This document is a set of Questions and Answers related to Solicitation No. N32253-24-Q-0037 for the dismantling and removal of elevators in Dry Dock #1 and Dry Dock #2 at the Pearl Harbor Naval Shipyard and Intermediate Maintenance Facility (PHNSY & IMF). The solicitation is a Firm Fixed-Price contract with a tentative performance period of June 10, 2024 to October 8, 2024. It is a 100% small business set-aside with a NAICS code of 238290 - Other Building Equipment Contractors. The solicitation does not require a performance bond, and no patching services are needed after the supporting anchors are removed. Progress payments will not be authorized, and the period of performance may be extended if there are submarines in the dry docks during the work. No pre-penalty exists for early contract completion. The government may provide technical manuals and photos/close-up pictures of the elevators upon contract award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N3225324Q0037 Q and A.docx | DOCX document | |
| Encl 1 - Site Visit Information.pdf | ||
| N3225324Q0037 AMD1.pdf | ||
| Site Visit DD1 and DD2 Elevator Dismantle and Removal.pdf | ||
| A4_Cranes_on_Base.pdf | ||
| N32253-24-Q-0037 Solicitation.pdf | ||
| A1_Safety_and_Health.pdf | ||
| A2_Environmental_Protection.pdf | ||
| A3_Contractor_Security.pdf | ||
| A5_OPSEC.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No. N32253-24-Q-0037 DD1 and DD2 Elevator Dismantling and Removal Questions and Answers
| Ques. # |
| Reference |
(para/page #, etc.)
| Question |
| Government Response |
| 1 |
| General question |
| Is bonding a requirement? If so, what is the amount? |
No, performance bond is not required.
| 2 |
| General question |
| Will there be photos provided of the elevators? |
| Pending approval to be released to the public. |
| 3 |
| General question |
| Will there be technical manuals provided to the contractors? |
Yes, PHNSY has a manual for the elevators to be provided upon award of the contract.
| 4 |
| General question |
| Once the supporting anchors are removed from the wall of the drydock, is the contractor required to provide patching services? If so, will you be providing the specs for this work? |
No patching service is required.
| 5 |
| General question |
| Will progress payments be authorized for this lengthy work? |
No, the period of performance is from 10 June 2024 through 8 October 2024.
| 6 |
| General question |
| Will the period of performance be extended if there are submarines in the drydock(s) while this work is being performed? |
| It is open for discussion, depending on what the situation is. |
| 7 |
| General question |
| Any chance of close in/tight in pictures? |
| Pending approval to be released to the public. |
| 8 |
| General question |
| Any pre-penalty for finishing earlier/faster? |
| No penalty. |
| 9 |
| General question |
| Is this the Dry dock in front of NIOC Hawaii Quarterdeck/beside? |
No.