AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

N33191-23-R-4003 DB Construct Maritime Operations Center (Renovate DFAC and Auditorium), Le Pecherie Naval Base, Tunisia See page 2 for description.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 08-Mar-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N3319123R4003

X 9B. DATED (SEE ITEM 11)

31-Jan-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

08-Mar-2023

CODE

NAVFAC EUROPE AFRICA CENTRAL

VIALE PORTO CAPODICHINO

NAPOLI 80144

N33191 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N3319123R4003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 00003

The purpose of Amendment 0003 is as follows:

1) The proposal due date is extended from March 10, 2023 at 1400 hrs. Central European Time (CET) to April 03, 2023 at 1400 hrs. CET.

2) Revision to Attachment 1 – Performance Technical Specifications (PTS) and Drawings dated March 07, 2023.

3) Answer Pre Proposal Inquiries (PPIs) numbers four (4) thru twelve (12). There have been twelve (12) PPI’s received to date.

4) Provide site visit sign in sheet.

1. Proposal Due Date:

Proposals shall be submitted electronically to Mr. Graeme L. Silva at graeme.l.silva.civ@us.navy.mil on or before the time specified in Block 13 of the Standard Form (SF) 1442. Compliance with the submittal closing time and receipt of proposals shall be determined by using the time indicated on the receiving Contract Specialist’s computer. The offeror is responsible to verify that the Government has received the proposals.

All documents submitted as part of the proposals shall be in English and sent in PDF format via email to the addresses stated above. Submit the Price Proposal and Non-Price Proposal in two separate PDF files. Total size per email shall not exceed 10 megabytes to ensure receipt by U.S. Government email systems.

2. Revisions to Attachment 1 – PTS dated March 07, 2023 Additions to the PTS are capitalized in bold font and deletions are in bold strikethrough. The revised PTS and all referenced attachments is being issued with this amendment as a single PDF titled, “N3319123R4003 Maritime Operation Center_Attach 1_PTS Revision Dated March 7, 2023”

3. PPI Questions and Answers:

Pre-Proposal Inquiry 0004 - It is specified as 'The Government will evaluate price based on the total price, exclusive of the Value Added Tax (VAT)' in section 00 72 00 - Contract clause (pg.6) of the RFP document. Are we also exempt from Customs and other taxes?

Answer: This project is exempt of value added tax (VAT), sales tax, custom fees and other similar fees as allowed by Tunisian laws and regulations. The contractor shall discuss the extent and requirements to obtain these exemptions with corresponding Tunisian fiscal authorities before starting any works (construction or design) on site.

The contractor shall implement the proper procedures for any procurements subject to any tax exception prior to the procurement, directly with the corresponding fiscal authorities. The US Government representatives will remain available for any support necessary. However, the initiative and responsibility to implement any tax exemption procedure relies exclusively on the contractor.

Pre-Proposal Inquiry 0005 - Could you please clarify that whether one static load test is enough for pile foundation?

Answer: One static load test will suffice.

Pre-Proposal Inquiry 0006 - It is seen in the site visit that the structural quality and stability of the dining building and auditorium is not good. Moreover, it is to be worried about restoring of the building will not be a solution for the mailto:graeme.l.silva.civ@us.navy.mil scope of the project. In addition, since the building age is over 50 years, risk level would be very high even if it were restored. According to scope of work, contractor is not responsible from structural strengthening works. Is contractor responsible from checking structural stability of the buildings? If yes, and structural stability is not found in good condition after contractor’s survey, will structural strengthening works considered as additional works?

Answer: The contractor shall perform a non-obtrusive structural test on the Auditorium as it is recommended in Attachment 9 of the PTS. No structural test is required for the dining facility, per Attachment 9. If the structure is found to be unstable, the project will be re-evaluated depending on funds availability.

Pre-Proposal Inquiry 0007 - Since the date of the site visit is very close, we request a 1 week extension to the bid closing date.

Answer: The proposal due date is extended from Friday, March 10, 2023 at 1400 hrs. to Monday, April 03, 2023 at 1400 hrs.

Pre-Proposal Inquiry 0008 - DFARS 252.204-7004 Level I Anti-Terrorism Awareness Training for Contractors (FEB 2019). As stipulated in the DFARS clause, will there be a French and Arabic version of this training available for Local Nationals who do not speak English and not able to take the online English version of the course? If yes, is there a cost for this training?

Answer: The DFARS clause 252.204-7004, shall be removed from the solicitation. The clause is not applicable to this solicitation or the resulting contract.

Pre-Proposal Inquiry 0009 - Reference RFP Page 5/41, Section 4 INSTRUCTION FOR SUBMITTING PRE- PROPOSAL INQUIRIES - Pre-proposal questions will be accepted ten (10) calendar days before the proposal due date, any inquiries made after that date may not be answered. Due to the delayed site visit for this program, we would like to know if an extension on submission of questions and proposal can be granted?

Answer: See RFI #7 above

Pre-Proposal Inquiry 0010 - The VAT exemption period takes longer than expected in Tunisia. Please confirm that the contractor will not start any Design activities including Topographic Survey or Geo-Technical survey without VAT exemption being approved by the Government.

Answer: Topographic survey and geo-technical survey are not part of this project. The topographic and geo-technical surveys are provided as Attachment 3 in the PTS. Per 1.1 Taxation of the PTS, "The contractor shall receive this [VAT] exemption prior to proceeding to construction." The government expects design to be concurrent with the VAT exemption process.

Pre-Proposal Inquiry 0011 - Please clarify if customs exemption applies for this project?

Answer: This project is exempt from value added tax (VAT), sales tax, custom fees and other similar fees as allowed by Tunisian laws and regulations. The contractor shall discuss the extent and requirements to obtain these exemptions with corresponding Tunisian fiscal authorities before starting any works (construction or design) on site.

The contractor shall implement the proper procedures for any procurements subject to any tax exception prior to the procurement, directly with the corresponding fiscal authorities. The US Government representatives will remain available for any support necessary. However, the initiative and responsibility to implement any tax exemption procedure relies exclusively on the contractor.

Pre-Proposal Inquiry 0012 - Reference to Attachment 1, 2.3.2 & 3.3.2 the following items are out of scope. Can the government confirm what if any of the below items should be included in the design, demolition or renovation of this project. (example - DFAC Cooking Vent Hood design and replacement is out of scope) The below listed disciplines are considered out of the scope of work of this contract.

• Lightning and Earthing System.

• Emergency Backup Systems.

• Mechanical (Plumbing, Drainage, Waste such as kitchen oil/grease collection).

• HVAC (Heating, Ventilation and Air Conditioning).

• Fire Protection and Fire Detection/Alarm.

• Telecommunication, Security and Audiovisuals.

• Physical Security.

Answer: The Government confirms the disciplines listed in 2.3.2 (DFAC) and 3.3.2 (Auditorium) located in Attachment 9 of the PTS is considered out of scope. The noted paragraphs pertain to the electrical design criteria for the DFAC and Auditorium.

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 10-Mar-2023 02:00 PM to 03-Apr-2023 02:00 PM.

SECTION 00 21 16 - INSTRUCTIONS TO PROPOSERS

The following have been deleted:

252.204-7004 Antiterrorism Awareness Training for Contractors. FEB 2019

(End of Summary of Changes)