Attachment 1 - Statement of Work
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_4_-_Submittal_Checklist.pdf | ||
| Attachment_2_-_Contract_Data_Sheet.pdf | ||
| Attachment_3_-_PPQ.pdf | ||
| Attachment_5_-_APP_Template.pdf | ||
| N33191-14-R-0629_SOL.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Prepared by: NAVFAC EURAFSWA HQ – CEBL Sonia Grillo
AFRICOM
Humanitarian Assistance Program
Toucountouna Middle School Expansion
Atakora, BENIN
OHASIS BN-HA-2013-022629
FY14
June 2014
TECHNICAL REQUIREMENTS
Toucountouna Middle School, Atakora, BENIN Attachment (1)
Table of Contents p. 2/84
TABLE OF CONTENTS
COVER PAGE
TABLE OF CONTENTS
LEGEND: ACRONYMS AND DEFINITIONS
1 PROJECT DESCRIPTION
1.1 GENERAL 10
1.2 SCOPE OF PROJECT 10
1.3 SIGNAGE 11
1.4 STANDARD NOMENCLATURE 11
1.5 PROCEDURE 12
Concept Design Final design Construction Schedule Quality Control Plan Accident Prevention Plan [APP] Interim Submittal Requirements Completion Submittal Requirements
2 PROJECT OBJECTIVES
2.1 MISSION STATEMENT 14
2.2 FACILITY FUNCTION 14
2.3 PROJECT SPECIFIC PRIORITIES 14
2.4 APPROPRIATE DESIGN 14
2.5 WORKFLOW PROCESS - HOURS OF OPERATION 14
3 SITE ANALYSIS
3.1 EXISTING SITE CONDITIONS 15
Facility Footprint
3.2 PHOTO DESCRIPTION 16
3.3 SITE DEVELOPMENT REQUIREMENTS 17
Design Constraints Access, Circulation, and Site Development
4 BUILDING REQUIREMENTS
4.1 NEW CLASSROOM BUILDINGS 19
Table of Contents p. 3/84
4.2 NEW LABORATORY BUILDING 19
4.3 SETTLEMENT OF EXTERNAL AREAS 19
4.4 NEW FACILITY SPACE TABULATION 19
4.5 MOE STANDARD DESIGN FOR CLASSROOMS 20
4.6 MOE STANDARD DESIGN FOR LABORATORY 21
4.7 DRY VENTILATED IMPROVED PIT (VIP) LATRINES 22
4.8 PROJECT SIGN 23
4.9 DEDICATION SIGN 23
5 ROOM MINIMUM REQUIREMENTS
5.1 FLOORS AND WALLS 24
5.2 VENTS, DOORS AND WINDOWS 24
5.3 DRY VIP LATRINES 24
5.4 PLUMBING AND FIXTURES 24
5.5 ELECTRICITY AND LIGHTING 25
5.6 GROUNDING SYSTEM 25
5.7 ELECTRICAL PANELBOARD 26
5.8 LIGHTNING PROTECTION SYSTEM (LPS) REQUIREMENTS 27
6 GENERAL WORK REQUIREMENTS
6.1 REFERENCE STANDARDS 28
6.2 WORK REQUIREMENTS 28
6.3 DESIGN GUIDANCE 28
6.4 PERFORMANCE TECHNICAL SPECIFICATIONS 28
6.5 SUBMISSIONS 29
Concept Design Final Design Construction Schedule Quality Control Plan Accident Prevention Plan
6.6 CONSTRUCTION GUIDANCE 31
6.7 CERTIFICATIONS, LICENSES, PERMITS, FEES, ETC. 31
6.8 COORDINATION 31
6.9 VEGETATION CONTROL 31
6.10 RESPONSIBILITY OF MATERIALS 31
Table of Contents p. 4/84
6.11 SAFETY AND PROTECTION 32
6.12 SPILL CONTINGENCY PLAN 32
6.13 SPECIAL SITE CONDITIONS 33
6.14 CLEANING 33
7 ENGINEERING SYSTEMS REQUIREMENTS
7.1 SECTION A10 FOUNDATIONS 34
A1010. Standard Foundations A1030. Slab On Grade
7.2 SECTION B10 SUPERSTRUCTURE 34
B1010. Floor Construction B1020. Roof Construction
7.3 SECTION B20 EXTERIOR ENCLOSURE 35
B2010. Exterior Walls
B201001. Balcony Walls, Guard Rails & Handrails B201002. Exterior Coatings
B2020. Exterior Windows B202001. Exterior Windows B202002. Exterior Glazing B201003. Exterior Louvers & Screens
B2030. Exterior Doors B203007. Gates
7.4 SECTION B30 ROOFING 36
B3010. Roof Coverings
B301001. Steep Slope Roofing Systems B301002. Low Slope Roofing Systems
7.5 SECTION C10 INTERIOR CONSTRUCTION 36
C1010. Partitions
C101001. Interior Guardrails C101002. Interior Screens C101003. Interior Windows C101004. Interior Glazing
C1020. Interior Doors C102001. Standard Interior Doors C102002. Glazed Interior Doors
C1030. Specialties C103001. Toilet Compartments and Accessories C103003. Marker Boards C103004. Counters C103005. Cabinets C103006. Ornamental Metal Work
7.6 C30 INTERIOR FINISHES 37
C3010. Wall Finishes C3020. Floor Finishes C3030. Ceiling Finishes C3040. Interior Coatings And Special Finishes
7.7 SECTION D20 PLUMBING 37
D2010. Plumbing Fixtures
D201001. Water Closets D201002. Urinals
Table of Contents p. 5/84
D201003 Lavatories D201004. Sinks D201005. Finish Trim
D2020. Domestic Water Distribution D202001. Pipes and Fittings D202002. Domestic Water Equipment D202003. Insulation & Identification D202004. Specialties D202005. Other Domestic Water Supply
7.8 SECTION D50 ELECTRICAL 38
D5010. Electrical Service And Distribution
D501002. Service Entrance Equipment D501004. Switchboard D501005. Enclosed Circuit Breakers
D5020. Lighting And Branch Wiring D502001. Branch Wiring D502002. Lighting Equipment D502003. Finish Trim D502004. Potential Drop
D5040. Other Electrical Services D504001. General Construction Items (Electrical) D504002. Emergency Lighting and Power D504003. Grounding Systems D504004. Lightning Protection D504005. Electric Heating
7.9 SECTION G10 SITE PREPARATION 40
G1010. Site Clearing
G101001. Clearing G1030 Disposal
7.10 SECTION G20 SITE IMPROVEMENTS 40
G2040. Site Development
G204001. Freestanding Walls & Gates
7.11 SECTION G30 SITE CIVIL/MECHANICAL UTILITIES 41
G301003. Water Storage
8 PERFORMANCE TECHNICAL SPECIFICATIONS (PTS)
8.1. NARRATIVE 42
8.2. SECTION A10: FOUNDATIONS [6/07] 42
A10 General A1010 Standard Foundations
A101001 Wall Foundations A101002 Column Foundations And Pile Caps A101003 Foundation Drainage
A1020 Slab On Grade A102001 Concrete Slabs On Grade A102002 Slab On Grade Insulation
A1030 Elevated Floor Slabs A1040 Concrete
A104001 Concrete Materials A104002 Concrete Formwork A104002 Concrete Reinforcement A104003 Placing Concrete Reinforcement A104004 Concrete Mixing A104005 Concrete Conveying A104006 Concrete Depositing A104007 Concrete Curing
Table of Contents p. 6/84
A104008 Hot Weather Concrete A104009 Concrete Construction Joints A104010 Concrete Testing
8.3. SECTION B10: SUPERSTRUCTURE [06/07] 48
B10 General B1010 Construction Components B1020 Wood B1030 Unit Masonry B1050 Steel
8.4. SECTION B20: EXTERIOR ENCLOSURE [04/07] 53
B20 General B2010 Exterior Walls
B201001 Unit Masonry B201002 Guardrails ad Handrails B201003 Exterior Painting and Special Coatings
B2020 Exterior Windows B202001 Standard Window Systems B202002 Louvered Windows B202003 Screens B202004 Roll Shutters
B2030 Exterior Doors B203001 Standard Doors Systems B203002 Door Frames B203003 Exterior Door Hardware B203004 Exterior Door Hardware Finishes B203005 Other Exterior Specialty Doors
8.5. SECTION B30: ROOFING [04/07] 56
B30 General B3010 Steep Slope Roof Systems
B301001 Slate Roofing B301002 Roof Tiles B301003 Metal Roof Panels B301004 Concrete Roof Panels
B3020 Low Slope Roof Systems B302001 Built-Up Asphalt Roofing (Aggregate Surfaced)
B3030 Flashings & Trim B303001 Flashing And Sheet Metal B301002 Gutters and Downspouts B301003 Roof Openings and Supports B301004 Other Roofing
8.6. SECTION C10: INTERIOR CONSTRUCTION [06/07] 59
C10 General C1010 Partitions
C101001 Unit Masonry C101002 Handrails C101003 Interior Painting And Special Coatings
C1030 Interior Doors C103001 Standard Doors Systems C103002 Door Frames C103003 Interior Door Hardware C103004 Interior Door Hardware Finishes C103005 Other Interior Specialty Doors
C1040 Specialties C104004 Counters C103005 Cabinets C104006 Casework
Table of Contents p. 7/84
8.7. SECTION C30: INTERIOR FINISHES [04/07] 62
C30 General C3010 Wall Finishes
C301001 Plaster Wall Finishes C301002 Tile Wall Finishes
C3020 Floor Finishes C302001 Ceramic Tile Floor Systems C302002 Ceramic Glazed Tile Floor C302003 Ceramic Mosaic Unglazed Floor Tiles C302004 Porcelain Floor Tile C302005 Quarry Floor Tile C302006 Terrazzo Floor Finishes C302007 Masonry And Stone Flooring C302008 Wall Base Finishes C302008 Stair Finishes C302009 Hardeners And Sealers
C3030 Ceiling Finishes C303001 Acoustical Ceiling Tiles And Panels C303002 Plaster Ceiling Finishes
C3040 Interior Painting And Special Finishes C304001 Painting Systems Per Substrate C304002 Concrete Finishes C304003 Concrete Masonry Finishes C304004 Plaster Finishes C304005 Metal Finishes C304006 Interior Wood Finishes
8.8. SECTION D20: PLUMBING [08/06] 68
D20 General D2010 Plumbing Fixtures
D201001 Water Closets D201002 Urinals D201003 Lavatories D201004 Sinks D201005 Showers/Tubs
D2020 Domestic Water Distribution D202001 Pipes & Fittings D202002 Valves & Hydrants D202003 Domestic Water Equipment D202004 Insulation & Identification
D2030 Sanitary Waste D203001 Waste Pipe & Fittings D203002 Vent Pipe & Fittings D203003 Floor Drains
8.9. SECTION D30: HVAC [06/07] 70
D30 General D3010 Heat Generating Systems
D301001 Boilers D301002 Heating Hot Water Distribution Systems D301003 Terminal Units D302001 Requirements D302002 Hot Water Heating Equipment Startup and Operational Tests
D3040 Performance Verification And Testing
8.10.SECTION D50: ELECTRICAL [08/06] 72
D5010 General
D501001 Quality Assurance D501002 Submittals
D5020 Electrical Service And Distribution D502001 Main Transformers D502002 Service Entrance Equipment
Table of Contents p. 8/84
D502003 Interior Distribution Transformers D502004 Switchboard D502005 Enclosed Circuit Breakers D502006 Motor Control Centers D502007 Other Service And Distribution
D5030 Lighting And Branch Wiring D503001 Branch Wiring D503002 Lighting Equipment D503003 Ballasts
D5050 Other Electrical Services D505002 Emergency Lighting And Power
8.11.SECTION G10: SITE PREPARATION 76
G10 General G1010 Site Clearing G1020 Site Demolition & Relocations
G102001 Building Mass Demolition G102002 Hazardous Components Abatement G102003 Aboveground Site Demolition G102004 Underground Site Demolition G102005 Fencing Relocation G102008 Site Cleanup
G1030 Site Earthwork G103001 Grading G103002 Common Excavation G103003 Rock Excavation G103004 Fill & Borrow G103005 Compaction G103006 Soil Stabilization G103007 Slope Stabilization G103008 Shoring G103009 Temporary Dewatering G103010 Temporary Erosion & Sediment Control G103011 Other Site Earthwork
G1040 Hazardous Waste Remediation
8.12.SECTION G20: SITE IMPROVEMENTS [08/06] 80
G20 General
G2010 Roadways G201001 Paved Surfaces G201002 Resurfacing
G2020 Pedestrian Paving G2030 Other Site Development G204001 Fencing & Gates G204002 Retaining Walls
Legend p. 9/84
LEGEND: ACRONYMS AND DEFINITIONS
As used throughout this solicitation/contract:
Contracting Officer [KO] is the Government’s representative in charge for executing the contract and responsible for any amendment.
Contractor is for the Offeror that has been awarded the contract COR stands for the Contracting Officer Representative, who is a qualified Government employee appointed by the KO to assist in the technical monitoring or administration of a contract D/B contract stands for Design and Build contract, which means that the contractor shall first provide a complete and executable design matching the specifications of the TR, then implement the construction in accordance to such a design.
DOD stands for U.S. Department of Defense ESR stands for Engineering System Requirements Government stands for the Government of the United States of America (U.S.A.);
HVAC stands for Heating, Ventilating and Air Conditioning NAVFAC EURAFSWA stands for Naval Facilities Engineering Command Europe, Africa and South West Asia; it is the Government’s executive agent for construction.
NTPC stands for Notice To Proceed with the Construction NTR stands for Navy Technical Representative, who is in charge to monitor the performance of work under the contract and is an accountable official for purposes of certifying payments Offeror is any constructor that submits a bid Project Manager [PM] is the Government’s technical representative in charge for managing the project (scope, cost, and schedule) from design authorization to closeout PTS stands for Performance Technical Specifications RFP stands for Request for Proposal RFQ stands for Request for Quote SF stands for Government’s standard form; this acronym is followed by a number identifying what contract action the form is intended for SOW stands for Statement Of Work: it is the detailed description of the work activities, deliverables and timeline the contractor will execute against in performance of specified work TEB stands for the Government Technical Evaluation Board in charge to receive, accept and evaluate the technical offers TR stands for Technical Requirements which are integrant part of the SOW and provide all the specifications for the design and the implementation of the project.
VIP stands for Ventilated Improved Pit which is the type of latrine to be implemented at the site as described in this SOW.
1. Project Description p. 10/84
1 PROJECT DESCRIPTION
1.1 GENERAL
This is a design-build project to expand a middle school in accordance to the requirements, sketches, and tables included hereby.
The work shall include - but not be limited to - the following: Demolition of existing structures, Foundations, Structures, Superstructures, Interior Construction, Roof System, Drainage System, Electrical System, Plumbing System, Exterior Area Settlement, Site Improvements and Other Work as required.
The work shall include a complete design and drawing package as described in this document.
Design-Build Procedure The Design-Build procurement method consists of a design phase and construction phase. The construction phase shall start only after acceptance of the contractor’s complete design.
The design shall be developed by qualified design professionals, either consistently employed in the contractor’s company or working for a design firm hired by the contractor for the purpose of this project.
The electrical work shall be implemented by a qualified installer able to release a certificate of compliance to the codes.
1.2 SCOPE OF PROJECT
The work shall consist of the following (dimensions are approximate):
a. Build two 41m x 12m Classroom Buildings, to include:
four 10m x 9m classrooms with access from veranda one veranda covering the full length of entrance side electrical system lightning protection system (LPS)
b. Build one 15m x 13m Laboratory Building, to include:
one 11m x 8m experimentation room with 5 workstations and one monitoring counter one 4m x 5 m preservation room one 4m x 6 m preparation room one veranda covering the full length of entrance side electrical system plumbing system
c. Build two dry Ventilated Improved Pit [VIP] latrine facilities, to include:
ten stalls (5 per gender, 2 for teachers) two basins with two faucets (for students, 1 per gender) two basins with one faucet (for teachers, 1 per gender) a screen wall
d. Dismantle two urinal facilities, the one located in the area of new Lab, and the one close to the existing latrines.
1. Project Description p. 11/84
The new work shall result into complete, safe and usable facilities, whose interior spaces shall reflect the space tabulations provided in Part 4.
Design and construction details are provided in Part 5, and specified in Parts 6, 7, and 8.
All buildings shall have concrete superstructure and masonry infill construction with basic finishes.
All buildings shall have a storm water drainage system to prevent erosion.
The work shall include - but not be limited to - the following: Demolition of existing structures, Foundations, Structures, Superstructures, Interior Construction, Roof System, Exterior Area Settlement, Site Improvements and Other Work as required.
Design shall meet all requirements of the RFP package. Drawings to be as described below and as required to communicate the design to the US Government, final users, contractor’s staff and sub-contractors. Material selection, specifications and installation to be as described the in the Engineering Systems Requirements (ESR), and in the Performance Technical Specification (PTS), included below as the last two parts.
The ESR and the PTS of this document provide a guideline for the design package. If an item in the project design is included in the ESR/PTS, the requirements of the ESR/PTS and applicable local codes shall govern. If an item in the project design is NOT included in the ESR/PTS, the requirements of applicable local codes shall govern.
Design Acceptance and Construction Authorization The construction cannot start until all submittals required by this contract are received and reviewed by the US Government and shown to meet the requirements of these Technical Requirements and the RFP package. The acceptance of the design and authorization to start construction will be issued by the NAVFAC EURAFSWA project manager.
1.3 SIGNAGE
Project Sign The Contractor shall provide a painted project sign to be located at the worksite as soon as the construction starts. The paint shall be water resistant and display the project name, the Beninese and American flags, and the wording explaining the cooperation between the two Governments.
The Contractor shall submit a proof of the sign for acceptance prior to construction.
See detailed requirements at par. 4.8
Dedication Sign The Contractor shall provide a project dedication sign (approximately 800 mm x 1200 mm) at the project site at least 2 weeks prior to project completion.
The project name shall appear at the top center, followed by the sentence “An everlasting example of friendship between the people of Benin and the United States” above the flags, and the sentence “Completed by the people of Benin and the United States of America on DD MONTH, YYYY” at the bottom.
The sign shall be constructed of sheet metal with a water resistant coating and affixed directly to the building at a location approved by the facility administrator and the COR.
The Contractor shall submit a proof of the sign for acceptance prior to manufacturing the sign.
See detailed requirements at par. 4.9
1.4 STANDARD NOMENCLATURE
This is an American document, and this note is to define the way in which numbers are presented herein:
1,000 = one thousand 3,500 = three-thousand five-hundred
1.08 = one and eight hundredths
0.1 = one-tenth
1. Project Description p. 12/84
1.5 PROCEDURE
The construction phase shall start only once that the official Notice to Proceed with Construction (NTPC) is issued by the NAVFAC EURAFSWA Project Manager/Contracting Officer.
The NTPC will not be issued until all required submittals are received and reviewed by the US Government and shown to meet the specifications of these Technical Requirements and the Solicitation package.
PRE-CONSTRUCTION SUBMITTALS CONSIST OF:
Concept Design Final Design Construction Schedule Quality Control Plan Accident Prevention Plan
CONCEPT DESIGN
The concept design shall be submitted within 50 calendar days of receipt of the award. The concept design is intended to assure all lay-out requirements are clearly met before the full design is developed. It shall identify site preparation, including items to be removed and to be kept. It shall provide the basic architectural design, including:
Current Site Layout plan with dimensions and distances Geotechnical Report Final Site Layout plan with dimensions and distances Final Plans, Elevations and Sections of each building object of the contract.
The Government shall review the concept design submission for compliance with these Technical Requirements and the Solicitation package and provide written comments to the contractor.
See paragraph 6.5 for detailed explanation about the concept design.
FINAL DESIGN
The contractor shall have 100 calendar days to complete the design, incorporating all concept design review comments provided by the US Government. Elapsed timelines may be considered depending on which option is awarded, if any.
In the event the contractor does not concur with the US Government comments, the contractor shall notify the contracting officer in writing of the reasons for the non-concurrence.
The final design shall meet all the requirements identified in these Technical Requirements and the Solicitation package and shall include:
Site Improvement Drawings Architectural Drawings Structural Drawings Plumbing Drawings Electrical Drawings All Calculations and Details required to validate the design.
See paragraph 6.3, 6.4 and 6.5 for detailed explanation about the final design.
CONSTRUCTION SCHEDULE
The contractor shall have 300 calendar days to complete the construction work.
Within the timeframe allowed for the final design submission, the contractor shall prepare and submit a schedule of construction where the different work segments are identified and associated to the timeframe set for completion. The construction schedule shall state which work segments completion determines the achievement of the construction steps associated to the progressive invoicing (i.e. 10% (design completion), 30%, 50%, 70% and 90% work progress). The final payment will be done on the facilities acceptance.
See paragraph 6.5 for more details about the construction schedule.
1. Project Description p. 13/84
QUALITY CONTROL PLAN
Within the timeframe allowed for the final design submission, the Contractor will prepare and submit a Quality Control Plan describing personnel, procedures, tests and installation techniques that he plans to perform to ensure the quality required by this document and his design is obtained.
ACCIDENT PREVENTION PLAN [APP]
Within the timeframe allowed for the final design submission, the Contractor will prepare and submit an APP describing procedures he plans to perform to ensure the safety of personnel and equipment on the job site. At a minimum, the safety plan must address types of personnel protective equipment to be used by personnel, types and frequencies of safety inspections, hazard analysis plan [AHA] to prevent safety incidents, and training utilized to familiarize employees with safety policies and practices.
See paragraph 6.5 for more details about the APP.
INTERIM SUBMITTAL REQUIREMENTS
During construction, the Contractor is required to submit:
Bi-weekly work progress report with photos Monthly work man-hours report Test results as required per the contract At least 10 days prior to installation of all electrical components, plumbing fixtures, windows and doors and associated hardware, a sample (or catalog photo) must be shown to the KO or COR for acceptance.
Possible construction schedule changes (to be motivated) Possible design changes (to be motivated) Invoices in accordance to work progress
COMPLETION SUBMITTAL REQUIREMENTS
Upon completion of project and prior to final payment, the Contract is required to submit:
Final as-built drawings Operations and maintenance plan A telephone contact number available for the duration of the warranty period.
~~~ End of Part 1 ~~~
2. Project Objectives p. 14/84
2 PROJECT OBJECTIVES
2.1 MISSION STATEMENT
DoD humanitarian assistance activities were first authorized by US Congress in 1986. In FY 1996, DoD was permitted to fund a wider variety of HA activities, including using contracts and deployment of U.S. Government personnel to conduct specific humanitarian projects.
Typical projects include the refurbishment of medical facilities, construction of school buildings, digging of wells, improvement of sanitary facilities, and training of host country personnel in internally displaced persons/refugee repatriation operations and in disaster relief and emergency response planning.
The DoD, in an attempt to assist in development and implementation of the Humanitarian Assistance Program, is funding and coordinating the project which is the subject matter of this contract.
NAVFAC EURAFSWA has been designated as the Construction Agent for this project.
2.2 FACILITY FUNCTION
The school complex is situated in a highly populated area lacking middle school facilities. The expansion of this school will improve a stable learning environment, and allow education to more young population in this area, so to influence children away from deviant behavior, and to produce more competent human resources for economic and social development of the Country.
2.3 PROJECT SPECIFIC PRIORITIES
Sustainable Design Integrate sustainable principles into the design, development and construction of the project.
Reduce the total cost of ownership of the facility using a whole building, life-cycle approach.
Provide integrated sustainable design strategies and features to minimize the energy consumption of the facilities; conserve resources; minimize adverse effects to the environment; and improve occupant productivity, health, and comfort.
Energy Conservation Integrate energy conservation principles into the design, development and construction of the project. Reduce the total cost and consumption of energy in the facility using a whole building approach.
2.4 APPROPRIATE DESIGN
The design is to maintain an indigenous character. As much as possible, materials are to be available locally to promote the local economy and to take advantage of the skills and experience of local trades-persons. Construction methods are to be in-line with those used locally to take advantage of the skills and experience of local trades-persons.
2.5 WORKFLOW PROCESS - HOURS OF OPERATION
The work of this contract is to be done during the hours the facility is normally open to the public.
If needs arise to work other than normal hours, obtain approval from, and coordinate with the facility owner.
~~~ End of Part 2 ~~~
3. Site Analysis p. 15/84
3 SITE ANALYSIS
3.1 EXISTING SITE CONDITIONS
The school complex is situated close to Toucountouna village in Atakora area, at coordinates
10.49403 and 1.382767.
The site is currently composed of seven buildings plus one 6–stall latrine and two 2-stall old urinals.
The school is connected to the public electric grid, and has a water supply delivery point located at the entrance of the area.
FACILITY FOOTPRINT
A scaled drawing with exact dimensions showing the site lay-out including location and dimensions of all existing buildings, latrines, obstacles, and perimeter wall (if any) with gate locations shall be included in the concept design.
Water delivery point Water delivery point
Electricity delivery point
3. Site Analysis p. 16/84
3.2 PHOTO DESCRIPTION
The school area is shown in the photos below:
View from Entrance
Area for new classrooms
Area for one VIP facility
Area for Laboratory
Urinals to be removed
Area for one VIP facility
Urinals to be removed
3. Site Analysis p. 17/84
3.3 SITE DEVELOPMENT REQUIREMENTS
An example of the final school layout is sketched below, with the new facilities shown in yellow.
Exact new facility positioning shall be selected to best fit the topography and the existing layout; it shall be coordinated with the PM and the school officials after the footprint of current layout has been submitted.
DESIGN CONSTRAINTS
Design of the facility and its location and orientation within the proposed site shall take into consideration all natural and man-made constraints, which include but aren’t limited to:
Topography: all site slopes shall be taken in account in order to minimize the need for cut and fill operations Vegetation / Landscaping: vegetation shall be protected, and landscaping design shall be maintainable Climatology (solar orientation, etc.): Design shall take advantage of prevailing wind direction and solar orientation to naturally moderate the interior temperature of the buildings Geotechnical Data: Foundations and structural components of the buildings shall be designed in accordance with geotechnical soils report information. Geotechnical engineering services shall be provided if no current report exists for the site. Design shall be in accordance to the seismic zone of classification of the project site.
Hydrographic Survey: a hydrographic survey shall be performed to determine the storm water runoff Vehicular Access and Circulation: existing vehicular access shall be taken in account Site Utilities: location and capacity of all existing utilities on site shall be verified prior to start design Site Drainage: the facilities shall be designed without negative impact from storm water runoff to the adjacent area of the site.
3. Site Analysis p. 18/84
Existing Buildings: Identify and accurately locate on the site plan all existing buildings on the site.
Fencing: Identify and accurately locate on the site plan all existing fencing on the site.
Permits: all permits, approvals, and authorizations needed to implement the design shall be obtained prior to start construction.
ACCESS, CIRCULATION, AND SITE DEVELOPMENT
Any proposed vehicular and/or pedestrian access, paths, sidewalks, steps, parking areas, outdoor recreation area, landscaping etc. shall be reported on the site plan, as well as areas of material storage and temporary security fencing.
All proposed drainage channels shall be shown on the site plan.
The location of the construction sign and any other signage required by local authorities shall be indicated on the site plan.
~~~ End of Part 3 ~~~
4. Building Requirements p. 19/84
4 BUILDING REQUIREMENTS
4.1 NEW CLASSROOM BUILDINGS
Two identical new classroom buildings shall be built in the area indicated at par. 3.3. Exact position shall be determined during the design phase.
Each building shall be made of four classrooms matching the Beninese construction standards for schools.
Each classroom shall be accessible from the veranda through a 160 cm door opening to the exterior.
The design shall maintain an indigenous character and to match the features of the existing school facilities (see photo below).
4.2 NEW LABORATORY BUILDING
A laboratory building served by water and electricity shall be built in the area indicated at par. 3.3.
Exact position shall be determined during the design phase.
The building shall be composed of one experimentation room equipped with 5 workstations, one preparation room, and one preservation room, as indicated at par. 4.8.
4.3 SETTLEMENT OF EXTERNAL AREAS
Coordination with school official is required in order to make sure that sufficient space is left vacant to be used as playground.
The Contractor shall grade the site to limit water from ponding and promote positive drainage off of the grounds.
4.4 NEW FACILITY SPACE TABULATION
Indicative data regarding the required size of the spaces in the new facilities are provided in the table below.
On the concept design submittal the contractor is required to provide exact dimensions corresponding to the actual design; a variance exceeding ±10% of the indicative size will not be considered acceptable.
New Classroom Buildings
Space Name Qty Unit m2
(Net)
Tot m2 (Net)
Optimal Size (m)
Ceiling Height (m) people per room
Remarks
Classroom 4 90 360 10 x 9 3.60 50 160 cm door; 5 windows, 2 blackboards, vent openings between the trusses on top part of front and rear walls
Veranda 1 36 72 1.8 x 20 3.60 - along the entrance side
4. Building Requirements p. 20/84
Laboratory Building
Space Name Qty Unit m2
(Net)
Tot m2 (Net)
Optimal Size (m)
Ceiling Height (m) people per room
Remarks
Experimentation Room
1 88 88 11 x 8 3.60 20 Five masonry counters w/sinks, one masonry counter w/o sink
Preparation Room
1 24 24 4 x 6 3.60 4 One L-shaped masonry counter with two sinks
Preservation Room
1 20 20 4 x 5 3.60 - Five masonry cabinets 90 x 50 x 200
Veranda 1 30 30 2 x 15 3.60 - along the entrance side
VIP Latrine Facility
Space Name Qty Unit m2
(Net)
Tot m2 (Net)
Optimal Size (m)
Ceiling Height (m) people per room
Remarks
Stalls 10 1.7 17 1.5 x 1.1 - 1 wall vents on the door and on the rear wall
Areas b/w stalls and screen wall
4 - 1 basin with two faucets for students, with 1 faucet for teachers
Dry pit 1 12 12 1.3 x 9 - 0 below the stalls, 6 m deep
4.5 MOE STANDARD DESIGN FOR CLASSROOMS
The typical floor plan layout for a 4-classroom block set by Beninese Ministry of Education standards is reported below:
4. Building Requirements p. 21/84
4.6 MOE STANDARD DESIGN FOR LABORATORY
The typical floor plan layout for a library building set by Beninese Ministry of Education standards is reported below:
4. Building Requirements p. 22/84
4.7 DRY VENTILATED IMPROVED PIT (VIP) LATRINES
Two 10-stall dry VIP latrine facilities shall be built in proximity of the existing ones.
Exact position to be determined in order to guarantee proper ventilation and easy access.
Special attention shall be provided to make sure the VIP facility is placed downwind of the school facilities, preferably where the soil is firmer and has good drainage. The doorway of the VIP latrine shall face the prevailing winds.
The latrine facilities shall be located at least 6 m away from any other surrounding construction, including the fence wall. Separate male/female access to be implemented.
The final design shall reflect the shape and dimensions of section and elevation reported above and on the side, and shall incorporate all requirements described at par.5.3.
A reference scheme for a 8-stall VIP design with separate access for teachers is shown below: the final design shall be adjusted to the number of stalls and faucets required in this document Central stalls shall be for teachers, if required.
4. Building Requirements p. 23/84
4.8 PROJECT SIGN
The Contractor shall provide a painted project sign to be located at the worksite as soon as the construction starts. The sign shall be made of wood and supported by wooden or metal posts.
The approximate size of the sign shall be 800mm x 1200mm and the sign shall be placed in such a way so as to provide the most visibility to passers-by; the location shall be agreed with the COR.
The Contractor shall submit a proof of the sign for approval prior to construction.
The paint shall be water resistant and display the following:
TOUCOUNTOUNA SECONDARY SCHOOL
EXPANSION
<Beninese flag> <American flag>
In cooperation with the Beninese Government, funding for this project is provided by the U.S. Government.
<Contractor’s Name>
Project name shall appear at the top center in 76mm (3 inch) tall capital block letters. The sentence below the flags shall be in 38mm (1.5 inch) sentence case lettering. Contractor company name may be added at the bottom of the sign.
4.9 DEDICATION SIGN
At least 2 weeks prior to project completion a project dedication sign shall be affixed at the project site. The sign shall be affixed directly to the building at a location approved by the facility administrator and the COR to provide optimal visibility.
The sign shall be constructed of sheet metal with a water resistant coating and shall have a frame around it. The frame material shall be wood and be approved by the COR prior to installation. The size of the sign shall be approximately 800 mm x 1200 mm.
No later than 4 weeks prior to the planned project completion, the Contractor shall contact the KO or the COR regarding final wording for the dedication sign.
The Contractor shall provide a proof of the sign for acceptance prior to manufacturing the sign.
The sign shall display the following:
TOUCOUNTOUNA SECONDARY SCHOOL
EXPANSION
An everlasting example of friendship between the people of Benin and the United States.
<translation into the Host Nation primary language>
<Beninese flag> <American flag>
Completed by the people of Benin and the United States of America on:
DD MONTH, YYYY
The project name shall appear at the top center in 76mm (3 inch) tall block letters, followed by the above sentence in 38mm (1.5 inch) sentence case lettering that shall be repeated in the Host Nation primary language. The Host Nation and American flags shall be placed as displayed in the above sketch. The sentence at the bottom shall be in 20mm (0.75 inch) sentence case lettering.
~~~ End of Part 4 ~~~
5. Room Minimum Requirements p. 24/84
5 ROOM MINIMUM REQUIREMENTS
5.1 FLOORS AND WALLS
All classroom floors shall be paved with perfectly flat polished maroon industrial concrete minimum 3 cm thick, compatible with Beninese Ministry of Education’s construction standards.
All laboratory floors shall be tiled flooring granting good resistance and easiness to be kept sanitized.
All walls shall be plastered and painted with glaze suitable for school use. Interior walls of laboratory (except preservation room) shall be tiled up to 2 m height.
Complete details are reported at Part 7 and Part 8, Section C30 of this document.
5.2 VENTS, DOORS AND WINDOWS
Wall vent openings sized 1m x 0.5 m, and protected by mosquito screens shall be implemented on the top part of front and rear walls between the trusses.
All door and window openings shall be equipped with lintels; all fixtures shall be in metal.
Windows shall be sized 2.4m x 1.2m shall be implemented in each classroom.
All window fixtures shall be 100% openable, equipped with adjustable jalousies, and protected by mosquito screens.
All entrance doors shall be 160 cm large and equipped with an emergency bar; all doors shall open to the exterior.
Complete details are reported at Part 7 and Part 8, Section C10 of this document.
5.3 DRY VIP LATRINES
Stall floors shall be reinforced concrete slabs with an opening to serve as a squat hole.
Stall roof shall be galvanized corrugated metal sheeting on timber rafters and purlins.
Dry pit shall be 6 m deep with plan dimensions equal to the total stall area.
Pit walls shall be lined with the masonry block.
Wall vents shall be at least 0.5m x 0.1m Each stall shall be equipped with a uPVC vent pipe 150mm extending at least 0.5m above the roof.
Vent pipe shall be covered with gauze mesh or fly-proof netting and shall ensure unobstructed air flow.
A 2m tall masonry screen wall shall be provided at the front of the latrine block, at least 1.2 m off the latrine doors.
The concept design for a 8-stall latrine is provided at par. 4.7 as a reference. The final design shall be in accordance to this concept and with the above detailed requirements.
5.4 PLUMBING AND FIXTURES
A water distribution system (and relevant waste water system) shall be implemented to provide running water to the sinks in the laboratory and in the new latrines.
5. Room Minimum Requirements p. 25/84
Grounding Symbol
Seven sinks shall be installed in the experimentation room in accordance to MOE standard.
A basin with two faucets shall be installed on the interior side of the latrine screen wall, on both male and female sides of each block.
The faucets shall be connected to the water supply; the basins shall be connected to the waste water/drainage system.
Complete details are reported at Part 7 and Part 8, Section D20 of this document.
5.5 ELECTRICITY AND LIGHTING
The electrical design shall keep into consideration the room use and the equipment to be installed. At least two 16A sockets shall be installed in each room, apart from the experimentation room where at least eight 16A sockets shall be installed.
Four ceiling fans shall be installed in the experimentation room; one ceiling fan shall be installed in the preparation room.
Three-way switches shall be installed close to each entry point to any space having more than one entrance.
Emergency lights shall be installed on each room’s main door. Exterior lights shall be suitable for external use.
It is required the installation of low consumption lamps in a number and size sufficient to guarantee proper illumination to each type of space. The average illumination over the room area at 80 mm above the floor shall be at least 107 lux for offices and classrooms and at least 11 lux for corridors.
Electrical cables shall be dimensioned in accordance to the loads relevant to each circuit.
In order to properly dimension the section of an electrical cable it is recommended to make reference to the table below showing the typical max resistance values for copper cables of different sizes and the relevant maximum current each one can bear.
Section (mm
R (Ω/km)
Max Current (A)
1 19.5 5
1.5 13.3 10
2.5 7.98 16
4 4.95 26
6 3.30 32
10 1.91 50
16 1.21 68
25 0.78 92
35 0.55 120
The potential drops (depending on the cable resistance and on the current through it, V=R*I) shall be kept under 4%.
The connection to the public electrical network shall be done in agreement to the electrical company requirements.
Complete details are reported at Part 7 and Part 8, Section D50 of this document.
5.6 GROUNDING SYSTEM
A grounding (earthing) system consisting of multiple connected rods shall be designed and implemented.
Rods shall be located away from most accessible areas, shall be protected from involuntary/unauthorized access and signposted by the earth symbol shown on the side. At least two rods per building shall be installed.
5. Room Minimum Requirements p. 26/84
Fig. 7 – Example of Panelboard
5.7 ELECTRICAL PANELBOARD
The electrical power feed shall be divided into subsidiary circuits by a panelboard providing a protective circuit breaker for each circuit. A main panelboard - providing a breaker for each line connecting to subpanels located at each new and renovated classroom block - shall be located immediately downstream the delivery point (meter). All electrical panels shall be housed in a common enclosure.
The panelboard enclosure shall be galvanized sheet steel cabinet minimum 1.5 mm thickness, properly mating the panelboard to be enclosed; enclosure’s door shall be lockable.
A main switch located upstream the main panelboard shall protect the electrical system against both overcurrents and residual (ground fault) currents through a Residual Current Breaker with Overcurrent (RCBO) protection whose sensitivity ID is 30 mA.
Sensitivity may be bigger in case other RCDs (Residual Current Devices) with ID = 30 mA are provided downstream to protect groups of circuits.
Fig. 6 shows an example of RCBO.
Each circuit in the panelboard shall be protected against over-currents by a thermal magnetic breaker whose nominal current is ≤ of the max current associated to the relevant cable section, as shown in the table at par. 5.3.
Each breaker shall be labeled to show which circuit it controls.
Lighting circuits and utilization circuits shall be kept separated and individually protected on the panel board.
Fig. 7 shows an example of panelboard design matching the above requirements.
Fig. 6 ‐ RCBO
5. Room Minimum Requirements p. 27/84
5.8 LIGHTNING PROTECTION SYSTEM (LPS) REQUIREMENTS
An LPS shall be implemented for all the new facilities.
It shall consist of a conductor system with air terminals on the roof of the buildings, bonding of the structure and other metal objects, grounding of electrodes, and interconnecting conductors.
A bimetallic connector shall be used to connect all copper cable conductors to all aluminum cable conductors.
Metal compatibility (galvanic action) shall be taken into consideration in order to avoid corrosion.
In any case a copper conductor shall be used to complete the connection to the grounding rod on both sides of each building.
Type and number of air terminals and ground rods to be used shall be determined by the Designer, based on local conditions, earth resistivity data, and on the size and type of the electrical installation.
Type and number of air terminals and ground rods to be used shall be determined by the Designer, based on local conditions, earth resistivity data, and on the size and type of the electrical installation.
It is required that LPS is designed and installed by qualified, trained, personnel.
For normal conditions, copper clad steel rods are typically used.
Galvanized coated steel or stainless steel rods are typically used where low soil resistivities are encountered and galvanic corrosion may occur between adjacent underground metallic masses and the copper-clad rods.
In high resistivity soils, 3 m sectional rods may be used to obtain the required resistance to ground; however where rock is encountered, additional rods, a counterpoise, or ground grid may be necessary.
~~~ End of Part 5 ~~~
6. General Work Requirements p. 28/84
6 GENERAL WORK REQUIREMENTS
6.1 REFERENCE STANDARDS
Construction shall be in accordance with sound construction practices, and shall conform to the latest revision/edition of the codes, criteria, and standards referenced below except as otherwise indicated by this Request for Proposal.
Construction shall also comply with applicable codes, ordinances and regulations of the Republic of Benin governing life/safety, fire protection, building construction, HVAC (heating ventilation and air conditioning) systems, plumbing systems and electrical systems in effect during this contract, except where specifically stated herein.
Any material installed that does not meet the requirements of the following Performance Technical Specification (PTS) and/or applicable codes, ordinances and regulations will be removed and reinstalled at Contractor’s expense.
6.2 WORK REQUIREMENTS
The building renovation and the exterior area settlement as described from Part 1 through 5 shall be in accordance to the specifications provided in the following Parts 7 and 8. All the engineering system requirements described in the Part 7 are more detailed in the corresponding Part 8.
Special attention shall be paid to develop and to adhere to the STRUCTURAL DESIGN and to the
ELECTRICAL DESIGN.
All the concrete and electrical work shall be tested and delivered with a Test Certificate issued by a local qualified entity.
6.3 DESIGN GUIDANCE
Design shall be in accordance with sound design and engineering practices, and shall conform to the latest revision/edition of the codes, criteria, and standards referenced below except as otherwise indicated by this Request for Proposal. Design shall also comply with applicable codes, ordinances and regulations of the Republic of Benin governing life/safety, fire protection, building construction, plumbing systems, electrical systems and sanitation systems in effect during this contract, except where specifically stated herein.
The advisory provisions of all codes, requirements, and standards shall be mandatory; substitute words such as “shall”, “must”, or “required” for words such as “should”, “may”, or “recommended,” wherever they appear. The results of these wording substitutions incorporate these code and standard statements as requirements. Reference to the “authority having jurisdiction” shall be interpreted to mean “Contracting Officer”. Comply with the required and advisory portions of the current edition of the standard at the time of contract award.
The last two sections of this document, in many instances, give multiple options for material and processes. It is the intent to give the contractor’s designer freedom to use one or multiple options in the design, based upon sound design and engineering practices and the requirements of the project.
Once an option is selected for the project, all requirements outlined in the PTS for that option are to be incorporated in the design.
6.4 PERFORMANCE TECHNICAL SPECIFICATIONS
The specifications for this project are requirements based, meaning that the technical details of how to meet this requirement are not included in the PTS.
The contractor shall determine the technical requirements for satisfying these specifications and present them as part of the design package.
The contractor’s design shall provide the technical requirements for the project and the contractor shall be responsible for ensuring their design meets all specifications presented in this SOW.
6. General Work Requirements p. 29/84
6.5 SUBMISSIONS
The Contractor shall be responsible for developing a design for the facility that meets all the operational requirements identified in this document. Contractor shall provide a full design of the facility to include drawings and all calculations and details required to validate the design.
CONCEPT DESIGN
Within 50 calendar days since the contract award, the contractor shall submit a concept design to consist of the following drawings:
- Current Site Plan (identifying existing items to demolish and existing items to remain)
- Final Site Plan (identifying existing items to remain and new items with dimensions)
- Floor Plans of new structures
- Exterior Elevations of new structures
- Sections of new structures
- List of final design documents to be submitted, to include an explanation of any documents listed below but not required
The Government shall review the submission and provide written comments to the contractor.
In the event the contractor does not concur with the Government comments, the contractor shall notify the Government in writing of the reasons for the non-concurrence.
FINAL DESIGN
Within 100 calendar days after the review of the concept design submittal is complete and comments are returned to the contractor, the contractor shall submit a complete, final design incorporating all the comments from the Government, to consist of the following (as required):
- Civil Drawings
- Site Demolition Plan
- Site Plan
- Grading Plan
- Architectural Drawings
- Floor Plans
- Roof Plans
- Room Finish Schedule
- Door and Window Schedules
- Exterior Elevations
- Building Sections
- Wall Sections
- Enlarged Plans
- Reflected Ceiling Plans
- Interior Elevations
- Door and Window Details
- Miscellaneous Details
- Structural Drawings
- Structural Notes/Basis of Design
- Pier Plan/Schedule
- Foundation Plan
- Floor and Roof Framing Plans
- Lateral-Force Resisting System
- Sections and Details
- Structure Calculation
- Plumbing Drawings
- Plumbing Plans
- Rain Drainage Plans
- Water tanks design
6. General Work Requirements p. 30/84
- Miscellaneous Details
- Electrical Drawings
- Notes, Legends, Symbols List
- Distribution Switchboard Scheme
- Grounding System Plan
- Single Line Diagrams
- Floor Plans, power and lighting
- Circuit/breaker size calculation
- Miscellaneous Details
CONSTRUCTION SCHEDULE
The contractor shall prepare a Construction Schedule in a format approved by the PM. The schedule shall identify the different work segments associated to the timeframe set for completion.
Payment will be tied to satisfactory completion of each of these work segments. The construction schedule shall state which work segments completion determines the achievement of the construction steps associated to the progressive invoicing - i.e. 10% (design completion), 30%, 50%, 70% and 90% work progress. The final payment will be done on the facilities acceptance.
The contractor shall submit the proposed schedule to the PM within the timeline allowed for the final design submission. The contractor shall have 360 calendar days to complete the work.
QUALITY CONTROL PLAN
The Contractor will prepare a Quality Control Plan describing personnel, procedures, tests and installation techniques that he plans to perform to ensure the quality required by these TR and by his design is obtained.
ACCIDENT PREVENTION PLAN
Within the timeframe allowed for the final design submission, the Contractor will prepare and submit an Accident Prevention Plan [APP] describing procedures he will put in place to ensure the safety of personnel and equipment on the job site.
The APP shall consist of the following 10 sections:
1. Signature Sheet
2. Background Information (area map)
3. Statement of Safety and Health Policy (signed company Safety Policy)
4. Responsibilities and Lines of Authority (Proof of competency/qualification of listed personnel)