Errata1_HIRMC-001-25_Redacted.pdf
PDF 83 KB Posted
- Solicitation number
- N32253-25-Q-0011
About this file
This is an errata document (Errata No. One) updating specification HIRMC-001-25 for maintenance work on High Pressure Air Compressors (HPACs) aboard a vessel. The work involves maintenance and repairs on No. 1 and No. 2 HPACs manufactured by Dresser-Rand Co. Class AA+ located in the Engine Room Mid Level Forward.
The scope includes installing new suction and discharge valve assemblies across all four stages, replacing/refurbishing the Programmable Logic Controller (PLC) and housing for No. 2 HPAC, installing new J1, J2, and J3 wire harnesses, overhauling pressure relief valves, cleaning the separator drain system, and flushing the oil lubricator system. The work requires a qualified on-site representative from Curtiss-Wright Fleet Solutions to inspect, maintain and repair the equipment. Known issues include abnormal drip rate indications on HPAC No. 1's lubricator and HPAC No. 2 tripping before reaching operational pressure. The contractor must submit completion reports within 5 days of work completion and all other reports within 30 days. No government furnished materials are provided.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Errata1_HIRMC-001-25_Redacted.pdf | ||
| SOW_HIRMC-001-25_Redacted.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
THIS PERMANENT CHANGE UPDATES THE SPECIFICATION BID PACKAGE.
SHIP:
HIRMC -001-25
ERRATA NUMBER:
SPECIFICATION NUMBER:
One
THE FOLLOWING ITEMS ARE REPLACED:
551-51-001
DATED: 12/5/2024 11:50:46PMPage 1 of 1
SHIP: ITEM NO: 551-51-001 (E1)
COAR: 26 PCN: EM01-L652
EM01-L653
CMP: NONE
PLANNER:
SSP: HIRMC -001-25 1 of 3 ITEM NO: 551-51-001 ERRATA NO. One
1. SCOPE:
1.1 Title: No.One and No.2 High Pressure Air Compressor (HPAC) Maintenance (GROOM); accomplish
1.2 Location of Work:
1.2.1 Engine Room Mid Level (ERML) Forward
1.3 Identification:
1.3.1 Quantity: (2 EA), High Pressure Air Compressor (HPAC); Mfr:
Dresser-Rand Co. Class AA+; APL: 06A030007
1.3.2 Quantity: (One EA), Programmable Logic Controller (PLC) and Housing
(E1)
1.3.3 Quantity: (One EA), J1 Wire Harness (E1)
1.3.4 Quantity: (One EA), J2 Wire Harness (E1)
1.3.5 Quantity: (One EA), J3 Wire Harness (E1)
2. REFERENCES:
2.1 Standard Items, FY-25 (CH-1)
2.2 S6220-CQ-MMO-A10 Rev 1, HIGH PRESSURE AIR COMPRESSOR, CLASS AA+
3. REQUIREMENTS:
3.1 Accomplish the requirements of 009-90 of 2.1.
3.1.1 Provide the services of a qualified on-site representative to inspect, maintain and repair the equipment listed in 1.3 and located in 1.2, in accordance with the requirements of 2.2 and Original Equipment Manufacturer's (OEM) proprietary drawings and specifications.
3.2 Remove existing and install new Suction and Discharge Valve Assemblies for the equipment located in 1.2 and listed in 1.3. First Stage: (2 EA) Suction Valve Assemblies and (2 EA) Discharge Valve Assemblies. Second Stage: (One EA) Suction Valve Assembly and (One EA) Discharge Valve Assembly. Third Stage: (2 EA) Suction Valve Assemblies and (2 EA) Discharge Valve Assemblies. Fourth Stage: (One EA) Suction Valve Assembly and (One EA) Discharge Valve Assembly, in accordance with the requirements of 2.2 and OEM proprietary drawings and procedures.
3.2.1 Remove existing and install new or refurbished equipment located in 1.2 and listed in 1.3.2 for the No. 2 HPAC.
(E1)
3.2.2 Remove existing and install new equipment located in 1.2 and listed in 1.3.3, 1.3.4 and 1.3.5 for the No. 2 HPAC.
(E1)
3.3 Remove existing, overhaul, adjust and reinstall, First, Second, Third, Fourth Stage Air Pressure Relief Valves and (2 EA) Water Pressure Relief Valves, for the equipment located in 1.2 and listed in 1.3, in accordance with the requirements of 2.2 and OEM proprietary drawings and
SSP: HIRMC -001-25 2 of 3 ITEM NO: 551-51-001 ERRATA NO. One procedures.
3.4 Open, inspect, clean and blow down the Separator Drain System piping, ensure the piping is free of blockages and foreign material, for the equipment located in 1.2 and listed in 1.3, in accordance with the requirements of 2.2 and OEM proprietary drawings and procedures.
3.4.1 Restore Separator Drain System piping upon completion of the requirements of 3.4.
3.5 Clean and flush Oil Lubricator System, ensure the piping is free of blockages and foreign material, for the equipment located in 1.2 and listed in 1.3, in accordance with the requirements of 2.2 and OEM proprietary drawings and procedures.
3.5.1 Restore Oil Lubricator System piping upon completion of the requirements of 3.5.
(Q)(G) "OPERATIONAL TEST"
3.6 Accomplish an operational test of the equipment located in 1.2 and listed in 1.3 in accordance with the requirements of 2.2.
3.6.1 Allowable air, water and/or oil leaks: None. All air, water and/or oil leaks resulting from the requirements of 3.2 through 3.5 and within the scope of work, shall be corrected by the contractor.
3.6.2 Submit one legible copy, in approved transferrable media, of a report certifying satisfactory work completion of this specification to the SUPERVISOR, within 5 days of completion.
3.7 All reports with no time specific submission requirement, shall be submitted to the SUPERVISOR within 30 days of work completion.
4. NOTES:
4.1 Known Source for qualified Technical Representative:
Curtiss-Wright Fleet Solutions
1675 Brandywine Ave., Suite F
Chula Vista, CA 91911
P.O.C: Brandon Paston
Office: (619) 482-3410
Cell: (619) 348-4746
Email: bpaston@curtisswright.com
4.2 HPAC No. One lubricator is experiencing abnormal drip rate indications.
4.3 HPAC No.2 trips before operational final pressure is reached.
4.4 If required by OPSEC Program Manager, contractor to accomplish work in accordance with signed OPSEC plan.
5. GOVERNMENT FURNISHED MATERIAL(GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
SSP: HIRMC -001-25 3 of 3 ITEM NO: 551-51-001 ERRATA NO. One
1. None.
5.3 KITTED MATERIAL:
1. None.