18R0212_Moldova_Schoosl_-_Attachment_1_-_PTS.pdf
PDF 5 MB Posted
- Solicitation number
- N3319118R0212
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 18R0212_Moldova_Schools_-_Attachment_3_~_Data_Sheet.docx | DOCX document | |
| N3319118R0212_Moldova_Schools_-_RFP.pdf | ||
| 18R0212_Moldova_Schools_-_Attachment_2_-_PPI.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662 Sanitation Improvements - Design and Build (Moldova)
Version 001
EUCOM Humanitarian Assistance Program
DROCHIA KINDERGARTEN#08
ELIZAVETA KINDERGARTEN
NICORENI MIDDLE SCHOOL
SANITATION IMPROVEMENTS
DESIGN AND BUILD (MOLDOVA)
OHASIS: MD-SubH-2017-00026661
MD-SubH-2017-00026665 MD-SubH-2017-00026662
Dec 2017
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
Contents
1. TAXATION 4
2. CONTRACT DESCRIPTION
2.1 LOCATION OF JOB SITES
2.2 LEGAL AND TECHNICAL REQUIREMENTS
2.3 MEASUREMENTS AND QUANTITIES
2.4 CONSTRUCTION PERMIT OR AUTHORIZATION
2.5 APPLICABLE REQUIREMENTS / STANDARDS
2.6 GENERAL CONTRACT DESCRIPTION
3. DROCHIA KINDERGARTEN#08 – BASE-BID
3.1 DROCHIA KINDERGARTEN – GENERAL SCOPE OF WORK OF BASE-BID
3.2 BATHROOM RENOVATION
3.2.1 DESIGN AND LAYOUT
3.2.2 GENERAL REQUIREMENTS FOR BATHROOMS
3.2.3 BATHROOMS NOT REQUIRING COMPLETE RENOVATION
3.3 KITCHENETTE RENOVATIONS
3.4 DESCRIPTION OF WORK BY GROUP
3.5 WATER AND SEWER OUTSIDE THE AREAS TO BE RENOVATED
3.6 NEW ROOF OVER TWO BLOCKS
3.7 ACT OF ACCEPTANCE
3.8 COMMEMORATIVE PLAQUE
3.9 SCAFFOLDING AND FALL PROTECTION
4. ELIZAVETA KINDERGARTEN – BASE-BID
4.1. ELIZAVETA KINDERGARTEN – GENERAL SCOPE OF WORK OF BASE-BID
4.2. KITCHEN AREAS RENOVATION
4.2.1. KITCHEN REQUIREMENTS – “TECHNOLOGIC PROJECT”
4.2.2. GENERAL TECHNICAL REQUIREMENTS FOR THE KITCHEN AREAS . 46
4.2.3. PICTURES OF THE KITCHEN AREAS
4.3. RENOVATION OF BATHROOMS - GENERAL
4.3.1. DESIGN AND LAYOUT
4.3.2. GENERAL REQUIREMENTS FOR BATHROOMS
4.4. KITCHENETTE RENOVATIONS
4.5. DESCRIPTION OF WORK BY ROOM
4.6. EXTERIOR SEWER MANAGEMENT
4.7. ACT OF ACCEPTANCE
4.8. COMMEMORATIVE PLAQUE
4.9. SCAFFOLDING AND FALL PROTECTION
5. NICORENI MIDDLE SCHOOL – BASE-BID
5.1. NICORENI MIDDLE SCHOOL – GENERAL SCOPE OF WORK OF BASE-BID
5.2. BATHROOMS AND MODIFICATIONS TO CLASSROOMS
5.2.1. TECHNICAL REQUIREMENTS FOR BATHROOMS
5.2.2. TECHNICAL REQUIREMENTS FOR 2 CLASSROOMS
5.2.3. PICTURES OF THE AREAS
5.3. NEW DINING ROOM AND MODIFICATIONS TO KITCHEN
5.3.1. MODIFICATIONS AND IMPROVEMENTS TO THE KITCHEN
5.3.2. NEW DINING ROOM
5.3.3. PICTURES OF THE KITCHEN AND DINING ROOM
5.4. NEW SEWAGE AND DRAINAGE MANAGEMENT SYSTEM
5.5. WATER CONNECTION
5.6. ELECTRICAL CONNECTION
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
5.7. COMMEMORATIVE PLAQUE
5.8. SCAFFOLDING AND FALL PROTECTION
6. DROCHIA KINDERGARTEN#08 – CONTRACT OPTION-1
6.1. THERMAL FAÇADE OVER 50% OF THE EXTERIOR FAÇADE OF THE KINDERGARTEN 87
6.2. PICTURES TO SHOW DESCRIPTION OF FAÇADE WORK
6.3. ADDITIONAL ROOFING WORK
7. ELIZAVETA KINDERGARTEN – CONTRACT OPTION-2
7.1. EXTERIOR CANOPY (7 X 26 M²)
7.2. PLAYGROUND AREA (200 M²)
7.2.1. FACILITY KI2 – CHILDREN CLIMBING-SLIDING
7.2.2. FACILITY IG1 – CHILDREN LABERYNTH
7.2.3. FACILITY IG2-1 – PANNEL
7.2.4. FACILITY L08-G – SWING
7.2.5. FACILITY B02 – COMBINED GAZEBO
8. NICORENI SCHOOL – CONTRACT OPTION-3
8.1. EXTERIOR COVERED STAIRWAY
8.2. NEW FLOORING FOR ADDITIONAL AREAS FOR YOUNGEST CHILDREN – 160 M² .. 120
8.3. NEW LED LIGHTING FOR THE SCHOOL FOR YOUNGEST CHILDREN
8.4. PICTURES TO DESCRIBE THE WORKS
9. PROCEDURE 122
9.1. PRINCIPLES
9.2. START OF CONSTRUCTION
9.3. GENERAL TECHNICAL REQUIREMENTS
9.4. CONSTRUCTION/DESIGN SCHEDULE AND CONTRACTUAL MILESTONES
9.5. CONSTRUCTION SCHEDULE (BAR CHART IS AUTHORIZED)
9.6. ACCIDENT PREVENTION PLAN / SAFETY PLAN
9.7. LANGUAGE 125
9.8. DELIVERABLES AND TECHNICAL DOCUMENTATION:
9.9. PICTURES: 127
9.10. QUALITY CONTROL PLAN:
9.11. CONSTRUCTION SIGN (3 SIGNS REQUIRED)
9.12. PAYMENT 129
9.13. SCHEDULE OF PRICES
9.14. OCCUPANCY OF THE BUILDING
9.15. PAYMENT FOR UTILITIES
9.16. DAMAGES/IMPACT TO EXISTING FACILITIES
9.17. CLOSE-OUT PROCEDURE
10. GENERAL WORK REQUIREMENTS
10.1. PROHIBITED ITEMS
10.2. RESPONSIBILITY OF NEW MATERIALS
10.3. RESPONSIBILITY AND OWNERSHIP OF REMOVED MATERIALS
10.4. SAFETY AND PROTECTION
10.5. CERTIFICATIONS, LICENSES, PERMITS, FEES, ETC
10.6. TECHNICAL DOCUMENTATION
10.7. COORDINATION
10.8. SPECIAL SITE CONDITIONS
10.9. CLEANING
10.10. SPARE PARTS
10.11. WARRANTY AND ACCEPTANCE
11. ANNEX 1: GUIDELINE TO PREPARE THE QUALITY CONTROL PLAN
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
1. TAXATION
This construction/renovation contract is subject to the Moldovan Government Decision No.
246 of 08.04.2010 on the application of the zero rate of VAT on the supply of goods and services in the country and providing tax and customs exemptions for ongoing projects of technical and investment assistance covered under the international treaties to which the Republic of Moldova is part. As such, the US Government will not pay VAT on any invoices related to this construction contract. The contractor is required to coordinate with the US Embassy and with competent Moldova authorities in order to implement the procedures as required by the Moldovan Government in order to obtain the VAT TAX EXEMPTION that applies to this contract as detailed and specified in the referenced Moldovan regulations.
Contractor shall start the tax exemption within 7 days after award of this contract. Contractor is required to make all necessary coordination and to allow for time for approval of the VAT Tax Exception. A minimum of 3 months and a maximum of 5 months are estimated for processing all required documentation after its submission until the name of the Prime Contractor is published on the official Moldovan Government publication "Monitorul Oficial". The contractor should have the tax exemption process finalized before they start actual construction works and before they contract for any service related with this contract.
It is the contractor's responsibility to properly and adequately follow the requirements of the applicable Moldovan regulations in order implement of a tax free contract environment as it may be applicable for the prime contractor, subcontractors and suppliers. Per existing legislation the Moldovan Government will not register for VAT exemption any of the subcontractors, for any of the projects. The US Government SHALL NOT be responsible to pay any taxes for this contract resulting from a contractor's failure to implement the proper procedures or from not complying with the timelines or from not following any other requirements of the Moldovan regulations which guarantee tax exemption exclusively as detailed and in compliance with their regulations.
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
2. CONTRACT DESCRIPTION
This contract includes all necessary permitting, design, construction and acceptance works in order to provide the sanitation improvements and other works described in this document, providing perfectly finished, certified and fully operational facilities.
This contract includes 3 separate and independent projects. Each project includes the design and the construction works required to provide the sanitation improvements and other works specified for each facility.
This contract includes all necessary administrative, design and construction works which are absolutely necessary in order to provide the work described in this document for each facility and as required by Moldovan regulations. This contract includes paying for all necessary official fees and inspection services required by these projects as required by Moldovan regulations.
All quality finishes and details described for one project are applicable for the other projects and vice versa, when these details are specified in one project but not in the other.
The contractor shall strictly follow the Moldovan technical and administrative regulations for all aspects of this project. Portions of this design-build contract require third party approvals and/or “expertise” reviews and approvals. It is the contractor’s requirement as part of this contract to coordinate with all necessary agencies and departments, and to pay for any third party and “expertise” that is required, and to pay for any official fees, in order to implement this design-build contract in strict compliance with Moldovan regulations. Contractor is responsible to pay for all applicable fees and inspections required by the scope of work of each facility.
NAVFAC will not provide final acceptance until the competent Moldovan authorities do not formally approve the works in this project and therefore any technical or administrative or construction details or elements, which are necessary by Moldovan regulations in order to formally approve the works are considered to be part of this project, even if not explicitly described within this document.
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
General location of 3 sites
2.1 Location of job sites
The 3 facilities are located in Drochia, Elizaveta and Nicoreni, as shown in the location maps included in this paragraph:
GENERAL LOCATION OF
3 PROJECT SITES IN
NORTHERN MOLDOVA
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
Location of job sites and distances between them
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
2.2 Legal and Technical Requirements
The contract is based on the following general requirements:
- Strict compliance with American Contracting Regulations, including the contracting requirements of the Department of Defense, the US Navy and the US Naval Facilities Engineering Command (NAVFAC).
- Strict compliance with Moldovan Technical, Legal and Administrative requirements, which are applicable for the scope of work described in this document.
- Compliance with Moldovan safety regulations, unless the US Safety regulations included in Manual EM385-1-1 are more strict and not in conflict with Moldovan regulations. In this last case, the US Safety regulations shall apply.
The project is based on the principle of strict compliance with Moldovan technical and administrative regulations, with US Contracting Regulations and with Moldovan Safety regulations, unless US regulations are more strict and not in conflict with Moldovan safety regulations. In case of conflict between Moldovan and US safety regulations, the contractor shall apply the Moldovan regulations. If the US regulations are stricter and not contrary to the Moldovan regulations, then the contractor shall apply the US regulation. The contractor shall inform the Contracting Officer Representative (COR) of any conflict between Moldovan and US safety regulations.
The contractor shall hire the services of the necessary licensed architects/engineers in Moldova to prepare the necessary designs and technical projects which are required for the scope of work included in this document for each facility.
Provide the final work as a complete and usable facility for each facility, including all items which are required by Moldova regulations and which may not be described in this Request for Proposal (RFP). Technical details, items of work, permits or fees that are not explicitly described in this RFP, but which are necessary to provide fully operational and finished facilities shall be considered part of this contract.
2.3 Measurements and Quantities
This contract complies with the US Contracting Regulations, and as such, measurements and quantities of materials and work are not provided, and if any are provided, they are only approximate and the contractor shall be responsible to verify them on site. The contractor needs to visit the job site in order to perform the necessary measurements and to observe the existing field conditions in order to prepare their cost proposal.
Several pictures are included in these Performance Technical Specifications (PTS). These pictures do not guarantee the existing conditions of the facilities at the time to prepare the cost proposal, and they are only a tool to describe the responsibilities of the contractor. The contractor is responsible to visit the sites in order to measure and quantify the required work, as well as to verify the existing conditions, prior to the submission of their cost proposal. The US Government is not responsible for any mistake in the contractor’s measurements or assumptions of field conditions.
IT IS ABSOLUTELY NECESSARY FOR THE CONTRACTOR TO VISIT THE JOB SITES IN ORDER TO
MEASURE AND TO QUANTIFY THE WORK INCLUDED IN THIS PROJECT AND TO VERIFY REAL
FIELD CONDITIONS. THIS PROJECT DOES NOT INCLUDE ACCURANTE MEASUREMENTS OF
QUANTITIES.
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
2.4 Construction Permit or Authorization
The contractor shall obtain formal written authorization from the competent Moldovan authority to perform the works included in the scope of work of this project in order for the Contracting Officer to authorize the start of works with the Notice to Proceed notification (NTP). Separate permits and/or construction authorizations shall be required for each one of the sites
This is a design-build contract.
The contractor is required, as part of this contract, to prepare all documentation, designs, reports, information, drawings, coordination and approvals by experts or monitoring entities, and everything that may be necessary as required by Moldovan regulations, in order to obtain these Permits or Authorizations. The contractor is responsible to pay for any third party inspection or expertise or any other official fee that may be required by Moldovan regulations for the scope of work of this project.
The contractor is also responsible for final acceptance of the works by the competent Moldovan authority. In case the beneficiary needs to call for this official acceptance, the contractor shall be responsible to coordinate with the beneficiary and to provide whatever information or documentation may be required by the beneficiary or by the competent approving authority.
It is absolutely necessary for the contractor to be familiar with the technical and administrative requirements of Moldovan legislation and regulations, in order to obtain all the necessary construction permits and licenses to execute this project.
2.5 Applicable Requirements / Standards
The project is based on the principle of strict compliance with Moldova technical and administrative regulations, with US Contracting Regulations and with Moldovan Safety regulations unless the US safety regulations are more strict and not in conflict with the Moldovan safety regulations.
The work shall meet all requirements of this Request For Proposal (RFP) package. Drawings to be as required in this RFP and with the necessary details and previous approvals (experts or monitoring entities) to submit the designs to the US Government, Local Moldovan Administration, final users, contractor’s staff and sub-contractors. Material selection, specifications and installation to be as described in this Performance Technical Specification (PTS). The Performance Technical Specification (PTS) are a guideline for the design package:
- If an item in the project design is included in the PTS, the requirements of the PTS, applicable local Moldovan codes and regulations, and international codes shall govern.
- If an item in the project design is NOT included in the PTS, the requirements of applicable local Moldovan codes and regulations, and international codes shall govern.
Provide the final works as a complete and usable facility for the school and kindergartens, including all required items not described in this RFP. Technical details, items of work, permits or fees that are not explicitly described in this RFP, but which are necessary to provide a fully operational and finished facility shall be considered part of this contract.
Any work not explicitly included in the scope of work of this project, but which is absolutely necessary to have perfectly operational facilities, as required by Moldovan regulations, shall be treated as part of the requirements of this contract.
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
2.6 General Contract Description
The contract includes the necessary work in order to perform the following general items of work for each education facility. This paragraph only includes conceptual description of general works.
The actual detailed scope of work included in this contract is included in their corresponding paragraphs within this document.
DROCHIA KINDERGARTEN#08 – General Scope of Work in Base-Bid
- Bathrooms: Complete renovation of 7 bathrooms
- Kitchenettes: Complete renovation of 3 kitchenettes
- Sewer lines: Complete replacement of all metal sewer lines for bathrooms and kitchenettes.
- Roof: Provide new metal roofing over 2 blocks on the facility.
DROCHIA KINDERGARTEN#08 – General Scope of Work in Contract Option-1
- Roof: Provide new metal roofing over one additional block in the kindergarten complex.
- Thermal Facade: Provide thermal façade over 50% of the façade surfaces of the kindergarten complex.
ELIZAVETA KINDERGARTEN – General Scope of Work of Base-Bid
- Kitchenettes: Complete renovation of 4 kitchenettes
- Sewage system: Provide new complete sewage system for the facility
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
ELIZAVETA KINDERGARTEN – General Scope of Work in Contract Option-2
- Metal Canopy: New metal canopy of 182 m²
- Playground area: New playground area of 200 m² with its corresponding installations.
NICORENI MIDDLE SCHOOL – General Scope of Work
- Bathrooms for two sections of school: youngest and oldest children, female teachers and handicapped children and male teachers.
- Renovations to Dining Room and Kitchen
- Sewage system
NICORENI MIDDLE SCHOOL – General Scope of Work in Contract Option-3
- New stairway to connect both floors of the school
- Additional flooring (160 m²)
- Additional lighting
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
Kindergarten#08 in Drochia
3. DROCHIA KINDERGARTEN#08 – BASE-BID
3.1 DROCHIA KINDERGARTEN – General Scope of Work of Base-Bid
The contract includes the items of work specified in this paragraph, which include the necessary work in order to have perfectly operational facilities.
The contract includes in its Base-Bid the following general works:
- Kitchenettes: Complete renovation of 3 kitchenettes
- Sewer lines: Replacement of all metal sewer lines from bathrooms and kitchenettes in the building.
- Roof: Provide new metal sheet roofing over 2 blocks on the facility.
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
3.2 Bathroom Renovation
The works includes everything necessary to have perfectly operational and modern bathroom facilities for the children in the areas described in the table below. Kitchenette renovation is described in the following paragraph, but the ones included in the contract are also described in the table below.
Group Name Bathroom Kitchenette Notes Stinjinei Not requiring renovation Not requiring renovation Need to change sewer lines from above Vasilioc Not requiring renovation Not requiring renovation Need to change sewer lines though floor Clopotsel Complete renovation
(approx. 6x2.1) Not requiring renovation
Fialca Not requiring renovation Complete renovation (approx. 1.6 x 2.6)
Need change sewer lines from above
Gladiola Complete renovation (approx.. 5.5 x 2.7)
Not requiring renovation Reutilize toilets Need sewer lines to street
Ghiotel Not requiring renovation Not requiring renovation Landish Complete renovation
(approx. 3.3.x3.1 + 2.1x2.1)
Complete renovation 2.0 x 2.1
Cimbrisor Not requiring renovation Not requiring renovation Romaartsa Complete renovation
(approx. 2.6 x 5.6) Not requiring renovation Bathroom partially renovated, problems with piping.
Viorele Complete renovation Not requiring renovation Reutilize 2 toilets Medical point Not requiring renovation Not applicable Nezabudca Complete renovation
(approx. 5.5x2.7) Complete renovation (approx. 2x.2.15)
Garofitsa Complete renovation (approx. 5.5.x 2.7)
Not requiring renovation Bathroom with same size as above but different layout
Busivoc Not requiring renovation Not requiring renovation Albastrele Not requiring renovation Not requiring renovation Teachers’ Not requiring renovation Not applicable
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
Sketch showing approximate layout for bathroom in Clopotsel Group
Sketch showing approximate layout for bathroom in Gladiola Group
3.2.1 Design and Layout
This is a design build. Each bathroom is different, with general overall sizes described in the table in the previous paragraph.
Each bathroom shall be designed in compliance with Moldovan regulations for kindergartens. This means that as a minimum each bathroom shall be provided with:
- 3 toilet seats sized for young children with partitions
- 3 sinks over continuous countertop
- Mirrors over the sinks
- One shower plate
- 2 electric hand driers (air blowers)
- Special kindergarten bathroom furniture
- Floor drain
- Faucet for janitorial purposes.
The contractor’s architect or design team shall provide sketches for each of the bathrooms to be renovated. The design shall be certified by the contractor’s design team or responsible individual, and it shall be formally and officially approved by competent Moldovan authorities.
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
Sketch showing approximate layout for bathroom in Landish Group
Sketch showing approximate layout for bathroom in Romaartsa or Violere Groups
Sketch showing approximate layout for bathroom in Nezabudca Group
Sketch showing approximate layout for bathroom in Garofitsa Group
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
3.2.2 General requirements for bathrooms
Design: Prior to performing any works on the bathrooms, the contractor shall hire the services of a licensed architect in Moldova to perform the design of the bathrooms, including the interior design (i.e. combination of colors for the tiles). No work shall be authorized to start until the contractor’s design is accepted by the Contracting Officer Representative.
The work includes:
- Demolitions: Complete demolition of all areas to be renovated, including heating systems, plumbing appliances, electrical installations, internal partitions, wall tiles, paint and plaster, and everything else within the bathroom areas.
- Floor: Provide new floors at the same height as the adjacent room. This means that the contractor shall remove the existing flooring surface before applying the new one. The installation of the new floor tiles over the existing flooring is not acceptable.
Provide new grès tiles of minimum dimension 40x40 cm, sloped towards new floor drains.
Install floor tiles diagonally with respect to the walls. Provide supporting mortar base as necessary and recommended by the floor tile manufacturer. Provide non slippery tiles.
Color and pattern to be selected by the beneficiary among ample selection to be provided by the contractor.
The floors shall be sloped towards the floor drain. Testing of the slopes shall be done by pouring one bucket of water in those rooms with water supply and waiting 5 minutes. After this period there shall be no sitting water on any surface of the new floor tiles (except the entrance tiled ramp).
Floor Material: Minimum size 40x40 cm. Porcelain stoneware (non-glazed) floor tiles of grès porcelain stoneware, laser cut, with water resistant joints. Grès Porcelain stoneware is a ceramic with a compact, hard, colored and non-porous body. The word “grès” means that the ceramic body of the tile is extremely vitrified, that is to say compact, hence the exceptional great resistance. The result is a lean clay body, little refractory, fired in a kiln (at 1200-1400 C°) until it reaches a non-porous vitrification and a complete water-proofing.
Provide wall base along all walls, with special wall trim pieces similar to the floor tiles.
Cutting floor tiles to be used as wall base is not acceptable.
- Floor drains: Provide minimum of one floor drain per bathroom room. Provide stainless steel floor drain with integral p-trap to avoid bad smells.
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
- Walls: Provide ceramic tiles from floor wall base to new ceiling surface. New walls shall be perfectly leveled. For that reason, the contractor shall estimate that they will need to remove all plaster on all walls in order to provide perfectly leveled plaster surface on which to attach the new wall tiles. The use of gypsum board to level the walls is not authorized.
The contractor shall also repair any cracks of structural defects before leveling the walls with the new plaster.
For the interior of the bathrooms, the contractor shall provide ceramic tiles from the floor (wall base ceramic tile) to the new ceiling surfaces. Ceramic tiles shall with minimum dimension 20x30 cm. Provide combinations of 3 colors and patterns per room, to be selected by beneficiary among ample selection to be provided by the contractor.
The edges of the ceramic tiles shall all be protected by exposed metal corner guard as shown in pictures in the following pages. Plastic corner protection is not authorized. No edge of any tile shall be exposed to the view. Provide non-glazed ceramic tiles (for walls) with water resistant joints, glued onto the surface of the wall. Provide with metal corner guards embedded in the wall tiles.
All installations (heating, electrical, water, sewer, drainage, vent,…) shall be covered under the new wall surfaces. No installations shall be visible once the project is finished, but they shall be provided with the necessary hatches for inspection and maintenance.
Provide perfect connection between piping and wall tiles by the use of properly attached stainless steel escutcheons.
- Masonry Partitions for New Layouts: New partitions required by new layout shall be made of thin masonry wall, not wider than 20 cm. Cover all surfaces with new ceramic tiles as with the rest of the walls.
- Ceiling: Provide acoustic suspended ceiling system (Armstrong type) over all internal areas of the bathrooms.
Prior to the installation of the new false ceiling surfaces, the contract includes removing the defective plaster, fixing any structural defects, and covering all ceiling surfaces with new reinforcing plaster
- Ventilation: As required by Moldovan regulations.
- Windows: Most windows were replaced by the beneficiary. The contract only includes replacing any remaining wooden doors and removing and reinstalling the existing PVC windows in order to provide a perfect connection between the existing windows and the new wall surfaces. For those windows to be replaced, the contractor shall provide new windows with similar quality as the ones replaced by the beneficiary.
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
- Doors: All entrance doors of the bathrooms shall be replaced with new. Provide new PVC doors without bottom threshold and without locks. The doors shall be installed without bottom threshold to avoid tripping hazards and to allow for proper ventilation. Provide stainless steel threshold to connect the new floor and the existing floor if necessary. Doors and frames to be delivered by the manufacturer as one complete unit, not to be assembled by the contractor on site. Provide PVC door trims. Do not use any wood material for the new doors.
Note: The width of the doors shall be minimum 90 cm of free opening.
Note: The location and width of the doors may be modified as a result of the contractor’s architect design.
- Heating: Provide new heating radiators, bimetal type. Provide new heating piping within the renovated areas recessed within the new walls or floors. Connection points between the existing and the new piping shall be exposed, or next to an access hatch for inspection and maintenance. Provide each radiator with isolation and control valves. Size and location of radiators shall be designed by the architect hired by the contractor, but as a minimum they shall be provided under each window. The radiators shall be supported by the walls, without any contact with the floor.
- Electrical: Provide complete new electrical installation for all new bathrooms. To supply electricity to the renovated areas, the contractor shall provide a new electric panel in the renovated areas, to be connected with the main electric panel of the kindergarten, immediately after the electric meter. This is to guarantee that 100% of the electrical installation for the renovated areas shall comply with European/Moldovan standards, even if the rest of the kindergarten does not. All electrical installation in the renovated areas to be recessed along the walls, ceilings, floors, so that no electrical cables or conduits are visible, including conduits, junction boxes, lighting fixtures, switches, electric panels, etc.
The electrical installation shall include:
o Designed and installed in accordance with European standards.
o New electric circuit from main school electric panel to be installed along the walls of the school, and covered by standard PVC channel for hiding cables.
o All electrical equipment to be CE certified.
o Provide differential protection of maximum 30 mA for each one of the bathrooms.
o All electrical installation within the areas to be renovated to be done in conduits recessed within the walls. Electric panels, cables, junction boxes, boxes for the switches, receptacle boxes,… shall all be installed recessed within the new walls, which are to be covered with ceramic tiles or above the suspended ceiling. Direct installation of the cables under the plaster is not acceptable. All cables to be installed under electric conduit, even above the false ceiling.
o New recessed LED lighting fixtures, provided with individual switches for each one of the rooms. One of the reasons to install false ceiling is to recess all lighting fixtures. Lighting fixtures to be provided with washable diffuser. Provide illumination levels as required by Moldova regulations.
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662 o Automatic start hand driers. Provide stainless steel automatic hand driers.
Hardwire to the walls, so that the cables are not exposed to the view. Provide two units per bathroom, one for the teacher’s bathroom and one for the handwashing area at the required height for children. Total of 6 units required.
o Provide individual circuits for lighting and power, so that when all hand driers are operating, there is no dimming in the lighting of the rooms. Voltage drop to be less than 3%. This will be tested for acceptance of electrical installation.
For any electrical installation that may be required outside the areas to be renovated, the contractor shall provide new cables installed under PVC channels properly attached to the existing walls and ceiling surfaces in order not to damage the existing walls.
- Water supply within the renovated areas: All water lines for the bathrooms shall be provided using water piping rated for domestic water use, or other material authorized by Moldovan regulations for such use. Within the renovated areas, the contractor shall design the size of the piping in order to provide proper flow and pressure when all toilets valves and faucets are open. Provide all water pipes inside of the bathroom areas recessed within the walls and floors, so that they are not exposed to the view. Provide standard stainless steel faucets single lever for cold and hot water control.
Connect water supply line from water meter or to another point within the kindergarten that meets Moldovan standards. Once the work is completed, the water installation shall comply with Moldovan standards. It is required that the contractor provides a certificate of compliance with Moldovan regulations for all works in this project in general, and with the water supply system in particular.
- Valves: Provide shut off valves for each individual plumbing appliance (sink, toilet,…) and for each room.
- Hot water: Provide one single electric hot water heater of minimum 50 liters capacity for every two bathrooms. Connect the kitchenette hot water to the new boiler, even if the kitchenette renovation in the group is not part of the contract.
- Janitorial faucet: Provide one wall mounted water faucet in each bathroom with cold and hot water (or each floor) for janitorial purposes (filling is water buckets).
- Sewer/drainage/vent inside the building: The contract includes new sewer/drainage/ventilation PVC piping for the bathrooms connected with the roof of the building. If this requires breaking through the roof deck in order to install the new pipes, the contractor shall be responsible to repair as necessary the roof waterproofing in those affected roof areas. All sewer pipes in the renovated areas to be covered by masonry wall or partitions so that the sewer lines are not exposed to the view in the renovated areas.
This includes the drainage pipes of the floor drains and sewer lines from toilets which shall be covered by the new false ceiling. Provide access points for maintenance of the lines.
Connect sewer lines to existing concrete manholes outside the kindergarten.
- Toilet Partitions (design to be approved by Kindergarten Director). The use of shop made toilet partitions is not authorized. The contractor shall use standard manufacturer’s product. The contractor shall provide a copy of the catalog from which the standard toilet partition is proposed. It is the intent of the project to build the toilets with privacy, but at the same time with possibility of adult supervision. For estimating purposed the toilets shall be provided with doors. The contractor shall provide a toilet from a standard catalog within the
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662 parameters of this contract for approval of the Contracting Officer and the Kindergarten Director. Size of the partitions shall be coordinated with the size of the rooms and size of the toilets. The separation between toilets can be made with masonry wall to be provided with the same finishes as the rest of the walls. The partitions shall be designed with minimum contact with the floor for hygienic reasons. It is estimated that the bathroom partitions shall be different depending on the age of the users of each particular group of children to be renovated. For youngest children, doors may not be required.
- Mirrors: To be provided over the countertop of the sinks. Mirror to be recessed within the new ceramic wall tiles of minimum size 0.6 meter high and with the same length as the countertops. Mirrors shall be surrounded by metal profile as shown in picture in following pages. The mirror shall be minimum 8 mm thickness for security reasons. This is required for all the bathrooms.
- Toilets: Provide kindergarten size toilets unless indicated otherwise by the kindergarten director. This will depend on the age of the users of the renovated bathrooms. For estimating purposes, the contractor shall estimate that all toilets except one shall be special size for kindergarten use. All materials shall be ceramic. The use of plastic water tanks is not authorized.
- Sinks: Sinks to be ceramic provided with faucets with hot and cold water. Use monoblock faucet with single lever to adjust the water temperature. Provide the required sinks over continuous countertops. No drainage piping from the sinks shall be visible, and if the design requires them to be visible, they shall be stainless steel. The use of visible plastic piping for the drainage of the sinks is not authorized.
- Countertop: The sinks shall be installed recessed on continuous artificial stone countertop with rounded edges and designed to support the load of people standing on top of the countertop. Testing of the countertop will be done by sitting 2 adults on the worst area of the countertop (approximately 200 kg). The use of wood for the countertop is not authorized. The countertop shall be made of artificial compound made of minimum 94% natural quartz with anti-bacterial protection. Provide with live colors (orange, blue, red of yellow), to be selected by the beneficiary among ample selection provided by the contractor. All exposed drainage piping from the sinks shall be stainless steel, provided with p-trap to avoid bad smell.
- Accessories: Provide all required accessories made of stainless steel, in order to have a perfectly finished and operational bathroom facility. This includes toilet paper holder, soap holder, wall hanger or door and window stops.
- Furniture: Approximately where indicated in red, the contractor shall provide typical kindergarten bathroom furniture to keep the towels, brushes and sanitation elements for each child. Use solid wood for the furniture. The use of composite wood is not authorized.
Install 30 units per bathroom.
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
Conceptual design of suspended ceiling when drainage piping and windows interfere with its installation. Use acoustic ceiling panels over galvanized metal supports
Recessed mirror with stainless steel framing as required by this contract.
Use 8 mm glazing for mirror.
Typical sizes for kindergarten sized toilet
Typical color chart for the countertop for the sinks, to be provided by the contractor to the Kindergarten Director to select the final color of the countertops. Provide live colors
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
Typical aluminum with anodized finish corner protection
Typical metal corner protection for all tiled corners and edges.
Typical automatic hand drier, to be hardwired (with electrical wires not visible)
Partitions from NAVFAC project in Ukraine
Example of sinks over artificial stone countertop (in recently completed project in Bulgaria)
Example of sinks over artificial stone countertop (in recently completed project in Moldova)
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
Typical bimetal radiator required for all new radiators in all renovated areas.
Example of sinks over artificial stone countertop (in recently completed project in Moldova)
Typical electrical conduits within walls
Typical electric conduit
Typical stainless steel drainage and p-trap, for the recessed sinks over the countertops.
Typical installation of the countertop before installing the sinks. Provided with metal structural supports.
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
Typical grès base boards. Use same model as for the floor tiles
Typical ceiling with recessed lighting fixtures. Provide
LED lighting fixture
Typical required continuous countertop for the sinks.
Use bright colors.
Typical required stainless steel drainage with p-trap for the sinks to be installed over the continuous countertop
Cutting homogeneous porcelain stoneware tiles
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
All electrical mechanisms to be recessed in the new walls. Provide wide mechanisms as shown.
Typical internal PVC sill required for all windows
Homogeneous characteristic of the porcelain stoneware in comparison with standard ceramic tile (not acceptable in this project)
LED lighting fixture to be recessed
LED lighting fixture to be recessed
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
Typical toilet partitions for the kindergarten without doors. Note that for estimating purposes the contractor shall estimate the partitions with doors. Use of wall recessed water tanks is acceptable but not required.
Typical required kindergarten toilet partitions with doors.
Typical kindergarten toilet in a partition
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
Potential acceptable toilet partitions without doors and wall mounted (without contact with the floor for easy cleaning) for the youngest children
Typical PVC channels for cable and water piping installation in areas not under the scope of work
Typical required Moldovan furniture compartments for kindergarten to be replaced with new ones of solid varnished wood.
Typical required kindergarten toilet partitions with doors.
Typical toilet with bottom sewer connection as the one required in this contract for the Strugurash bathroom. Do not use toilets with back connection. WC’s drainage/sewer piping shall not be visible.
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
3.2.3 Bathrooms not requiring complete renovation
The contract includes the complete renovation of 7 bathrooms. However, the building includes a minimum of 9 additional bathrooms. These bathrooms have received some level or renovation and therefore, the contractor shall minimize the work in these areas to the items of work described herein.
The purpose of this project is to provide adequate sanitation facilities. For that reason it is imperative that the project includes the replacement of all those sewer lines not found to meet Moldovan regulations or that are defective. Therefore the contract includes replacing all metal sewer lines with new PVC gravity sewer lines, from all bathrooms to the nearest manhole outside the facility. This includes any metal sewer lines that go through the ceiling deck and into the floor.
The contract includes cleaning as necessary the sewer lines from the exterior manholes to the nearest manhole outside the plot of land of the kindergarten, or replacing those sections of sewer line found not to comply with Moldovan regulations or that cannot be repaired in case there are roots inside the sewer lines.
The contractor shall estimate that they will have to remove sewer lines in all bathrooms, with the need to destroy most of the flooring in the ground floor bathrooms in order to provide new PVC sewer lines from the plumbing appliances to the nearest manhole outside the building.
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
Sketch showing approximate layout for kitchenettes
3.3 Kitchenette Renovations
The works includes everything necessary to have perfectly operational and modern kitchenette facilities for the children in the areas described in the table in paragraph 3.2.
Similarly to the bathrooms requiring complete renovation, the contractor shall provide complete renovation of these 3 small areas, by providing new floors, half size walls, wall tiles, new electrical with 4 electrical receptacles over the countertop, one sink over countertop and kitchen furniture to store silverware, plates and glasses, as well as other minor cooking and food dispensing materials. All quality and finishes to be similar to those specified for the bathrooms.
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
Stinjinei bathroom (ground floor): Not requiring complete renovation. Contractor to remove metal sewer lines from floor above to the nearest manhole outside the kindergarten building. Need to make hole in the floor.
Vasilioc bathroom (above Stinjinei). Requiring removing the metal piece of the sewer line connecting with Stinjinei group.
Stinjinei kitchnette: No work required here.
Vasilioc bathroom: Need to replace the sewer/vent lines connecting with roof. Need to restore the ceiling and the waterproofing of the building as it could be affected by the contractor’s work
3.4 Description of Work by Group
The following pictures include some general comments about the required work for some of the bathrooms and kitchenettes. All description of work included in the picture comments are part of this contract and the contractor shall execute them as if explicitly described in the corresponding paragraph.
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
Clopotsel Group bathroom requiring complete renovation/reconstruction.
Fialca Group bathroom (ground floor), not requiring complete renovation, but only replacement of all metal sewer lines similarly to those described for Vasislioc.
renovation/reconstruction. In second floor.
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
Gladiola bathroom requiring complete renovation/reconstruction. Toilets to be reutilized
Landish bathroom requiring complete renovation/reconstruction
Fialca kitchenette to be completely reconstructed. All to be removed. Piping to be installed within the walls. Hot water connected with nearest hot water line in the building.
Gladiola bathroom on the ground floor requiring complete renovation/reconstruction
Fialca kitchenette. Remove wooden partition and provide half size wall to separate the new required ceramic flooring. Provide new lighting to have 600 lux above food processing areas.
Gladiola bathroom requiring complete renovation/reconstruction. Internal partition to be removed as required by the contractor’s design
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
Cimbrisor bathroom not requiring complete renovation.
Repair water leak.
Cimbrisor bathroom. Contractor to remove all metal sewer lines and replace with PVC lines, restoring all affected surfaces to original conditions.
Landish bathroom in the second floor requiring complete renovation/reconstruction
Landish kitchenette to be completely rebuilt, provided with everything new.
Landish bathroom requiring complete renovation/reconstruction
Landish kitchenette to be completely rebuilt, provided with everything new.
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
Nezabuca kitchenette requiring complete reconstruction
Garofitsa bathroom on second floor requiring complete renovation. Reconstruction after removing all internal partitions.
Cimbrisor bathroom, in the ground floor, not requiring complete renovation, but requiring metal piping replacement, including those under the floor
Viorele (above Romaartsa), to be completely renovated.
Need to correct roof penetration for water leaks. 2 toilets can be reutilized.
Romaartsa (ground floor), to be completely repaired/reconstructed. The piping to be connected to the exterior sewer manholes.
Nezabudca (ground floor) requiring complete renovation
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
3.5 Water and Sewer outside the areas to be renovated
The general basis of design is that all renovated works shall comply with Moldovan regulations. A renovated bathroom cannot comply with latest regulations if their water lines are connected with old metal water lines or if their sewer lines are connected with metal sewer lines that are rusted and full of roots.
For that reason, the contract includes connecting the water lines of the 7 bathrooms and the 3 kitchenettes to the water meter supplying water to the kindergarten. The contract includes removing the old water lines in compliance with Moldova regulations to avoid dead end pipes.
Additionally, it includes the sewer lines from all the bathrooms (16 units) and kitchenettes (14 units) to the nearest manhole outside the plot of land. This means that the contractor shall remove all the metal sewer lines from the 16 bathrooms and 14 kitchenettes and provide new connections with the exterior manholes using PVC gravity lines, certified in Moldova to be used in gravity sewer systems. This means that the contractor shall be required to dig new channels or trenches within the ground floor of the kindergarten, in order to install the new gravity sewer/drainage lines.
The contractor is responsible to restore all flooring to original conditions.
From the nearest manhole to the first manhole outside the plot of land, the contractor shall inspect and clean or replace the sewer lines in order to verify that the sewer system complies with the regulations. It is also included the necessary potential repairs to the concrete manholes, including the repairs and internal plastering that may be required.
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
Two blocks, where the main entrance is located, to be provided with new thermally insulated metal roofing
3.6 New Roof over Two Blocks
The contractor shall design and build a new metal roofing over the two block in the North-West of the facility, including walkways and all flat surfaces with the general basis of design outlined herein:
- Esthetics similar to the new roofs provided by the beneficiary.
- 4 planes – 4 slopes pitched roof
- Minimum slope as required by Moldovan technical regulations
- Extending 0.8 meters on the perimeter (eave). If one of the blocks would be for example
21.15 x 17.85 m, then the horizontal projection of the roof would be minimum of 22.75 x
19.45 m.
Drochia Kindergarten#08, Elizaveta Kindergarten & Nicoreni Middle School OHASIS 26661 – 26665 - 26662
Typical joints of roof panels
- Weight supported by the building structure. No weight shall be supported by the horizontal structural beams of the building. The contractor’s architect shall perform a full structural analysis of the existing building to guarantee and certify that the building structure will not support overloads as the result of the new roof construction. For that reason, it is estimated that the contractor’s design shall include:
o Metal beam around the perimeter of the roof parapet to evenly distribute the weight of…