19R0411_VHF_Ward_-_Attach_1_-_PTS.pdf
PDF 2 MB Posted
- Solicitation number
- N3319119R0411
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 19R0411_VHF_Ward_-_Amend_0001.pdf | ||
| 19R0411_VHF_Ward_-_RFP.pdf | ||
| 19R0411_-_Attach_2_-_PPI.docx | DOCX document | |
| 19R0411_-_Attach_3_-_Price_Schedule.doc | DOC document | |
| N3319119R0411_19R0411_Sierra_Leone_-_Pre_sol.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 1 to N33191-19-R-0411
Prepared by: NAVFAC EURAFSWA HQ – XEBL Sonia Grillo
Department of State
UPGRADE LASSA FEVER WARD TO
VIRAL HEMORRAGIC FEVER WARD
Kenema Government Hospital [KGH] Kenema, Sierra Leone
Case V8-B-HAA/2018
FY19
March 2019
TECHNICAL REQUIREMENTS
Upgrade to VHF Ward
Attachment (1) to N33191-19-R-0411
Table of Contents p. 2/100
TABLE OF CONTENTS
COVER PAGE
TABLE OF CONTENTS
ACRONYMS AND GLOSSARY
1 PROJECT DESCRIPTION
1.1 GENERAL
1.2 LEGAL AND TECHNICAL REQUIREMENTS
1.3 SCOPE OF PROJECT
Base Bid - CLIN 001:
a. Upgrade the Doffing/Decontamination
b. Implement an Ambulance Decontamination Bay sized 10 m x 8 m
c. Install Additional overhead water tank
d. Expand and Correct the Barrier System to Separate Dirty and Clean Areas
e. Upgrade the Perimeter Fencing
f. Perform Minor Correction Work
g. Shelter the Drop-Off Area and Uncovered Passageways
h. Implement a Dedicated Vehicular Access to the Morgue
i. Construct a Family Visitation Center
j. Construct a Personal Protection Equipment [PPE] Storage Warehouse Option A – CLIN 002:
Pave all Corridors and Passageways (~1,000 sqm) Option B – CLIN 003:
Provide Internal Yard Landscaping (~1,100 sqm)
OPTION C – CLIN 004:
Build 2 Sentry-boxes (~5 sqm) Option D – CLIN 005:
Pave Access Ways connecting Gates to Public Road (~40 sqm)
1.4 SIGNAGE
Project Sign Dedication Sign
1.5 PROCEDURE
Pre-Construction Submittal Requirements
Concept Design Final Design Construction Schedule Quality Control Plan Accident Prevention Plan [APP] Site Safety and Health Officer [SSHO] Certification Construction Permits as required by Sierra Leonean and KGH regulation Worksite Delimitation Plan
Interim Submittal Requirements Completion Submittal Requirements
1.6 CONTRACT MILESTONES
1.7 STANDARD NOMENCLATURE
2 PROJECT OBJECTIVES
Attachment (1) to N33191-19-R-0411
Table of Contents p. 3/100
2.1 MISSION STATEMENT
2.2 FACILITY FUNCTION
2.3 PROJECT SPECIFIC PRIORITIES
2.4 APPROPRIATE DESIGN
2.5 WORKFLOW PROCESS - HOURS OF OPERATION
3 SITE ANALYSIS
3.1 EXISTING SITE CONDITIONS
3.2 PHOTO DESCRIPTION
3.3 SITE DEVELOPMENT REQUIREMENTS
Design Constraints
Access, Circulation, and Site Development
4 BUILDING REQUIREMENTS
4.1 DOFFING/DECONTAMINATION ROOM UPGRADE
4.2 AMBULANCE DECONTAMINATION BAY
4.3 ADDITIONAL OVERHEAD WATER TANK
4.4 DOUBLE BARRIER SYSTEM EXPANSION AND CORRECTION
4.5 PERIMETER FENCING UPGRADE
4.6 MINOR CORRECTION WORK
4.7 DROP-OFF AND PASSAGEWAYS SHELTERING
4.8 VEHICULAR ACCESS TO THE MORGUE
4.9 FAMILY VISITATION CENTER
4.10 PPE STORAGE WAREHOUSE
4.11 CORRIDOR/PASSAGEWAY FLOORING (OPTION A)
4.12 INTERNAL YARD LANDSCAPING (OPTION B)
4.13 TWO SENTRY-BOXES (OPTION C)
4.14 ACCESS WAY FROM PUBLIC ROAD PAVING (OPTION D)
4.15 EXAMPLE OF FINAL LAYOUT
4.16 EXAMPLE OF CORRECT CIRCULATION SYSTEM
4.17 PROJECT SIGN
4.18 DEDICATION SIGN
5 ROOM MINIMUM REQUIREMENTS
5.1 VHF NEW BUILDING FINISHES
5.2 FLOORS, WALLS AND CEILINGS
Attachment (1) to N33191-19-R-0411
Table of Contents p. 4/100
5.3 DOORS, WINDOWS, AND OPENINGS
5.4 PLUMBING AND FIXTURES
5.5 ELECTRICITY AND LIGHTING
5.6 GROUNDING SYSTEM
5.7 ELECTRICAL PANELBOARD
6 GENERAL WORK REQUIREMENTS
6.1 REFERENCE STANDARDS
6.2 WORK REQUIREMENTS
6.3 DESIGN GUIDANCE
6.4 PERFORMANCE TECHNICAL SPECIFICATIONS
6.5 PRE-CONSTRUCTION SUBMITTAL PACKAGE
Concept Design
Final Design
Construction Schedule
Quality Control Plan
Accident Prevention Plan
Site Safety and Health Officer [SSHO] Certification
Construction Permit
6.6 CONSTRUCTION GUIDANCE
6.7 CERTIFICATIONS, LICENSES, PERMITS, FEES, ETC
6.8 COORDINATION
6.9 VEGETATION CONTROL
6.10 RESPONSIBILITY OF MATERIALS
6.11 SAFETY AND PROTECTION
6.12 SPILL CONTINGENCY PLAN
6.13 SPECIAL SITE CONDITIONS
6.14 CLEANING
7 ENGINEERING SYSTEMS REQUIREMENTS
7.1 SECTION A10 FOUNDATIONS
A1010. Standard Foundations
A1030. Slab On Grade
7.2 SECTION B10 SUPERSTRUCTURE
B1010. Floor Construction
B1020. Roof Construction
7.3 SECTION B20 EXTERIOR ENCLOSURE
B2010. Exterior Walls
B201001. Balcony Walls, Guard Rails & Handrails
B201002. Exterior Coatings
B2020. Exterior Windows
B202001. Exterior Windows
B202002. Exterior Glazing
Attachment (1) to N33191-19-R-0411
Table of Contents p. 5/100
B201003. Exterior Louvers & Screens
B2030. Exterior Doors
B203007. Gates
7.4 SECTION B30 ROOFING
B3010. Roof Coverings
B301001. Steep Slope Roofing Systems
B301002. Low Slope Roofing Systems
7.5 SECTION C10 INTERIOR CONSTRUCTION
C1010. Partitions
C101001. Interior Guardrails
C101002. Interior Screens
C101003. Interior Windows
C101004. Interior Glazing
C1020. Interior Doors
C102001. Standard Interior Doors
C102002. Glazed Interior Doors
C1030. Specialties
C103001. Toilet Compartments and Accessories
C103003. Marker Boards
C103004. Counters
C103005. Cabinets
C103006. Ornamental Metal Work
7.6 C30 INTERIOR FINISHES
C3010. Wall Finishes
C3020. Floor Finishes
C3030. Ceiling Finishes
C3040. Interior Coatings And Special Finishes
7.7 SECTION D20 PLUMBING
D2010. Plumbing Fixtures
D201001. Water Closets
D201002. Urinals
D201003 Lavatories
D201004. Sinks
D201005. Finish Trim
D2020. Domestic Water Distribution
D202001. Pipes and Fittings
D202002. Domestic Water Equipment
D202003. Insulation & Identification
D202004. Specialties
D202005. Other Domestic Water Supply
7.8 D30 HEATING, AND VENTILATING , AIR CONDITIONING (HVAC)
D3010. Heat Generating Systems
D302001. Boilers
7.9 SECTION D50 ELECTRICAL
D5010. Electrical Service And Distribution
D501002. Service Entrance Equipment
D501004. Switchboard
D501005. Enclosed Circuit Breakers
D5020. Lighting And Branch Wiring
D502001. Branch Wiring
D502002. Lighting Equipment
D502003. Finish Trim
D502004. Potential Drop
D5040. Other Electrical Services
D504001. General Construction Items (Electrical)
D504002. Emergency Lighting and Power
D504003. Grounding Systems
D504004. Lightning Protection
D504005. Electric Heating
Attachment (1) to N33191-19-R-0411
Table of Contents p. 6/100
7.10 SECTION G10 SITE PREPARATION
G1010. Site Clearing
G1020. Site Earthwork
G102001. Grading
G102002. Blasting
G102003. Compaction
G1030 Disposal
7.11 SECTION G20 SITE IMPROVEMENTS
G2010 Roadways and Parking Lots
G2020 Pedestrian Paving
G2030 Fencing and Gates
G2040. Site Development
7.12 SECTION G30 SITE CIVIL/MECHANICAL UTILITIES
G3010. Water Supply
G301002. Water Storage
G3020. Sanitary Sewer
G302001. Sanitary Sewer Piping
G302002. Sanitary Sewer Manholes
G302003. Sewer & Waste Water Holding Tanks
G302003. Septic Systems Tanks
G3030. Fuel Distribution
G303001. Natural Gas/Propane [LPG] Distribution Piping
G303002. Gas Storage Tanks
G40 SITE ELECTRICAL UTILITIES
G4010. Electrical Distribution
G401003. Switches, Controls And Devices
G401006. Underground Electric Conductors
G401007. Ductbanks, Manholes, Handholes And Raceways
G401008. Grounding Systems
G401009. Metering
G4020. Site Lighting
G402001. Exterior Lighting Fixtures And Controls
G402004. Lighting Poles
G402005. Underground Electric Conductors
G402006. Ductbanks, Manholes And Handholes
G402007. Grounding Systems
8 PERFORMANCE TECHNICAL SPECIFICATIONS (PTS)
8.1. NARRATIVE
8.2. SECTION A10: FOUNDATIONS [6/07]
A10 General
A1010 Standard Foundations
A101001 Wall Foundations
A101002 Column Foundations And Pile Caps
A101003 Foundation Drainage
A1020 Slab On Grade
A102001 Concrete Slabs On Grade
A102002 Slab On Grade Insulation
A1030 Elevated Floor Slabs
A1040 Concrete
A104001 Concrete Materials
A104002 Concrete Formwork
A104002 Concrete Reinforcement
A104003 Placing Concrete Reinforcement
A104004 Concrete Mixing
A104005 Concrete Conveying
A104006 Concrete Depositing
A104007 Concrete Curing
A104008 Hot Weather Concrete
Attachment (1) to N33191-19-R-0411
Table of Contents p. 7/100
A104009 Concrete Construction Joints
A104010 Concrete Testing
8.3. SECTION B10: SUPERSTRUCTURE [06/07]
B10 General
B1010 Construction Components
B1020 Wood
B1030 Unit Masonry
B1050 Steel
8.4. SECTION B20: EXTERIOR ENCLOSURE [04/07]
B20 General
B2010 Exterior Walls
B201001 Unit Masonry
B201002 Guardrails ad Handrails
B201003 Exterior Painting and Special Coatings
B2020 Exterior Windows
B202001 Standard Window Systems
B202002 Louvered Windows
B202003 Screens
B202004 Roll Shutters
B2030 Exterior Doors
B203001 Standard Doors Systems
B203002 Door Frames
B203003 Exterior Door Hardware
B203004 Exterior Door Hardware Finishes
B203005 Other Exterior Specialty Doors
8.5. SECTION B30: ROOFING [04/07]
B30 General
B3010 Steep Slope Roof Systems
B301001 Slate Roofing
B301002 Roof Tiles
B301003 Metal Roof Panels
B301004 Concrete Roof Panels
B3020 Low Slope Roof Systems
B302001 Built-Up Asphalt Roofing (Aggregate Surfaced)
B3030 Flashings & Trim
B303001 Flashing And Sheet Metal
B301002 Gutters and Downspouts
B301003 Roof Openings and Supports
B301004 Other Roofing
8.6. SECTION C10: INTERIOR CONSTRUCTION [06/07]
C10 General
C1010 Partitions
C101001 Unit Masonry
C101002 Handrails
C101003 Interior Painting And Special Coatings
C1030 Interior Doors
C103001 Standard Doors Systems
C103002 Door Frames
C103003 Interior Door Hardware
C103004 Interior Door Hardware Finishes
C103005 Other Interior Specialty Doors
C1040 Specialties
C104004 Counters
C103005 Cabinets
C104006 Casework
8.7. SECTION C30: INTERIOR FINISHES [04/07]
C30 General
C3010 Wall Finishes
C301001 Plaster Wall Finishes
C301002 Tile Wall Finishes
Attachment (1) to N33191-19-R-0411
Table of Contents p. 8/100
C3020 Floor Finishes
C302001 Ceramic Tile Floor Systems
C302002 Ceramic Glazed Tile Floor
C302003 Ceramic Mosaic Unglazed Floor Tiles
C302004 Porcelain Floor Tile
C302005 Quarry Floor Tile
C302006 Terrazzo Floor Finishes
C302007 Masonry And Stone Flooring
C302008 Wall Base Finishes
C302008 Stair Finishes
C302009 Hardeners And Sealers
C3030 Ceiling Finishes
C303001 Acoustical Ceiling Tiles And Panels
C303002 Plaster Ceiling Finishes
C3040 Interior Painting And Special Finishes
C304001 Painting Systems Per Substrate
C304002 Concrete Finishes
C304003 Concrete Masonry Finishes
C304004 Plaster Finishes
C304005 Metal Finishes
C304006 Interior Wood Finishes
8.8. SECTION D20: PLUMBING [08/06]
D20 General
D2010 Plumbing Fixtures
D201001 Water Closets
D201002 Urinals
D201003 Lavatories
D201004 Sinks
D201005 Showers/Tubs
D2020 Domestic Water Distribution
D202001 Pipes & Fittings
D202002 Valves & Hydrants
D202003 Domestic Water Equipment
D202004 Insulation & Identification
D2030 Sanitary Waste
D203001 Waste Pipe & Fittings
D203002 Vent Pipe & Fittings
D203003 Floor Drains
8.9. SECTION D30: HVAC [06/07]
D30 General
D3010 Heat Generating Systems
D301001 Boilers
D301002 Heating Hot Water Distribution Systems
D301003 Terminal Units
D302001 Requirements
D302002 Hot Water Heating Equipment Startup and Operational Tests
D3040 Performance Verification And Testing
8.10. SECTION D50: ELECTRICAL [08/06]
D5010 General
D501001 Quality Assurance
D501002 Submittals
D5020 Electrical Service And Distribution
D502001 Main Transformers
D502002 Service Entrance Equipment
D502003 Interior Distribution Transformers
D502004 Switchboard
D502005 Enclosed Circuit Breakers
D502006 Motor Control Centers
D502007 Other Service And Distribution
D5030 Lighting And Branch Wiring
D503001 Branch Wiring
Attachment (1) to N33191-19-R-0411
Table of Contents p. 9/100
D503002 Lighting Equipment
D503003 Ballasts
D5050 Other Electrical Services
D505002 Emergency Lighting And Power
8.11. SECTION G10: SITE PREPARATION
G10 General
G1010 Site Clearing
G1020 Site Demolition & Relocations
G102001 Building Mass Demolition
G102002 Hazardous Components Abatement
G102003 Aboveground Site Demolition
G102004 Underground Site Demolition
G102005 Fencing Relocation
G102008 Site Cleanup
G1030 Site Earthwork
G103001 Grading
G103002 Common Excavation
G103003 Rock Excavation
G103004 Fill & Borrow
G103005 Compaction
G103006 Soil Stabilization
G103007 Slope Stabilization
G103008 Shoring
G103009 Temporary Dewatering
G103010 Temporary Erosion & Sediment Control
G103011 Other Site Earthwork
G1040 Hazardous Waste Remediation
8.12. SECTION G20: SITE IMPROVEMENTS [08/06]
G2010 Roadways and Parking Lots
G201001 Bases & Subbases
G201002 Curbs & Gutters
G201003 Paved Surfaces
G201002 Resurfacing
G2020 Pedestrian Paving
G2030 Fencing & Gates
G2040 Other Site Development
8.13. SECTION G30: SITE CIVIL/MECHANICAL UTILITIES [08/06]
G3010 Water Supply
G301001 Well Systems
G301002 Potable Water Distribution
G301003 Potable Water Storage
G3020 Sanitary Sewer
G302001 General Requirements
G302001 Sanitary Sewer Piping
G302002 Septic Tanks & Drain Fields
G302003 Sewer & Waste Water Holding Tanks
G3030 Fuel Distribution
303001 Gas Distribution Piping (Natural Gas)
303002 Gas Distribution Piping Liquified Petroleum Gas (LPG])
Attachment (1) to N33191-19-R-0411
Acronyms and Glossary p. 10/100
ACRONYMS AND GLOSSARY
As used throughout this solicitation/contract:
# stands for number, or for a generic digit BOD stands for beneficial occupancy date; it sets the date of facilities acceptance and warranty start COR stands for the Contracting Officer Representative, who is a qualified Government employee appointed by the KO to assist in the technical monitoring or administration of a contract D/B contract stands for Design and Build contract, which means that the contractor shall first provide a complete and executable design matching the specifications of the TR, then implement the construction in accordance to such a design.
DMV stands for Domestic Violence Haven DOD stands for U.S. Department of Defense ESR stands for Engineering System Requirements Government or Govt. stands for the Government of the United States of America (U.S.A.);
HC stands for High Containment Ward HVAC stands for Heating, Ventilating and Air Conditioning KO stands for Contracting Officer ; it is the Government’s representative in charge for executing the contract and responsible for any amendment.
KTR stands for Contractor ; it is the Offeror that has been awarded the present contract LC stands for Low Containment Ward LPS stands for Lightning Protection System MOU stands for memorandum of understanding NAVFAC EURAFSWA stands for Naval Facilities Engineering Command Europe, Africa and South West Asia; it is the Government’s executive agent for construction.
NTPC stands for Notice To Proceed with the Construction NTR stands for Navy Technical Representative, who is in charge to monitor the performance of work under the contract and is an accountable official for purposes of certifying payments Offeror is any constructor that submits a bid PM stands for Project Manager ; it is the Government’s technical representative in charge for managing the project (scope, cost, and schedule) from design authorization to closeout PPC Portland Cement Concrete PPE stands for Personal Protection Equipment PTS stands for Performance Technical Specifications RFP stands for Request for Proposal RFQ stands for Request for Quote KGH stands for Kenema Government Hospital, located in Kenema.
SF stands for Government’s standard form; this acronym is followed by a number identifying what contract action the form is intended for SOW stands for Statement Of Work : it is the detailed description of the work activities, deliverables and timeline the contractor will execute against in performance of specified work TEB stands for the Government Technical Evaluation Board in charge to receive, accept and evaluate the technical offers TR stands for Technical Requirements which are integrant part of the SOW and provide all the specifications for the design and the implementation of the project.
Attachment (1) to N33191-19-R-0411
1. Project Description p. 11/100
1 PROJECT DESCRIPTION
1.1 GENERAL
This is a design-build project to upgrade the existing Lassa Fever Ward, located in the Kenema Government Hospital [KGH] compound, to become a Viral Hemorrhagic Fever Ward , in accordance to the requirements, sketches, and tables included hereby. The facility is not in use.
Since the ward is intended for highly infectious diseases, the circulation must be split in clean and dirty paths that have never to get in touch.
The project site is located at the GPS coordinates: 7.874003, -11.183762 and the current site layout is shown at par. 3.1.
The work shall include a complete design and drawing package as described in this document.
The design shall meet all requirements of Sierra Leone Building Code.
The design shall be developed by licensed architect(s)/engineer(s) in Sierra Leone , either consistently employed in the contractor’s company or working for a design firm hired by the contractor for the purpose of this project.
Design-Build Procedure The Design-Build procurement method consists of a design phase and construction phase. The construction phase shall start only after acceptance of complete final design and pre-construction submittals.
Design Acceptance and Construction Authorization The construction cannot start until all pre-construction submittals required by this contract are received and reviewed by the US Government and shown to meet the requirements of these Technical Requirements and the RFP package. The acceptance of the design and authorization to start construction will be issued by the NAVFAC EURAFSWA designated project manager.
The design shall meet all requirements of the RFP package. The drawings shall be as described below and as required to communicate the design to the US Government, end users, contractor’s staff and sub-contractors. Material selection, specifications and installation to be as described the in the Part 7. Engineering Systems Requirements (ESR), and in the Part 8. Performance Technical Specification (PTS), included below.
The ESR and the PTS of this document provide generalized technical requirements that apply to multiple facility types and include more requirements than applicable to this specific project.
Therefore, only the RFP requirements (as specified in Parts 1 through 6) that apply to the project provide a guideline for the design package. If an item that applies to the project is included in the ESR/PTS, the requirements of the ESR/PTS and applicable local codes shall govern. In case an item that applies to the project is NOT included in the ESR/PTS, the requirements of applicable local codes shall govern.
1.2 LEGAL AND TECHNICAL REQUIREMENTS
The contract is based on the following general requirements:
Strict compliance with American Contracting Regulations, including the contracting requirements of the Department of Defense, the US Navy and the US Naval Facilities Engineering Command (NAVFAC).
Strict compliance with Sierra Leonean Technical, Legal and Administrative requirements, which are applicable for the scope of work described in this PTS.
Compliance with Sierra Leonean safety regulations unless US safety are more stringent and not contrary to Sierra Leonean regulations.
The project is based on the principle of strict compliance with Sierra Leonean technical and administrative regulations, with US Contracting Regulations and with Sierra Leonean Safety
Attachment (1) to N33191-19-R-0411
1. Project Description p. 12/100 regulations, unless US regulations are more strict and not in conflict with Sierra Leonean safety regulations.
In case of conflict between Sierra Leone and US safety regulations, the contractor shall apply the Sierra Leonean regulations.
If the US regulations are stricter and not contrary to the Sierra Leonean regulations, then the contractor shall apply the US regulation.
The contractor shall inform the Contracting Officer of any conflict between Sierra Leonean and US safety regulations.
The contractor shall hire the services of a licensed architect/engineer in Sierra Leone to prepare the necessary designs and technical projects which are required for the scope of work included in this document for each facility.
Provide the final work as a complete and usable facility for each facility, including all items which are required by Sierra Leone regulations and which may not be described in this RFP. Technical details, items of work, permits or fees that are not explicitly described in this RFP, but which are necessary to provide fully operational and finished facilities shall be considered part of this contract.
1.3 SCOPE OF PROJECT
Furnish all necessary design, labor, materials, and supervision to provide complete and usable facilities including, but not limited to: Foundations, Structures, Superstructures, Interior Construction, Roof System, Finishes, Drainage System, Electrical System, Plumbing System, Exterior Area Settlement, Demolition of existing structures, Site Improvements and Other Work as required.
The work shall consist of the following (dimensions are indicative):
BASE BID - CLIN 001:
a. UPGRADE THE DOFFING/DECONTAMINATION to include:
A shower in a masonry shower box with epoxy painted walls and glass door
b. IMPLEMENT AN AMBULANCE DECONTAMINATION BAY SIZED 10 M X 8 M to include:
Shelter on the entire area Anti-slip epoxy coated reinforced concrete slab over the entire area Epoxy painted lockable masonry cabinet with waterproof metal door Two high pressure pumps connected to a chlorination tank Floor drainage system connected to wastewater system Electrical system with IP67 fixtures Plumbing system
c. INSTALL ADDITIONAL OVERHEAD WATER TANK to include:
18,000 liter CPVC (Chlorinated Polyvinyl Chloride) tank Reinforced concrete or metal structure to support the tank at least 2 m above ground piping and accoutrement to connect to water distribution system piping and accoutrement to collect water from public network piping and accoutrement to collect storm water from roof harvesting
d. EXPAND AND CORRECT THE BARRIER SYSTEM TO SEPARATE DIRTY AND CLEAN AREAS to include but not to be limited to:
Double barriers from the PPE warehouse to the fence wall and to the triage Double barriers from family center to the fence wall and to LC Double barriers along internal yard side of the ramp connecting LC and HC Barrier system corrections around the laundry to get a safe dirty-enter/clean-exit Any other barrier addition or modification required to insulate the dirty area
Attachment (1) to N33191-19-R-0411
1. Project Description p. 13/100
e. UPGRADE THE PERIMETER FENCING to include:
1 m high security metal railing on the top of the existing wall and gates (~400m)
f. PERFORM MINOR CORRECTION WORK to include but not to be limited to:
repair leaking roofs repaint spots on ceilings smooth and seal cracked or irregular surfaces to make them easy to sanitize replace or correct unsuitable fixtures (handles, door hardware, taps) install external basins (already at the site) install a tap with drainage close to the morgue correct the stairs at the southern end of HC Install rubber decelerators on the steeper part of the ramp connecting LC and HC deviate the lower part of the ramp from LC to HC and remove the unsuitable part implement a ramp on the dirty side of LC to allow patients to access the family center correct septic tanks that may contaminate the environment or the water table (if any) other minor repairs as needed grade the access way from public road (Mikalu Street) to main external gate to make it viable to ambulances pave the access way from the main gate to the drop-off and decontamination bay
g. SHELTER THE DROP-OFF AREA AND UNCOVERED PASSAGEWAYS to include:
a sheltering structure over the patient drop-off area (~ 100m) to be continuous with the triage roof a continuous sheltering structure over all uncovered passageways (~300m)
h. IMPLEMENT A DEDICATED VEHICULAR ACCESS TO THE MORGUE to include:
Vehicular gate in the existing external fencing on the main road About 10 m paved road from the gate to the morgue entrance Grade the access way from public road to the gate to make it viable to ambulances
i. CONSTRUCT A FAMILY VISITATION CENTER to include:
Stand alone block (~15 sqm) to be located between LC and northern fencing Separate access for relatives and patients with double barrier in the middle Electrical System
j. CONSTRUCT A PERSONAL PROTECTION EQUIPMENT [PPE] STORAGE WAREHOUSE to include:
Stand alone block (~30 sqm) to be located between HC and northern fencing No access to/from the dirty area Bolted metal shelves along the walls Electrical system
The new work shall result into complete, safe and usable facilities, whose interior spaces shall reflect the space tabulation and layout provided in Part 4 .
Design and construction details are provided in Part 5 , and specified in Parts 6, 7, and 8.
All buildings shall have concrete superstructure and masonry infill construction with basic finishes.
All buildings shall have a storm water drainage system to prevent erosion.
Attachment (1) to N33191-19-R-0411
1. Project Description p. 14/100
Optional Items:
The following items may be included pending funds availability (dimensions are indicative).
OPTION A – CLIN 002:
PAVE ALL CORRIDORS AND PASSAGEWAYS (~1,000 SQM)
to include:
Anti-slip epoxy flooring on all untiled external passageways, both on dirty and clean sides
OPTION B – CLIN 003:
PROVIDE INTERNAL YARD LANDSCAPING (~1,100 SQM)
to include:
Grade the soil to make the slope as even as possible and to prevent rainwater ponding Plant easy-to-maintain grass suitable to the soil and the climate allover the area Plant 10 easy-to-maintain trees suitable to the soil and the climate
OPTION C – CLIN 004:
BUILD 2 SENTRY-BOXES (~5 SQM)
to include:
A 1.5m x 1.5m sentry-box close to each gate on the public road Electrical system
OPTION D – CLIN 005:
PAVE ACCESS WAYS CONNECTING GATES TO PUBLIC ROAD (~40 SQM)
to include:
Paving suitable for vehicular access Curbstones on road sides
1.4 SIGNAGE
Project Sign
The Contractor shall provide a painted project sign to be located at the worksite as soon as the construction starts. The paint shall be water resistant and display the project name, the Sierra Leonean and American flags, and the wording explaining the cooperation between the two Governments.
The Contractor shall submit a proof of the sign for acceptance prior to construction.
See detailed requirements at par. 4.4
Dedication Sign The Contractor shall provide a project dedication sign (approximately 100 cm x 150 cm) at the project site at least 2 weeks prior to project completion.
The sign shall be constructed of sheet metal with a water resistant coating and affixed directly to the building at a location approved by the facility administrator and the COR.
The Contractor shall submit a proof of the sign for acceptance prior to manufacturing the sign, in accordance to the details described at par. 4.5
The sign location as well as any other signage required by local authorities shall be indicated on the site plan and agreed by the PM and the end user.
Attachment (1) to N33191-19-R-0411
1. Project Description p. 15/100
1.5 PROCEDURE
The construction phase shall start only once that the official Notice to Proceed with Construction (NTPC) is issued by the NAVFAC EURAFSWA Contracting Officer.
The NTPC will not be issued until all required pre-construction submittals are received and reviewed by the US Government and shown to meet the specifications of these Technical Requirements and the Solicitation package.
PRE-CONSTRUCTION SUBMITTAL REQUIREMENTS
The complete pre-construction submittal packages shall consist of:
Sierra Leonean License of Engineer/Architect in charge of Design Concept Design Final Design Construction Schedule Quality Control Plan Accident Prevention Plan SSHO Certification Construction permit(s) Worksite Delimitation Plan
All submittals shall be electronically submitted in pdf format to the PM/COR. The font sizes shall be readable when the file is printed on A4 paper.
See paragraph 6.3, 6.4 and 6.5 for detailed explanation about the pre-construction submittals.
Concept Design The concept design shall be completed within 90 calendar days of receipt of the award. The concept design is intended to assure all lay-out requirements are clearly met before the full design is developed. It shall identify site preparation, including items to be removed and to be kept. It shall provide the basic architectural design, including:
Current Site Layout plan with dimensions and distances Topographic Site Plan Final Site Layout plan with dimensions and distances Final Plans, Elevations and Sections of each new facility object of the contract.
The Concept Design shall be accompanied by the Geotechnical Report and by the
Sierra Leonean License held by the Engineer/Architect in charge of Design.
Government shall review the concept design submission for compliance with these Technical Requirements and the Solicitation package and provide written comments to the contractor.
See paragraph 6.5 for detailed explanation about the concept design.
Final Design The contractor shall have 120 calendar days to complete the design, incorporating all design review comments provided by the US Government. In the event the contractor does not concur with the US Government comments, the contractor shall notify the contracting officer in writing of the reasons for the non-concurrence.
The final design shall meet all the requirements identified in these Technical Requirements and the Solicitation package and shall include:
List of all drawings, with identifying code and title Civil Drawings (to be identified as C-##) Architectural Drawings (to be identified as A-##) Structural Drawings (to be identified as S-##) Plumbing Drawings (to be identified as P-##) Electrical Drawings (to be identified as E-##) Other Drawings (to be identified as O-##) All Calculations and Details required to validate the design.
The electronic file name associated to each drawing shall commence with the correspondent code, followed by a title shortly describing the content.
See paragraph 6.3, 6.4 and 6.5 for detailed explanation about the final design.
Attachment (1) to N33191-19-R-0411
1. Project Description p. 16/100
Construction Schedule The contractor shall have 360 calendar days to complete the construction work.
Within the timeframe allowed for the final design submission, the contractor shall prepare and submit a schedule of construction where the different work segments are identified and associated to the timeframe set for completion. The construction schedule shall state which work segments completion determines the achievement of the construction steps associated to the progressive invoicing (i.e. 10% (design completion), 25%, 40%, 55%, 70%, and 85% work progress). The final payment will be done on the facilities acceptance.
See paragraph 6.5 for more details about the construction schedule.
Quality Control Plan Within the timeframe allowed for the final design submission, the Contractor will prepare and submit a Quality Control Plan describing personnel, procedures, tests and installation techniques that he plans to perform to ensure the quality required by this document and his design is obtained.
Accident Prevention Plan [APP] Within the timeframe allowed for the final design submission, the Contractor will prepare and submit an APP describing procedures he plans to perform to ensure the safety of personnel and equipment on the job site. At a minimum, the safety plan must address types of personnel protective equipment to be used by personnel, types and frequencies of safety inspections, activity hazard analysis [AHA] to prevent safety incidents, and training utilized to familiarize employees with safety policies and practices.
See paragraph 6.5 for more details about the APP.
Site Safety and Health Officer [SSHO] Certification Within the timeframe allowed for the final design submission, the Contractor shall provide the certification for the Site Safety and Health Officer (SSHO) appointed to stay full time on-site ; the SSHO is required to have completed the OSHA 40-hour online training “EM385-1-1 Safety and Health (Sections 1÷34)”, which is offered for free at: http://www.oshatrain.org/pages/professional-training-courses.html) and to have at least one year of proved experience as SSHO in construction projects.
See paragraph 6.5 for more details about the SSHO.
Construction Permits as required by Sierra Leonean and KGH regulation Within the timeframe allowed for the final design submission, the Contractor shall verify that nothing prevents the construction from starting, shall submit copy of the construction permit, and copy of any agreement entered with the end user in order to coordinate the hospital operability during the construction work.
Worksite Delimitation Plan Within the timeframe allowed for the final design submission, the Contractor shall submit a site plan showing how the worksite will be delimited in the several phases of work, to make sure to prevent unauthorized access and to allow safe operation of the facilities not included in the contract.
INTERIM SUBMITTAL REQUIREMENTS
During construction, the Contractor is required to submit:
Bi-weekly work progress report with photos Monthly work man-hours report Test results as required per the contract At least 10 days prior to installation of all electrical components, plumbing fixtures, windows and doors and associated hardware, a sample (or catalog photo) must be shown to the COR for acceptance.
Possible construction schedule changes (to be motivated) Possible design changes (to be motivated) Invoices in accordance to work progress
COMPLETION SUBMITTAL REQUIREMENTS
Upon completion of project and prior to final payment, the Contract is required to submit:
Final as-built drawings
Attachment (1) to N33191-19-R-0411
1. Project Description p. 17/100
Operations and maintenance plan A telephone contact number available for the duration of the warranty period.
1.6 CONTRACT MILESTONES
The work required by this contract shall be carried out in 570 days from contract award. Possible time extensions may be allowed on KTR’s written request if a proved reason justifying the delay is acknowledged.
The key contract milestones as scheduled by this document are summarized in the following table:
TIMING
a CONCEPT DESIGN SUBMISSION Within 90 days of contract award b PRE-CONSTRUCTION SUBMITTAL COMPLETION Within 210 days of contract award c NOTICE TO PROCEED WITH CONSTRUCTION Upon acceptance of all required deliverables d CONSTRUCTION COMPLETION within 360 days of NTPC e FINAL INSPECTION Within 2 months of work completion f BENEFICIAL OCCUPANCY DATE [BOD] RELEASE On work acceptance (after all punch list items found during Final Insp. have been fixed) g WARRANTY PERIOD 1 year from BOD
1.7 STANDARD NOMENCLATURE
This is an American document, and this note is to define the way in which numbers are presented herein:
1,000 = one thousand 3,500 = three-thousand five-hundred
1.08 = one and eight hundredths
0.1 = one-tenth
~~~ End of Part 1 ~~~
Attachment (1) to N33191-19-R-0411
2. Project Objectives p. 18/100
2 PROJECT OBJECTIVES
2.1 MISSION STATEMENT
DoD humanitarian assistance activities were first authorized by US Congress in 1986. In FY 1996, DoD was permitted to fund a wider variety of HA activities, including using contracts and deployment of U.S. Government personnel to conduct specific humanitarian projects.
Typical projects include the refurbishment or the new construction of medical and school facilities, digging of wells, improvement of sanitary facilities, and training of host country personnel in internally displaced persons/refugee repatriation operations and in disaster relief and emergency response planning.
The DoS, in an attempt to assist in the upgrade of a DoD Humanitarian Assistance Program, is funding and coordinating the project which is the subject matter of this contract.
NAVFAC EURAFSWA has been designated as the Construction Agent for this project.
2.2 FACILITY FUNCTION
The hospital complex is situated in a region exposed to viral hemorrhagic fever outbreaks. The upgrade of the present Lassa Fever Ward into a facility suitable even to Ebola Fever patients will create opportunities for containing the outbreaks and to offer adequate care to patients as well as safety to health workers.
2.3 PROJECT SPECIFIC PRIORITIES
Sustainable Design Integrate sustainable principles into the design, development and construction of the project.
Reduce the total cost of ownership of the facility using a whole building, life-cycle approach.
Provide integrated sustainable design strategies and features to minimize the energy consumption of the facilities; conserve resources; minimize adverse effects to the environment; and improve occupant productivity, health, and comfort.
Energy Conservation Integrate energy conservation principles into the design, development and construction of the project. Reduce the total cost and consumption of energy in the facility using a whole building approach.
2.4 APPROPRIATE DESIGN
The design is to maintain an indigenous character. The new facility’s style and finishes shall resemble those of Lassa Ward.
As much as possible, materials are to be available locally to promote the local economy and to take advantage of the skills and experience of local trades-persons. Construction methods are to be in-line with those used locally to take advantage of the skills and experience of local trades-persons.
2.5 WORKFLOW PROCESS - HOURS OF OPERATION
The work of this contract is to be done during the regular working hours.
The effect of noise and dust on people in the surrounding area shall be kept as minimal as possible.
If needs arise to work other than normal hours, the schedule shall be coordinated with the facility owner, and approved by or COR.
~~~ End of Part 2 ~~~
Attachment (1) to N33191-19-R-0411
3. Site Analysis p. 19/100
Drop off area
HC Ward
Water tank
LC Ward
Morgue Laundry
Ramp
Internal Gate
Triage
Main Gate
Doffing
Clean path
Dirty path
KGH boundaries
LF Ward Compound
3 SITE ANALYSIS
3.1 EXISTING SITE CONDITIONS
The Kenema Government Hospital is a large enclosed complex located in Kenema and it is easily accessible from the city roads.
The area occupied by the lassa fever ward is a fenced compound situated at the GPS coordinates:
7.874003, -11.183762, currently accessible from the KGH through an internal gate, and from the public road named Mikalu Street through a main gate which is currently not connected to the road by any drivable passageway.
The LFW complex is composed of Triage, High Containment [HC], Low Containment [LC], Doffing, Laundry, Incinerator, Morgue and Admin Building, plus concrete passageways connecting all facilities in accordance to a clean/dirty circulation system intended to prevent the infectious diseases from spreading out.
The satellite view with details is reported on the side.
The fenced ward area is highlighted with a purple dotted square, and the main facilities are indicated in blue.
The clean and dirty path are roughly indicated in green and red respectively, and the arrows indicate the circulation direction.
A wider satellite view showing the entire KGH compound is reported below:
Attachment (1) to N33191-19-R-0411
3. Site Analysis p. 20/100
CURRENT CONCEPT
CLEAN/DIRTY CIRCULATION
LAYOUT
FACILITY FOOTPRINT:
A scaled drawing with exact dimensions showing the current site lay-out (including position and dimensions of surrounding existing buildings, obstacles, access roads, walkways, and perimeter fence) shall be included in the concept design.
Below a scheme of the existing facilities is provided (dimensions are indicative):
Attachment (1) to N33191-19-R-0411
3. Site Analysis p. 21/100
LC Ward
Laundry
Incinerator
Barriers to be repositioned to separate clean and dirty paths
VIEW FROM NORTH-EST
HC Ward LC Ward Passagew ays to be sheltered
Clean Path
HC Ward Passagew ays to be sheltered
Clean Path
Incinerator
Concrete pathway to be reshaped to allow sufficient distance from clean area
3.2 PHOTO DESCRIPTION
The following pictures try to provide a description of the present Lassa Fever Ward complex, including the dirty and clean pathways that shall be made completely separated in the VHF Ward:
VIEW FROM NORTH b/w Admin and LC
Admin
LC Ward
LC Ward
Clean Path
Admin LC Ward
Internal Yard
VIEW FROM NORTH-EST
LC Ward HC Ward
Passageways to be sheltered
Clean Path
VIEW FROM SOUTH
Admin Bldg LC Ward
Laundry
HC Ward
Doffing
Passageways to be sheltered
Dirty Path
Clean Path
Dirty Path
Clean Path
Laundry
Barriers to be repositioned to separate clean and dirty paths
Incinerator
Concrete pathway to be reshaped to allow sufficient distance from clean area
VIEW FROM NORTH b/w HC and Admin
HC Ward
Admin
Clean Path
Attachment (1) to N33191-19-R-0411
3. Site Analysis p. 22/100
Example of decoration for kid’s room Drainage channel along the compound fencing
Drainage channels around RMH buildings
View to the morgue from
VIEW FROM NORTH b/w Admin and LC
Incinera Morgu
Laundry
View from West to the main gate
Main
Admi
Tri ag e
Clean Path
Main
Admi
Tri ag e
Untiled floor
View from west to the main gate
Main Gate
Admin
Triage
View from Public Road to the main gate
View from LC to west Dirty side of LC ward
Ramp to be built here to allow patient access to the family center
Ramp to be built here
View to north from the morgue
Dirty Path
View to north from the drop-off area
Main Gate
Drop-off area to be sheltered
Triage
View to south from the drop-off area
HC Ward
Dirty Path
Dirty Path Passageway to be sheltered
View to the morgue from
Incinerator Morgue
Laundry
Clean Path
Attachment (1) to N33191-19-R-0411
3. Site Analysis p. 23/100
Dirty traps in the ward rooms and restrooms to be flattened/smoothened and sealed to prevent bacteria and virus proliferation
Ceiling spots due to roof leakage in the Admin Bldg Ceiling spots due to roof leakage in a Ward room
Below are more photos showing examples of items that require corrections wherever they are in the present LF ward:
Attachment (1) to N33191-19-R-0411
3. Site Analysis p. 24/100
3.3 SITE DEVELOPMENT REQUIREMENTS
An example of the VHF layout in line with the contract terms is sketched below.
Exact layout shall be determined to best fit the topography and the operability, and shall be coordinated