Attachment_1_-_PTS_N33191-14-R-0634_Renovate_Literacy_and_Health_Center_Gabon.pdf
PDF 712 KB Posted
- Solicitation number
- N33191-14-R-0634
About this file
Performance Technical Specifications (RFP N33191-14-R-0634)
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment_5_-_APP_Template.pdf | ||
| Attachment_2_-_Contract_Data_Sheet.doc | DOC document | |
| Attachment_4_-_Submittal_Checklist.doc | DOC document | |
| Attachment_3_-_PPQ.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment (1)
Prepared by: NAVFAC EURAFSWA HQ – CEBL Sonia Grillo
AFRICOM
Humanitarian Assistance Program
Literacy and Public Health Education Center Renovation and Expansion
Libreville, GABON
OHASIS GB-HA-2013-00020033
FY14
May 2014
TECHNICAL REQUIREMENTS
Literacy and Public Health Education Center, Libreville, GABON
Table of Contents p. 2/95
TABLE OF CONTENTS
COVER PAGE
TABLE OF CONTENTS
LEGENDA: ACRONYMS AND DEFINITIONS
1 PROJECT DESCRIPTION
1.1 GENERAL
1.2 SCOPE OF PROJECT
1.3 SIGNAGE
1.4 STANDARD NOMENCLATURE
1.5 PROCEDURE
Concept Design Final design Construction Schedule Quality Control Plan Accident Prevention Plan [APP]
2 PROJECT OBJECTIVES
2.1 MISSION STATEMENT
2.2 FACILITY FUNCTION
2.3 PROJECT SPECIFIC PRIORITIES
Sustainable Design Energy Conservation
2.4 APPROPRIATE DESIGN
3 SITE ANALYSIS
3.1 EXISTING SITE CONDITIONS
4 BUILDING REQUIREMENTS
Facility Footprint ..................................................... Error! Bookmark not defined.
Access, Circulation, and Site Development .......... Error! Bookmark not defined.
4.1 SPACE REQUIREMENTS ................................. ERROR! BOOKMARK NOT DEFINED.
4.2 PROJECT SIGN
4.3 DEDICATION SIGN
4.4 SETTLEMENT OF EXTERNAL AREAS ............... ERROR! BOOKMARK NOT DEFINED.
Table of Contents p. 3/95
4.5 EXTERIOR CHARACTER
5 ROOM MINIMUM REQUIREMENTS
5.1 ROOF AND SUPERSTRUCTURE
5.2 FLOORS, WALLS AND CEILING
5.3 DOORS AND WINDOWS ................................. ERROR! BOOKMARK NOT DEFINED.
5.4 PLUMBING AND FIXTURES
5.5 ELECTRICITY AND LIGHTING
5.6 ELECTRICAL PANELBOARD AND GROUNDING SYSTEM
6 GENERAL WORK REQUIREMENTS
6.1 REFERENCE STANDARDS
6.2 WORK REQUIREMENTS
6.3 DESIGN GUIDANCE
6.4 PERFORMANCE TECHNICAL SPECIFICATIONS
6.5 SUBMISSIONS
Concept Design Final Design Construction Schedule Quality Control Plan Accident Prevention Plan
6.6 CONSTRUCTION GUIDANCE
6.7 CERTIFICATIONS, LICENSES, PERMITS, FEES, ETC
6.8 COORDINATION
6.9 VEGETATION CONTROL
6.10 RESPONSIBILITY OF MATERIALS
6.11 SAFETY AND PROTECTION
6.12 SPILL CONTINGENCY PLAN
6.13 SPECIAL SITE CONDITIONS
6.14 CLEANING
7 ENGINEERING SYSTEMS REQUIREMENTS
7.1 SECTION A10 FOUNDATIONS
A1010. Standard Foundations A1030. Slab On Grade
7.2 SECTION B10 SUPERSTRUCTURE
B1010. Floor Construction
Table of Contents p. 4/95
B1020. Roof Construction
7.3 SECTION B20 EXTERIOR ENCLOSURE
B2010. Exterior Walls
B201001. Balcony Walls, Guard Rails & Handrails B201002. Exterior Coatings
B2020. Exterior Windows B202001. Exterior Windows B202002. Exterior Glazing B201003. Exterior Louvers & Screens
B2030. Exterior Doors B203007. Gates
7.4 SECTION B30 ROOFING
B3010. Roof Coverings
B301001. Steep Slope Roofing Systems B301002. Low Slope Roofing Systems
7.5 SECTION C10 INTERIOR CONSTRUCTION
C1010. Partitions
C101001. Interior Guardrails C101002. Interior Screens C101003. Interior Windows C101004. Interior Glazing
C1020. Interior Doors C102001. Standard Interior Doors C102002. Glazed Interior Doors
C1030. Specialties C103001. Toilet Compartments and Accessories C103003. Marker Boards C103004. Counters C103005. Cabinets C103006. Ornamental Metal Work
7.6 C30 INTERIOR FINISHES
C3010. Wall Finishes C3020. Floor Finishes C3030. Ceiling Finishes C3040. Interior Coatings And Special Finishes
7.7 SECTION D20 PLUMBING
D2010. Plumbing Fixtures
D201001. Water Closets D201002. Urinals D201003 Lavatories D201004. Sinks D201005. Finish Trim
D2020. Domestic Water Distribution D202001. Pipes and Fittings D202002. Domestic Water Equipment D202003. Insulation & Identification D202004. Specialties D202005. Other Domestic Water Supply
D2030. Sanitary Waste D203001. Waste Pipe & Fittings D203002. Vent Pipe & Fittings D203003. Floor Drains
Table of Contents p. 5/95
7.8 SECTION D50 ELECTRICAL
D5010. Electrical Service And Distribution
D501002. Service Entrance Equipment D501004. Switchboard D501005. Enclosed Circuit Breakers
D5020. Lighting And Branch Wiring D502001. Branch Wiring D502002. Lighting Equipment D502003. Finish Trim D502004. Potential Drop
D5040. Other Electrical Services D504001. General Construction Items (Electrical) D504002. Emergency Lighting and Power D504003. Grounding Systems D504004. Lightning Protection D504005. Electric Heating
7.9 SECTION G10 SITE PREPARATION
G1010. Site Clearing
G101001. Clearing G1030 Disposal
7.10 SECTION G20 SITE IMPROVEMENTS
G2040. Site Development
G204001. Freestanding Walls & Gates
7.11 SECTION G30 SITE CIVIL/MECHANICAL UTILITIES
G3010. Water Supply G3020. Sanitary Sewer
G302001. Sanitary Sewer Piping G302002. Sanitary Sewer Manholes G302003. Sewer & Waste Water Holding Tanks G302003. Septic Systems Tanks
7.12 SECTION G40 SITE ELECTRICAL UTILITIES
System Description General System Requirements
G4010. Electrical Distribution G401007. Ductbanks, Manholes, Handholes And Raceways G401008. Grounding Systems
G4020. Site Lighting G402001. Exterior Lighting Fixtures And Controls G402005. Underground Electric Conductors G402006. Ductbanks, Manholes And Handholes G402007. Grounding Systems
8 PERFORMANCE TECHNICAL SPECIFICATIONS (PTS)
8.1. NARRATIVE
8.2. SECTION A10: FOUNDATIONS [6/07]
A10 General A1010 Standard Foundations
A101001 Wall Foundations A101002 Column Foundations And Pile Caps A101003 Foundation Drainage
Table of Contents p. 6/95
A1020 Slab On Grade A102001 Concrete Slabs On Grade A102002 Slab On Grade Insulation
A1030 Elevated Floor Slabs A1040 Concrete
A104001 Concrete Materials A104002 Concrete Formwork A104002 Concrete Reinforcement A104003 Placing Concrete Reinforcement A104004 Concrete Mixing A104005 Concrete Conveying A104006 Concrete Depositing A104007 Concrete Curing A104008 Hot Weather Concrete A104009 Concrete Construction Joints A104010 Concrete Testing
8.3. SECTION B10: SUPERSTRUCTURE [06/07]
B10 General B1010 Construction Components B1020 Wood B1030 Unit Masonry B1050 Steel
8.4. SECTION B20: EXTERIOR ENCLOSURE [04/07]
B20 General B2010 Exterior Walls
B201001 Unit Masonry B201002 Guardrails ad Handrails B201003 Exterior Painting and Special Coatings
B2020 Exterior Windows B202001 Standard Window Systems B202002 Louvered Windows B202003 Screens B202004 Roll Shutters
B2030 Exterior Doors B203001 Standard Doors Systems B203002 Door Frames B203003 Exterior Door Hardware B203004 Exterior Door Hardware Finishes B203005 Other Exterior Specialty Doors
8.5. SECTION B30: ROOFING [04/07]
B30 General B3010 Steep Slope Roof Systems
B301001 Slate Roofing B301002 Roof Tiles B301003 Metal Roof Panels B301004 Concrete Roof Panels
B3020 Low Slope Roof Systems B302001 Built-Up Asphalt Roofing (Aggregate Surfaced)
B3030 Flashings & Trim B303001 Flashing And Sheet Metal B301002 Gutters and Downspouts B301003 Roof Openings and Supports B301004 Other Roofing
Table of Contents p. 7/95
8.6. SECTION C10: INTERIOR CONSTRUCTION [06/07]
C10 General C1010 Partitions
C101001 Unit Masonry C101002 Handrails C101003 Interior Painting And Special Coatings
C1030 Interior Doors C103001 Standard Doors Systems C103002 Door Frames C103003 Interior Door Hardware C103004 Interior Door Hardware Finishes C103005 Other Interior Specialty Doors
C1040 Specialties C104004 Counters C103005 Cabinets C104006 Casework
8.7. SECTION C30: INTERIOR FINISHES [04/07]
C30 General C3010 Wall Finishes
C301001 Plaster Wall Finishes C301002 Tile Wall Finishes
C3020 Floor Finishes C302001 Ceramic Tile Floor Systems C302002 Ceramic Glazed Tile Floor C302003 Ceramic Mosaic Unglazed Floor Tiles C302004 Porcelain Floor Tile C302005 Quarry Floor Tile C302006 Terrazzo Floor Finishes C302007 Masonry And Stone Flooring C302008 Wall Base Finishes C302008 Stair Finishes C302009 Hardeners And Sealers
C3030 Ceiling Finishes C303001 Acoustical Ceiling Tiles And Panels C303002 Plaster Ceiling Finishes
C3040 Interior Painting And Special Finishes C304001 Painting Systems Per Substrate C304002 Concrete Finishes C304003 Concrete Masonry Finishes C304004 Plaster Finishes C304005 Metal Finishes C304006 Interior Wood Finishes
8.8. SECTION D20: PLUMBING [08/06]
D20 General D2010 Plumbing Fixtures
D201001 Water Closets D201002 Urinals D201003 Lavatories D201004 Sinks D201005 Showers/Tubs
D2020 Domestic Water Distribution D202001 Pipes & Fittings D202002 Valves & Hydrants D202003 Domestic Water Equipment D202004 Insulation & Identification
Table of Contents p. 8/95
D2030 Sanitary Waste D203001 Waste Pipe & Fittings D203002 Vent Pipe & Fittings D203003 Floor Drains
8.9. SECTION D30: HVAC [06/07]
D30 General D3010 Heat Generating Systems
D301001 Boilers D301002 Heating Hot Water Distribution Systems D301003 Terminal Units D302001 Requirements D302002 Hot Water Heating Equipment Startup and Operational Tests
D3040 Performance Verification And Testing
8.10. SECTION D50: ELECTRICAL [08/06]
D5010 General
D501001 Quality Assurance D501002 Submittals
D5020 Electrical Service And Distribution D502001 Main Transformers D502002 Service Entrance Equipment D502003 Interior Distribution Transformers D502004 Switchboard D502005 Enclosed Circuit Breakers D502006 Motor Control Centers D502007 Other Service And Distribution
D5030 Lighting And Branch Wiring D503001 Branch Wiring D503002 Lighting Equipment D503003 Ballasts
D5050 Other Electrical Services D505002 Emergency Lighting And Power
8.11. SECTION G10: SITE PREPARATION
G10 General G1010 Site Clearing G1020 Site Demolition & Relocations
G102001 Building Mass Demolition G102002 Hazardous Components Abatement G102003 Aboveground Site Demolition G102004 Underground Site Demolition G102005 Fencing Relocation G102008 Site Cleanup
G1030 Site Earthwork G103001 Grading G103002 Common Excavation G103003 Rock Excavation G103004 Fill & Borrow G103005 Compaction G103006 Soil Stabilization G103007 Slope Stabilization G103008 Shoring G103009 Temporary Dewatering G103010 Temporary Erosion & Sediment Control G103011 Other Site Earthwork
G1040 Hazardous Waste Remediation
Table of Contents p. 9/95
8.12. SECTION G20: SITE IMPROVEMENTS [08/06]
G20 General
G2010 Roadways G201001 Paved Surfaces G201002 Resurfacing
G2020 Pedestrian Paving G2030 Other Site Development G204001 Fencing & Gates G204002 Retaining Walls
8.13. SECTION G30: SITE CIVIL/MECHANICAL UTILITIES [08/06]
G30 General G3010 Water Supply
G301001 Well Systems G301002 Potable Water Distribution G301003 Potable Water Storage
G3020 Sanitary Sewer G302001 General Requirements G302001 Sanitary Sewer Piping G302002 Septic Tanks & Drain Fields G302003 Sewer & Waste Water Holding Tanks
8.14. SECTION G40: SITE ELECTRICAL UTILITIES [06/07]
G4010. General
G401001 Quality Assurance G401002 Submittals
G4020 Electrical Distribution G402001 Substations G402002 Transformers G402003 Switches, Controls And Devices G402004 Overhead Electric Conductors G402005 Towers, Poles, Crossarms And Insulators G402006 Underground Electric Conductors G402007 Ductbanks, Manholes, Handholes And Raceways G402008 Grounding Systems G402009 Metering G402010 Cathodic Protection Systems G402011 Equipment Requirements For Coastal And High Humidity Areas
G4030 Site Lighting G403001 Exterior Lighting Fixtures And Controls G403004 Lighting Poles G403005 Underground Electric Conductors G403006 Ductbanks, Manholes and Handholes G403007 Grounding Systems .............................................. Error! Bookmark not defined.
Legenda p. 10/95
LEGENDA: ACRONYMS AND DEFINITIONS
As used throughout this solicitation/contract:
Contracting Officer [KO] is the Government’s representative in charge for executing the contract and responsible for any amendment.
Contractor is for the Offeror that has been awarded the contract.
COR stands for the Contracting Officer Representative, who is a qualified Government employee appointed by the KO to provide technical direction/clarification and guidance with respect to contract specifications or statement of work. COR is the accountable official for purposes of certifying payments D/B contract stands for Design and Build contract, which means that the contractor shall first provide a complete and executable design matching the specifications of the TR, then implement the construction in accordance to such a design.
DOD stands for U.S. Department of Defense ESR stands for Engineering System Requirements Government stands for the Government of the United States of America (U.S.A.);
HVAC stands for Heating, Ventilating and Air Conditioning NAVFAC EURAFSWA stands for Naval Facilities Engineering Command Europe, Africa and South West Asia; it is the Government’s executive agent for construction.
NTPC stands for Notice To Proceed with the Construction.
Offeror is any constructor that submits a bid.
Project Manager [PM] is the Government’s technical representative in charge for managing the project (scope, cost, and schedule) from design authorization to closeout. PM and COR maybe the same person.
PTS stands for Performance Technical Specifications RFP stands for Request for Proposal RFQ stands for Request for Quote SF stands for Government’s standard form; this acronym is followed by a number identifying what contract action the form is intended for SOW stands for Statement Of Work: it is the detailed description of the work activities, deliverables and timeline the contractor will execute against in performance of specified work TEB stands for the Government Technical Evaluation Board in charge to receive, accept and evaluate the technical offers TR stands for Technical Requirements which are integrant part of the SOW and provide all the specifications for the design and the implementation of the project.
VIP stands for Ventilated Improved Pit which is the type of latrine to be implemented at the site as described in this SOW.
1. Project Description p. 11/95
1 PROJECT DESCRIPTION
1.1 GENERAL
Renovate and expand an education center - currently consisting of a 24m x 11m building including two classrooms, one library and five offices - as described in this document and in accordance to the sketches/tables included hereby.
The work shall include a complete design and submittal package as described below.
1.2 SCOPE OF PROJECT
The work shall consist of the following (dimensions are approximate):
a. Renovate the existing facilities (Item A) to include:
Reinforce foundations where needed Remove and replace the plumbing system Remove and relocate the septic system and sewer pipes Remove and replace the electrical system Repair plaster on exterior walls Remove all interior partitions and implement 1 entrance hall, 4 classrooms and 8 toilets Paint all interior and exterior walls Remove and replace the entire roof structure Remove and replace the floors Remove and replace the ceilings Remove all window and door fixtures and replace in accordance to the new layout Remove and replace window grids Implement access ramps Implement a lightning protection system (LPS) Settle and fence the external area on the front side.
b. Build a 150 sqm 1-story building (Item B) on the back side of the Item A to include:
One library Five offices One veranda One sheltered connection to Item A Electrical system
LPS
External settlement including a retaining wall on the new building back side to control drainage from the hill
The new work shall result into complete, safe and usable facility, whose interior space layout shall match the space requirements provided in the Part 3.4.
Design and construction details are provided in Part 5, and specified in Parts 6, 7, and 8..
All buildings shall have concrete superstructure and masonry infill construction with basic finishes.
All buildings shall have a storm water drainage system to prevent erosion.
All systems to be replaced shall be re-designed first.
The work shall include - but not be limited to - the following: Demolition of Existing Construction, Interior Construction, Roof System, Plumbing Systems, Mechanical Systems, Electrical Systems, Exterior Area Settlement, Site Improvements and Other Work as required.
Design shall meet all requirements of the RFP/RFQ package. Drawings to be as described below and as required to communicate the design to the US Government, final users, contractor’s staff and
1. Project Description p. 12/95 sub-contractors. Material selection, specifications and installation to be as described the in the Engineering Systems Requirements (ESR, Part 7), and in the Performance Technical Specification (PTS, Part 8), included below as the last two parts.
The ESR and the PTS of this document provide a guideline for the design package. If an item in the project design is included in the ESR/PTS, the requirements of the ESR/PTS and applicable local codes shall govern. If an item in the project design is NOT included in the ESR/PTS, the requirements of applicable local codes shall govern.
The design shall be developed by qualified design professionals, either consistently employed in the contractor’s company or working for a design firm hired by the contractor for the purpose of this project.
The electrical work shall be implemented by a qualified installer able to release a certificate of compliance to the codes.
1.3 SIGNAGE
Project Sign The Contractor shall provide a painted project sign to be located at the worksite as soon as the construction starts. The paint shall be water resistant and display the project name, the Gabonese and American flags, and the wording explaining the cooperation between the two Governments.
The Contractor shall submit a proof of the sign for acceptance prior to construction.
See detailed requirements at par. 4.2
Dedication Sign The Contractor shall provide a project dedication sign (approximately 800 mm x 1200 mm) at the project site at least 2 weeks prior to project completion.
The project name shall appear at the top center, followed by the sentence “An everlasting example of friendship between the people of Gabon and the United States” above the flags, and the sentence “Completed by the people of Gabon and the United States of America on DD MONTH, YYYY” at the bottom.
The sign shall be constructed of sheet metal with a water resistant coating and affixed directly to the building at a location approved by the facility administrator and the COR.
The Contractor shall submit a proof of the sign for acceptance prior to manufacturing the sign.
See detailed requirements at par. 4.3
1.4 STANDARD NOMENCLATURE
This is an American document, and this note is to define the way in which numbers are presented herein:
1,000 = one thousand 3,500 = three-thousand five-hundred
1.08 = one and eight hundredths
0.1 = one-tenth
1. Project Description p. 13/95
1.5 PROCEDURE
The construction phase shall start only once that the official Notice to Proceed with Construction (NTPC) is issued by the NAVFAC EURAFSWA Project Manager/Contracting Officer.
The NTPC will not be issued until all required submittals are received and reviewed by the US Government and shown to meet the specifications of these Technical Requirements and the Solicitation package.
PRE-CONSTRUCTION SUBMITTAL CONSIST OF:
Concept Design Final Design Construction Schedule Quality Control Plan Accident Prevention Plan
CONCEPT DESIGN
The concept design shall be submitted within 50 calendar days of receipt of the award. The concept design is intended to assure all lay-out requirements are clearly met before the full design is developed. It shall identify site preparation, including items to be removed and to be kept. It shall provide the basic architectural design, including plans, elevations and sections.
Current Site Layout plan with dimensions and distances Geotechnical Report Structural Report about the current status of the existing structures Final Site Layout plan with dimensions and distances Final Plans, Elevations and Sections of each building object of the contract.
The Government shall review the concept design submission for compliance to these Technical Requirements and the Solicitation package and provide written comments to the contractor.
See paragraph 6.5 for detailed explanation about the concept design.
FINAL DESIGN
The contractor shall have 100 calendar days to complete the design, incorporating all concept design review comments provided by the US Government.
In the event the contractor does not concur with the US Government comments, the contractor shall notify the contracting officer in writing of the reasons for the non-concurrence.
The final design shall meet all the requirements identified in these Technical Requirements and the Solicitation package and shall include:
Site Improvement Drawings Architectural Drawings Structural Drawings Electrical Drawings Plumbing Drawings Mechanical Drawings Basis of Design All Reports, Calculations and Details required to validate the design.
See paragraph 6.3, 6.4 and 6.5 for detailed explanation about the final design.
CONSTRUCTION SCHEDULE
The contractor shall have 270 calendar days to complete the work.
Within the timeframe allowed for the final design submission, the contractor shall prepare and submit a schedule of construction where the different work segments are identified and associated to the timeframe set for completion. The construction schedule shall state which work segments completion determines the achievement of the construction steps associated to the progressive invoicing (i.e. 10% (design completion), 30%, 50%, 70% and 90% work progress). The final payment will be done on the facilities acceptance.
See paragraph 6.5 for more details about the construction schedule.
1. Project Description p. 14/95
QUALITY CONTROL PLAN
Within the timeframe allowed for the final design submission, the Contractor will prepare and submit a Quality Control Plan describing personnel, procedures, tests and installation techniques that he plans to perform to ensure the quality required by this document and his design is obtained.
ACCIDENT PREVENTION PLAN [APP]
Within the timeframe allowed for the final design submission, the Contractor will prepare and submit an APP describing procedures he plans to perform to ensure the safety of personnel and equipment on the job site. At a minimum, the safety plan must address types of personnel protective equipment to be used by personnel, types and frequencies of safety inspections, hazard analysis plan [AHA] to prevent safety incidents, and training utilized to familiarize employees with safety policies and practices.
See paragraph 6.5 for more details about the APP
INTERIM SUBMITTAL REQUIREMENTS
During construction, the Contractor is required to submit:
Bi-weekly work progress report with photos Monthly work man-hours report Test results as required per the contract At least 10 days prior to installation of all electrical components, plumbing fixtures, windows and doors and associated hardware, a sample (or catalog photo) must be shown to the KO or COR for acceptance.
Possible construction schedule changes (to be motivated) Possible design changes (to be motivated) Invoices in accordance to work progress
COMPLETION SUBMITTAL REQUIREMENTS
Upon completion of project and prior to final payment, the Contract is required to submit:
Final as-built drawings Operations and maintenance plan A telephone contact number available for the duration of the warranty period.
~~~ End of Part 1 ~~~
2. Project Objectives p. 15/95
2 PROJECT OBJECTIVES
2.1 MISSION STATEMENT
DoD humanitarian assistance activities were first authorized by US Congress in 1986. In FY 1996, DoD was permitted to fund a wider variety of HA activities, including using contracts and deployment of U.S. Government personnel to conduct specific humanitarian projects.
Typical projects include the refurbishment of medical facilities, construction of school buildings, digging of wells, improvement of sanitary facilities, and training of host country personnel in internally displaced persons/refugee repatriation operations and in disaster relief and emergency response planning.
The DoD, in an attempt to assist in development and implementation of the Humanitarian Assistance Program, is funding and coordinating the project which is the subject matter of this contract.
NAVFAC EURAFSWA has been designated as the Construction Agent for this project.
2.2 FACILITY FUNCTION
The existing Literacy Center promotes public health education programs. The renovation and expansion of its facilities will offer more opportunities to uneducated teenage mothers and other educationally disadvantaged adults and young people in the community to get access to information and materials like basic reading, computation, public health, family planning methods, public health awareness, and vocational training.
2.3 PROJECT SPECIFIC PRIORITIES
Sustainable Design
Integrate sustainable principles into the design, development and construction of the project.
Reduce the total cost of ownership of the facility using a whole building, life-cycle approach.
Provide integrated sustainable design strategies and features to minimize the energy consumption of the facilities; conserve resources; minimize adverse effects to the environment;
and improve occupant productivity, health, and comfort.
Energy Conservation Integrate energy conservation principles into the design, development and construction of the project. Reduce the total cost and consumption of energy in the facility using a whole building approach.
2.4 APPROPRIATE DESIGN
The design is to maintain an indigenous character. As much as possible, materials are to be available locally to promote the local economy and to take advantage of the skills and experience of local trades-persons. Construction methods are to be in-line with those used locally to take advantage of the skills and experience of local trades-persons.
~~~ End of Part 2 ~~~
4. Building Requirements p. 16/95
3 SITE ANALYSIS
3.1 EXISTING SITE CONDITIONS
The current facility is approximately 25 years old and in a general state of disrepair.
The foundation and walls are constructed of concrete, with a wood truss roofing system covered by galvanized metal roofing material. The interior partitions are wood frame walls.
The roof structure is heavily damaged. The concrete portions of the structure are generally in good repair, excepting for needing minor patching in some areas and new paint overall.
There are four separate concrete staircases leading into the structure. The ground around the two staircases in the front of the building has eroded away leaving a large step-up to get onto the stairs.
The bathroom with a sink and toilet drains into a small septic system in the rear of the building.
The electrical system is in poor condition, the electrical box and wiring was damaged and jury-rigged.
The building is connected to the public electrical, water, and telephone systems.
3.2 CURRENT SITE LAYOUT
The site layout allows for building expansion to the rear of the existing structure.
Expansion to the right to the front side is limited due to proximity of property lines.
The space on left side is intended for parking area.
FACILITY FOOTPRINT
A scaled drawing with exact dimensions showing the site lay-out including location and dimensions of all existing buildings, latrines, obstacles, and perimeter wall (if any) with gate locations shall be included in the concept design.
4. Building Requirements p. 17/95
3.3 PHOTO DESCRIPTION
The facilities currently consist of a 24m x 11m building located at Derriere La Prison in Libreville.
Photos 1 and 2 shows the building front and rear façades as they currently appear.
Photos 3 and 4 show the interior finishes and partitions.
Photo 5 shows the current restroom with non-operational faucet and flushable water closet; fixtures are connected to an unusable sewage system and septic tank
Photo 6 shows the existing electrical delivery point and the old, unsafe, and not functional switchboard panel.
Photo 2
Photo 4 Photo 3
Photo 5
Photo 1
Photo 6
4. Building Requirements p. 18/95
Openab le
3.4 SITE DEVELOPMENT REQUIREMENTS
An example of the final school layout is roughly sketched below.
Final new facility layout and orientation shall be selected to best fit the topography in order to minimize the required grading work.
It shall be coordinated with the PM and the school officials after the footprint of current layout has been submitted.
DESIGN CONSTRAINTS
Design of the facility and its location and orientation within the proposed site shall take into consideration all natural and man-made constraints, which include but aren’t limited to:
Topography: all site slopes shall be taken in account in order to minimize the need for cut and fill operations Vegetation / Landscaping: vegetation shall be protected, and landscaping design shall be maintainable Climatology (solar orientation, etc.): Design shall take advantage of prevailing wind direction and solar orientation to naturally moderate the interior temperature of the buildings Geotechnical Data: Foundations and structural components of the buildings shall be designed in accordance with geotechnical soils report information. Geotechnical engineering services shall be provided if no current report exists for the site. Design shall be in accordance to the seismic zone of classification of the project site.
Hydrographic Survey: a hydrographic survey shall be performed to determine the storm water runoff Vehicular Access and Circulation: existing vehicular access shall be taken in account
4. Building Requirements p. 19/95
Site Utilities: location and capacity of all existing utilities on site shall be verified prior to start design Site Drainage: the facilities shall be designed without negative impact from storm water runoff to the adjacent area of the site.
Existing Buildings: Identify and accurately locate on the site plan all existing buildings on the site.
Fencing: Identify and accurately locate on the site plan all existing fencing on the site.
Permits: all permits, approvals, and authorizations needed to implement the design shall be obtained prior to start construction.
ACCESS, CIRCULATION, AND SITE DEVELOPMENT
Any proposed vehicular and/or pedestrian access, paths, sidewalks, steps, parking areas, outdoor recreation area, landscaping etc. shall be reported on the site plan, as well as areas of material storage and temporary security fencing.
All proposed drainage channels shall be shown on the site plan.
The location of the construction sign and any other signage required by local authorities shall be indicated on the site plan.
~~~ End of Part 3 ~~~
4. Building Requirements p. 20/95
4 BUILDING REQUIREMENTS
4.1 NEW LAY-OUT OF EXISTING BUILDING
The interior partitioning shall be reshaped to obtain an entrance lobby, 4 classrooms, and male and female toilets.
Access doors shall be centrally located on the front and rear façade; the four current access doors shall be converted into emergency doors; the main door on the front shall be accessible through a ramp to allow disabled access.
Adjacent classrooms shall be separated by a flexible/removable wall partition so to accommodate larger classes and social events.
Top openings on the front façade shall be closed with glass bricks in order to retain sunlight entry but to prevent noise disruption coming from the nearby heavily trafficked street.
4.2 LAY-OUT OF NEW BUILDING
The new block addition shall be shaped and oriented as better fitting the available space so to minimize the need of grading the flanking hill.
4.3 LIGHTNING PROTECTION SYSTEM (LPS)
An LPS shall be implemented to protect all facilities.
It shall consist of a conductor system with air terminals on the roof of the buildings, bonding of the structure and other metal objects, grounding of electrodes, and interconnecting conductors.
A bimetallic connector shall be used to connect all copper cable conductors to all aluminum cable conductors.
Metal compatibility (galvanic action) shall be taken into consideration in order to avoid corrosion.
In any case a copper conductor shall be used to complete the connection to the grounding rod on both sides of each building.
Type and number of air terminals and ground rods to be used shall be determined by the Designer, based on local conditions, earth resistivity data, and on the size and type of the electrical installation.
4.4 SETTLEMENT OF EXTERNAL AREAS
The area between the Literacy Center front façade and the public road shall be paved and fenced off in order to prevent use as a road bypass for vehicles.
All the external area pertaining to the Center shall be graded to limit water from ponding and to promote positive drainage off of the grounds. Grated gutters shall be implemented as needed.
4. Building Requirements p. 21/95
4.5 SPACE TABULATION
Indicative data regarding the required size of the spaces in the new facilities are provided in the table below.
On the concept design submittal the contractor is required to provide exact dimensions corresponding to the actual design; a variance exceeding ±10% of the indicative size will not be considered acceptable.
Item A (Existing Building)
Space Name Qty Unit m2
(Net)
Tot m2 (Net)
Optimal Size (m)
Ceiling Height (m) people per room
Remarks
Entrance Hall 1 20 20 4 x 5 2.90 - To be connected to the rear access door
Classroom 4 50 200 10 x 5 2.90 30 Partition between adjacent rooms to be removable
Toilets 2 12.5 25 4.4 x 2.8 2.90 - 3 wc, 2 sinks and 2 urinals for men 5 wc, 4 sinks for women
Item B (New Building)
Space Name Qty Unit m2
(Net)
Tot m2 (Net)
Optimal Size (m)
Ceiling Height (m) people per room
Remarks
Office 5 11 56 2.8 x 4 2.90 2 access door from veranda; at least 2 windows on opposite walls,; vent blocks above all openings
Library 1 49 49 7 x 7 2.90 10 Access from veranda, at least 6 windows on opposite walls
Storage 1 3 3 2 x 1.5 2.90 - access from the library
Toilet 1 3 3 2 x 1.5 2.90 - 1 wc, 1 sink, 1 shower, vent block above the door
Veranda 1 54 108 1.8 x 30 2.90 - along the access side
4.6 EXTERIOR CHARACTER
The design is to maintain an indigenous character and match the existing features of the complex.
4.7 PROJECT SIGN
The Contractor shall provide a painted project sign to be located at the worksite as soon as the construction starts. The sign shall be made of wood and supported by wooden or metal posts.
The approximate size of the sign shall be 800mm x 1200mm and the sign shall be placed in such a way so as to provide the most visibility to passers-by; the location shall be agreed with the
COR.
The Contractor shall submit a proof of the sign for approval prior to construction.
4. Building Requirements p. 22/95
The paint shall be water resistant and display the following:
LITERACY AND HEALTH EDUCATION CENTER
RENOVATION AND EXPANSION
<Gabonese flag> <American flag>
In cooperation with the Gabonese Government, funding for this project is provided by the U.S. Government.
<Contractor’s Name>
Project name shall appear at the top center in 76mm (3 inch) tall capital block letters. The sentence below the flags shall be in 38mm (1.5 inch) sentence case lettering. Contractor company name may be added at the bottom of the sign.
4.8 DEDICATION SIGN
At least 2 weeks prior to project completion a project dedication sign shall be affixed at the project site. The sign shall be affixed directly to the building at a location approved by the facility administrator and the COR to provide optimal visibility.
The sign shall be constructed of sheet metal with a water resistant coating and shall have a frame around it. The frame material shall be wood and be approved by the COR prior to installation. The size of the sign shall be approximately 800 mm x 1200 mm.
No later than 4 weeks prior to the planned project completion, the Contractor shall contact the KO or the COR regarding final wording for the dedication sign.
The Contractor shall provide a proof of the sign for acceptance prior to manufacturing the sign.
The sign shall display the following:
LITERACY AND HEALTH EDUCATION CENTER
RENOVATION AND EXPANSION
An everlasting example of friendship between the people of Gabon and the United States.
<translation into the Host Nation primary language>
<Gabonese flag> <American flag>
Completed by the people of Gabon and the United States of America on:
DD MONTH, YYYY
<translation into the Host Nation primary language>
The project name shall appear at the top center in 76mm (3 inch) tall block letters, followed by the above sentence in 38mm (1.5 inch) sentence case lettering that shall be repeated in the Host Nation primary language. The Host Nation and American flags shall be placed as displayed in the above sketch. The sentence at the bottom shall be in 20mm (0.75 inch) sentence case lettering.
~~~ End of Part 4 ~~~
5. Room Minimum Requirements p. 23/95
5 ROOM MINIMUM REQUIREMENTS
5.1 ROOF AND SUPERSTRUCTURE
The existing roof structure shall be removed and replaced with galvanized or otherwise coated steel trusses, and aluminum-zinc coated steel or aluminum corrugated panels formed at the manufacturing plant. Panel thickness shall be 22 gauge.
All the doors, windows and passages shall be equipped with reinforced concrete lintels extending at least 15 cm over each corner of the opening.
Complete details are reported at Part 7 and Part 8, Section B10 and B30 of this document.
5.2 FLOORS, WALLS AND CEILING
All floors shall be tiled flooring granting good resistance and easiness to be kept sanitized.
The existing floors shall be removed and replaced.
All the walls shall be plastered and painted with glaze suitable for school use, except toilets that shall be tiled ceiling to floor. Existing walls to stay shall be repaired, plastered and painted as above said.
All the rooms shall be provided with false ceilings to replace the existing one. In case electrical conduits are laid above the ceiling, adequate ventilation shall be guaranteed through vents protected from small animals access.
Complete details are reported at Part 7 and Part 8, Section C30 of this document.
5.3 VENTS, DOORS AND WINDOWS
Wall vent blocks protected by mosquito screens shall be implemented above each opening to the exterior in the new building.
Windows shall be adequately sized and positioned to guarantee ventilation.
All windows shall be 100% openable, and grated to be protected from access.
All window fixtures shall be equipped with mosquito screens.
All classroom and library doors to the exterior shall be at least 160 cm large and equipped with an emergency bar; all doors shall open to the exterior.
Complete details are reported at Part 7 and Part 8, Section B20 of this document.
5.4 PLUMBING AND FIXTURES
The entire plumbing system shall be re-designed and replaced.
The water connection shall be rehabilitated and the feeding pipeline replaced with one adequately sized The plumbing system shall be complete and usable for the facility usage consisting of all fixtures, sanitary waste and vent piping systems, accessories, finish trim, anchorage and other specialty piping and equipment within 1.5 meter (5 foot) of the building.
Provide working space around all equipment.
Provide concrete pads under all equipment.
Provide all required fittings, connections and accessories required for a complete and usable system.
Anchor all plumbing fixtures securely into their final location.
Provide floor-mounted flush tank type water closets Provide the water supply by connecting to the existing water service.
provide copper piping for above ground installations, and use PVC or CPVC piping buried piping installations
5. Room Minimum Requirements p. 24/95
Provide escutcheons or other finish trim where pipes supplying plumbing fixtures penetrate visible, finish wall surfaces
Design and implement a septic system.
Complete details are reported at Part 7 and Part 8, Section D20 of this document.
5.5 ELECTRICITY AND LIGHTING
The entire electrical system shall be removed, re-designed, and replaced, including the feeder.
The electrical design shall keep into consideration the different use that each room is intended for and the relevant equipment to be installed. At least two 16A sockets shall be installed in each room up to 12 sqm (excluding toilets and storage room, at least four 16A sockets shall be installed in rooms between 12 and 30 sqm, at least six 16A sockets shall be installed in areas between 30 and 50 sqm, at least one sealed 16A socket shall be installed in each toilet area.
It is required the installation of low consumption lamps in a number and size sufficient to guarantee proper illumination to each type of space. The average illumination over the room area at 80 mm above the floor shall be at least 107 lux for offices and classrooms and at least 11 lux for corridors.
Three-way switches shall be installed close to each entry point to any space having more than one entrance.
Emergency lights shall be installed on each emergency door, and on each room’s main door.
At least one ceiling fan shall be installed in each room up to 12 sqm (excluding toilets and storage room). At least two ceiling fans shall be installed in rooms between 12 and 30 sqm. At least four ceiling fans shall be installed in areas between 30 and 50 sqm.
Electrical cables shall be dimensioned in accordance to the loads relevant to each circuit.
In order to properly dimension the section of an electrical cable it is recommended to make reference to the table below showing the typical max resistance values for copper cables of different sizes and the relevant maximum current each one can bear.
Section (mm2)
R (Ω/km)
Max Current (A)
1 19.5 5
1.5 13.3 10
2.5 7.98 16
4 4.95 26
6 3.30 32
10 1.91 50
16 1.21 68
25 0.78 92
35 0.55 120
The potential drops (depending on the cable resistance and on the current through it, V=R*I) shall be kept under 4%.
The connection to the public electrical network shall be done in agreement to the electrical company requirements.
Complete details are reported at Part 7 and Part 8, Section D50 of this document.
5. Room Minimum Requirements p. 25/95
Fig. 7 – Example of Panelboard
5.6 ELECTRICAL PANELBOARD AND GROUNDING SYSTEM
The electrical power feed shall be divided into subsidiary circuits by a panelboard providing a protective circuit breaker for each circuit. The panelboard shall be housed in a common enclosure.
The panelboard enclosure shall be galvanized sheet steel cabinet minimum 1.5 mm thickness, properly mating the panelboard to be enclosed; enclosure’s door shall be lockable.
A main switch located upstream the panelboard shall protect the electrical system against both overcurrents and residual (ground fault) currents through a Residual Current Breaker with Overcurrent protection (RCBO) whose sensitivity ID is 30 mA. Sensitivity may be bigger in case other RCDs (Residual Current Devices) with ID = 30 mA are provided downstream to protect groups of circuits.
Fig. 6 shows an example of RCBO.
Each circuit in the panelboard shall be protected against over-currents by a thermal magnetic breaker whose nominal current is ≤ of the max current associated to the relevant cable section, as shown in the table at par. 5.3.
Each breaker shall be labeled to show which circuit it controls.
Lighting circuits and utilization circuits shall be kept separated and individually protected on the panel board.
Fig. 7 shows an example of panelboard design matching the above requirements.
Fig. 6 - RCBO
5. Room Minimum Requirements p. 26/95
A grounding (earthing) system consisting of multiple connected rods shall be designed and implemented.
Rods shall be located away from most accessible areas, shall be protected from involuntary/unauthorized access and signposted by the earth symbol shown on the side.
5.7 LIGHTNING PROTECTION SYSTEM REQUIREMENTS
Type and number of air terminals and ground rods to be used shall be determined by the Designer, based on local conditions, earth resistivity data, and on the size and type of the electrical installation.
It is required that LPS is designed and installed by qualified, trained, personnel.
For normal conditions, copper clad steel rods are typically used.
Galvanized coated steel or stainless steel rods are typically used where low soil resistivities are encountered and galvanic corrosion may occur between adjacent underground metallic masses and the copper-clad rods.
In high resistivity soils, 3 m sectional rods may be used to obtain the required resistance to ground; however where rock is encountered, additional rods, a counterpoise, or ground grid may be necessary.
The rod selection for each facility shall be coordinated as specified in the following paragraphs.
~~~ End of Part 5 ~~~
Fig. 8 – Grounding Symbol
6. General Work Requirements p. 27/95
6 GENERAL WORK REQUIREMENTS
6.1 REFERENCE STANDARDS
Construction shall be in accordance with sound construction practices, and shall conform to the latest revision/edition of the codes, criteria, and standards referenced below except as otherwise indicated by this Technical Requirements.
Construction shall also comply with applicable codes, ordinances and regulations of the Republic of Gabon governing life/safety, fire protection, building construction, HVAC (heating ventilation and air conditioning) systems, plumbing systems and electrical systems in effect during this contract, except where specifically stated herein.
Any material installed that does not meet the requirements of the following Performance Technical Specification (PTS) and/or applicable codes, ordinances and regulations will be removed and reinstalled at Contractor’s expense.
6.2 WORK REQUIREMENTS
The building renovation and the exterior area settlement as described from Part 1 through 5 shall be in accordance to the specifications provided in the following Parts 7 and 8. All the engineering system requirements described in the Part 7 are more detailed in the corresponding Part 8.
Structural Report is required to describe the status of the existing structure.
Special attention shall be paid to develop and adhere to the STRUCTURAL DESIGN as well as to the ELECTRICAL DESIGN.
All the electrical work shall be implemented by a qualified installer also responsible for testing the system and delivering with a Compliance Certificate issued by a local qualified entity.
6.3 DESIGN GUIDANCE
Design shall be in accordance with sound design and engineering practices, and shall conform to the latest revision/edition of the codes, criteria, and standards referenced below except as otherwise indicated by this Technical Requirements. Design shall also comply with applicable codes, ordinances and regulations of the Republic of Gabon governing life/safety, fire protection, building construction, HVAC systems, plumbing systems, electrical systems and sanitation systems in effect during this contract, except where specifically stated herein.
The advisory provisions of all codes, requirements, and standards shall be mandatory; substitute words such as “shall”, “must”, or “required” for words such as “should”, “may”, or “recommended,” wherever they appear. The results of these wording substitutions incorporate these code and standard statements as requirements. Reference to the “authority having jurisdiction” shall be interpreted to mean “Contracting Officer”. Comply with the required and advisory portions of the current edition of the standard at the time of contract award.
The last two sections of this document, in many instances, give multiple options for material and processes. It is the intent to give the contractor’s designer freedom to use one or multiple options in the design, based upon sound design and engineering practices and the requirements of the project. Once an option is selected for the project, all requirements outlined in the PTS for that option are to be incorporated in the design.
6.4 PERFORMANCE TECHNICAL SPECIFICATIONS
The specifications for this project are requirements based, meaning that the technical details of how to meet this requirement are not included in the PTS.
The contractor shall determine the technical requirements for satisfying these specifications and present them as part of the design package.
The contractor’s design shall provide the technical requirements for the project and the contractor shall be responsible for ensuring their design meets all specifications presented in this SOW.
6. General Work Requirements p. 28/95
6.5 SUBMISSIONS
The Contractor shall be responsible for developing a design for the facility that meets all the operational requirements identified in this document. Contractor shall provide a full design of the facility to include drawings and all calculations and details required to validate the design.
CONCEPT DESIGN
Within 50 calendar days since the contract award, the contractor shall submit a concept design to consist of the following drawings:
- Structural Report of existing structures
- Geotechnical Report
- Site Demolition Plan (identifying existing items to demolish and existing items to remain)
- Site Plan (identifying existing items to remain and new items)
- Floor Plans of new structures
- Exterior Elevations of new structures
- Sections of new structures
- List of final design documents to be submitted, to include an explanation of any documents listed below but not required
The Government shall review the submission and provide written comments to the contractor.
In the event the contractor does not concur with the Government comments, the contractor shall notify the Government in writing of the reasons for the non-concurrence.
FINAL DESIGN
Within 100 calendar days after the review of the concept design submittal is complete and comments are returned to the contractor, the contractor shall submit a complete, final design incorporating all the comments from the Government, to consist of the following (as required):
- Civil Design
- Site Demolition Plan
- Site Plan
- Grading Plan
- Utility Plan
- Architectural Design
- Floor Plans
- Roof Plans
- Room Finish Schedule
- Door and Window Schedules
- Exterior Elevations
- Building Sections
- Wall Sections
- Enlarged Plans
- Reflected Ceiling Plans
- Interior Elevations
- Stair Plan and Sections
- Door and Window Details
- Miscellaneous Details
- Structural Design
- Structural Notes/Basis of Design
- Pier Plan/Schedule
- Foundation Plan
6. General Work Requirements p. 29/95
- Floor and Roof Framing Plans
- Lateral-Force Resisting System
- Sections and Details
- Structure Calculation
- Mechanical Design
- Mechanical Plans
- Schematic Diagrams
- Equipment Schedules
- Miscellaneous Details
- Plumbing Design
- Plumbing Plans
- Plumbing Schedule
- Plumbing Riser Diagrams
- Miscellaneous Details
- Electrical Design
- Notes, Legends, Symbols List
- Distribution Switchboard Scheme
- Grounding System Plan
- Single Line Diagrams
- Floor…