This solicitation is for the construction of a Military Working Dog facility at Plovdiv, Bulgaria. The Naval Facilities Engineering Command is seeking offers for a firm fixed-price construction contract to design and build kennels, a training area, and support facilities. Offerors must submit proposals no later than February 15, 2023. The period of performance is 365 calendar days from notice to proceed. The awardee will be responsible for all necessary design, engineering, permitting, construction, utilities, and commissioning to deliver a fully operational facility. Site work will include fencing, lighting, and hardscaping. The facility must meet Unified Facilities Criteria standards and Bulgarian building codes.

View the file

Other files for this federal contract opportunity

Other files attached to D-B Construct Military Working Dog Facility, Plovdiv, Bulgaria, newest first.
File Type Posted
N3319123R4018_A0001_SF30.pdf PDF
N3319123R4018_MWD_Bulgaria_Amend_0002.pdf PDF
N3319123R4018 MWD Bulgaria Attach 2 - PPI.docx DOCX document
N3319123R4018 MWD Bulgaria Attach 4 - 252.229-7001.docx DOCX document
N3319123R4018 MWD Bulgaria Attach 7 - Safety Checklist.docx DOCX document
N3319123R4018 MWD Bulgaria Attach 3 - Price Schedule.doc DOC document
N3319123R4018 MWD Bulgaria Attach 6 - PPQ.docx DOCX document
N3319123R4018 MWD Bulgaria RFP.pdf PDF
N3319123R4018 MWD Bulgaria Attach 5 - Data Sheet.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

[BU-P-GAE]

Request for Proposal (RFP) Design-Build

Construct Military Working Dog Facility

In:

Plovdiv, Bulgaria

Final

August 2023

PREPARED BY:

NAVFAC EURAFCENT

Expeditionary Capabilities Team (XCT) Viale Porto 51

Aeroporto Capodichino 80144, Napoli, IT

Project Manager: Alexander Dodge, RA

APPROVED BY: Fredelix “Alex” Menez, PE

For Commander, NAVFAC

NAVFAC EURAFCENT:

Date: 20 August 2023

New Construction of Military Working Dog Facility Plovdiv (Bulgaria)

Page 2 of 113 Version: 001

Contents

1 TAXATION

2 GENERAL DESCRIPTION OF THE PROJECT

2.1 GENERAL DESCRIPTION OF WORK

2.2 LOCATION OF PROJECT

2.3 LEGAL AND TECHNICAL REQUIREMENTS

2.4 GENERAL CONTRACT DESCRIPTION

2.5 GENERAL PROJECT DESCRIPTION AND SCOPE OF WORK

2.6 CONSTRUCTION PERMIT AND AUTHORIZATION

2.6 MEASUREMENTS AND QUANTITIES

2.7 DESIGN PHASE - GENERAL

2.8 CONSTRUCTION PHASE - GENERAL

3 GENERAL SCOPE OF WORK OF MILITARY WORKING DOG FACILITY IN PLOVDIV (BASE‐BID)

3.1 GENERAL FACILITY LAYOUT

3.2 ELEMENTS INTERFERING WITH THE NEW CONSTRUCTION

3.3 GENERAL DESIGN / CONSTRUCTION REQUIREMENTS FOR STRUCTURES

3.4 REQUIREMENTS FOR SUPPORT BUILDING

3.4.1 WATER SERVICE CONNECTION

3.4.2 WATER DISTRIBUTION AT SUPPORT BUILDING

3.4.3 ELECTRICAL SERVICE CONNECTION

3.4.4 ELECTRICAL DISTRIBUTION AT SUPPORT BUILDING

3.4.5 BACKUP POWER

3.4.6 INTERIOR LIGHTING

3.4.7 HEATING / AIR CONDITIONING

3.4.8 TELEPHONE / INTERNET

3.4.9 FIRE ALARM

3.4.10 TELEVISION SIGNAL

3.4.11 SEWER SYSTEM

3.4.12 CEILINGS

3.4.13 INTERIOR WALL SURFACES

3.4.14 INTERIOR FLOOR SURFACES

3.4.15 THERMAL FACADE

3.4.16 ROOFING

3.4.17 EXTERIOR DOORS

3.4.18 EXTERIOR WINDOWS

3.4.19 INTERIOR DOORS AND DOOR SIGNS

3.4.20 COVERED ENTRYWAY AND WALKWAY

3.4.21 INTERNAL CORRIDOR

3.4.22 SPECIFIC REQUIREMENTS FOR SUPPORT BUILDING ROOMS

3.4.22.1 KENNEL MASTER OFFICE

3.4.22.2 DOG HANDLER WORK STATION AREA

Page 3 of 113 Version: 001

3.4.22.3 MULTI‐PURPOSE ROOM

3.4.22.4 TACK ROOM (STORAGE)

3.4.22.5 FOOD STORAGE

3.4.22.6 BATHROOM, SHOWER, AND LOCKER AREA

3.4.23 COMMEMORATIVE PLAQUE

3.5 REQUIREMENTS FOR KENNEL AREA

3.5.1 DESCRIPTION

3.5.2 GENERAL REQUIREMENTS

3.5.3 KENNEL RUNS

3.5.4 DOG HOUSES

3.5.5 FOOD PREP AREA

3.5.6 DRAINAGE

3.5.7 FLOORING

3.5.8 VENTILATION

3.5.9 HEATING

3.5.10 WATER DISTRIBUTION AT KENNEL AREA

3.6 REQUIREMENTS FOR OBEDIENCE COURSE

3.6.1 DESCRIPTION

3.6.2 REQUIREMENTS

3.6.3 OBSTACLE LOCATION AND SEQUENCE

3.6.4 OBSTACLE – BARRELS

3.6.5 OBSTACLE – CONCRETE TUNNEL

3.6.6 OBSTACLE – CONCRETE STAIRS

3.6.7 OBSTACLE – CONCRETE HURDLES

3.6.8 OBSTACLE – CONCRETE WINDOW

3.6.9 OBSTACLE – “A” FRAME

3.6.10 OBSTACLE – CONCRETE DOG WALK

3.7 SPECIFIC REQUIREMENTS FOR DOG EXERCISE AREA

3.7.1 DESCRIPTION

3.7.2 REQUIREMENTS

3.8 REQUIREMENTS FOR DOG BREAK AREA

3.8.1 DESCRIPTION

3.8.2 REQUIREMENTS

3.9 REQUIREMENTS FOR EXTERIOR ELEMENTS

3.9.1 SIGNAGE

3.9.2 EXTERIOR LIGHTING

3.9.3 ACCESS, CONNECTING, AND PERIMETER SIDEWALKS

3.10 REQUIREMENTS FOR CCTV SECURITY SYSTEM AND INSTALLATION

3.10.1 DESCRIPTION OF WORK

3.10.2 REQUIREMENTS

3.10.3 INSTALLATION

3.10.4 PROGRAMMING

3.10.5 TRAINING AND TESTING

4 OMISSIONS FROM THE PROJECT SPECIFICATIONS

4.1 ADDITIONAL REQUIREMENTS

5 PROCEDURE AND GENERAL CONTRACT REQUIREMENTS AND GUIDELINES

5.1 PRINCIPLES

5.2 PROHIBITED ITEMS

5.3 START OF CONSTRUCTION

5.4 RESPONSIBILITY FOR NEW MATERIALS

5.5 DESIGN

5.6 DESIGN‐BUILD PROCEDURE

5.7 CONSTRUCTION/DESIGN SCHEDULE AND CONTRACTUAL MILESTONES

5.8 CONSTRUCTION SCHEDULE (BAR CHART IS AUTHORIZED)

5.9 SAFETY: ACCIDENT PREVENTION PLAN

Page 4 of 113 Version: 001

5.10 COORDINATION AND PHASING

5.11 SPECIAL SITE CONDITIONS

5.12 LANGUAGE

5.13 SUBMITTALS – TECHNICAL INFORMATION

5.14 DELIVERABLE

5.15 PICTURES

5.16 RESPONSIBILITY AND OWNERSHIP OF REMOVED MATERIALS

5.17 CERTIFICATIONS, LICENSES, PERMITS, FEES, ETC

5.18 QUALITY CONTROL PLAN

5.19 CONSTRUCTION SIGN

5.20 PAYMENT THE USE OF WAWF IS REQUIRED

5.21 SCHEDULE OF PRICES

5.22 PERFORMANCE GUARANTEE

5.23 UTILITIES

5.24 DAMAGES/IMPACT TO EXISTING FACILITIES

5.25 CLEANING

5.26 SPARE PARTS

5.27 WARRANTY AND TRAINING

5.28 CLOSE‐OUT PROCEDURE

-/-/-/-/-/-/-/- END OF TECHNICAL SPECIFICATION -/-/-/-/-/-/-/-/-

Page 5 of 113 Version: 001

1 TAXATION

In accordance with Agreement between the Government of USA and the Government of Bulgaria on Defense Cooperation, the Value Added Tax (VAT) for the project will be paid for by the beneficiary. The contractor shall be responsible for coordinating the purchase of all materials and all transactions that incur a VAT with the beneficiary in order for them to pay the VAT. For this reason, the contractor shall work directly with the corresponding authorities from the beneficiary, the Bulgarian Ministry of Defense (MOD), US Forces and the US Embassy.

Page 6 of 113 Version: 001

2 GENERAL DESCRIPTION OF THE PROJECT

2.1 General Description of Work

This Performance Technical Specification (PTS) consists of a Base‐Bid and one Contract‐Option. The work described is new construction for a Military Working Dog (MWD) facility in Plovdiv, Bulgaria. The facility consists of kennels, a handler/trainer support building, and dog training areas. The contract option includes roadway and parking surface improvements.

2.2 Location of project

This project is in Plovdiv on a site that currently contains military barracks. The facility is to be constructed in downtown Plovdiv, south‐southwest of the intersection of Sankt Petersburg and Mendeleev Boulevards, as shown in the following images.

See the following illustrations / images for the approximate location.

Location of Plovdiv with respect to Sofia, Bulgaria

Page 7 of 113 Version: 001

Location of project – view 2 of 3

Location of project – view 1 of 3

Page 8 of 113 Version: 001

Location of project – view 3 of 3

Page 9 of 113 Version: 001

2.3 Legal and Technical Requirements

The project execution is based on the following general requirements:

- Strict compliance with American contracting regulations, including the contracting requirements of the Department of Defense, the US Navy and the US Naval Facilities Engineering Systems Command

(NAVFAC).

- Strict compliance with Bulgarian technical, legal and administrative requirements, which are applicable for the scope of work described in this PTS.

- Compliance with Bulgarian safety regulations, unless the US safety regulations described in United States Army Corps of Engineers (USACE) EM385‐1‐1 are more stringent and not in conflict with the Bulgarian regulations, in which case, the US safety regulations shall apply. The contractor shall inform the Contracting Officer Representative (COR) of any conflict between Bulgarian and US safety regulations.

- Compliance with technical and administrative requirements described in this document.

- The contractor shall hire the services of licensed architects/engineers in Bulgaria to prepare the necessary designs and technical specifications which are required for the scope of work included in this document.

- Provide the final work as a complete and usable facility, including all items required by Bulgarian regulations regardless of whether they are described in this document. Technical details, items of work, permits or fees that are not explicitly described in this document, but which are necessary to provide fully operational and finished facilities shall be considered part of the contract.

The work shall meet all requirements of this PTS. Drawings required by this PTS and with the necessary details and previous approvals (experts or monitoring entities) to submit the designs to the US Government, Local Bulgarian Administration, final users, contractor’s staff and sub‐contractors. Material selection, specifications and installation are to be as described in these specifications.

2.4 General Contract Description

The method of completion for this project is Design‐Build. The contractor is responsible for both the design and construction of the facility. The US Government has provided a full set of plans that are included in this

PTS. The Design‐Build project includes two phases: Design and Construction. The selected contractor is required to adhere to the design provided and to update the plans to the current Bulgarian codes and correct any errors or omissions.

Note: The contractor’s architect/engineer and design team shall coordinate each phase of design with the beneficiary. However, the beneficiary, as well as the contractor, are bound by the requirements of the contract and the requirements of Bulgarian regulations and legislation. If the beneficiary requests any item of work in addition to the requirements of the contract or beyond the minimum requirements of Bulgarian regulations and legislation, the contractor shall not incorporate those requests into the design, but the contractor shall immediately notify the COR.

Version: 001

Note: The contract includes third‐party review of all items of work which are required by Bulgarian regulations. In case Bulgarian regulations do not allow for the contractor to be the client for this independent review, the contractor shall pay for the third‐party review and assign a different party as the client for this independent company, which could be the Contracting Officer Representative or other agency authorized by the Contracting Officer (i.e. a representative from Bulgarian MoD).

Note: The contractor needs to be familiar with the regulations of Bulgaria to account for the different required permits, reviews, and authorizations for renovation and new construction works.

2.4.1 Design Phase:

The Contractor shall provide a complete design prepared in compliance with applicable architectural, engineering, planning and construction codes of Bulgaria. The Contractor shall utilize services of architects and engineers licensed to practice in Bulgaria.

For those items of work which do not require a formal construction permit or design, the licensed architect/engineer shall prepare and submit for acceptance the necessary drawings and/or sketches to formalize and explain to the beneficiary and to the Contracting Officer Representative the works that they are proposing to perform.

This is a DESIGN‐BUILD contract in which the US Government already has the preliminary technical documents This PTS includes a description of the required finished work. This means that the contractor is responsible to do the following:

‐ Make necessary designs as required by this PTS for the different items of work.

‐ Obtain NAVFAC’s acceptance of the designs and the approval of the beneficiary and all pertinent and competent Bulgarian authorities, including the Ministry of Defense and the Military Working Dog Group.

‐ Obtain required formal technical approvals from competent and required Bulgarian authorities, including the necessary expert review by third‐party company and/or “technical expertise” as required by Bulgarian regulations (monitoring company) for the scope of work included in this contract.

‐ Execute the construction/renovation works

‐ Obtain the acceptance of NAVFAC and the partial and final approvals by the competent and required Bulgarian authorities and third‐party experts (monitoring company) for the executed construction works.

The contract includes all necessary items of work in order for the construction to be certified in compliance with latest Bulgarian standards and regulations.

The design shall be prepared in compliance with applicable construction codes, urban planning and construction practices in Bulgaria.

As required by Bulgarian regulations, for those elements that are required by Bulgarian regulations, the contractor shall hire (and pay for) the services of a “Third party quality control supervisor” authorized by the Government of Bulgaria to supervise and approve each phase of the design and the construction, including final commissioning and acceptance of the completed works. This company would report directly to the US Government representative and the beneficiary if required by the Bulgarian regulations, but all their services shall be paid by the contractor. In case the Bulgarian regulations does not allow for the contractor to be the client for this independent review, the contractor shall pay for the third‐party review and assign a different party as the client for this independent company, which could be the Ministry of Defense, a representative from the Military Working Dog Group, or other agency authorized by the Contracting Officer.

The contractor’s final designs and sketches shall be signed, stamped and certified by a licensed architect/engineer in Bulgaria. The level of detail of the design (extent of specifications, number and size of drawings, calculations, etc.) shall be sufficient to verify the compliance with the requirements of this contract and as required by the regulations of Bulgaria and the different agencies involved in the process.

Note: The contractor needs to be familiar with the regulations of Bulgaria, in order to account for the different required permits, reviews and authorizations for renovations of education facilities.

A design‐build contract means that the contractor is responsible not only to perform the works described in this document, but to prepare all necessary designs and technical projects. However, this document includes designs in Annex B.

Hire a Bulgarian licensed/certified architect/engineer to certify and take ownership of the available design, including assuming responsibility for any omission, mistake or error in these drawings. In this case, the contractor’s licensed architect/engineer shall complete the design as necessary and required by Bulgarian regulations.

The US Government is not responsible for any mistakes, omissions or errors in the available technical projects. This is a design‐build contract in which the US Government provides description of the required completed/renovated facility, and the contractor is responsible to make any necessary designs required for such item of work. This document is a PTS for a Design‐Build project.

Contract execution requires performing the works as described in this PTS and the technical projects included in Annex B. The Annex is included to describe the scope of work of this contract. However, this document includes technical requirements in addition to those included in the attached technical projects.

This contract includes the work described in the attached technical projects plus additional works and requirements described herein.

The contractor shall hire the services of an architect/engineer licensed in Bulgaria to prepare the new

The contractor is responsible to review, modify, amend and extend, if necessary, the available technical project, in order to verify that it complies with the latest Bulgarian regulations. If the available technical project complies 100% with all applicable Bulgarian regulations, the contractor can utilize the technical projects included in Annex B, with the notes and exceptions and additional requirements described in this PTS document. The contractor shall be responsible, and it shall be part of their contract, to perform all works included in their designs. All designs shall include the items of work included in this document, as well as those items of work not included in this document, but required by Bulgarian regulations in order to have operational and functional facilities.

Once the final design is prepared, it shall be accepted by the COR before the contractor sends it to the local authorities to obtain the corresponding Construction Permit. The accepted final design will be incorporated into the contract.

2.5 General Project Description and Scope of Work

The project is divided into a Base‐Bid and one contract Option. The Base‐Bid is the minimum part of the project that will be awarded to a construction firm. Contract options may or may not be awarded depending upon availability of funds and other factors that the US Government will unilaterally consider. The contractor shall provide a separate price for the Base‐Bid and for the contract options as required by the solicitation documents. In general terms, the works include the design and construction for the following items of work:

In general terms, the scope includes the following items of work:

- CLIN 0001 ‐ Base‐Bid:

Fully finished and operational Military Working Dog (MWD) facility of solid reinforced concrete construction, thermally insulated and metal sheet roofing to include an administrative support building and a kennel building, separated by a covered walkway.

- CLIN 0002 ‐ Option 0001:

Three fenced outdoor areas, along with obstacles for a MWD obedience course

Tables, desks, chairs, computer, phones, refrigerator, beds, televisions, and other movable equipment are not part of the contract, unless otherwise indicated in these technical specifications. Only those elements that are fixed, permanently attached to the building or considered as an integral part of the facility, and specifically described in the contract specifications or in the applicable Bulgarian regulations, are included, unless otherwise indicated in this document.

2.6 Construction Permit and Authorization

The contractor shall obtain formal written authorization from the competent Bulgarian authority to perform the works included in the scope of work of this project.

Note: The works will be executed in a Bulgarian military installation, and therefore under the jurisdiction of the military authorities. Nevertheless, to guarantee compliance with Bulgarian regulations, all technical and administrative requirements for projects outside of military installations shall be applicable to these works, with the potential exception of different procedures for obtaining the necessary construction permits.

For those items of work requiring a formal construction permit, it is absolutely necessary that the contractor is familiar with the Bulgarian regulatory procedures to obtain them.

The contractor shall hire the services of an architectural firm or engineer licensed in Bulgaria, to perform all the designs, shop drawings and to facilitate the procedures to obtain the construction permits that are required by the scope of work of this document.

The contractor is required, as part of the contract, to prepare all documentation, designs, reports, information, drawings, coordination and approvals by experts or monitoring entities, and everything that may be necessary as required by Bulgarian regulations, to obtain the necessary construction permit. The contractor is responsible to pay for any third‐party inspection or expertise that may be required by Bulgarian regulations for the scope of work of this project. The contractor shall be familiar with the requirements in order to prepare their bids, regarding the obligatory administrative and technical procedures in Bulgaria for new construction.

As previously stated, the contract includes third‐party review of all items of work required as per Bulgarian regulations. In case Bulgarian regulations do not allow for the contractor to be the client for this independent expert company, the contractor shall pay for the third‐party review and assign a different party as the client for this independent company, which could be the Contracting Officer Representative or other agency authorized by the Contracting Officer Representative.

No work shall be performed until the contractor shows verifiable evidence that they have obtained all the necessary permits or authorizations for each element of work included in this PTS. This shall be certified by the third‐party independent monitoring entity.

2.6 Measurements and Quantities

This PTS complies with US contracting regulations, and as such, measurements and quantities of materials and work are not provided, and if any are provided, the contractor shall be responsible to verify on site. The contractor needs to visit the job site in order to perform the necessary measurements and to observe the existing field conditions in order to prepare their cost proposal.

The contractor should be familiar with the geotechnical conditions in Plovdiv and with the seismic technical requirements in order to account for the necessary foundations and building structures required in compliance with Bulgarian regulations. For estimating purposes, the contractor shall estimate that the existing soils are the worst (least favorable) available in Plovdiv for the foundation and structure design.

The US Government is not responsible for any mistake in the contractor’s measurements or assumptions of field conditions.

2.7 Design Phase - General

ANNEX B contains a complete design package; it is the intent of this PTS that the final design delivered shall match the supplied design exactly. The only changes or modifications for the contractor’s designer of record is to correct errors and omissions in the attached design, update the design to meet current Bulgarian Building Codes, and to make any changes in the building systems to conform to current industry standards and improve efficiency. For components illustrated in the design but not specified in the design, the specifications in this PTS shall govern.

The designs shall be prepared in compliance with applicable construction codes, applicable urban planning and construction practices in Bulgarian military installations. The contractor shall hire the services of an architect (or architectural firm) licensed in Bulgaria to design all works, as detailed in this document. At the same time, after obligatory coordination with the Municipality of Plovdiv and/or Bulgarian Ministry of Defense, the contractor shall hire (and pay for) the services of a “Third Party quality control Supervision” authorized by the Government of Bulgaria to supervise and approve each phase of the design and the construction, including final commissioning and acceptance of the facility. This company shall report directly to the US Government representative and the beneficiary if required by the Bulgarian regulations, but all their services shall be paid by the contractor.

All costs related with the procedures and requirements to obtain the Construction Permit shall be paid by the contractor. The design shall comply with all applicable regulations in Bulgaria for the scope of work of the contract.

The contractor’s final designs shall be signed, stamped and certified by a licensed architect in Bulgaria, it shall be approved by an authorized “Revision Entity - Expertise”, by any other agency which shall be required by Bulgarian regulations for the scope of work of this project, and it shall be approved by the competent Bulgarian authorities for construction projects on military installations before its construction is authorized to start. The level of detail of the design (extent of specifications, number and size of drawings, calculations, etc.) shall be sufficient to verify the compliance with the requirements of this PTS and as required by the regulations of Bulgaria and of the competent Bulgarian authorities for this project.

2.8 Construction Phase - General

Once the contractor completes the design and they show evidence of formal authorization by the competent local authorities and Monitoring Entity, and the contractor shows that they have completed other administrative contract requirements (Accident Prevention Plan, Quality Control Plan, Schedule, etc.) the Contracting Officer will inform the contractor that they may start the construction phase of this design-build contract. This notification is called Notice to Proceed or NTP. NTP is required prior to beginning construction.

During the construction phase the contractor shall be responsible to execute the construction works, but also to monitor, inspect and certify them as required by Bulgarian regulations. All costs for both the construction and its inspection and certification are the responsibility of the contractor.

In case this is not legally possible, the contractor shall pay the monitoring and third-party inspection agencies through other agencies or departments.

The construction shall follow the design and technical projects or shop drawings prepared by the architect/engineer and for which the contractor shall obtain the construction permit or authorization.

The architect/engineer who prepares the design shall visit the site for every important and relevant phase of work to partially accept the completed works. In addition to the requirements of the Bulgarian regulations for the visits of the designer, once the works start, the architect/engineer shall visit the site at a minimum once every week.

Two days in advance of the site visit, the contractor shall inform the Office of Defense Cooperation (ODC) Bulgaria and the beneficiary of the planned arrival time to the job site (with copy to NAVFAC

PM).

In addition to these minimum weekly visits, the architect shall visit the site when NAVFAC’s PM visits the job sites, estimated to occur once every two months.

In addition to these visits, the third-party experts will visit the site as required by Bulgarian regulations, and also when NAVFAC’s PM visits the site.

Work will not be accepted until Final Act of Acceptance is provided.

3 GENERAL SCOPE OF WORK OF MILITARY WORKING DOG FACILITY IN PLOVDIV

(BASE‐BID)

These PTS describe work for a 100% DESIGN‐BUILD contract. The Base‐Bid includes the design and construction of a new facility to be used as a Military Working Dog training and support area for Plovdiv Military Forces. With details in subsequent sections, the general basis of design includes:

- Support building, single‐level, estimated to be o be subdivided as follows:

o Kennel Master offices o Open area for computer workstations o Multipurpose training, classroom, break room o Combined unisex bathroom, shower, and locker room o Storage rooms, including separate food storage with outdoor access o Mechanical room

- Kennel building that is single‐level and estimated to be 9 m x 14 m indoor area with two additional

3x14m attached outdoor spaces. To be subdivided as follows:

o Kennels for eight military working dogs, with indoor and outdoor portions o Food preparation area o Storage area o Mechanical room

- Sidewalks of 1 m width around the perimeter of each building.

- Covered walkway between Kennel and Support buildings, minimum 6 m length.

- Utility services connection to existing local services including telephone, internet, electrical, water, and sewer.

- Three stainless‐steel chain‐link fenced areas, approximately as detailed in this document, surrounded by 2.5 m tall fencing.

- Creation of specific concrete obstacles for obedience course.

- Access and connecting walkways of 2 m width.

- Exterior lighting

- CCTV security system, with control station in guard shack in separate building.

3.1 General Facility Layout

The facility layout shall conform to the design as supplied in ANNEX B

3.2 Elements interfering with the new construction

It is estimated that new construction shall be placed in an area without any prior construction within its footprint. However, it is possible that there will be underground utility lines which may need to be rerouted in coordination with the construction of the new facilities. The contractor is responsible to survey the area prior to submission of their bid or to place the building where it does not interfere with any utility line.

Anything interfering with the new construction and extending more than 1 meter above or below the new facilities shall be rerouted (if still in use) or demolished by the contractor if no longer in use. The contractor shall locate and reroute any potential utility line (cables, piping, etc.) that may interfere with new construction.

The contractor shall design the construction to minimize removing any tree. The removal of any tree shall be done by the beneficiary following the same principle: contractor to notify the beneficiary with 2 months advance notice and contractor to remove what will be left under grade elevation.

The contractor shall copy the Contracting Officer Representative on any official correspondence related to this PTS between the contractor and the beneficiary.

3.3 General Design / Construction Requirements for Structures

General requirements:

- Emergency Escapes: The building shall comply with the emergency escapes requirements of the

Bulgarian regulations. All exterior doors shall open to the outside and be equipped with the required panic hardware.

- Ceiling height: 2.8 meters from finished floor to suspended acoustic ceiling

- Windows: The contractor shall provide the necessary windows to maximize the use of natural light, to provide ventilation and to provide an esthetically pleasant building.

- Structure: Reinforced concrete superstructure: foundations, columns, beams, deck. No wood shall be used as a permanent structural member.

- It is noted that the design of the foundations depends on the results of a geotechnical report, which is not included in these PTS. For estimating purposes, the contractor shall estimate the worst soil conditions available in this part of Bulgaria. The contractor needs to be familiar with recent construction projects in the area to estimate the necessary foundations for the new facility.

Contractor needs to obtain this information from beneficiary, from Ministry of Defense, or from other local sources, prior to submission of their bids.

- Exterior Enclosure: Use traditional solid natural stone bricks or other concrete masonry units (CMU) authorized by Bulgarian construction standards with masonry walls, with rigid thermal insulation, mesh, plaster, and paint. Provide similar finishes as the existing installation HQ building.

- Internal Partitions: Masonry walls, plastered, and paint. The rest of interior partitions shall be made with ceramic masonry walls, as thin as allowed by Bulgarian regulations to maximize the usable area of the new facility.

- Seismic: Strict compliance with seismic criteria applicable for this region of Bulgaria. It must be noted that the seismic requirements in Bulgaria are very high, which will require very heavy reinforcements and building structure.

- Elevation: Ground floor of new construction shall be 0.3 m higher than average grade elevation surrounding the new building.

- Drainage: Provide adequate drainage system around the new construction. The contractor shall grade the grounds around the new construction as far as technically necessary to guarantee that there will not be any accumulation of rain water next to the new construction. This will require underground drainage or sloping and grading of all the areas.

- Roof: Similar to installation’s existing HQ’s building. Provide thermal insulation on the roof. Provide with minimum 0.8 meter wide roof eaves.

3.4 Requirements for Support Building

Some rooms will have specific requirements that are described in later in this PTS.

3.4.1 Water Service Connection

The contractor is responsible for connecting water service for the new buildings from the main water utility network in the military installation, to include the necessary valves and water meter as required by the Bulgarian MoD and/or the water utility company. The contractor shall prepare a technical project to perform the water connection as required by Bulgarian regulations.

For estimating purposes, the contractor can estimate that the connection to existing water shall be within 115 meters from the construction site. The contractor is responsible to survey the area in coordination with the Bulgarian military representatives to determine the optimal point of connection.

The water line from the connection point to the new building shall be installed underground with the required thermal insulation. All exterior surfaces damaged by the construction activities, but mainly by the required excavations, shall be restored to their original conditions.

The diameter of the new water line from the connection point to the new building shall be the same diameter as the water line to be intercepted. This is to maximize the available pressure and flow in the new facility. If the water line to be intercepted is 50 mm, the new water line from the connection point to the new facility shall be 50 mm. If the water line to be intercepted is 100 mm, the new water line shall be 100 mm.

Local existing water connection and potential point of connection

3.4.2 Water Distribution at Support Building

Provide cold water to all plumbing appliances and faucets and hose bids. Provide hot water to all internal faucets, sinks, and showers. Use water piping certified to be used in domestic potable water systems.

Provide thermal insulation for hot water piping for energy savings and for cold water to avoid water condensation on the piping.

All water piping to be recessed within the floors, walls and ceiling so that they are not exposed to the view.

Where possible the water pipes shall be installed above the suspended ceiling for easier inspection and maintenance.

Pressure test all water lines at least at 2.5 times the maximum operating pressure or as required by Bulgarian regulations (whatever is higher)

3.4.3 Electrical Service Connection

The electrical installation for the new facility shall be designed and installed in strict compliance with Bulgarian electrical code and regulations.

For estimating purposes, the contractor shall estimate that the new facility shall be electrically independent from the rest of the military installation. This will require a separate connection to the electrical utility company, with its required electric meter, separate contract and separate electric feeder. For this reason, the new building shall be electrically fed from an existing substation owned, controlled and managed by the electric utility company, which for estimating purposes the contractor shall estimate that it is located within 200 meter radius of the future construction site.

From the substation, the contractor shall provide underground electrical installation to the new building.

The contractor shall install the underground cables in underground conduits, providing one spare conduit of the same diameter as the one used for the electrical feeder. Provide new necessary exterior concrete manholes to facilitate pulling the cables, or their future replacement in case of malfunction.

The contractor will coordinate and obtain permission from the local power utility company for service connection, including all technical information required.

The contractor will secure the services of a licensed engineer to prepare the necessary electrical design. The contractor shall prepare a full technical project for the electrical installation.

The contractor will provide:

- New cables

- New electrical protection

- New electric panels

- New electric meter

- New underground cable to the main electric panel of the building, in conduit, not direct buried.

- Restoration of any services affecting by the installation

The contractor shall be responsible to pay any official fees related with the electrical connection to the utility company, as for the preparation of the power supply contract.

Typical underground electrical conduit (provide one spare conduit)

Local electrical substation, within 200 m of construction site

Typical underground electrical conduit (provide one spare conduit)

3.4.4 Electrical Distribution at Support Building

The building shall be provided with one main electrical panel to be recessed within the walls of the building.

The contractor’s designer shall decide the location of this main panel, but it is recommended to install it in the mechanical room and from there to provide feeders to new electric panels for the main areas of the building.

All electrical installations in the building shall be recessed, so that no cables or conduits shall be exposed to the view. This includes the electric panels and boxes.

All electrical circuits to be installed under conduit or on certified cable trays above the suspended ceiling.

Conduits to be recessed within the floors, walls and ceiling so that they are not exposed to the view. Direct installation of cables under the plaster without conduit IS NOT AUTHORIZED.

All electrical equipment to be used shall be CE certified. All circuits to be provided with differential protection of 30 mA.

The contractor shall provide a complete electrical project, including all necessary boxes and protection. It shall include the necessary grounding and lighting protection as required by Bulgarian electrical code.

The number and location of electrical receptacles is to be determined by the contractor’s designer, but for estimating purposes the contractor shall estimate a minimum of 25 electrical receptacles in the new building under the Base‐Bid. All rooms and areas shall have minimum of 1 electrical receptacle.

Contractor will incorporate automatic transfer switch for backup generator power.

Approximate location of existing electrical connection

<200m

Typical electrical conduits within walls

Typical required electrical panel to be recessed on the walls

All electrical mechanisms to be recessed in the new walls. Provide wide mechanisms as shown. Provide telephone plugs as the one shown on the middle left of the picture.

3.4.5 Backup Power

The contractor will provide a new weatherproof pad‐mounted automatic start electric generator rated at 125% capacity for full load of the facility. This means that if the maximum load of the building is calculated at 10.5 KVA, the generator shall be rated for 14.0 KVA or the immediate highest generator, which in this case would be a standard 15 KVA generator.

The generator and installation shall follow the following basis of design:

The contractor shall design and install a generator system, including all required accessories to have perfectly operational automatic system. Contractor shall provide a pad‐mounted generator rated for exterior use and recommended by the manufacturer to be installed in areas with inclement winter weather and resistive heating. In addition to the weatherproof enclosure provided by the manufacturer, the contractor shall provide a light metal canopy to protect the engine‐generator set from the rain and snow.

The horizontal projection of the canopy shall be 3 times larger than the horizontal projection of the engine‐ generator set.

Location of the generator to be determined by the contractor’s designer team, in coordination with beneficiary.

The engineer hired by the contractor, responsible for the electrical design shall design this emergency generator with an Automatic Transfer Switch.

Generator set (generator and diesel engine) and the automatic transfer switch shall be a complete package provided by the same manufacturer, designed for exterior/outdoor use.

The generator set shall have a selector switch to select between automatic and manual operation.

Under automatic operation, the generator shall start automatically when a power outage of more than 5 seconds is detected and shall connect the facility loads within 30 seconds. Once the utility power returns, Typical cable trays above suspended ceiling. This is required throughout the building.

the generator shall stop after 10 minutes of interrupted utility power supply and shall connect the facility loads to the utility power within 1 second. Synchronization for returning to utility power is not required.

The generator shall be provided with fuel storage for minimum of 24 hours of use running at 75% capacity.

Provide the manufacturer’s recommended concrete foundation and anti‐vibration pads.

Perform testing recommended by the manufacturer.

Perform commissioning (initial operation) by the manufacturer’s authorized technical personnel. Payment for the generator shall not be authorized until the contractor provides certificate from the manufacturer’s authorized technician that the generator was installed, commissioned and tested in accordance with the manufacturer’s recommendations.

Contractor is responsible to provide fuel for testing and to fill the fuel tank after commissioning is completed.

Typical pad mounted generator with a light metal canopy (this one obviously larger than the one required by our project)

3.4.6 Interior Lighting

The contractor shall provide a lighting design for the new facility, showing the illumination design pattern for each room in compliance with EN 12464‐1. In each room, the design shall include the number and location of specific LED lighting fixtures, to show that they meet the minimum lighting levels required by standard EN 12464‐1. These designs are normally done by the manufacturer of the proposed lighting fixtures. For the final inspection and acceptance, the contractor shall provide the services of a certified third‐party inspection company with a lighting meter to test the illumination levels. This test shall be done in presence of the beneficiary representative.

Models: All models shall be selected by the contractor’s designer, to meet the requirements specified herein.

- All lighting fixtures to use LED technology

- All internal areas in the building provided with suspended acoustic ceiling shall be provided with recessed lighting fixtures.

- Any internal areas with exposed ceiling structure shall be provided with surface mounted lighting fixtures.

- As a minimum, one of every 10 internal lighting fixtures shall be provided with autonomous battery to operate for a minimum of 30 minutes in case of power failure.

- Include electrical exit signs with LED technology.

- Provide exterior led lighting fixtures with photocell and manual control as described in separate paragraph.

Simplified electric diagram

Standard lighting design

Typical recessed LED lighting fixture

Professional 3D lighting design

3.4.7 Heating / Air Conditioning

Heating will be provided through commercial grade electric baseboard heaters.

The contractor shall also provide a heat pump to provide additional heat in the winter or cold air in the summer to support building. The contractor shall provide cooling and heating system using split‐type inverter technology heat pump units. Provide heat pumps with exterior units protected from the view and snow to the maximum extent possible.

The contractor shall hire the services of a specialized company or engineer to design the new air conditioning system. For estimating purposes, the contractor can estimate a system with the following technical parameters:

- Heat pump system using inverter technology or variable refrigerant flow. Capable of providing hot and cold air and maintaining 22 degrees Celsius in hottest summer conditions.

- Remote temperature control.

- Drainage of the condensate to exterior.

Typical required illumination levels for various spaces

3.4.8 Telephone / Internet

Provide minimum of four receptacles for telephone and internet connection.

Location for the four wall receptacles for telephone and Internet shall be indicated by the beneficiary. The contractor is responsible to provide all necessary installations to provide fully operational signal to the wall outlets from the nearest available point (or points) of connection with the service provider. This includes conduits, cables, cabinets, boxes, switches and anything else that may be necessary in compliance with the Bulgarian regulations and with the technical requirements of the service provider (telephone and Internet).

The contractor is responsible to pay for any official connecting fee that may be applicable. As with the electrical connection, the contractor is not responsible to sign the contract with the service provider, but they are responsible to coordinate with the beneficiary.

Typical required heat pump – Inverter Technology

3.4.9 Fire Alarm

Provide Fire Alarm system as required by Bulgarian regulations for this type of facility. Provide all required smoke detectors, pull stations, horns and strobe lights. All cables and boxes shall be recessed within the walls if allowed by Bulgarian regulations.

If technically possible, the main fire alarm panel is to be recessed on the hallway wall in an accessible area.

3.4.10 Television Signal

Provide 2 operational TV wall receptacles or outlets with full signal to watch Bulgarian public television.

The contractor will include two television wall receptacles, at the exact location to be determined by the beneficiary representative.

TV sets and TV supports are not part of the contract.

3.4.11 Sewer System

The contractor is responsible to survey the area, not to alter any of the existing services, and to restore all surfaces to their original condition. The contract includes connecting the sewer of the new building to an existing sewer system within the military property.

All drainage/vent/sewer pipes are to be covered by masonry wall, partitions, false ceiling, etc., so that they are not exposed. Provide access points for maintenance of the lines.

Design and installation of sewer system must be in accordance with Bulgarian regulations.

Coordinate with the local municipality for specific requirements and permissions for connection of a new line to the centralized sewer system.

Minimum size for sewer piping outside of the footprint of the new buildings shall be 250 mm (internal diameter) even if Bulgarian regulations allow for smaller diameter piping. Concrete manholes shall be placed at every change of direction, at each connection between piping outside the footprint of the new buildings and at every 40 linear meters of straight sewer line. Minimum slope to be 0.5 %.

Typical metal framing for acoustic ceiling

Typical ceiling with recessed lighting fixtures

3.4.12 Ceilings

All internal surfaces shall be provided with new suspended acoustical ceiling, rated for the intended location (except mechanical room)

For all bathroom / shower area: Provide metal suspended ceiling tiles.

For all other suspended ceiling areas: Provide acoustic suspended ceiling tiles.

All materials for the acoustic suspended ceiling (tiles, supports, rails, etc.) shall be provided from the same manufacturer.

All installations to be installed above the suspended ceiling for easy maintenance. This includes electrical conduits, water pipes, heating piping, air conditioning gas and drainage lines, fire alarm cables, communication infrastructure, and everything else that may be technically possible.

3.4.13 Interior Wall Surfaces

All internal walls shall be provided with plastered and paint finish. All paint to be used for interior surfaces shall be certified as antibacterial and antifungal.

All installations (heating pipes, conduits, water lines, etc.) shall be recessed within the finished wall surfaces;

however, the wall surfaces shall be designed to allow for easy maintenance of all recessed utilities.

The use of gypsum board for any wall surface is not authorized.

3.4.14 Interior Floor Surfaces

All internal flooring surfaces shall be provided with extra heavy resistant porcelain stoneware, using large or extra‐large format tiles.

Porcelain stoneware tiles shall be minimum 40x40 CM (color to be selected by the beneficiary). Other acceptable sizes could be 50x50, 30x60, 60x60, 75x75 or any other standard size not smaller than 0.16 m² per tile. Thickness to be minimum 8 mm. It is acceptable to provide smaller size tiles exclusively in the bathrooms, given that they are the same model but smaller sized tiles.

Provide homogeneous grès porcelain tiles. Provide large format tiles with minimum size 0.16 m²/tile. It must be noted that the price for porcelain homogeneous gres tiles is at least 50% higher than regular grès ceramic tiles. The contractor shall provide matching wall base board from the same model as the tiles. Cutting the tiles to provide the wall base is not authorized.

Grès Porcelain stoneware is a ceramic with a compact, hard, colored and non‐porous body. Tiles shall be homogeneous or non‐glazed. This means that all the material of the tile is made of the same material. If we cut a tile, there would be no difference between the bottom, the top of the middle of the tile. The word “grès” means that the ceramic body of the tile is extremely vitrified, that is to say compact, hence the exceptional great resistance. The result is a lean clay body, little refractory, fired in a kiln (at 1200‐1400 C°) until it reaches a non‐porous vitrification and a complete water‐proofing.

The new ceramic tiles shall be high quality, provided with the following technical features:

- Scratch hardness of surface (Mohs) >8 (according to EN101)

- Resistant to impacts: Complies with ISO 10545‐5

- Water Absorption: Tested by ISO 10545 ‐ 3 ≤ 0.5%

- Deep abrasion resistance: Tested by ISO 10545 – 6: Max 175 mm3

- Frost resistance: Tested by ISO 10545 – 12: Tiles must not produce noticeable alteration to surface

- Chemical resistance: Tested by ISO 10545 – 13: Tiles must not produce noticeable signs of chemical attack

- Friction coefficient (slipperiness): Tested by ASTM C 1028 ≥ 0,60

- Size: Minimum 40x40 cm

Tile installation shall be done following manufacturer’s instructions and recommendations.

All floors shall be perfectly leveled. In the toilet room the floors shall be sloped towards the new floor drains.

Typical porcelain stoneware tile

Recommended installation of the tiles using double glue, on the floor and on the tile.

Cross-section of homogeneous porcelain stoneware tiles. Minimum 8 mm thickness required.

Homogeneous characteristic of the porcelain stoneware in comparison with standard ceramic tile (Ceramic tile not acceptable in this project)

Typical grès base boards and flooring. Use same model for baseboards as for the floor tiles.

3.4.15 Thermal Facade

Provide impact resistant thermal façade on all exterior walls of the building as in the pictures below.

Minimum 8 cm of rigid thermal insulation (wool rock) and 1 cm of rigid plaster protection (double mesh).

Provide exterior with treatments and colors to match existing installation buildings.

Provide with proper finishes to avoid any water or insects to get within the thermal insulation.

Provide perfect connection between the top of the thermal façade and the roof eave. Provide perfect connection between the bottom of the thermal façade and the new perimeter concrete sidewalks to avoid any possibility of water infiltration.

Existing Installation Building (match exterior treatments and colors)

Typical thermal facades

3.4.16 Roofing

Provide pitched roofing system with similar finishes as the existing installation buildings,…