Technical Specifications

View the file

Other files

File Type Posted
Attachment_2_-_Contract_Data_Sheet.doc DOC document
N33191-13-R-1245.pdf PDF
Attachment_3_-_PPQ.doc DOC document
Attachment_4_-_Submittal_Checklist.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EUCOM Humanitarian Assistance

Program

Renovations to School#03 - Sevastopol

Sevastopol, Ukraine

OHASIS ID-22093

August 2013

VERSION 001

Renovation of School#03 OHASIS ID-22093

VERSION-001

1. PROJECT DESCRIPTION

1.1. GENERAL

Provide all material, equipment and labor to renovate School#03 in Sevastopol (Ukraine), as identified herein.

1.2. GENERAL SCOPE OF WORK

The work is divided into a BASE-BID and 1 CONTRACT OPTION. The Government reserves the right to unilaterally award, or not to award, the contract options. The contractor will provide separate pricing for the Base-Bid and the contract option as required in the solicitation documents.

Base Bid:

Complete repair of bathroom facilities Complete repair of the indoor physical education facility (gymnasium) Commemorative plaque

Option-1: Renovation of the Auditorium (or Assembly Hall)

1.3. LEGAL AND TECHNICAL REQUIREMENTS

The project execution is based on the following principles:

- Strict compliance with American Contracting Regulations, including the requirements of the Department of Defense, the US Navy and Naval Facilities Engineering Command

(NAVFAC).

- Strict compliance with Ukrainian Technical, Legal and Administrative requirements, which are applicable for the renovation project described in the scope of work.

- Compliance with the most stringent of US and Ukrainian safety regulations.

1.2 Construction Permit or Authorization

The contractor shall obtain formal written authorization from the competent Ukrainian authority to perform the works included in the scope of work of this project.

The contractor is required, as part of this contract, to prepare all documentation, designs, reports, information, drawings, and everything that may be necessary as required by Ukrainian regulations, in order to obtain this Permit or Authorization.

Picture#02: Aerial view of the school

Picture#01: Location school#03 within the city downtown

1.3 Location of project

The project is located in Ukraine, in downtown Sevastopol.

Design and build (but not limited to) :

- Bathroom renovation

- Gymnasium Renovation

(paragraph 2)

Design and build (but not limited to) :

- Interior repairs to Assembly Hall

(Paragraph 3)

BASE-BID OPTION-1

1.4 Existing Conditions

To show existing conditions, several pictures are included in this PTS. These pictures were taken in April 2012 and May 2013. The pictures do not guarantee the existing conditions of the building at the time to prepare the bid for the contract, and they are only a tool to describe the responsibilities of the contractor. The contractor is responsible to visit the sites in order to measure and quantify the required work, as well as to verify the existing conditions, prior to the submission of their proposal.

IT IS ABSOLUTELY NECESSARY FOR THE CONTRACTOR TO VISIT THE JOB SITES IN ORDER TO

MEASURE AND TO QUANTIFY THE WORK INCLUDED IN THIS PROJECT AND TO VERIFY REAL

FIELD CONDITIONS. THIS PROJECT DOES NOT INCLUDE ACCURATE MEASUREMENTS. ALL

MEASUREMENTS SHOULD BE VERIFIED BY THE CONTRACTOR ON SITE.

1.5 Structure of the Contract

The contract includes the complete renovation of the School as detailed herein. The work is divided into Base-Bid and Contract Option-1. The Base-Bid is the minimum part of the project that will be awarded to a construction firm. The Option-1 will be awarded (or not) depending upon availability of funds, as well as other factors. The contractor shall provide a separate price for the Base-Bid and for the contract option, as required by the solicitation documents.

Picture#03: Bathroom areas requiring complete renovation. Not to scale. Approximate dimensions.

2. DETAILED SCOPE OF WORK (BASE BID)

This portion of the contract described in paragraph 2 and all its subparagraphs corresponds to the minimum portion of the contract that will be awarded to the successful offeror.

2.1 COMPLETE RENOVATION OF THE BATHROOMS

The contractor shall repair the bathrooms in order to provide a perfectly finished, modern and operational bathroom facility. The works include the existing boys and girls bathroom, as well as the common areas (stairway and lobby) shown in picture#03 below.

2.1.1 PHASING OF BATHROOM WORK

It is estimated that all works will be performed while the school remains under operation. The bathrooms shown in picture#03 Are the only operational bathrooms of the school, and therefore they need to remain operational during the performance of works. For that reason the work shall be performed are indicated:

- Phase 1 – Bathrooms: Boys toilet

The girls toilet will remain operational during the performance of repair works in the boys toilet. The school will use the girls bathroom for boys and girls with their own supervision and control of who uses the bathrooms.

- Phase 2 – Bathrooms: Girls Toilet

Works shall not start until works in the boys bathroom are complete and accepted by the Contracting Officer. Boys bathroom will be used by boys and girls (controlled by the School Administration) while the contractor works on the girls bathroom.

Common areas: Such as the stairway and lobby will be performed in close coordination with the school Administration to minimize disruption to the use of the bathrooms by the children.

Picture#04: Different phases required for the renovation works.

Phasing:

Phase 1: Blue (boys bathrooms)

Phase 2: Red (girls bathrooms)

Orange: Common areas

Picture#05: Existing distribution of the areas to be renovated

2.1.2 DESIGN OF BATHROOM

This is a design-build contract. The contractor shall hire the services of an interior designer or an architect to provide a proposed design for the renovated bathrooms, with the requirements outlined in this document.

Currently, as shown in picture#05, the bathroom facilities are divided into:

- Boys areas: Entrance, handwash and toilet areas

- Girls areas: Handwash, toilet and teachers areas.

- Common areas: Lobby and stairway

The project includes the necessary design and work in order to have the following fully operational appliance and fixtures in each area as listed below:

- Boys Toilet:

o 4 European Style toilets o 5 urinals at different heights with prefabricated wall mounted aluminum partitions.

o Prefabricated aluminum partitions for the toilets o Ventilation to the exterior of the facility o Floor drain

- Boys Handwash:

o 4 sinks over continuous countertop o Mirror (2.0 x 0.6 m)

- Boys Entrance o 2 automatic hand driers

- Girls Handwash:

o 4 sinks over continuous countertop o Mirror (3.0 x 0.6 m) o 2 automatic hand driers

- Girls Toilet:

o 6 European Style toilets o Prefabricated aluminum partitions for the toilets o Ventilation to the exterior of the facility

- Teachers Toilet:

o 2 European Style toilets (wall mounted) o Prefabricated aluminum partitions for the toilets o Ventilation to the exterior of the facility o 2 sinks over continuous countertop o Mirror (1.0 x 0.6 m)

Notes to be considered for the design:

- The design of the bathrooms shall be made to maximize:

o Privacy of the users o Efficient use of available space o Comfortability o Sustainability o Durability o Esthetics

- The finished condition bathrooms may require modification of the size of the exterior windows. This may be necessary in the teachers toilet area, or as required by the contractor’s interior designer. The exterior façade shall be provided with similar finishes as the existing façade, so that there is no evidence of modification of the window size.

- The existing internal partition in the teachers’ toilet shall be removed. The internal partitions separating areas can be modified as required by the contractor’s proposed and approved design.

Picture#06: Potential conceptual design for bathrooms

2.1.3 TECHNICAL REQUIREMENTS FOR NEW BATHROOMS

The work shall include everything necessary in order to have a perfectly operational and modern bathroom facility for the school. The work shall include, but shall not be limited to the following items of work:

- Demolitions: Demolish everything within the areas to be renovated. This includes floor and wall tiles, electrical installation, water, sewer and vent piping, existing plumbing fixtures, windows, doors, necessary partitions, and everything that may interfere with the construction of the new bathroom facilities.

- Floor: Remove existing tiles and provide new grès tiles of minimum dimension 40x40 cm, sloped towards a new floor drain. Do not install the new floor tiles over the existing tiles. This is specially important in the areas with low ceiling. Provide supporting base as necessary and recommended by the manufacturer. All floor shall be at the same elevation. Provide non slippery tiles, sloped towards floor drains (one for each room) to be connected with the new sewer piping system. Install floor tiles diagonally with respect to the walls. Color and pattern to be selected by the beneficiary among ample selection to be provided by the contractor.

Floor Material: Non-glazed floor tiles of grès material (artificial granite), laser cut, with water resistant joints. Grès Porcelain stoneware is a ceramic with a compact, hard, colored and non-porous body. The word “grès” means that the ceramic body of the tile is extremely vitrified, that is to say compact, hence the exceptional great resistance. The result is a lean clay body, little refractory, fired in a kiln (at 1200-1400 C°) until it reaches a non-porous vitrification and a complete water-proofing.

Provide wall base with special wall trim pieces similar to the floor tiles. Cutting floor tiles to be used as wall base is not acceptable.

- Floor drains: Provide one floor drain per room. Total of 5 floor drains are required for the new bathroom facilities. Provide stainless steel floor drain with integral p-trap to avoid bad smells.

- Walls: Remove plaster as necessary in order to provide a perfectly leveled surface in which to install the new ceramic tiles. Repair any cracks of structural defects before leveling the walls. Provide ceramic tiles from the floor (wall base ceramic tile) to the ceiling. Ceramic tiles shall with minimum dimension 20x30 cm. Provide combination of 3 colors and patterns, to be selected by beneficiary among ample selection to be provided by the contractor. Provide friso (decorative tile) in middle and highest heights. Middle one can be substituted by metal friso, as seen in picture#13.

The edges of the ceramic tiles shall all be protected by exposed metal corner guard as shown in picture#14. No edge of any tile shall be exposed to the view.

Provide non-glazed ceramic tiles (for walls) with water resistant joints, glued onto the surface of the wall. Provide with stainless steel corner guards embedded in the wall tiles.

- Partitions for new layout: If applicable. New partitions that may be required by new layout shall be made of thin masonry wall, not wider than 20 cm. Cover all surfaces with new ceramic tiles as with the rest of the walls. It is also estimated that new false walls will need to be built in several areas to hide the water tanks for the toilets and the piping installation.

- Ceiling: The existing ceiling has different heights. In the common and girls areas it is very low and in the boys area it is high. For that reason the ceiling finishes shall be different in each area as required below:

o Areas with low ceilings: Repair existing ceiling surfaces. The work includes removing the defective plaster, fixing any structural defects, providing one leveling plaster layer and finishing with washable paint.

o Areas with high ceilings: Provide gypsum board plastered ceiling. The work includes removing the defective plaster, fixing any structural defects, and covering all ceiling surfaces with plastered and painted gypsum board supported by new galvanized metal structure. Provide with access hatches as necessary to allow for maintenance of any installation over the ceiling surface. Paint with washable (oil based) paint. Use “green” type gypsum board, rated and certified to be used in humid atmospheres. Install as high as technically possible, allowing sufficient space for the utilities that may be installed over the suspended ceiling and for the recessed lighting fixtures. Once work is completed, all existing piping to remain shall be installed above the drop ceiling surfaces, so that no piping is exposed to the view.

- Electrical: Provide complete new electrical installation for the renovated bathrooms.

Provide a new electric panel connected with the main electric panel of the school to supply electricity to the new bathroom facilities. All electrical installation to be recessed along the walls, ceilings, floors, so that no electrical cables or conduits are exposed to the view, including conduits, junction boxes, lighting fixtures, switches, electric panels, etc. The electrical installation shall include:

o Designed and installed in accordance with European standards.

o All electrical equipment to be CE certified.

o All electrical installation to be done in conduits recessed within the walls. Electric panels, cables, junction boxes, boxes for the switches, receptacle boxes,… shall all be installed recessed within the new walls, which are to be covered with ceramic tiles. Direct installation of the cables under the plaster is not acceptable. All cables to be installed under electric conduit, even above the drop ceiling.

o Two electrical receptacles: One electrical receptacle in each the teacher’s bathrooms and another in the Common area lobby. No electrical receptacles in the other areas.

o Lighting fixtures: Provide illumination levels as required by Ukrainian regulations:

For high ceiling areas provided with new gypsum board ceiling: Provide new recessed rapid start fluorescent lighting fixtures, with washable diffuser.

Equipment to be recessed, so that only the diffuse is exposed after the installation.

For low ceiling areas provide similar type of lighting fixture (fluorescent rapid start) but surface mounted.

o Automatic start hand driers. Hardwire to the walls, so that the cables are not exposed to the view.

o Provide individual circuits for lighting and power, so that when all hand driers are operating, there is no dimming in the lighting of the rooms. Voltage drop to be less than 3%. This will be tested for acceptance of electrical installation.

o Ventilation: Provide forced (electrical ) ventilation as detailed in next bullet.

- Ventilation: The bathroom facilities shall be provided with 3 separate and independent electrical air exhaust or ventilation system. Each exhaust fan shall be provided with a switch to select among 3 speeds for the fan. As a minimum, the fan capacity shall be sufficient to replace the volume of air in the corresponding area in a maximum of 4 minutes:

o Teachers Toilet: Provide an air exhaust to the exterior. It is recommended to install the air exhaust directly in the new window to be provided. The ceiling is very low and therefore there is no space for any air ducts.

o Girls Toilet: Same as above.

o Boys Toilet: Provide an air exhaust system to be installed over the new drop ceiling so that the fan, air ducts or opening to the exterior is not exposed to the view.

- Water supply: Provide new water line from the nearest available water line with sufficient flow and pressure to supply all plumbing fixtures. The acceptance criteria would be to flush all toilets and 4 sinks at the same time. There shall be no visually noticeable drop in pressure or flow in the 4 faucets of the sinks. Provide all water pipes inside of the bathroom areas recessed within the walls, so that they are not exposed to the view. Provide mechanic automatic faucets (not electric) in all sinks. Do not provide hot water to the bathrooms.

- Hot water: Not required.

- Windows: Replace existing windows and resize as necessary for the new design of the bathrooms. Provide new 5 chamber PVC profile window with double non transparent glazing (6-16-6). For estimating purposes the contractor shall estimate that 80% of the window surface to open vertically and horizontally, and to be provided with removable mosquito net.

Provide with PVC sill inside and aluminum sill outside. Repair all adjacent surfaces, interior and exterior, so that there is no evidence of any construction activity.

- Doors: The contract includes replacing all doors in the areas to be renovated. The number and location of doors shall be determined by the new design to be proposed by the contractor. Some doors shall be replaced, and some other existing doors shall be substituted by an opening with an arc in the top. The contractor shall propose their design, but as a guideline the doors highlighted in green in picture#07 are estimated to have to be replaced, and the doors highlighted in red are estimated to be replaced with an opening with an arc on the top. There shall be different type of doors, depending on their use:

o Exterior door: There is one exterior door in the hallway area: This door shall be replaced with new thermally insulated PVC door, provided with glass opening in the upper half provided with double glazing of minimum thickness 6 mm.

Picture#07: Potential required doors and wall openings with arc on the top o Interior doors to be replaced with new: Provide new PVC doors without bottom threshold without locks, except for the teachers bathroom that shall be provided with locks. Provide doors where required by new design. Do not provide locks for the doors to the children’s toilets. Provide new doors connecting the bathrooms with the lobby at the necessary location required by the design of the bathrooms. Door and frame to be delivered by the manufacturer as one complete unit, not to be assembled by the contractor on site. Provide proper metal or concrete lintel beams over the door opening as necessary.

o Interior doors to be replaced with opening with arc: The design shall avoid unnecessary doors. It is estimated that the door openings highlighted in red in picture#07 shall be replaced with an opening finished with an arc in the top.

- Heating: Provide new heating radiators, bimetal type. Provide new heating piping recessed within the new walls, floors or ceiling. Once the work is completed the heating piping shall not be visible at any location within the renovated areas. Provide each radiator with isolation and control valves (picture#11)

- Sewer/drainage/vent: The contract includes the removal of all sewer/water/vent lines within the renovated areas. Provide new sewer/drainage/ventilation PVC piping for the bathrooms connected with the exterior of the building. All sewer pipes in the renovated areas to be covered by masonry wall or partition so that the sewer lines are not exposed to the view.

Provide access points for maintenance of the lines. Connect sewer lines to the city sewer lines. The contractor shall inspect the area to locate the nearest city sewer manhole to which connect the new sewer lines. The contractor shall provide new concrete manholes outside of the school/bathroom facility, as necessary by Ukrainian regulations. Connection of the new sewer system to be described in separate paragraph.

- Pre-manufactured aluminum toilet partitions (design to be approved by School Director).

The partitions shall be standard manufacturer product, and shall not be shop made for this project by non-qualified manufacturer. Contractor to show manufacturer’s standard catalog with the toilet partitions to the Contracting Officer Representative for acceptance before their purchase. Design with minimum contact between the partitions and the floor to allow for easy cleaning. Provide with locks, interior hangers, toilet paper holder and ample space for the users. Design of the partitions shall be coordinated with the size of the rooms and size of the toilets.

- Toilets: Provide all water tanks recessed within the walls. Provide each water tank actuator with two buttons for water saving. Toilet seats to be ceramic wall mounted (suspended) for the teachers area and ceramic floor mounted for the rest of the areas. Recess all water tanks within the walls. It is estimated that new false walls will need to be built to hide all the water tank and mechanical installations. Provide installation for easy maintenance of the mechanical equipment within the walls.

- Sinks: The sinks shall be ceramic and shall be installed under continuous artificial stone countertop with rounded edges and designed to support the load of people standing on top of the countertop. The countertop shall be made of artificial compound made of minimum 94% natural quartz with anti-bacterial protection. Provide with live colors (orange, blue, red of yellow), to be selected by school director among ample selection provided by the contractor. All exposed drainage piping from the sinks shall be stainless steel, provided with p-trap to avoid bad smell.

- Mirrors: Minimum thickness 8 mm. To be provided with the sizes and where indicated in paragraph 2.1.2. Provide mirror over the sinks. Mirror to be recessed within the new ceramic wall tiles with the required length and 0.6 meter high. Surround mirror by ceramic friso or stainless steel friso.

- Piping (General): All piping and installations in the renovated areas shall be installed above the drop ceiling or under the new wall or floor surfaces. No installations shall be visible after the renovation works. This includes the installations that go through the renovated areas.

- Accessories: Provide all required accessories made of stainless steel, in order to have a perfectly finished and operational bathroom facility. This includes toilet paper holder, soap holder, wall hanger or door and window stops.

2.1.4 EXTERIOR SEWER

The sewer from the renovated toilets shall be routed by gravity pipes to the exterior of the facility, and shall be connected to the city sewage centralized system. The location of the connection manholes is unknown. The contractor shall survey the area and locate the nearest concrete manhole to which connect the sewer lines.

The exterior sewer lines shall be minimum 200 mm internal diameter and installed with minimum of 1% slope.

The contractor shall provide the necessary new concrete manholes that are required by Ukrainian regulations, but they shall be installed at a maximum of every 40 meters or at every change of direction of the piping.

Manholes: Provide water tight manholes with concrete or cast iron covers. Provide channels in the bottom for proper flow of sewage.

Piping: Provide PVC sewer piping with minimum slope 1%. Minimum size of piping shall be 200 mm of internal diameter.

Picture#08: Typical acceptable railing

Picture#09: Typical tiles to be used for the new steps.

2.1.5 COMMON AREAS / STAIRWAY

The contract includes the renovation of all areas from the ground floor to the semi-basement where the bathrooms are located. This includes the renovation of the entrance lobby and entrance stairway as shown in picture#05.

All requirements of the bathrooms apply to this area, but in particular and/or in addition, the contractor shall consider the following elements as requirements of their contract:

- The contract includes 2 runs of stairway, not the entire stairway to the highest floor of the building. Only the orange highlighted areas in picture#05.

- Walls: Shall be provided with ceramic tiles, only in the lowest 1.5 meters. Remove paint and plaster before leveling the walls. The rest of the walls shall be repaired, plastered and painted.

- Floors: The lobby shall the provided with similar tiles as for the bathrooms. The stairway shall be provided with tiles specifically designed for stairways

- Stairway: Cover the stairways steps with grès ceramic tiles, with same quality as the tiles to be provided for the bathrooms, but specially designed to be used in stairways.

o Horizontal tiles: Provide non slippery tiles, with rounded edges.

o Vertical tiles: Provide different pattern as shown in picture#09.

- Railing: Remove the existing railing and provide new heavy duty stainless steel railing. The new railings shall be capable of resisting 50 kg of horizontal force at any point, without any visible deflection. The railing shall be design so that small children cannot get between the railing vertical bars.

Picture#12: Typical recessed mirror, continuous countertop and wall opening with arc on the top

Picture#13: Typical aluminum with anodized finish corner protection

Picture#14: Typical stainless steel corner protection for tiled corners.

Picture#11: Typical bimetal radiator required for all rooms.

Picture#10: Typical automatic hand drier

Picture#19: Typical lighting fixture to be recessed on the new false ceiling

Picture#17: Typical gypsum board ceiling before plastering

Picture#18: Use exclusively “green” type gypsum boards

Picture#16: Typical ceiling with recessed fluorescent lighting for areas with high ceilings.

Picture#20: Typical friso for bathrooms

Picture#15: Typical friso or decorative tile in middle and upper portions of the walls.

Picture21: Typical installation of floor tiles diagonally with respect to the walls

Picture#22: Typical grès base boards

Picture#26: Typical required continuous countertop for the sinks. Picture#25: Typical required continuous countertop for the sinks.

Picture#23:Typical lighting fixture to be surface mounted in areas with low ceilings

Picture#24: Typical lighting fixture to be surface mounted in areas with low ceilings

Picture#27:Typical wall mounted toilet installation

Picture#28: Typical wall mounted sink to be installed with water tank recessed within the walls

Picture#29: Typical floor mounted sink to be installed with water tank recessed within the walls

Picture#30: Potential finishes for girls toilets

Picture#31: Typical required aluminum partitions

Picture#32: Typical required aluminum partitions

Picture#33: Typical installation of the countertop before installing the sinks

Picture#36: 2 runs of stairway to be completely renovated

Picture#37: Area of the stairway to be renovated. Replace exterior door at the top-left of the picture.

Picture#34: Typical required stainless steel drainage with p-trap for the sinks to be installed over the continuous countertop

Picture#35: Typical color chart for the countertop for the sinks, to be provided by the contractor to the School Director to select the final color of the countertops.

Picture#38: Typical toilet and piping to be removed.

Picture#39: Typical condition of boys toilet. Remove existing partitions.

Picture#42: Entrance to boys bathrooms from lobby

Picture#43: Entrance to boys bathrooms from lobby

Picture#40: Entrance to boys toilet. Door to be replace with entrance with arc on the top or new door with glass to maximize the use of natural light. Provide gypsum board false ceiling.

Picture#41: Existing handwashing area in boys bathroom

Picture#44: Girls toilets

Picture#45: Detail of girls toilet. Remove existing masonry partitions.

Picture#48: Girls toilets and teachers toilets at the end

Picture#49: Window in teachers area to be replaced with a new one with size as needed in order to fit with the new countertop for the 2 required sinks.

Picture#46: Remove, replace or reroute all piping so that no piping is visible after the renovation works.

Picture#47: Cover all piping under the new wall surfaces, including piping coming from above. Replace all vent piping up to the exterior of the building. This may require work in other areas of the school not under the scope of work of the project.

2.2 COMPLETE RENOVATION OF THE GYMNASIUM

The contractor shall completely repair the indoor physical education facility as detailed herein. The area under the scope of work of the contract is exclusively the main gymnasium room, which is a room with internal dimensions of approximately 19.5 x 11.5 meters. For required level of quality and finishes the contractor can visit the renovated gymnasiums in School#22 in Sevastopol or School#14 in Simferopol. The works include, but are not limited to the following:

- Walls: Remove existing composite wood wainscot and paint from walls by manual or mechanical means, level and repair all surfaces and provide 3 coats of paint. In order to level the wall surfaces, new plaster will be required in extensive areas. In some areas the reinforcing is exposed, or the cover of metal structural members is insufficient. The exposed reinforcement shall be repaired by epoxy based mortar and the loose plaster removed and properly repaired. It must be noted that part of the heating piping and electrical conduits need to be recessed along the walls, and therefore this will require repair works along the walls. Provide new surfaces resistant to impacts. Provide washable paint (3 colors to be selected by School Director).

Provide wall protection in lowest 2 meters (see bullet on wall protection)

- Wall Protection: Provide wall wainscot in lowest 2 meters of walls (similar in size as the existing one). Material to be natural wood (not composite as in the existing gym), linoleum or other similar approved material (not plastic). Material to comply with Ukrainian Fire Code.

- Ceiling: Remove the paint by manual or mechanical means. Repair structural damages as on the walls. Level all surfaces and provide 3 coats of paint.

- Heating: Design and install a heating system as required for the new flooring to be installed and in coordination with the new required ventilation system (see bullet about ventilation). Remove all heating piping, radiators and wooden protection system. Provide and install new heating system connected with the building heating system. Connect at a location where the piping has sufficient capacity to provide the required heat in the room, considering the additional heat losses caused by the new required ventilation. Provide proper physical protection for the new aluminum radiators to be used as benches for the children (see paragraph below on benches).

Piping for heating system to be recessed along the walls or floors or otherwise not exposed to the view by approved shield. Heating piping shall not be seen in the renovated areas.

- Benches: Provide benches to protect the heating system as shown in picture#57 and #58. The contractor shall remove all existing wood from the gymnasium and provide new benches in coordination with the protection of the new heating radiators as in picture#57 and #58. Provide along the walls with radiators. Material to be in accordance with recommendations of the manufacturer of the radiators and in accordance with Ukrainian Fire Code.

- Electrical: Replacement of the entire electrical installation. The contractor shall completely remove the electrical installation in this room (including lighting fixtures on the ceiling). All loads to be connected to a new electric panel. The new electrical panel shall be connected with the main electric panel of the school or to a location within the school with sufficient capacity for the gymnasium loads and in compliance with Ukrainian electrical regulations. The new electrical installation for the gymnasium shall be provided with new wall mounted receptacles (4 units) protected against impacts and a new lighting system. The lighting fixtures shall be halogen sports type lighting fixtures, protected against impacts, and capable of providing 500 lux at any location of the room. The lighting fixtures shall be controlled by individual switches to be located at the entrance of the room, and they shall not be controlled by the circuit breakers of the main electric panel. A minimum of 8 new lighting fixtures are required, to be installed at different

Picture#50: Provide similar wall hung professional basketball with break-away rim.

locations. Control lighting by 4 different switches. Each switch to control 2 lighting fixtures. All electrical conduits to be PVC recessed along the walls. No electrical conduit shall be exposed to the view. Provide 4 electrical wall receptacles, at the locations to be indicated by the School Director. Provide emergency exit lights.

- External Windows: The exterior windows are new and shall not be replaced as part of this contract. However, the contractor shall remove, clean, paint and reinstall the metal protection for the windows.

- Doors: Replace all doors connecting with the main gymnasium room. Remove the existing doors and replace with new solid wood flush doors of similar size, similar to the one shown in picture#60. Remove all wood from the door openings, including frames, anchors and trims. The doors shall be minimum 4 cm thick and provided with the required locks and hardware. Provide see through window with 8 mm glazing. Protected against impacts.

- Wood racks/volleyball support: Replacement of “wood racks” in the gym. Remove existing wooden racks and provide new ones of similar size in the same location. Provide 2 new volleyball support poles (with one volleyball net) anchored to the walls.

- Basketball boards: Provide 2 new professional basketball boards (2 units). Reutilize the existing supports to the maximum extent technically possible. Reutilize the existing basketball boards on the sides of the gymnasium. All rims of the basketball boards shall be installed with the rim at

3.05 m from the finished floor surface.

Professional basketball boards shall be installed at both ends of the gymnasium and shall be made of methacrylate backboards of 10 mm thickness (with foam protection in the bottom) properly anchored to the walls, and with break-away basketball rims (see picture #50).

- Floor: Complete removal of the existing wood flooring and its supporting structure. Installation of a new sports rated natural wood flooring surface. The contractor shall remove the existing wood flooring and support system and provide new sports rated solid natural wood flooring.

Once the existing floor is removed, the contractor shall perform any modification that may be necessary to install the new flooring system (i.e. reroute heating lines or leveling). The use of aggregate to level the floor is not acceptable, not to increase the weight of floor on the existing building structure. Leveling shall be done with wood, and following manufacturer’s recommendations.

Flooring system shall be specifically designed to be used in indoor sport facilities, such as basketball courts, and the contractor shall show evidence of previous use of this flooring system for similar use. The flooring system shall be rated by the manufacturer to be installed in a location with the weather conditions of Sevastopol and with natural ventilation system, without cooling capacity or capacity to control the humidity. Finish material shall be 22mm strip made of oak, beech or similar resistance hard wood. Base shall have 2 layers of minimum 12 mm plywood, resilient polyurethane pads, vapor barrier, and required leveling wood material.

Floor shall be varnished following manufacturer’s recommendations. Floor to be installed by experienced workers following manufacturer’s recommendations and striped for basketball and volleyball. Hollow sound of any portion of the finished floor when bounced with a basketball shall

Picture#51: Natural ventilation

Picture#52:Forced ventilation be justification for non acceptance of the floor. Manufacturer representative shall certify surface preparation, installation and finishes before any payment is authorized for the sports rated wood flooring.

See pictures 53, 54, 55 and #56 for typical floor installation for an indoor wooden basketball court. The contractor does not need to follow these specific designs for the floor, except the thickness of the surface wood boards that shall be minimum of 22 mm and provided with tight joints (not similar to existing flooring to be removed) and other requirements described in the paragraphs above.

No payment will be authorized for any wood flooring until the manufacturer technical representative certifies the correct surface preparation and the correct installation of the new flooring.

- Ventilation: The gymnasium used to have ceiling ventilation, however this was blocked years ago by the school administration. The contractor shall design and install a new ventilation system for the project includes the design and installation of a new ventilation system in coordination with the heating system, all as required by Ukrainian applicable regulations. The ventilation system shall be a combination of forced and natural combination. Exterior opening shall be covered with an 180 degree angle as shown in pictures#51 and #52 to avoid any rain water to get into the buildings. All exterior openings shall be provided with bird protection nets.

Both systems (natural and forced) shall be installed as far as possible from each other in order to maximize air exchange in the room:

Forced ventilation: Provide one exhaust fan with connection to the exterior of the facility..

Exhaust fan shall be variable speed, controlled by a single switch (recessed on the walls as the rest of the electrical installation) and the capacity of the fan shall be sufficient to replace at high speed all the air volume of the room in 5 minutes.

Natural Ventilation: In coordination with the forced ventilation and heating, the contractor shall design and install a natural air ventilation system. The opening shall be controlled by mechanical means from the floor level.

Picture#58: Required benches

Picture#57: Required benches

Picture#55: Required floor finishes

Picture#53: Typical composition of a typical sports rated basketball flooring

Picture#54: Typical composition of a typical sports rated basketball flooring

Picture#56: Typical top wood assembly

Picture#62: Provide new similar wood racks

Picture#60:Typical new door

Picture#59: Volleyball pole as the new one required

Picture#64: Required basketball basket (2 units only). Reutilize the existing supports as much as technically possible.

Picture#63: Typical general look for new renovated areas

Picture#61: Typical required wall protection

Picture#65: Existing wood racks to be replaced with new.

Coordinate location and design with School Director.

Picture#66: basketball support to be reutilized to the maximum extent technically possible.

Picture#69: Ceiling opening covered by School years ago.

Picture#70: General view of the gymnasium. All doors to be replaced with new.

Picture#67: Wall protection to be replaced with new made of natural wood (not composite)

Picture#68: Details of ceiling defects to be repaired.

Reutilize the lateral basketball boards.

Picture#71: Typical similar plaque provided in a different project.

2.3 COMMEMORATIVE PLAQUE

At the end of the construction works, the contractor shall provide and install 1 commemorative plaque at the main entrance, at the exact location to be indicated by the Contracting Officer Representative. The plaque shall have the following information engraved on it:

Colored Flag of Ukraine

Colored Flag of the United States of America

EUCOM Logo

This text: “The Sanitation improvements of this school and the repairs to the Gymnasium were accomplished as a partnership between the people of the United States of America and the people of Ukraine, through the combined efforts of the United States European Command, Office of Defense Cooperation, US Embassy Ukraine and City Administration of Sevastopol - Date”

Same text as above in Ukrainian.

The plaque shall have the following characteristics:

- Fabricated with powder coated aluminum with permanent printed 3.5 cm high, style font

"Arial" letters. Adhesive letters will not be accepted.

- Minimum dimensions 50 centimeters wide by 35 centimeters high. Minimum thickness 8 millimeters

- Resistant to outdoor weather and UV radiation.

- Plaque to be manufactured by specialized company.

- Before purchasing the plaques, the contractor shall submit the design to the Contracting

Officer for approval.

Picture#74: Acceptable man-lift

Picture#72: Required type of scaffold

Picture#73: Required type of scaffold

2.4 SCAFFOLDING AND FALL PROTECTION

In order to execute the works included in this project, the contractor shall be required to use scaffolding and/or elevating working platforms.

Despite the scaffolds that may be authorized by Ukrainian regulations, the contractor is only authorized to utilize European Standard scaffolds similar to the ones shown in pictures below.

These scaffolds shall be installed and used in accordance with manufacturer’s recommendations. In case the contractor needs to access the façade at any particular point without the need to install scaffolds, the contractor shall use a CE certified self-propelled man-lift, similar to the one shown in picture below. The use of other type of scaffolds, other non CE certified man-lifts, or any type of ladders for façade or roof work, IS NOT AUTHORIZED.

Picture#75: some components of European scaffolding

3. DETAILED SCOPE OF WORK (CONTRACT OPTION-1)

This portion of the contract described in paragraph 3 and all its subparagraphs corresponds to the work included in Contract Option-1. The work included in this contract option shall only be executed if, and only if, Option-1 is awarded. The scope of the project includes the repairs to the Assembly Hall as detailed herein.

3.1. ROOF OF THE ASSEMBLY HALL

During the last site visit in May 2013 the roof lad severe leaks caused by openings in the corrugated asbestos containing roof sheets. The repair of the roof is not included in this contract and it shall be repaired by the School Administration. The roof contains asbestos and it cannot be repaired, altered or accessed by the construction contractor as part of this contract. This contract does not include any asbestos handling or repairs to asbestos containing materials.

Any work in the Assembly Hall shall not start until the Contracting Officer or the Contractor receives official notification from the School Administration that all roof leaks over the Assembly Hall have been corrected.

3.2. GENERAL

The Assembly Hall used to be a chapel. As such, it is provided with numerous ornamental and decorative elements. If this contract option is awarded, the contractor shall hire the services of a licensed architect or interior designer to provide a complete design with the elements required by this contract, for the acceptance of the Contracting Officer and the approval of the School Administration.

3.3. CEILING

The work includes removing the existing false ceiling and replacing it with new gypsum board ceiling. Before covering the ceiling with new gypsum boards, the contractor shall repair all structural defects, and covering all ceiling surfaces with plastered and painted gypsum board supported by new galvanized metal structure. Provide with access hatches as necessary to allow for maintenance of any installation over the ceiling surface.

Provide ornamental decoration made of gypsum, of similar size as the existing ones.

Provide new lighting recessed in the new ceiling surfaces.

Paint all surfaces as required by the contractor proposed design. A maximum of 2 colors are required for the ceiling. Install at the same height as the existing false ceiling.

3.4. CURTAIN RAILS

The stage curtain replacement is not included in this contract. However, this contract includes providing the necessary heavy duty railing to support a double curtain. The contractor shall provide 2 parallel curtain rails, for the school to install the curtains when the project is finished.

3.5. WALLS

The work includes repairing all wall surfaces and providing new paint covering. Similarly to the ceiling surfaces, the contractor shall repair the existing decoration as recommended by their designer. Once the project is completed, the number and sizes of the decoration shall be similar to the sizes of the existing ones.

A combination of 3 colors is required for the new renovated walls.

3.6. FLOORS

The work does not include any repairs to the floors. However, the existing floor and the stage shall be protected during construction work. The contractor is responsible to restore all floor surfaces to their original condition.

3.7. HEATING

The lack of proper heating is one of the main deficiencies of the room. The work includes removing all existing radiator and piping and designing a new central heating system in order to provide the required temperatures in the winter given the supply of central heating water.

The contractor shall hire the services of a licensed engineer to size and locate the new heating radiators. The new heating radiators shall be as required for the renovated bathrooms. All heating pipes to be covered under the walls of covered by approved protection, so that no heating piping is visible after the work is completed.

The design of the covers of the heating radiators shall be prepared by the designer hired by the contractor is coordination with the finishes of the walls.

3.8. ELECTRICAL

The work includes the complete replacement of the electrical installation of the Assembly Hall. All technical requirements of the electrical work in the Base-Bid are applicable to this section. In particular the contractor shall perform the following works:

- Demolitions: Remove all electrical installations.

- Electric Panel: The contractor shall provide one new main electric panel to be recessed within the repaired walls. The electrical panel shall be fed from the main electric panel of the school or from a location with sufficient power for the intended loads.

- Receptacles: Provide 4 around the seating area and 12 in the stage area. All receptacles to be recessed in the wall surfaces. Provide special receptacles for larger electrical loads if required for any installations in the stage area.

- Existing systems: The contractor shall remove and reinstall any existing communication systems in compliance with Ukrainian regulations.

- Room Lighting: The contractor shall design and install 2 separate lighting systems for the room:

o Ceiling lighting: Provide recessed rapid start fluorescent. Provide circular lighting fixtures. Control by 4 separate switches to control the amount of lights. With all lights connected the room shall have 200 lux at 1 meter height. Minimum of 20 units similar to the ones shown in pictures#78 and #79 o Wall lighting: Provide at the same location as the existing wall lights LED technology lighting fixtures, designed to be wall mounted. Provide one single dimmer to control the amount of light. Do not provide a switch.

- Stage Lighting: The contractor’s hired architect of interior designer shall design a stage lighting system with the following minimum characteristics:

o Controlled in the stage area with individual dimmer for each light o 3” Fresnel type lighting fixtures with 250 W lamp and possibility of changing colors (6 units) o Possibility of manually adjusting the direction to aim the lights

Picture#76: Typical multi zone split type air conditioning system with 4 wall mounted units

3.9. MULTI-ZONE INVERTER TECHNOLOGY SPLIT-TYPE AIR CONDITIONING

The project includes providing air conditioning to the Assembly Hall. Main source of heating shall be provided with the new radiators connected to the central heating system, nevertheless the air conditioning shall use heat pump technology, to provide heating and cooling. Heating by the use of electric resistance is not authorized.

The contractor shall hire the services of a specialized company or engineer to design the new air conditioning system. For estimating purposes, the contractor can estimate a system with the following technical parameters:

- Remove the existing air conditioning systems and deliver them to the school Administration.

- Heat pump system using inverter technology or variable refrigerant flow. Capable of providing hot and cold air.

- The contractor shall provide one exterior unit and 4 internal units.

- With minimum visual impact to the façade of the building.

- Individual temperature control.

- Drainage from the condensate of each room to be connected with the exterior ground

- Designed to provide 22 degrees Celsius in worst summer conditions in Sevastopol.

Picture#77: Fresnel type lighting for the stage.

Picture#78: Fluorescent lighting fixture to be installed in

Picture#81: Ceiling with ornamental elements to be replaced with new ornamental elements

Picture#82: Effects of water leaks on the ceiling. Remove existing lighting and wall mounted cables. All electrical installation to be recessed on the walls.

Picture#79: Fluorescent lighting fixture to be installed in

Picture#80: Details of existing ceiling to be removed.

Picture#83: Wall and ceiling damages

Picture#84: View from the stage to the entrance

Picture#87: Roof defects to be repair by others.

Picture#88: General view of the exterior of the Assembly hall with roof defects to be repaired by others.

Picture#85: Radiator protection to be replaced by new ones designed by the contractor’s architect of interior designer.

Picture#86: Details wall damages caused by water infiltration

4. PROJECT OBJECTIVES

The project is to improve the general environment of the users of this School, and in particular to improve the sanitation conditions, and thus, improve the quality of their education.

The contractor shall integrate sustainable principles into the development and construction of the project to reduce the total cost of ownership of the facility using a whole building, life-cycle approach.

Provide integrated sustainable principles and features to minimize the energy consumption of the facilities; conserve resources; minimize adverse effects to the environment; and improve occupant productivity, health, and comfort.

Integrate energy conservation principles into the development and construction of the project.

Provide energy efficient lighting fixtures.

5. PROCEDURE

This construction contract is based on 3 principles:

- Strict compliance with American Contracting Regulations, including the requirements of the

Department of Defense, the US Navy and Naval Facilities Engineering Command (NAVFAC).

- Strict compliance with Ukrainian technical and legal regulations

- Strict compliance with the most stringent of US and Ukrainian Safety regulations

The contractor shall provide a Construction Permit from the Municipality, or the competent Ukrainian authority authorizing the works included in this contract, or an official letter signed by an Ukrainian authority certifying…

This is the start of the file's text. The full file is on GovTribe.