Vendor_QandA_Milling_Machine_Dismantle.pdf

PDF 89 KB Posted

Attached to
Dismantle of Monarch Milling Machine
Solicitation number
N32253-26-Q-0079
Issued by

About this file

This is a Questions and Answers document for a federal solicitation issued by PHNSY & IMF (Pearl Harbor Naval Shipyard & Intermediate Maintenance Facility).

The solicitation N32253-26-Q-0079 concerns the dismantle of a Monarch Milling Machine. The document clarifies contractor responsibilities and work parameters through five key Q&As issued on 09/03/2026. The contractor is responsible solely for dismantling, palletizing, and staging the machine with no off-site hauling or disposal required. Equipment movement will be accomplished using appropriately rated forklifts or material handling equipment (MHE), as the work area cannot accommodate a crane. The contractor must furnish all pallets and dunnage, with the restriction that no engineered timber or metal may be used for these materials. Regarding residual fluids found in the machine, the contractor is responsible for containment and cleanup only, with disposal handled by the PHNSY Waste facility. No photographs of the milling machine, staging area, or access route are available; however, additional information has been added to Section 3.12 of the Performance Work Statement to provide necessary details for bid preparation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PHNSY & IMF: N32253

Solicitation – N32253-26-Q-0079

Monarch Milling Machine Dismantle

RESPONSES TO QUESTIONS (09/03/2026)

1. Question: Please confirm the contractor is only responsible for dismantling, palletizing, and staging the machine, with no off-site hauling or disposal required.

Answer: PWS updated for clarification.

2. Question: Can an appropriately rated forklift/MHE be used to move the dismantled components, or is a crane required?

Answer: Work area will not accommodate a crane.

3. Question: Are pallets/dunnage contractor-furnished, and are there any specific requirements?

Answer: Contractor to furnish pallets/dunnage. No engineered timber or metal to be used as pallets or dunnage.

4. Question: For any residual fluids, is the contractor responsible for containment/cleanup only, or disposal as well?

Answer: Residual fluids will be disposed to PHNSY Waste facility.

5. Question: If available, please also provide any photos/details of milling machine, designated staging area and access route.

Answer: No photos are available. Additional info added to Section 3.12.