Appropriate Design
1.2.4 Design Phase
1.2.2 Construction Phase
1.2.3 Contract Milestones
1.3 CONTRACTUAL BASE-BID AND BID OPTIONS
1.3.1 Base-Bid
1.3.2 Bid Option 1
1.3.3 Bid Option 2
1.3.4 Bid Option 3
2. GENERAL SCOPE OF WORK
2.1. GENERAL DEMOLITION SCOPE OF WORK
2.2. GENERAL SITE/CIVIL SCOPE OF WORK
2.3. GENERAL STRUCTURAL SCOPE OF WORK
2.4. GENERAL ARCHITECTURAL SCOPE OF WORK
2.5. GENERAL MECHANICAL SCOPE OF WORK
2.6. GENERAL PLUMBING SCOPE OF WORK
2.7. GENERAL ELECTRICAL SCOPE OF WORK
3. DETAILED SCOPE OF WORK
3.1. DETAILED SITE/CIVIL SCOPE OF WORK
3.1.1. Topographic Survey
3.1.2. Geotechnical Report
3.1.3. Clearing and Grubbing
3.1.4. Grading, Excavation, and Compaction
3.1.5. Site Drainage & Stormwater Runoff
3.1.6. Utilities
3.1.7. Construction Contractor’s Laydown Area
3.1.8. Permits
Bizerte, Tunisia
WON: 1807573
3.1.9. Environmental
3.1.10. Existing Conditions and Interference with Construction
3.2. DETAILED STRUCTURAL SCOPE OF WORK
3.2.1. Facility Foundations and Floor Slabs
3.2.2. Building Structural System
3.3. DETAILED ARCHITECTURAL SCOPE OF WORK
3.3.1. Floor Plan
3.3.2. Thermal Facade
3.3.3. Roof System (sandwich panels)
3.3.4. Windows
3.3.5. Interior Doors
3.3.6. Exterior Doors
3.3.7. Ceilings
3.3.8. Flooring
3.3.8. Walls
3.3.9. Fixed Furniture and Equipment
3.4. DETAILED MECHANICAL SCOPE OF WORK
3.4. Ventilation System
3.5. DETAILED PLUMBING SCOPE OF WORK
3.5.1. Domestic Water Service
3.5.2. Sanitary Sewer Service
3.5.3. Bathroom Requirements
3.6. DETAILED ELECTRICAL SCOPE OF WORK
3.6.1. Electrical Service Connection
3.6.2. Interior Lighting
3.6.3. Exterior Lighting
3.6.4. Electrical Distribution
3.6.5. Fire Alarm System
4. BID OPTIONS
5. ADMINISTRATIVE REQUIREMENTS
5.1. TAXATION
5.2. LEGAL AND ADMINISTRATIVE REQUIREMENTS
5.2.1 Contract Compliance
5.2.2 Responsibility for Fees
Bizerte, Tunisia
WON: 1807573
5.2.3 Requirement for Third-Party Services
5.2.4 Period of Performance (600 calendar days)
5.2.5 Hours of Operation and Temporary Construction Site Plan
5.3 OMISSIONS FROM SPECIFICATIONS
5.4 AUTHORITY TO MAKE CONTRACT CHANGES
5.5 MEASUREMENTS AND QUANTITES
5.5.1. Assumptions of Site Conditions
5.6 SCHEDULE OF PRICES
5.7 PAYMENT
5.8 SAFETY REQUIREMENTS
5.8.1 Safety Regulations
5.8.2 Accident Prevention Plan
5.8.3 Tunisian Safety Requirements
5.8.4 Additional Safety Requirements
5.8.5 Scaffolding, Manlifts, and Fall Protection
5.9 CONSTRUCTION SIGN & COMMEMORATIVE PLAQUE
5.9.1 Construction Sign
5.9.2 Commemorative Plaque
5.10 QUALITY CONTROL PLAN
5.11 CONTRACT CLOSE-OUT REQUIREMENTS
5.11.1 Contract Close-Out Procedures
5.11.2 Warranties
5.11.3 Training and Operations and Maintenance (O&M) Manuals
5.11.4 Cleaning
5.11.5 Damage to Existing Site & Facilities
5.11.6 Spare Parts and Materials
Attachment 1: Quality Control Plan
Attachment 2: Concept Site Plan
Attachment 3: Concept Drawings
Attachment 4: Tunisian Navy Base Site Development Drawings
Bizerte, Tunisia
1. PROJECT OVERVIEW
This Project includes the Design-Build of maritime training and support facilities for the Maritime Center of Excellence (MCOE) at the Tunisian Navy Base- Bizerte, Tunisia for the Tunisian Marine Special Operation Forces (SOF) and the Navy Commando courses. Facilities will support US and partner nation trainings between the Tunisian Marine SOF and US Marines Forces Africa (MARFORAF), as well as the Tunisian Navy Commandos and the US Navy (NAVAF). The Contractor shall provide all services necessary to provide a complete and usable facilities with a maximum period of performance of 600 calendar days after award of the contract. Contract will be executed by Naval Facilities Engineering Command (NAVFAC) through the Building Partner Capacity 333 (BPC 333) Defense Security Cooperation Agency (DSCA) funding program, on behalf of the US Embassy Tunisia Office of Security Cooperation (OSC) and Tunisian Ministry of Defence (MOD), through US Africa Command (AFRICOM).
1.1 PROJECT LOCATION
The project site is located on a Tunisian military facility known as the Maritime Center of Excellence Naval Base & Ras Echaara Naval Base, near the city of Bizerte, across the water from La Pecherie 51st Regimental Commando Marine (RCM) Headquarters. The figures below provide detailed location information.
GPS coordinates are: N 37.237880, E 9.89928
Note: The Contractor shall conduct a pre-bid site visit to verify existing conditions prior to submission of their offer to the US Government. The Contractor may consult with the Tunisian MOD if additional information concerning site conditions are required. The Contractor shall coordinate their site visit and any request for information regarding site conditions with the NAVFAC Project Manager (PM) or other representative from the United States Office of Security Cooperation in Tunis:
NAVFAC PM: Morgan Danner morgan.b.danner.civ@us.navy.mil NAVFAC Civil Engineer: Fredelix Menez fredelix.o.menez.civ@us.navy.mil NAVAF LNO Tunisia: LTJG Brian McClendon McClendonBT@state.gov mailto:morgan.b.danner.civ@us.navy.mil mailto:fredelix.o.menez.civ@us.navy.mil
Bizerte, Tunisia
Country Location
General Site Location of MCOE
La Pecherie Naval Base & MCOE Site / Naval Base
U.S. Embassy Tunis
Bizerte, Tunisia
WON: 1807573
1.2 DESIGN-BUILD CONTRACT
The method of completion for this project is Design-Build. The Contractor is responsible for both the design and construction of the facility. The US Government shall only provide conceptual plans, general specifications, and requirements as outlined in this Request for Proposal (RFP) and Scope of Work (SOW). The Design-Build project includes two phases: Design and Construction. Contractor is responsible for all permits associated with proceeding from the design phase to the construction phase and all associated coordination with local authorities and agencies.
1.2.1 Acronyms
NAVFAC Contracting Officer (KO) = official contract authority on contract award document
NAVFAC Contracting Officer Representative (COR) = acts on behalf of the KO to represent the government and support technical decisions on scope, design, engineering, and construction.
Final contract authority is routed from the COR to the KO for official implementation. NAVFAC COR is dual hatted as the NAVFAC Project Manager (PM).
Contractor (KTR) = contracted company awarded this scope of work for execution
Designer of Record (DOR) = works for or with the Contractor to produce the required design phase documents and is the authority for the design to be properly stamped and signed for permit by local authorities
1.2.2 Sustainable Design
Sustainable principles must be integrated into the design, development and construction of the project.
The total cost of facility ownership is to be reduced using whole-building, life-cycle approaches.
Sustainable design strategies and features are to be integrated throughout planning, design and construction of the facilities to minimize energy consumption; conserve resources; minimize adverse effects on the environment; and improve occupant productivity, health and comfort.
1.2.3 Appropriate Design
Design and construction choices must maintain a local, aesthetic character. To the greatest extent possible and while still meeting the requirements presented herein, labor and materials are to be acquired locally to promote the local economy. Construction methods are to align with those used locally to take advantage of the skills and experience of local tradespersons. All construction materials and installed equipment shall be new.
1.2.4 Design Phase
The Contractor shall provide a complete design prepared in compliance with applicable architectural, engineering, planning and construction codes of Tunisia and the local municipality. The Contractor shall utilize services of architects and engineers licensed to practice in Tunisia to act as the Designer of Record (DOR). The Contractor and any Sub-contractors employed by the Contractor must be licensed and certified to practice in Tunisia.
The US Government shall only provide conceptual plans, requirements, and specifications as detailed in this document. The Contractor shall develop a design that meets all requirements and specifications
Bizerte, Tunisia
WON: 1807573
contained in this Scope of Work.
In addition to meeting the requirements detailed in this document, the Contractor shall incorporate all design requirements necessary to meet laws, regulations, and codes of Tunisia and the local municipality. Contractor shall commence a topographical and geotechnical study of the project area to facilitate the design. The design phase will proceed as follows:
Post-Award Kick-Off Meeting (PAK): The Contractor will conduct a Post-Award Kick-Off meeting within 5 days of contract award to review the project scope of work and identify the design phase schedule. Meeting will also discuss other logistics, like the first site visit, base access, and introduce the Contractor to the key players of the Government team. (Attendees shall include but not limited to; NAVFAC COR, NAVFAC KO, NAVFAC Civil Engineer, Office of Security Cooperation US Embassy Tunisia, and MOD.
The Contractor shall submit PAK meeting minutes and the Construction Schedule, Quality Control Plan and Accident Prevention Plan (APP) within 10 days of the PAK Meeting.
- Draft Construction Schedule: The Contractor shall have 600 calendar days to complete the construction work. By the timeline set for the final design submission. The Contractor shall prepare and submit a schedule of construction where the different work segments are identified and associated to the timeframe set for completion. The construction schedule shall state which work segments completion determines the achievement of the construction steps associated to the progressive invoicing (i.e. 10% (design completion), 25%, 40%, 55%, 70%, and 85% work progress). The final payment will be done on the facilities acceptance. (Additional information on Contract Milestones are noted in Section 1.2.3.)
- Quality Control Plan: By the timeline set for the final design completion, the Contractor will prepare and submit a Quality Control Plan describing personnel, procedures, tests and installation techniques that he plans to perform to ensure the quality required by this document and his design is obtained. (Additional information on the quality control plan is noted in Section 5.10 and Attachment 1.)
o Quality Control portion will provide the roles, responsibilities, qualifications, and training of the construction team including the QC Manager, Superintendent, Site Supervisors and the overall Project Manager. The following requirements are established for the Superintendent and QC Manager:
Superintendent: The Superintendent must have a minimum of five years of experience as a Superintendent on previous projects of similar size and complexity. The Superintendent may not also serve as the Site Safety and Health Officer (SSHO) nor QC Manager. The Contractor must submit the proposed on-site Project Superintendent’s resume providing his or her experience, references and qualifications to the KO for approval. The KO reserves the right to interview the proposed on-site Project Superintendent at any time to verify the submitted qualifications.
QC Manager: The QC Manager is responsible for the program outlined in the Quality Control Plan. The Superintendent may not also serve as the QC Manager. The QC Manager must have a minimum of 15 years of combined experience as a Project Superintendent, QC Manager, Bizerte, Tunisia
WON: 1807573
inspector, Project Manager, Project Engineer or Construction Manager on projects of similar size and complexity. The QC Manager must possess a current certificate showing successful completion of the NAVFAC Contractor Quality Management (CQM) Training or similar approved local certification.
- Accident Prevention Plan: By the timeline set for the final design completion, the
Contractor will prepare and submit an APP describing procedures to ensure the safety of personnel and equipment on the job site. At a minimum, the safety plan must address types of personnel protective equipment to be used by personnel, types and frequencies of safety inspections, activity hazard analysis (AHA) to prevent safety incidents, and training utilized to familiarize employees with safety policies and practices.
The Contractor shall then proceed to provide to the US Government not less than three (3) design submissions and the pre-construction submittals as follows:
Conceptual Design: The Contractor shall conduct a site visit(s) to asses existing conditions and infrastructure at the project location. Contractor shall examine and identify all connection points for utilities and distribution systems, as well as collect other data required to fulfill the SOW.
During these site visits, the Contractor shall collect all existing relevant documentation such as record drawings for building operating plans, shop drawings, operations and maintenance records, building orientation details and known operational issues. Contractor will then prepare a conceptual design that details an approximate 35% solution to the facility design. This conceptual design shall include all necessary detail to show a feasible design that meets the requirements of the contract. The Contractor shall coordinate with the Beneficiary and NAVFAC Contracting Officer Representative “COR” (note that the NAVFAC COR and the NAVFAC PM for this contract are the same person, from here on the use of NAVFAC COR will be used for duties applicable to that role) to ensure that all user and contractual requirements are met. The Conceptual design should at minimum contain details for:
- Site design
- Conceptual site grading plan
- Demolition Plan
- Architectural floorplans of each facility
- Architectural elevations, including window and door locations of each facility
- Conceptual structural plan
- Conceptual mechanical plan
- Conceptual electrical plan
The NAVFAC COR will review the Conceptual Design.
Pre-Final Design: The Contractor shall prepare a pre-final design that represents a 95% solution to the facility design. This design shall include everything necessary for the Contractor to submit the design to the relevant Government authorities. The Pre-final design shall include the completed topographical survey and the geotechnical report and data necessary to finalize the civil plans and foundations. The Pre-final design should contain:
- Detailed Site Plan
Bizerte, Tunisia
WON: 1807573
- Detailed Civil Plan, including grading, drainage, water and sewer plans
- Topographic Survey
- Geotechnical Report
- Detailed Architectural floorplans of each facility
- Detailed Architectural Elevations of each facility
- Detailed Architectural Sections of each facility
- Detailed Roof Plan, including drainage features (gutters and downspouts)
- Detailed Structural Plan, including foundation and building structural plans
- Detailed Mechanical Plan (Ventilation, Fans, Air Conditioning)
- Detailed Plumbing Plan
- Detailed Electrical Power Plan
- Detailed Lighting Plan
- Detailed Equipment Plan (if applicable)
The Pre-Final Design shall be submitted to the NAVFAC COR to ensure that the contractual design requirements have been met.
The NAVFAC Contracting Officer Representative’s (NAVFAC Project Manager) approval of the Pre-Final Design does not constitute authority to begin construction work.
Final Design: The Contractor shall prepare a Final, 100% design package. The Contractor shall submit the Final Design Package to the relevant Government of Tunisia Authorities for approval.
Once approved by the relevant Government of Tunisia, the Contractor shall provide to the NAVFAC COR a copy of the Final Design. The Final Design shall be submitted with a copy of the original approval documentation provided by the relevant Tunisian Government Authority.
Pre-Construction Submittals:
- Copy of the approved design by relevant Tunisian authority
- Final Design stamp and signed by Tunisian Licensed Engineer/Architect DOR
- Final Design
- Final Construction Schedule
- Schedule of Prices
- Site Safety and Health Officer (SSHO) Certification
- Construction Permit(s)
- Worksite Layout Plan
- Construction Sign Mock-up per section 5.9
All submittals shall be electronically submitted in pdf format to the NAVFAC COR. (Additional details on the pre-construction submittals relevant to the construction phase are noted in Section 1.2.2.)
The NAVFAC COR will accept the final design after receipt of the approval documentation from the local authority and issue a “Notice-to-Proceed” (NTP) to Construction with concurrence from the NAVFAC KO.
1.2.2 Construction Phase
The Contractor is responsible for acquiring all necessary approvals and permits from the competent Tunisian authorities, as required by Tunisian Law. The NAVFAC KO & COR shall issue a Notice-to- Proceed, authorizing the Contractor to begin construction works. The Notice-to-Proceed shall only be
Bizerte, Tunisia
WON: 1807573
issued once the Contractor provides a copy of the construction permit and other approval documentation required by the relevant Tunisian authorities.
All work required under this contract shall meet the laws, regulations, and codes of the Government of Tunisia. The US Government shall not be responsible for authorizing nor approving any construction works.
The Contractor shall coordinate all construction works with the local Tunisia MOD Beneficiary. The construction site is located on a Tunisian Military Installation. The Contractor shall comply with specific restrictions regarding construction on the Tunisian Military site.
Site Safety and Health Officer (SSHO) Certification:
By the timeline set for the final design completion, the Contractor shall provide the certification for the Site Safety and Health Officer (SSHO) appointed to stay full time on-site; the SSHO is required to have completed the OSHA 30-hour online training “EM385-1-1 Safety and Health (Sections 1-34),” which is offered for free at: https://www.oshacademy.com/programs/30-hour-constructionsafety-health.html ) and to have at least one year of proved experience as SSHO in construction projects. (Additional information on the safety requirements of the contract are noted in Section 5.8.)
Construction Permits as Required by Tunisian Regulation:
By the timeline set for the final design completion, the Contractor shall verify that nothing prevents the construction from starting, shall submit copy of the construction permit, and copy of any agreement entered with the beneficiary in order to coordinate the surrounding facility operability during the construction work.
Worksite Layout Plan:
By the timeline set for the final design completion, the Contractor shall submit a site plan showing how the worksite will be delimited (even in different phases of work, if the case) and organized to prevent unauthorized access, to allow safe operation of the facilities not included in the contract and to guarantee safe circulation and operation within the worksite. The plan shall indicate temporary drainage channels, vehicular and/or pedestrian access, paths, sidewalks, steps, parking areas, material storage areas, etc.
Interim Submittal Requirements:
During construction, the Contractor is required to submit:
- Bi-weekly work progress report with photos
- Bi-weekly or Monthly construction conference calls with the NAVFAC COR as determined based on the frequency of the work activities
- Test results as required per the contract
- At least 10 days prior to installation of all electrical components, plumbing fixtures, windows and doors and associated hardware, a sample (or catalog photo) must be shown to the COR for Government Review
- Updated construction schedules if changes occur
- Possible design changes
- Invoices in accordance to work progress
Completion Submittal Requirements:
Upon completion of project and prior to final payment, the Contractor is required to submit:
- Final As-Built drawings https://www.oshacademy.com/programs/30-hour-constructionsafety-health.html https://www.oshacademy.com/programs/30-hour-constructionsafety-health.html
Bizerte, Tunisia
WON: 1807573
- Act of Acceptance
- Commemorative Plaque per section 5.9
- Contract Close-Out documents per section 5.11 o Operations and Maintenance Manuals (O&M) o Warranties o List of Training o List of Spare Parts
1.2.3 Contract Milestones
The Contractor is responsible for acquiring all necessary approvals and permits from the competent Tunisian authorities, as required by Tunisian Law. The NAVFAC KO & COR shall issue a Notice-to- Proceed, authorizing the Contractor to begin construction works. The Notice-to-Proceed shall only be issued once the Contractor provides a copy of the construction permit and other approval documentation required by the relevant Tunisian authorities.
The Contractor must perform all work within 600 calendar days after contract award. The Contractor must provide a bar-chart style schedule minimally depicting the major contract milestones indicated in the table below. Project phases and/or other milestones deemed significant by the Contractor may also be depicted.
The schedule must indicate the proposed start and completion dates for all design phase site visits;
concept, pre-final, and final design work; permit application submittals; and construction start/end dates. Failure to comply with these milestones will be objective basis for invoice retention or further contractual action by the KO.
Contract Milestone Timeline (days are calendar days)
Award Day 0
PAK Meeting +5 days after award
PAK Meeting Mins, Draft Construction Schedule, Quality Control Plan, Accident Prevention Plan
+5 days after PAK
Concept (35%) Design +30 days after award
Government review comments of concept design +5 days after concept design submittal
Pre-final (90%) Design +30 days after concept comments
Government review comments of pre-final design +10 days after pre-final design submittal
Final (100%) design & Pre-construction Submittals +30 days after submittal of pre-final comments
Governmental approval of final design +5 days after final design submittal
NTP Pending approval of final design and pre-construction submittals. (Approximately +120 days after award.)
Construction sign installation (design and text must +10 days after NTP
Bizerte, Tunisia
WON: 1807573
Contract Milestone Timeline (days are calendar days) be approved by COR)
Construction completion +540 days after award
Commemorative plaque/sign installation (design, text and installation site must be approved by the COR and Tunisian Government)
+575 days after award
Final inspection notification The Contractor shall notify the KO with a minimum of 60 calendar days prior to the requested official final inspection
Final Act of Acceptance and Building Occupancy Date (BOD)
Pending punch list resolution
Contract completion +600 days after award
Warranty period +1 year from BOD
1.3 CONTRACTUAL BASE-BID AND BID OPTIONS
This Design-Build Contract is separated into a Base-Bid and three (3) Bid Options. The Contractor shall submit separate pricing for the Base-Bid and each Bid Option. The Scope of Work requirements for the base-bid are listed in Section 2 and Section 3 of this Performance Technical Specification. The Scope of Work requirements for each Bid Option are listed in Sections 2 and 4.
The award of Contract Bid Options depends on availability of funds, as well as other factors that the US Government will unilaterally consider. Below is a figure showing the locations of the various components described in the Scope of Work.
Bizerte, Tunisia
Concept Site Plan of proposed facilities included; Base Bid- Blue, Bid Options-Purple (See Attachment 02)
Bizerte, Tunisia
WON: 1807573
1.3.1 Base-Bid
The Base-Bid includes the minimum requirements to construct the Vehicle & Equipment Boat Storage Facility – BPC 333 Case “MCOE Phase I.” This will include the area surrounding the location of the Vehicle & Equipment Boat Storage to include; site prep, excavation, grading, compaction, utility stub-outs, and entry/exit roadways to the facility. Existing site is vacant with no existing infrastructure in place. Overall facility descriptions and sizes are as follows:
*Note: Square Meters referenced as “SM” or “m2 “, Square Yards as “SY,” Square Feet as “SF,” Feet as
“FT.”
1. Site Work:
o Site location is to the North corner of the MCOE site as shown in above diagram o Site work to include a cleared, grubbed, and excavated area for the facility as shown in above diagram to the extents of the planned development area o Site work to include level and compacted grade for facility foundation and slab o Site work to include area for facility utilities to be connected to base network and marked and labeled appropriately o Site work to include sloping terrain around facility to ensure proper stormwater drainage and rain water runoff o Site work to include an entry/exit road connection for vehicles to pull into the facility overhead door o Site work to include an entry/exit sidewalk connection for pedestrians to enter the facility at each man door o Existing condition is noted as dry terrain with brush, rocks, dust, not level but gradual slope exists to the waterfront o Low amount of rain and very remote location
2. Vehicle & Equipment Boat Storage Facility 375 SM o To accommodate storage of Maritime Boats (Rigid Hull Inflatable Boats (RHIBs), SAFE Boats, and other equipment for use at the Tunisian Navy Maritime Center of Excellence) o Floor slab to support weight of maritime vessels and trailers
Base Bid- Vehicle & Equipment Boat Storage Facility
Base Bid- Facility Site Work Boundary
Bizerte, Tunisia
WON: 1807573
o Facility to be approximately 25M x 15M and contain the following interior spaces:
One (1) office area (20 SM) One (1) Unisex bathroom with 1 USA standard toilet, 1 sink, 1 shower, and locker space One (1) manually driven overhead door (approximately 6M x 5M) opening north facing for vehicle entry/exit with bollards on each side One (1) open bay for equipment boat storage Two (2) pedestrian doors for entry/exit, one at each end of the facility o Facility to include interior systems as follows:
Air Conditioning (AC units) Passive cooling systems (windows, large overhead fans, exhaust fans, ventilation fans) Electrical power distribution for outlets and lighting Electrical power distribution and backbone infrastructure conduit for future connection of speakers and wall/ceiling mounted cameras (CCTV) Electrical telecommunications telephone conduit, wiring, and receptacles Electrical telecommunications fiber conduit, wiring, and receptacles Fire alarm systems Domestic hot and cold water Sanitary sewer Roof rain water collection, drainage, and disposal (consider rainwater harvesting for energy reduction and consumption needs) All utilities shall be extended to 3 meters beyond the exterior façade to be connected by the Tunisian Navy into the base network (electrical, telecommunications, fire alarm, domestic water, sanitary, and rain runoff/stormwater drainage)
Bizerte, Tunisia
Example Vehicle & Equipment Boat Storage Facility Floor Plan
(Overhead and Man Doors not included)
1.3.2 Bid Option 1
Contract Bid Option #1 includes: One (1) Close Quarter Battle (CQB) Trainer Shoot-House – BPC 333 Case “SOMTU Phase I” 216 SM:
o To accommodate Maritime Close Quarter Battle training simulations on maritime vessels and within shipping containers for use with simulated/blank munitions o Site work to include:
Cleared, grubbed, and excavated area for the facility Level and compacted grade for facility foundation and slab Area for facility utilities to be connected to base network and marked and labeled appropriately Grading terrain around facility to ensure proper stormwater drainage and rain water runoff o Concrete slab to support weight of shipping containers and extend slightly beyond the edge of each base container to allow for staging area for trainings o Use of 9-10 Shipping Containers to create a base facility of approximately 11M x 12M with the following requirements:
Three (3) levels of shipping containers, reducing in number of shipping containers and SM on each level
Bizerte, Tunisia
WON: 1807573
Two (2) exterior “Breaching Type” doors, all other exterior doors to be typical metal port doors with associated hardware
Two (2) interior “Breaching Type” doors, all other interior doors to be typical interior metal doors with associated hardware
Exterior shipping ladders and railings to provide access to each level and general fall protection safety during trainings
Plexiglass observation windows on top story Exhaust fans Electrical power distribution and lighting Electrical power distribution and backbone infrastructure conduit for future connection of speakers and wall/ceiling mounted cameras (CCTV) Electrical telecommunications telephone conduit, wiring, and receptacles Electrical telecommunications fiber conduit, wiring, and receptacles All utilities shall be extended to 3 meters beyond the exterior façade to be connected by the Tunisian Navy into the base network (electrical, telecommunications, and rain runoff/stormwater drainage)
Bizerte, Tunisia
Example Close Quarter Battle Trainer Shoot-House Elevations
(9-10 Shipping Containers used)
1.3.3 Bid Option 2
Contract Bid Option #2 includes: One (1) Beach Obstacle Course – BPC 333 Case “RCMS Phase I:”
o To accommodate Maritime Beach Obstacle training exercises and simulations o Site work to include:
Cleared, grubbed, and excavated area for the course Grading mild slopes and compacted for the course Grading terrain toward the waterfront to ensure proper stormwater drainage and rain water runoff o Course to follow the layout of obstacles as shown in diagram below:
Bizerte, Tunisia o Track material for course to be recycled plastic/rubber tire material to withstand weather and erosion and offer soft landing for obstacle users o Obstacles to be lumbar treated for exterior use o All metal connectors, bolts, screws, nails, nuts, dowels, and associated accessories to be galvanized steel for exterior use o Obstacles to use ropes and nets coated for exterior use o Provide two (2) Electrical power distribution points (exterior rated outlets/plugs/sockets) near start and finish of obstacle course for connection of electrical equipment or portable lighting for training Electrical utility will to be connected by the Tunisian Navy into the base network from this established point
Bizerte, Tunisia
WON: 1807573
1.3.4 Bid Option 3
Contract Bid Option #3 includes: One (1) 25M & One (1) 50M Shooting Range – BPC 333 Case “RCM MCOE Phase II:”
o To accommodate Maritime Shooting training exercises and simulations at both the 25M and 50M ranges with live munitions 5.56mm and below o Site work to include:
Cleared, grubbed, and excavated area for the facilities Level and compacted grade for shooting platform’s foundations and slabs Area for facility utilities to be connected to base network and marked and labeled appropriately Grading terrain around facility to ensure proper stormwater drainage and rain water runoff o Each shoot range to include a concrete covered shooting platform with appropriate foundation and slab designed to the appropriate structural loads o Each shoot range to include dividing walls of earth and stone materials o Each shoot range to include a bullet trap o Each shoot range to include 12 lanes with associated targets o Range to follow the layout as shown in diagram below and be situated in the proposed location:
Bizerte, Tunisia
WON: 1807573
o Each covered shooting platform to have electrical power and lighting for safe training environments and equipment hook-ups All utilities shall be extended to 3 meters beyond the exterior façade to be connected by the Tunisian Navy into the base network (electrical and rain runoff/stormwater drainage as required)
2. GENERAL SCOPE OF WORK
This project includes the design and construction of military facilities and areas at the Maritime Center of Excellence (MCOE), Bizerte Tunisia. Scope of work includes the previously mentioned facilities, supporting infrastructure, and site work. The purpose of the facilities are to provide the Tunisia MOD a strategic training area that can accommodate partner nations for exercises in Tunisian Marine Special Operation Forces (SOF) and the Navy Commando courses. The facilities will provide modern training platforms that accommodate more advance user groups from allied nations to train in country.
Type of work includes but is not limited to; Vehicle & Equipment Boat Storage Facility, Close Quarter Battle Trainer Shoot-House Facility, Beach Obstacle Course, and both a 25M & 50M Shooting Range. As such, the facilities shall be constructed to provide adequate space, functionality, and support equipment to accomplish necessary operations and military personnel. Personnel will use the facilities for live action trainings in association with the courses and planned exercises.
2.1. GENERAL DEMOLITION SCOPE OF WORK
Demolition shall include removal of all debris and waste from the site. Removal of existing safety hazards (i.e. debris concrete, rebar, dilapidated parts or pieces of structures, pieces of structures fallen or dislodged by weather).
2.2. GENERAL SITE/CIVIL SCOPE OF WORK
The Site/Civil work for this project includes the clearing and grubbing of the areas where the new facilities will be located, and adjacent areas as described in this document. All required site/civil work must be completed in order to have fully operational facilities. All grading shall be done to facilitate stormwater flow away from each facility and promote proper drainage throughout the site. Civil work also includes extending the necessary utilities (electrical power, drainage, water, sewer, etc.) to make each facility complete and usable. Work will include roadway and pedestrian walk way extensions to facility movement to the exterior of the facilities. Civil work, including grading, will be required for the improvements defined in Section 1.3.
2.3. GENERAL STRUCTURAL SCOPE OF WORK
The Structural work for this project includes providing building structural systems that meet all Tunisian code requirements, consider seismic criteria and local soil conditions, all dead and live loads including rain and wind loads, and are designed to meet specific requirements related to the floor slab, equipment/boat weights at concrete pads and floor slabs, and vehicle weights at roads.
Bizerte, Tunisia
WON: 1807573
2.4. GENERAL ARCHITECTURAL SCOPE OF WORK
The Architectural work for this project includes providing functional facilities that meet administrative requirements and the unique requirements of the Maritime Center of Excellence. Architectural considerations should include adequate space planning, providing doors and windows to allow for efficient movement through the facilities and to maximize daylighting, providing efficient interior wall configurations, and appropriate roofing designs at all facilities as required.
The Interiors work for this project includes Structural Interior Design. Provide finishes as specified for walls, ceilings, and floors. Provide interior finishes for the Vehicle & Equipment Boat Storage Facility inclusive of floor finishes, wall paint, ceiling finishes, and wall and window coverings. Provide sealed concrete for all exterior concrete platforms.
2.5. GENERAL MECHANICAL SCOPE OF WORK
The Mechanical work for this project includes providing a cooling and ventilation system to provide adequate cooling during the summer season for the Vehicle & Equipment Boat Storage Facility. Provide a passive ventilation system with the use of exhaust fans at the Close Quarter Battle Trainer Shoot- House.
2.6. GENERAL PLUMBING SCOPE OF WORK
The Plumbing work for this project includes providing domestic hot and cold water and a sanitary sewer system at the Vehicle & Equipment Boat Storage Facility. All facilities to have proper rain runoff/stormwater drainage systems as required to remove water from the facility and disperse of it into the base network. Water systems shall consider use of Rainwater Harvesting and/or a Grey Water system to reuses water, clean, and place it back into the system to reduce water consumption on site.
All fixtures to be low flow, energy saving, water saving fixtures. Storm drainage is required at all facilities.
2.7. GENERAL ELECTRICAL SCOPE OF WORK
The Electric work for this project includes providing service and distribution equipment, wiring, receptacles and grounding, interior and exterior lighting and controls, emergency lighting, telecommunications telephone and fiber, and security speaker and camera distribution at the Vehicle & Equipment Boat Storage Facility and Close Quarter Battle Trainer Shoot-House. Fire alarm systems to be provided at the Vehicle & Equipment Boat Storage Facility.
Provide electrical service and distribution equipment, wiring, receptacles, and grounding at the Beach Obstacle Course.
Provide electrical service and distribution equipment, wiring, receptacles and grounding, interior and exterior lighting and controls, and emergency lighting at the 25M & 50M Shooting Range platforms.
Consideration shall be given to provide energy saving equipment and appliances, low consumption electrical equipment, and potential for alternative energy sources to reduce electrical demand, i.e. Solar Power, and Solar Hot Water Heating.
Bizerte, Tunisia
WON: 1807573
3. DETAILED SCOPE OF WORK
3.1. DETAILED SITE/CIVIL SCOPE OF WORK
The Site/Civil work for this project includes all activities required to prepare the site for work associated with the project, but is not limited to, the following activities in order to ensure that the new facilities are complete and functional.
Prior to starting work, physically verify the location of all existing utilities and obtain additional survey data required to provide a quality final design. Include the topographic survey and geotechnical survey as needed in all design submittals. Verify the location of all utilities prior to construction.
Minimize the impact of construction activity on operations and neighboring facilities. Identify and obtain permits to comply with host nation regulatory requirements associated with the work. Determine correct permit fees and pay said fees. Perform work in accordance with the obtained permits.
Coordinate and obtain the NAVFAC COR's approval for proposed haul route(s), work site access point(s), employee parking location(s) and material laydown and storage area(s). Refer to Site Analysis for additional site preparation functional program information.
3.1.1. Topographic Survey
Contractor will need to conduct a topographic survey of the site. Contractor is responsible for conducting a survey as necessary to assist with the design and construction of the project and ensure proper stormwater drainage and site grading and leveling are provided prior to the start of work.
3.1.2. Geotechnical Report
The Contractor shall conduct subsurface soils exploration, investigation, testing and analysis for the design and construction of the site improvements.
The Contractor-provided Geotechnical Engineer is required to be experienced with soil conditions in the region where the project site is located. The Geotechnical Engineer is required to evaluate the RFP data, obtain and evaluate additional data to support the design and construction, and prepare a Geotechnical Report.
Work done by the Geotechnical Engineer shall be coordinated with the NAVFAC COR so as not to interfere with normal base operations. A minimum of two weeks prior to the Foundation Work Design submittal, provide the Contractor’s Geotechnical Report (searchable Adobe Acrobat PDF version). The report will become the property of the Government. Provide the geotechnical reports generated during construction, such as pile driving results and analysis, to the NAVFAC COR (searchable PDF version).
The Geotechnical Report shall include, but not be limited to, the following:
- Project site description, vicinity map and site map indicating the location of borings and any other sampling locations. Provide notes on any groundwater observations. If groundwater is anticipated or observed, conduct 24-hour groundwater observations for at least 20 percent of the borings.
Bizerte, Tunisia
WON: 1807573
- Results of field and laboratory testing. Address existing subsurface conditions, selection and design of the foundation and floor slab, underground construction including utility installation and other site specific requirements (such as soil stabilization and slope stability).
- Engineering analysis, discussion and recommendations addressing:
o Settlement analysis o Bearing capacity analysis o Foundation selection (shallow, deep, special) and construction considerations;
dimensions and installation procedures o Site preparation (earthwork procedures and equipment, compaction requirements, building slab preparation, soil sensitivity to weather and equipment, groundwater influence on construction, mitigation of expansive soils or liquefaction potential, and dewatering requirements).
o Sheeting and shoring considerations.
o Pavement design calculations with parameters defined, actual or assumed, and recommended thicknesses and materials.
o Infiltration rate.
o Haul routes and stockpile locations for earthwork.
o Calculations to support conclusions and recommendations.
o Present recommendations on a structure-by-structure basis.
A registered Geotechnical Engineer is required to sign the Geotechnical Report. Accompany the submitted report with a cover letter identifying any report recommendations proposed to be adopted into the design which are interpreted by the Contractor as a changed condition to Geotechnical or Pavement related requirements of the RFP.
The Contractor's final design drawings must include any relevant information presented in the RFP, as well as additional borings and laboratory test result data performed by the Contractor. The data provided is required to include:
- Logs of Borings and related summary of laboratory test results and groundwater observations. Provide 24-hour groundwater observations for at least 20 percent of the borings, minimum one boring. Provide notes explaining any abbreviations or symbols used and describing any special site preparation requirements.
- Indicate the locations of borings on the drawings. Revise the design drawings to reference the Contractor’s Geotechnical Report as being a basis for design.
Bizerte, Tunisia
WON: 1807573
3.1.3. Clearing and Grubbing
The Contractor shall clear and grub the site for project construction. Vegetation on the project site to be removed as part of clearing and grubbing will become the property of the Contractor and must be disposed off-site.
Clear trees, shrubs, brush, and vegetation for construction of the project. Clearing includes the felling, trimming, and cutting of trees into sections and the satisfactory disposal of the trees and other vegetation designated for removal, including downed timber, snags, brush, and rubbish occurring within the areas to be cleared.
Preserve and protect trees, shrubs and vegetation not directly impacted by the construction.
Remove and dispose of trees to a depth of at least 18 inches (450 mm) below ground surface. Fill depressions with satisfactory material and compact. Mound fill 2 inches (50 mm) above adjacent surface to allow for settling when not part of a subbase.
Remove stumps to a depth of at least 18 inches (450 mm) below ground surface. Fill depressions with satisfactory material and compact. Mound fill 2 inches (50 mm) above adjacent surface to allow for settling when not part of a subbase.
Within the clearing limits, remove and dispose of logs, shrubs, brush, matted roots, roots larger than 2 inches (50 mm) in diameter, and other debris to a depth of at least 18 inches (450 mm) below ground surface. Fill depressions made by grubbing with satisfactory material and compact to make the new surface conform to the adjacent surface of the ground.
Remove any existing concrete and asphaltic concrete paving and slabs as required for construction of the project. Remove the existing aggregate base in areas to receive new pavement to the depth of the proposed pavement section below new finish grade. Remove the existing aggregate base in areas not to receive new pavement to a depth of 8 inches (200 mm) below existing adjacent grade and break remaining pavement (if any) to allow drainage. Provide neat saw cuts at limits of pavement removal;
protect saw cuts so that new pavement butts against the existing without feathering.
Bizerte, Tunisia
Existing Site Condition, approximate slope to waterfront
Bizerte, Tunisia
WON: 1807573
3.1.4. Grading, Excavation, and Compaction
Perform site grading in accordance with standard practices.
Prior to excavation, Contractor must contact the host nation. Contractor will be responsible for obtaining dig permits.
Finished grade shall slope away from buildings at 1:10 for a distance of six feet (3 m) from building.
Finish floor elevations for new facilities shall be 12-inch (30 cm) minimum above the highest adjacent finished grade.
Establish finish floor elevations so that the floor is a minimum of four inches (10cm) above highest grade adjacent to the building. Provide a slope away from the building of 1:10 for a distance of five feet (150cm) from all sides of the building.
The Contractor shall preserve natural topographic features to minimize the impact on the existing drainage patterns at and adjacent to the site.
Finish grading shall provide drainage towards new and existing drainage features. Finish grading shall not result in low spots that hold water or that direct runoff towards new or existing facilities and/or site amenities.
The Contractor shall preserve natural topographic features to minimize cut and fill requirements. Re-use suitable excavation material as fill material as needed. All unsuitable material and surplus excavation shall become the property of the Contractor and shall be disposed of as specified above.
Requests for additional compensation shall not be made by the Contractor for degree of hardness or difficulty encountered in removal of material. All unsuitable material and surplus excavation shall become the property of the Contractor and shall be disposed of as specified above.
If necessary, provide borrow and select fill from acceptable sources in accordance with the Geotechnical Report.
Where sufficient topsoil and satisfactory materials are not available on the project site, provide suitable borrow materials.
Remove unsatisfactory soil materials from the site as specified above and replace with satisfactory soil materials.
Soils that are determined as clean fill via testing shall be backfilled and compacted in accordance with these requirements.
Blasting is not permitted.
Compact in accordance with ASTM D698 (or Tunisian equivalent) except for roads, airfields, lay-down areas, and other heavily loaded areas, which should use ASTM D1557 (or Tunisian equivalent) compaction; or the recommendations of the Contractor’s Geotechnical Engineer, whichever is greater.
Stabilize slopes through appropriate grading and site design for a minimum factor of safety of 1:5 or slope that does not exceed the maximum slope per local code requirements.
Ensure that all designated ground surfaces have the proper compaction necessary for structural foundations, concrete pads, parking areas, etc. and other improvements as necessary.
Bizerte, Tunisia
WON: 1807573
Perform the work necessary to bring the subgrade material into final shape and compacted condition.
All waste materials shall become the property of the Contractor and shall be transported, disposed of and/or recycled off site. Burning will not be allowed.
During hauling, prevent spillage on roads, or adjacent areas.
Provide the minimum erosion control necessary to prevent sediment transfer to the proposed landing zone.
3.1.5. Site Drainage & Stormwater Runoff
Grading design must convey stormwater runoff away from each facility and is transported around the facility in a safe manner based on standard practice, preventing standing water. Design must account for offsite drainage if applicable. Identify if any existing drainage problems exist, such as flooding, ponding or erosion, and propose grading and drainage solutions to alleviate this. All calculations are to be provided with the Basis of Design. Provide grading and drainage plan. Tie in use of a Rainwater Harvesting and/or Grey Water system if applicable.
3.1.6. Utilities
Extend utilities as necessary per the table below to ensure facilities are complete and functional.
Facility Power Telecom Water Sewer
Vehicle & Equipment Boat Storage
Stub out the electrical utilities to 3 meters beyond exterior building façade to be connected by Tunisian Navy to base network
Stub out the telecommunications for telephone and fiber to 3 meters beyond exterior building façade to be connected by Tunisian Navy to base network
Stub out the water utilities to 3 meters beyond exterior building façade to be connected by Tunisian Navy to base network
Stub out the sanitary sewer utilities to 3 meters beyond exterior building façade to be connected by Tunisian Navy to base network
Close Quarter Battle (CQB) Trainer Shoot-House
Stub out the electrical utilities to 3 meters beyond exterior building façade to be connected by Tunisian Navy to base network
Stub out the telecommunications for telephone and fiber to 3 meters…
This is the start of the file's text. The full file is on GovTribe.