N33191-14-R-0627_Construct_Bichna_School _Mauritania.doc

DOC document 171 KB Posted

Attached to
Construct Hassi Ehel Ahmed Bichna School Federal contract opportunity
Solicitation number
N33191-14-R-0627
Issued by
Department of the Navy Naval Facilities Engineering Command

About this file

Solicitation document (RFP N33191-14-R-0627)

View the file

Other files for this federal contract opportunity

Other files attached to Construct Hassi Ehel Ahmed Bichna School, newest first.
File Type Posted
Attachment_5_-_APP_Template.pdf PDF
Attachment_2_-_Contract_Data_Sheet.doc DOC document
Attachment_1_-_Performance_Technical_Specification.pdf PDF
Attachment_3_-_PPQ.doc DOC document
Attachment_4_-_Submittal_Checklist.doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section 00010 - Solicitation Contract Form

ITEM NO
SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT

Project

Reconstruction of Bichna School

FFP

Provide all labor, supervision, materials, equipment and applicable safety precautions necessary for the reconstruction of the Hassi Ehel Ahmed Bichna School located in Assaba, Mauritania as described in the Performance Technical Specification (Attachment 1).

FOB: Destination

PURCHASE REQUEST NUMBER: 14R0627

NET AMT

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN
INSPECT AT
INSPECT BY
ACCEPT AT
ACCEPT BY
0001
N/A
N/A
N/A
Government

DELIVERY INFORMATION

CLIN
DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
UIC
0001
450 dys. ADC

N/A

FOB: Destination

Section 00100 - Bidding Schedule/Instructions to Bidders

INSTRUCTIONS TO BIDDERS

READ ALL INSTRUCTIONS CAREFULLY

I

INSTRUCTIONS FOR PREPARATION OF PROPOSALS

1. GENERAL

Proposals shall be submitted electronically to David Leigh, david.leigh@eu.navy.mil, on or before the time specified in Block 13 of the Standard Form (SF) 1442. The submittal closing time and receipt of proposals shall be established by the time on the receiving Contract Specialist computer. The offeror is responsible to verify Government receipt of proposals.

Proposals shall be submitted in English and sent in PDF format. Submit the Price Proposal and Non-Price Proposal in two separate PDF files. Total size shall not exceed 5 megabytes.

The solicitation will result in the award of one (1) firm-fixed price contract to one (1) successful offeror offering the LOWEST PRICE TECHNICALLY ACCEPTABLE OFFEROR.

ALL QUESTIONS CONCERNING THIS SOLICITATION SHALL BE ADDRESSED TO DAVID LEIGH VIA EMAIL AT david.leigh@eu.navy.mil.

2.

FAR 52.236-27 - SITE VISIT (CONSTRUCTION) (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors are urged and expected to inspect the site where the work will be performed.

(b) No official site visit is scheduled, however, the contractor is responsible to verify current conditions of the job site. If contractors wish to visit the site, they shall coordinate with Sonia Grillo, Project Manager +39 081-811-4134 and email: Sonia.Grillo.IT@eu.navy.mil. Coordinates to the site location can be found at paragraph 3.1, Existing Site Conditions, page 15 of the Performance Technical Specification (Attachment 1).

3.

REQUIRED PROPOSAL DOCUMENTS

To be found responsible, the offeror shall submit all of the following requested items:

A)

PRICE PROPOSAL

(1) Solicitation Submittal Requirements:

STANDARD FORM 1442, SOLICITATION, OFFER, AND AWARD

- The Offeror MUST complete Blocks 14 through 20c. In Block 14 please include a Point of Contact with a valid phone number and email address. Offerors shall provide an NCAGE Code in Block 14.

(b)

SECTION 00010 – SOLICITATION CONTRACT FORM, PRICE SCHEDULE

- The Offeror MUST fill out the dollar amount for Contract Line Item Number (CLIN) 0001 in Section 00010 – Solicitation Contract Form, see page 3 of the SF1442 for details of the CLIN. The amounts shall be the total amount to complete the construction of the Base Item, exclusive of VAT. Offerors shall provide their Price Proposal in U.S. Dollars. Award will be made in US Dollars; therefore the offeror’s bank must be able to accept US Dollars as payment. Offeror must have a bank.

(c)

SECTION 00600 - REPRESENTATIONS AND CERTIFICATIONS

- The Offeror MUST sign and acknowledge the Representations and Certifications applicable to this procurement in Section 00600 – Representations and Certifications.

(2) Basis of Evaluation: The Government will evaluate price based on the total price, exclusive of VAT. Total price consists of the Base Item (see Section 00010 – Solicitation Contract Form of the solicitation). Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:

(i) Comparison of proposed prices received in response to the solicitation.

(ii) Comparison of proposed prices with the Independent Government Estimate.

(iii) Comparison of proposed prices with available historical information.

(iv) Comparison of market survey results.

B) NON-PRICE PROPOSAL

The Technical Proposal MUST include the following factors:

Factor 1 - Corporate Experience:

Solicitation Submittal Requirements: The offeror MUST provide a minimum of one (1) but no more than two (2) relevant project(s) for which the offeror was the prime contractor, subcontractor or Joint Venture partner. Relevant project(s) MUST meet the following requirements:

1. Design and new construction or renovation activities for a school, community center, administration building or similar structure; and

2. Demonstrate a similarity in magnitude with a value of at least $250,000; and

3. Performed within the last 5 years at the date of issuance of this RFP; and

4. Must be at least 70% complete at the date of issuance of this RFP.

Failure to submit one (1) relevant project may lead to the offeror being eliminated from competition for failing to submit a complete proposal. If more than two (2) projects are submitted, only the two (2) most recently completed projects will be evaluated.

Projects must show experience in construction in order to be considered acceptable for this factor.

Use the Contract Data Sheet (Attachment 2) to submit projects. In lieu of the Contract Data Sheet, offerors can provide relevant project information documentation separately. Whether submitted on the Contract Data Sheet or as separate documentation, project descriptions for each project shall explain the detailed scope of work performed and the relevancy to the project requirements of this solicitation. Offerors must include sufficient information in their proposal to establish the relevancy of their submitted projects.

· All projects submitted that are outside of the specified period will not be considered relevant.

· Proposals that fail to provide all requested data, an accessible point of contact, or correct phone/fax numbers may result in the project not being evaluated or the project being found not relevant.

· The total length for each project shall not exceed two (2) pages.

A project is defined as a construction project performed under a single task order or contract. For multiple award and indefinite delivery/indefinite quality type contracts, the contract as a whole should not be submitted as a project and if submitted will not be evaluated; rather, offerors should submit the work performed under a task order as a project.

If the offeror is a Joint Venture (JV), relevant project experience should be submitted for projects completed by the Joint Venture entity. If the Joint Venture does not have shared experience, projects should be submitted for EACH Joint Venture partner. Offerors are still limited to a total of two (2) projects combined.

Basis of Evaluation: To receive an acceptable rating in this factor, the offeror must demonstrate experience performing at least one (1) relevant project as defined in the solicitation submittal requirements or one (1) relevant project for each Joint Venture partner without shared experience together. The assessment of the offeror’s relevant experience will be used as a means of evaluating the capability of the offeror to successfully meet the requirements of the RFP. The Government will review a maximum of 2 projects. An offeror will be rated UNACCEPTABLE if the offerer does not submit the minimum number of relevant projects (1). Any projects submitted in excess of the two (2) for Corporate Experience will not be considered.

Factor 2 - Safety:

Solicitation Submittal Requirements: The offeror MUST provide a narrative describing the overall contract specific Safety Plan. Offerors shall describe the procedures which will be implemented to ensure compliance and understanding of applicable Mauritanian safety laws and regulations, and applicable US safety regulations (EM 385-1-1) in order to provide for a safe construction site. At a minimum, the narrative shall include:

· Experience and qualifications of the Site Health and Safety Officer (full-time, on-site)

· Safety meetings with workers

· Personal Protective Equipment for workers, as prescribed by local Mauritanian safety and health laws and as required by EM 385-1-1 regulations.

The maximum number of pages allowed is two (2) pages, 8.5 x11, with a minimum of 12 font. If more than two (2) pages are submitted, only the first two (2) pages will be evaluated. The successful offeror will be required to provide an Accident Prevention Plan upon contract award (template provided as Attachment 5).

Basis of Evaluation: To receive an acceptable rating in this factor, the submitted safety narrative must address the minimum requirements listed above. Offerors who submit a plan that address these requirements will be rated ACCEPTABLE.

Factor 3 – Past Performance:

Solicitation Submittal Requirements: The offeror shall provide a past performance evaluation for each project submitted under Factor 1 – Corporate Experience.

Whether a Past Performance Questionnaire (PPQ) (Attachment 3), or separate past performance information documentation is submitted ensure correct phone numbers and email addresses are provided for the client point of contact. Failure of references to be able to respond to past performance inquiries may preclude the Government’s ability to assign a performance confidence assessment. If the client requests, questionnaires or separate past performance documentation may be submitted directly to the Government’s point of contact, David Leigh at david.leigh@eu.navy.mil.

For all of the projects, offerors may include performance recognition documents such as awards, customer letters of commendation, and any other forms of performance recognition, if available. If the evaluation is in other than English, provide a translation of the evaluation into English.

The Government may review any other sources of information for evaluating past performance. Sources may include, but are not limited to, past performance information retrieved through the Past Performance Information Retrieval System (PPIRS) using all CAGE/DUNS numbers of team members (partnership, joint venture, teaming arrangement, or parent company/subsidiary/affiliate) identified in the offeror’s proposal, inquiries of owner representative(s), and any other known sources not provided by the offeror.

While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the offeror.

Basis of Evaluation: The degree to which past performance evaluations and all other past performance information reviewed by the Government (e.g., PPIRS, Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), performance recognition documents, and information obtained from any other source) reflect a trend of satisfactory performance considering:

- A pattern of successful completion of tasks;

- A pattern of deliverables that are timely and of good quality;

- Recency of tasks performed that are identical to, similar to, or related to the task at hand.

To be considered Acceptable, a minimum of one (1) relevant project as defined in Factor 1 – Corporate Experience must have past performance ratings of “Satisfactory” or higher. Ratings of “Marginal” or lower will be considered “Unacceptable.”

Offerors lacking relevant past performance history will not be evaluated favorably or unfavorably in past performance. In the context of acceptability/unacceptability “unknown” shall be considered “Acceptable.” However, as noted above, failure to submit one (1) relevant project may lead to the offeror being eliminated from competition for failing to submit a complete proposal.

II

BASIS OF AWARD

The solicitation will result in the award of one (1) firm-fixed price contract to one (1) successful OFFEROR offering the LOWEST PRICE TECHNICALLY ACCEPTABLE OFFEROR.

An overall non-price factors rating must be at least “ACCEPTABLE” in order to be eligible for award. An “UNACCEPTABLE” rating in any factor results in the overall non-price factors proposal being rated “UNACCEPTABLE” unless corrected through discussions. An overall non-price factors rating of “UNACCEPTABLE” makes a proposal ineligible for award.

In accordance with FAR 9.104-3, the Contracting Officer shall require acceptable evidence of the prospective contractor’s ability to obtain required resources and be determined responsible. If the Contracting Officer determines the lowest price technically acceptable offeror to not be responsible, the Government reserves the right to award to the next responsible, lowest price technically acceptable offeror. The Government may award to the lowest price technically acceptable offeror without discussions.

III

REQUIREMENTS FOR OFFERORS

DUNS, NCAGE AND SAM REGISTRATION

The Government requires an offeror to have a current DUNS Number, NCAGE Code, and register in the System for Award Management (SAM) prior to award of a contract with the US Government. It is the responsibility of the offeror to comply and register. If you currently do not have a DUNS, NCAGE, or SAM registration, information is provided below to assist you. Offerors must provide a Dun and Bradstreet (DUNS) number and NCAGE code when submitting proposals.

If you do not already have a DUNS or NCAGE code the following instructions are given:

DUNS:

Please take these steps to receive a DUNS number:

1. Go to http://fedgov.dnb.com/webform

2. Click "Begin DUNS Search"

3. Choose your country and fill out a short form.

4. Dun & Bradstreet will list up to 3 matches. If your entity is not listed, choose "request new DUNS" and continue from there. Dun & Bradstreet generally responds to each webform submittal within 24-48 hours.

SAM:

To create an account and access SAM as a new user:

1. Go to https://www.sam.gov

2. Click on “Create User Account”

3. Complete the requested information, and then click “Submit/Create.”

4. Select “Individual User Account.”

5. You will receive an email confirming you have created a user account in SAM. You can now register an entity, search For Official Use Only (FOUO) information, and (if you are a designated government official) enter exclusions into the system.

To register in SAM as an entity:

1. Login to SAM with your user ID and password (received after completing the steps above)

2. Gather all of the required information needed to complete your registration.

3. Click on "Register New Entity" from the left side navigation pane.

4. Complete and submit the online registration. It is estimated that it will take approximately 30 minutes to complete registration if you already have all the necessary information on hand, depending upon the size and complexity of your entity.

5. You will receive an email confirming that your registration is in process. Note that new registrations can take an average of 7-10 business days to process in SAM. SAM must send out some information for validation with outside parties before your registration can be activated.

Required information for SAM registration:

· Your Data Universal Numbering System (DUNS) number from Dun & Bradstreet, and the name and address associated with that DUNS

· Your Taxpayer Identification Number and the name associated with that TIN, if applicable (from your W-2 or W-9)

· Your Contractor and Government Entity (CAGE) Code (or NCAGE), if you already have one (if you don't, one will be assigned to you during registration)

· Your Electronic Funds Transfer information, such as your financial institution's ABA Routing Number and your account number, along with the bank phone or fax number

**Please contact the Federal Service Help Desk at https://www.fsd.gov/app/sam/ if you have any questions during the registration process**

The DUNS and NCAGE numbers must be indicated on the SF 1442 in the same block as your company name.

ENGLISH SPEAKING REPRESENTATIVE

At all times when any performance of the work at the site is being conducted by any employee of the Contractor or his subcontractors, the Contractor shall have a representative present on the site who is capable of explaining the work operations and receiving instruction in the English language. The Contracting Officer shall have the right to determine without appeal of such decision, whether the proposed representative has sufficient technical and lingual capabilities and the Contactor shall immediately replace any individual not acceptable to the Contracting Officer.

JOINT VENTURE REQUIREMENTS

Joint Venture (JV) offerors shall provide with their proposal a notarized legal document that establishes the JV. The JV Agreement shall take effect upon the submission of the proposal and remain irrevocable until one (1) year after the work has been finally inspected and accepted by the Government. Submission of the notarized legal document that establishes the JV shall be furnished with the proposal in its original language version along with a certified English translation of the notarized JV document. The Joint Venture must be formed and valid at the time of submission of the proposal. The validated notarized legal document must include language that each member of the JV will be jointly and severally liable for the performance of the whole contract and will be incorporated into the contract award if award is made to the JV.

(a) Name of firms that form the Joint Venture and the name of the Joint Venture

(b) Name and title of the corporate officials signing in behalf of each party

(c) Solicitation number

(d) Description of the responsibilities in terms of work category for each partner

(e) The statement "The composition and structure of the Joint Venture will remain unchanged from award to one (1) year after the work has been finally inspected and accepted by the Government.”

(f) Date of issuance of the agreement and notarized signature of the corporate officials signing in behalf of each party.

(g) Statement under oath stating that the Joint Venture(JV) is in compliance at the time of proposal submission with all applicable laws, rules, and regulations. This statement must be signed under oath by all members comprising the Joint Venture.

The U.S. Government reserves the right to review the actual JV Agreement to determine its basis and compliance with the applicable laws. Any internal agreements affecting the internal composition of the existing JV and its potential liabilities in relation to the contract (bonds, insurance, etc) will be sent to the Contracting Officer to provide notice of the same. Any change in the composition of the JV will require the JV to formally request a Novation Agreement in accordance with FAR 42.12, which will be approved/disapproved at the discretion of the Contracting Officer.

ATTACHMENTS

Attachment 1: Performance Technical Specification and Statement of Work

Attachment 2: Contract Data Sheet

Attachment 3: Past Performance Questionnaire

Attachment 4: Submittal Checklist (NO submittal required with the proposal. For information only)

Attachment 5: Accident Prevention Plan (NO submittal required with the proposal. For information only)

Section 00600 - Representations & Certifications

REPS AND CERTS

CERTIFICATION REGARDING ACCEPTANCE OF SPECIFIC PROVISIONS OF THE CONTRACT

The Contractor hereby acknowledges that is has read and accepts the following clauses contained in FAR 52.204-8 Representations and Certifications (May 2012) that are applicable to this procurement:

52.203-2 Certificate of Independent Price Determination (Apr 1985)

52.203-11 Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions (Sep 2007)

52.209-5 Certification Regarding Responsibility Matters (Apr 2010)

52.222-38, Compliance with Veterans' Employment Reporting Requirements (Sep 2010)

52.225-20 Prohibition on Conducting Restricted Business Operations in Sudan—Certification (Aug 2009)

52.225-25 Prohibition on Contracting with Entities Engaging in Sanctioned Activities Relating to Iran--Representation and Certification (Dec 2012) Date

Contractor Signature

Section 00700 - Contract Clauses

CLAUSES INCORPORATED BY REFERENCE

52.203-5
Covenant Against Contingent Fees
APR 1984
52.203-7
Anti-Kickback Procedures
OCT 2010
52.203-12
Limitation On Payments To Influence Certain Federal Transactions
OCT 2010
52.204-7
System for Award Management
JUL 2013
52.204-13
System for Award Management Maintenance
JUL 2013
52.211-13
Time Extensions
SEP 2000
52.214-34
Submission Of Offers In The English Language
APR 1991
52.214-35
Submission Of Offers In U.S. Currency
APR 1991
52.215-1
Instructions to Offerors--Competitive Acquisition
JAN 2004
52.217-7
Option For Increased Quantity-Separately Priced Line Item
MAR 1989
52.222-1
Notice To The Government Of Labor Disputes
FEB 1997
52.222-50 Alt I
Combating Trafficking in Persons (Aug 2007) Alternate I
AUG 2007
52.223-18
Encouraging Contractor Policies To Ban Text Messaging While Driving
AUG 2011
52.225-13
Restrictions on Certain Foreign Purchases
JUN 2008
52.225-14
Inconsistency Between English Version And Translation Of Contract
FEB 2000
52.225-25
Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-- Representation and Certifications.
DEC 2012
52.228-3
Worker's Compensation Insurance (Defense Base Act)
APR 1984
52.229-6
Taxes--Foreign Fixed-Price Contracts
FEB 2013
52.232-5
Payments under Fixed-Price Construction Contracts
SEP 2002
52.232-23
Assignment Of Claims
JAN 1986
52.232-27
Prompt Payment for Construction Contracts
JUL 2013
52.232-35
Designation of Office for Government Receipt of Electronic Funds Transfer Information
JUL 2013
52.232-36
Payment by Third Party
JUL 2013
52.233-1 Alt I
Disputes (Jul 2002) - Alternate I
DEC 1991
52.233-2
Service Of Protest
SEP 2006
52.233-3
Protest After Award
AUG 1996
52.233-4
Applicable Law for Breach of Contract Claim
OCT 2004
52.236-2
Differing Site Conditions
APR 1984
52.236-5
Material and Workmanship
APR 1984
52.236-7
Permits and Responsibilities
NOV 1991
52.236-13
Accident Prevention
NOV 1991
52.236-17
Layout of Work
APR 1984
52.236-21 Alt II
Specifications and Drawings for Construction (Feb 1997) Alternate II
APR 1984
52.236-26
Preconstruction Conference
FEB 1995
52.236-28
Preparation of Proposals--Construction
OCT 1997
52.242-14
Suspension of Work
APR 1984
52.243-5
Changes and Changed Conditions
APR 1984
52.244-6
Subcontracts for Commercial Items
DEC 2013
52.246-1
Contractor Inspection Requirements
APR 1984
52.246-12
Inspection of Construction
AUG 1996
52.246-13
Inspection--Dismantling, Demolition, or Removal of Improvements
AUG 1996
52.248-3
Value Engineering-Construction
OCT 2010
52.249-1
Termination For Convenience Of The Government (Fixed Price) (Short Form)
APR 1984
52.249-10
Default (Fixed-Price Construction)
APR 1984
252.201-7000
Contracting Officer's Representative
DEC 1991
252.203-7000
Requirements Relating to Compensation of Former DoD Officials
SEP 2011
252.203-7002
Requirement to Inform Employees of Whistleblower Rights
SEP 2013
252.204-7003
Control Of Government Personnel Work Product
APR 1992
252.204-7004 Alt A
System for Award Management Alternate A
MAY 2013
252.209-7004
Subcontracting With Firms That Are Owned or Controlled By The Government of a Terrorist Country
DEC 2006
252.222-7002
Compliance With Local Labor Laws (Overseas)
JUN 1997
252.225-7041
Correspondence in English
JUN 1997
252.225-7042
Authorization to Perform
APR 2003
252.227-7022
Government Rights (Unlimited)
MAR 1979
252.227-7023
Drawings and Other Data to become Property of Government
MAR 1979
252.227-7033
Rights in Shop Drawings
APR 1966
252.229-7000
Invoices Exclusive of Taxes or Duties
JUN 1997
252.232-7008
Assignment of Claims (Overseas)
JUN 1997
252.232-7010
Levies on Contract Payments
DEC 2006
252.233-7001
Choice of Law (Overseas)
JUN 1997
252.236-7000
Modification Proposals-Price Breakdown
DEC 1991
252.236-7001
Contract Drawings, and Specifications
AUG 2000
252.243-7001
Pricing Of Contract Modifications
DEC 1991
252.247-7023
Transportation of Supplies by Sea
JUN 2013

CLAUSES INCORPORATED BY FULL TEXT

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 450 days.* The time stated for completion shall include final cleanup of the premises.

*The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.

(End of clause)

52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $200.00 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(End of clause)

52.213-4 TERMS AND CONDITIONS--SIMPLIFIED ACQUISITIONS (OTHER THAN COMMERCIAL ITEMS) (JAN 2014)

(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses that are incorporated by reference:

(1) The clauses listed below implement provisions of law or Executive order:

(i) 52.222-3, Convict Labor (June 2003) (E.O. 11755).

(ii) 52.222-21, Prohibition of Segregated Facilities (Feb 1999) (E.O. 11246).

(iii) 52.222-26, Equal Opportunity (MAR 2007) (E.O. 11246).

(iv) 52.222-50, Combating Trafficking in Persons (FEB 2009) (22 U.S.C. 7104(g)).

(v) 52.225-13, Restrictions on Certain Foreign Purchases (FEB 2006) (E.o.s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).

(vi) 52.233-3, Protest After Award (Aug 1996) (31 U.S.C. 3553).

(vii) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Pub. L. 108-77, 108-78).

(2) Listed below are additional clauses that apply:

(i) 52.232-1, Payments (Apr 1984).

(ii) 52.232-8, Discounts for Prompt Payment (Feb 2002).

(iii) 52.232-11, Extras (Apr 1984).

(iv) 52.232-25, Prompt Payment (July 2013).

(v) 52.232-39, Unenforceability of Unauthorized Obligations (Jun 2013).

(vi) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (Dec 2013).

(vii) 52.233-1, Disputes (JUN 2008).

(viii) 52.244-6, Subcontracts for Commercial Items (July 2013).

(ix) 52.253-1, Computer Generated Forms (Jan 1991).

(b) The Contractor shall comply with the following FAR clauses, incorporated by reference, unless the circumstances do not apply:

(1) The clauses listed below implement provisions of law or Executive order:

(i) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (July 2013) (Pub. L. 109-282) (31 U.S.C. 6101 note) (Applies to contracts valued at $25,000 or more).

(ii) 52.222-19, Child Labor--Cooperation with Authorities and Remedies (JAN 2014) (E.O. 13126). (Applies to contracts for supplies exceeding the micro-purchase threshold.)

(iii) 52.222-20, Walsh-Healey Public Contracts Act (OCT 2010) (41 U.S.C. 35-45) (Applies to supply contracts over $15,000 in the United States, Puerto Rico, or the U.S. Virgin Islands).

(iv) 52.222-35, Equal Opportunity for Veterans (SEP 2010) (38 U.S.C. 4212) (applies to contracts of $100,000 or more).

(v) 52.222-36, Affirmative Action for Workers with Disabilities (OCT 2010) (29 U.S.C. 793). (Applies to contracts over $15,000, unless the work is to be performed outside the United States by employees recruited outside the United States.) (For purposes of this clause, United States includes the 50 States, the District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, and Wake Island.)

(vi) 52.222-37, Employment Reports on Veterans (SEP 2010) (38 U.S.C. 4212) (applies to contracts of $100,000 or more).

(vii) 52.222-41 (REMOVED).

(viii) 52.223-5, Pollution Prevention and Right-to-Know Information (May 2011) (E.O. 13423) (Applies to services performed on Federal facilities).

(ix) 52.223-15, Energy Efficiency in Energy-Consuming Products (DEC 2007) (42 U.S.C. 8259b) (Unless exempt pursuant to 23.204, applies to contracts when energy-consuming products listed in the ENERGY STAR Program or Federal Energy Management Program (FEMP) will be--

(A) Delivered;

(B) Acquired by the Contractor for use in performing services at a Federally-controlled facility;

(C) Furnished by the Contractor for use by the Government; or

(D) Specified in the design of a building or work, or incorporated during its construction, renovation, or maintenance.)

(x) 52.225-1, Buy American Act--Supplies (FEB 2009) (41 U.S.C. 10a-10d) (Applies to contracts for supplies, and to contracts for services involving the furnishing of supplies, for use in the United States or its outlying areas, if the value of the supply contract or supply portion of a service contract exceeds the micro-purchase threshold and the acquisition--

(A) Is set aside for small business concerns; or

(B) Cannot be set aside for small business concerns (see 19.502-2), and does not exceed $25,000.)

(xi) 52.232-33, Payment by Electronic Funds Transfer--System for Award Management (Jul 2013). (Applies when the payment will be made by electronic funds transfer (EFT) and the payment office uses the System for Award Management (SAM) database as its source of EFT information.)

(xii) 52.232-34, Payment by Electronic Funds Transfer--Other than System for Award Management (Jul 2013). (Applies when the payment will be made by EFT and the payment office does not use the SAM database as its source of EFT information.)

(xiii) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (FEB 2006) (46 U.S.C. Appx 1241). (Applies to supplies transported by ocean vessels (except for the types of subcontracts listed at 47.504(d).)

(2) Listed below are additional clauses that may apply:

(i) 52.209-6, Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Aug 2013) (Applies to contracts over $30,000).

(ii) 52.211-17, Delivery of Excess Quantities (SEPT 1989) (Applies to fixed-price supplies).

(iii) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations. (MAR 2009) (Pub. L. 110-247) (Applies to contracts greater than $25,000 that provide for the provision, the service, or the sale of food in the United States.)

(c) FAR 52.252-2, Clauses Incorporated by Reference (FEB 1998). This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

HTTP://FARSITE.HILL.AF.MIL

(d) Inspection/Acceptance. The Contractor shall tender for acceptance only those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. The Government must exercise its postacceptance rights--

(1) Within a reasonable period of time after the defect was discovered or should have been discovered; and

(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

(e) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence, such as acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.

(f) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges that the Contractor can demonstrate to the satisfaction of the Government, using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred that reasonably could have been avoided.

(g) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.

(h) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.

(End of clause)

52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984)

The Contractor shall perform on the site, and with its own organization, work equivalent to at least 50% percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.

(End of clause)

52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994)

(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (i) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.

(b) This warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the Government takes possession.

(c) The Contractor shall remedy at the Contractor's expense any failure to conform, or any defect. In addition, the Contractor shall remedy at the Contractor's expense any damage to Government-owned or controlled real or personal property, when that damage is the result of--

(1) The Contractor's failure to conform to contract requirements; or

(2) Any defect of equipment, material, workmanship, or design furnished.

(d) The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The Contractor's warranty with respect to work repaired or replaced will run for 1 year from the date of repair or replacement.

(e) The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.

(f) If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor's expense.

(g) With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall--

(1) Obtain all warranties that would be given in normal commercial practice;

(2) Require all warranties to be executed, in writing, for the benefit of the Government, if directed by the Contracting Officer; and

(3) Enforce all warranties for the benefit of the Government, if directed by the Contracting Officer.

(h) In the event the Contractor's warranty under paragraph (b) of this clause has expired, the Government may bring suit at its expense to enforce a subcontractor's, manufacturer's, or supplier's warranty.

(i) Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material or design furnished by the Government nor for the repair of any damage that results from any defect in Government-furnished material or design.

(j) This warranty shall not limit the Government's rights under the Inspection and Acceptance clause of this contract with respect to latent defects, gross mistakes, or fraud.

(End of clause)

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

http://farsite.hill.af.mil (End of provision

252.225-7043 ANTITERRORISM/FORCE PROTECTION POLICY FOR DEFENSE CONTRACTORS OUTSIDE THE UNITED STATES (MAR 2006)

(a) Definition. United States, as used in this clause, means, the 50 States, the District of Columbia, and outlying areas.

(b) Except as provided in paragraph (c) of this clause, the Contractor and its subcontractors, if performing or traveling outside the United States under this contract, shall--

(1) Affiliate with the Overseas Security Advisory Council, if the Contractor or subcontractor is a U.S. entity;

(2) Ensure that Contractor and subcontractor personnel who are U.S. nationals and are in-country on a non-transitory basis, register with the U.S. Embassy, and that Contractor and subcontractor personnel who are third country nationals comply with any security related requirements of the Embassy of their nationality;

(3) Provide, to Contractor and subcontractor personnel, antiterrorism/force protection awareness information commensurate with that which the Department of Defense (DoD) provides to its military and civilian personnel and their families, to the extent such information can be made available prior to travel outside the United States; and

(4) Obtain and comply with the most current antiterrorism/force protection guidance for Contractor and subcontractor personnel.

(c) The requirements of this clause do not apply to any subcontractor that is--

(1) A foreign government;

(2) A representative of a foreign government; or

(3) A foreign corporation wholly owned by a foreign government.

(d) Information and guidance pertaining to DoD antiterrorism/force protection can be obtained from Naval Criminal Investigative Service (NCIS).

(End of clause)

252.229-7001 TAX RELIEF (JUN 1997)

(a) Prices set forth in this contract are exclusive of all taxes and duties from which the United States Government is exempt by virtue of tax agreements between the United States Government and the Contractor's government. The following taxes or duties have been excluded from the contract price:

NAME OF TAX: _______________ RATE (PERCENTAGE): _______________

(b) The Contractor's invoice shall list separately the gross price, amount of tax deducted, and net price charged.

(c) When items manufactured to United States Government specifications are being acquired, the Contractor shall identify the materials or components intended to be imported in order to ensure that relief from import duties is obtained. If the Contractor intends to use imported products from inventories on hand, the price of which includes a factor for import duties, the Contractor shall ensure the United States Government's exemption from these taxes. The Contractor may obtain a refund of the import duties from its government or request the duty-free import of an amount of supplies or components corresponding to that used from inventory for this contract.

(End of clause)

252.243-7002 REQUESTS FOR EQUITABLE ADJUSTMENT (DEC 2012)

(a) The amount of any request for equitable adjustment to contract terms shall accurately reflect the contract adjustment for which the Contractor believes the Government is liable. The request shall include only costs for performing the change, and shall not include any costs that already have been reimbursed or that have been separately claimed. All indirect costs included in the request shall be properly allocable to the change in accordance with applicable acquisition regulations.

(b) In accordance with 10 U.S.C. 2410(a), any request for equitable adjustment to contract terms that exceeds the simplified acquisition threshold shall bear, at the time of submission, the following certificate executed by an individual authorized to certify the request on behalf of the Contractor:

I certify that the request is made in good faith, and that the supporting data are accurate and complete to the best of my knowledge and belief.

(Official's Name)

(Title)

(c) The certification in paragraph (b) of this clause requires full disclosure of all relevant facts, including--

(1) Certified cost or pricing data if required in accordance with subsection 15.403-4 of the Federal Acquisition Regulation (FAR); and

(2) Data other than certified cost or pricing data, in accordance with subsection 15.403-3 of the FAR, including actual cost data and data to support any estimated costs, even if certified cost or pricing data are not required.

(d) The certification requirement in paragraph (b) of this clause does not apply to----

(1) Requests for routine contract payments; for example, requests for payment for accepted supplies and services, routine vouchers under a cost-reimbursement type contract, or progress payment invoices; or

(2) Final adjustment under an incentive provision of the contract.

5252.201-9300 CONTRACTING OFFICER AUTHORITY (JUN 1994)

In no event shall any understanding or agreement between the Contractor and any Government employee other than the Contracting Officer on any contract, modification, change order, letter or verbal direction to the Contractor be effective or binding upon the Government. All such actions must be formalized by a proper contractual document executed by an appointed Contracting Officer. The Contractor is hereby put on notice that in the event a Government employee other than the Contracting Officer directs a change in the work to be performed, it is the Contractor’s responsibility to make inquiry of the Contracting Officer before making the deviation. Payments will not be made without being authorized by an appointed Contracting Officer with the legal authority to bind the Government.

5252.209-9300 ORGANIZATIONAL CONFLICTS OF INTEREST (JUN 1994)

The restrictions described herein shall apply to the Contractor and its affiliates, consultants and subcontracts under this contract. If the Contractor under this contract prepares or assists in preparing a statement of work, specifications and plans, the Contractor and its affiliates shall be ineligible to bid or participate, in any capacity, in any contractual effort which is based on such statement of work or specifications and plans as a prime contractor, subcontractor, consultant or in any similar capacity. The Contractor shall not incorporate its products or services in such statement of work or specification unless so directed in writing by the Contracting Officer, in which case the restriction shall not apply. This contract shall include this clause in its subcontractor's or consultants' agreements concerning the performance of this contract.

5252.236-9303 ACCIDENT PREVENTION (NOV 1998)

(a) The Contractor will maintain an accurate record of, and will report to the Contracting Officer in the manner and on the forms prescribed by the Contracting Officer, all accidents resulting in death, traumatic injury, occupational disease, and damage to property, materials, supplies and equipment incident to work performed under this contract.

(b) Compliance with the provisions of this article by subcontractors will be the responsibility of the Contractor.

(c) Prior to commencement of the work, the Contractor may be required to:

(1) submit in writing his proposals for effectuating provision for accident prevention;

(2) meet in conference with representatives of the Contracting Office to discuss and develop mutual understandings relative to administration of the overall safety program

5252.242-9300

GOVERNMENT REPRESENTATIVES (OCT 1996)

The contract will be administered by an authorized representative of the Contracting Officer. In no event, however, will any understanding or agreement, modification, change order, or other matter deviating from the terms of the contract between the Contractor and any person other than the Contracting Officer be effective or binding upon the Government, unless formalized by proper contractual documents executed by the Contracting Officer prior to completion of this contract. The authorized representative as indicated hereinafter:

_X_(1) The Contracting Officer’s Representative (COR) will be designated by the Contracting Officer as the authorized representative of the Contracting Officer. The COR is responsible for monitoring performance and the technical management of the effort required hereunder, and should be contacted regarding questions or problems of a technical nature.

_ X_(2) The designated Contract Specialist will be the Administrative Contracting Officer's representative on all other contract administrative matters. The Contract Specialist should be contacted regarding all matters pertaining to the contract or task/delivery orders.

___(3) The designated Property Administrator is the Administrative Contracting Officer's representative on property matters. The Property Administrator should be contacted regarding all matters pertaining to property administration.

5252.242-9305

PRE-PERFORMANCE CONFERENCE (JUL 1995 )

Within 10 days of contract award, prior to commencement of the work, the Contractor will meet in conference with representatives of the Contracting Officer, at a time to be determined by the Contracting Officer, to discuss and develop mutual understanding relative to scheduling and administering work.

Section 00800 - Special Contract Requirements