N32253-15-T-0021_0005.pdf
PDF 47 KB Posted
- Attached to
- Sanitary Tank, Clean and Gas Free
- Solicitation number
- N32253-15-T-0021
About this file
Amendment 0005
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N32253-15-T-0021_0004.pdf | ||
| N32253-15-T-0021_0003.pdf | ||
| N32253-15-T-0021_0002.pdf | ||
| N32253-15-T-0021_0001.pdf | ||
| N32253-15-T-0021w.Attachs_Redacted.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to incorporate Questions and Responses, set a cut off for questions to be submitted and to extend the due date in block 8 of the SF 1449.
Please submit any additional questions no later than 13 April. 2015; 1400 (HST).
The due date for submittal of quotations is extended to 14 April 2015; 12:00 PM (HST).
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 13-Apr-2015
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N32253-15-T-0021
X 9B. DATED (SEE ITEM 11)
29-Mar-2015
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
13-Apr-2015
CODE
PEARL HARBOR NAVAL SHIPYARD & IMF
667 SAFEGUARD ST., STE 100,
JBPHH HI 96860-5033
N32253 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N32253-15-T-0021
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
QUESTIONS AND RESPONSES
Question#4: Is the sub in dry dock where the work will be done, or in the water? And which dry dock will it be in?
Response#4: The current plans are to accomplish the cleaning of the USS Hawaii sanitary tanks during their "nesting" period while the submarine is in the water.
Question#5: Why is the sub personnel chlorinating and opening the tanks? The tank cleaners should be doing that. Will there be any other chemical introduced in to the tank besides bleach when the Navy is chlorinating?
Response#5: The work spec is written for the initial chlorination and pump down of the sanitary tanks to be accomplished by ship's force. Only bleach is added to during the initial chlorination. In addition, the tanks are being chlorinated by ships force because of the orientation of the access cover to the tanks being on the side on the Virginia Class. Ship's Force will introduce chlorine when the system is closed/intact, once the tank covers are opened the tanks will not be able to be filled to the top as in a traditional 688 class submarine.
Question#6: The specs stated that the bleach should sit for an hour, however, Navy Regs specify at least 24 hours, which is correct? Is Gamazyne allowed?
Response#6: Cannot find anywhere in work spec that states the bleach should sit for an hour, initial chlorination will be at least 24 hours. The Engineering approved work spec only allows for bleach to be used at this time.
(End of Summary of Changes)