Turbochargers PWS Rev 3.23.26.pdf
PDF 374 KB Posted
- Attached to
- USNS COMFORT (T-AH 20)Auxiliary Diesel Generator (ADG) Turbocharger and T-AH Class Pump Replacements
- Solicitation number
- N3220526Q7007
About this file
This is a Performance Work Statement (PWS) for the design, procurement, and installation of replacement turbochargers on the USNS COMFORT (T-AH 20) Auxiliary Diesel Generators.
The contract includes three CLINs: CLIN 0001 (Design), OPTION CLIN 0002 (Procurement), and OPTION CLIN 0003 (Installation and Testing). Under CLIN 0001, the contractor must design and develop a comprehensive design package for retrofitting six MAN Diesel turbochargers (Type NR26/98, Model TCR18-42145) across three auxiliary diesel generator engines, including inlet and exhaust compensators and integration with the ship's machinery control and monitoring system. The design package must include engineering drawings, work items, calculations, test procedures, and technical manuals, all requiring ABS and USCG approval. Design deliverables follow a three-phase review process (P1 Preliminary, P2 Review, Final) with submission deadlines spanning one calendar year from contract award. CLIN 0002 requires procurement of turbocharger integration components, specialty tools, automation components, lagging/insulation, and related equipment; Factory Acceptance Testing signed off by ABS/USCG; and delivery to the shipyard on the East or Gulf Coast, whichever is more expensive. CLIN 0003 covers installation and testing within a 90-day window during a 2028 shipyard availability, with 45 days' notice provided, and includes provision of a qualified MAN-certified installation team, operational testing, dock trials, sea trials, and as-built documentation. The total period of performance extends through December 31, 2028, with design completion required within one calendar year of award. All work must comply with SOLAS, ABS Marine Vessel Rules, USCG, IEEE requirements, and MSC standards. Key personnel positions (Project Manager, Lead Design Engineer, QA Engineer, Lead Installation Technician, and Installation Team Members) are identified with no substitutions permitted without Contracting Officer approval. The contractor must pickup and deliver all documentation at MSC N7 offices in Norfolk, Virginia, and assume travel costs for ship checks on the East or Gulf Coast and 2028 installation activities. All deliverables become exclusive government property with unlimited rights; the contractor retains no restrictions on use, modification, reproduction, or transfer.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Combined_Synopsis_Solicitation N3220526Q7007_Rev.4.docx | DOCX document | |
| Combined_Synopsis_Solicitation N3220526Q7007_Rev.3.docx | DOCX document | |
| Combined_Synopsis_Solicitation N3220526Q7007_Rev.2.docx | DOCX document | |
| Combined_Synopsis_Solicitation N3220526Q7007_Rev.1.docx | DOCX document | |
| Combined_Synopsis_Solicitation N3220526Q7007.docx | DOCX document | |
| CLSExport_N3220526Q7007.pdf | ||
| N10425Q7007 JA signed N00L_Redact.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USNS COMFORT (T-AH 20) Auxiliary Diesel Generator (ADG) Turbocharger Replacements
1. BACKGROUND: The USNS COMFORT (T-AH 20) is outfitted with three (3) MAN Diesel model 12V 25/30 Auxiliary Diesel Generators (ADG) with twin MAN Diesel Turbochargers, the installed turbocharger is an Exhaust Gas Turbocharger Type NR26/98, Max Temp 650°C, 32000RPM, pulse system, Year built – 1984.
The current turbocharger model is obsolete, and the replacement model is not a direct replacement.
1.1 This contract requires the services of a company specializing in MAN Diesel Generator Systems to design, procure, and provide installation services to retrofit six turbochargers to also include inlet and exhaust compensators, and including all regulatory body approvals. The turbochargers will be provided as Government Furnished Material (GFM) and have already been purchased. The equipment affected is as follows:
1.1.1 Three (3) MAN Diesel/B&W Type 12V 25/30, medium speed, non-reversible, four stroke engine of trunk piston design with twin exhaust gas turbochargers, 2843hp, 2120kW, 900RPM, 1711 psi (118 bar), Year built – 1984.
1.1.1.1 Engine No. 1045141 (No. 1 ADG)
1.1.1.2 Engine No. 1045142 (No. 2 ADG)
1.1.1.3 Engine No. 1045143 (No. 3 ADG)
1.1.2 Replacement required for Auxiliary Diesel Generator Turbochargers, six (6) total, two (2) units per engine, MAN Diesel Exhaust Gas Turbocharger with air cooler, Type NR26/98, Max Temp 650°C, 32000RPM, pulse system. The new Turbochargers (TCR18-42145) have already been purchased by Military Sealift Command(MSC) and will be provided to the contractor.
1.1.3 Modify ADG automation and controls and integrate with the ship’s machinery control and monitoring system by subcontracting Technical Marine Service, Inc (TMS).
1.1.4 Not used.
1.2 All system design, materials, and fabrication shall be in accordance with the latest Safety of Life at Sea (SOLAS) regulation, American Bureau of Shipping (ABS)Marine Vessel Rules, and United States Coast Guard (USCG), Condition Found Report (CFR’s). System design, and installation shall meet all applicable ABS, USCG, and IEEE requirements.
1.3 This contract will be awarded with three CLIN’s as follows:
1.3.1 CLIN 0001 will be to identify and perform the design portion to install new Turbochargers to include all associated components. Develop installation plans, inspection criteria and test plan for replacing the Turbochargers.
1.3.2 OPTION CLIN 0002 will be to procure equipment, modify, and fabricate the required parts to install the six (6) Turbochargers (three (3) each left bank and three (3) each right bank) and associated components for all three (3) engines including associated components and material. It will also include the procurement of spare parts.
1.3.3 OPTION CLIN 0003 provides services for installation, commissioning and testing of the ADG turbochargers, and components associated with the design of CLIN 0001, and parts procured in
CLIN 0002.
2. CLIN 0001 - DESIGN
2.1 Scope
2.1.1 Design integration for the new turbochargers and associated equipment and components with the ADG’s to also include inlet and exhaust compensators and associated gaskets, flanges, expansion pieces, insulation, automation, etc. for the USNS COMFORT.
2.1.2 Not used.
2.1.3 Provide a design Package for replacing the Auxiliary Diesel Generator Turbochargers consisting of drawings, work items, calculations, installation estimates, advanced planning products, test procedures, and technical manuals to include all structural, electrical, electronic, automation, communication and mechanical systems required for the installation of the identified turbochargers. Submit all final deliverables to MSC. The equipment affected by this item is as follows:
2.1.3.1 Three (3) MAN Diesel/B&W Type 12V 25/30, medium speed, non-reversible, four stroke engine of trunk piston design with twin exhaust gas turbochargers, 2843hp, 2120kW, 900RPM, 1711 psi (118 bar), Year built – 1984 (USNS COMFORT).
2.1.3.2 Six (6) Turbochargers (Three (3) – Left Bank and Three (3) – Right Bank (USNS
COMFORT).
2.1.3.3 ADG automation and control interface with the ship’s machinery control and monitoring system (USNS COMFORT).
2.1.3.4 Not used.
2.2 Kick Off Meeting (CDRL A001)- Host a Kick-Off Meeting within one (1) week of Contract issuance.
Contact the Contracting Officer’s Representative (COR) and arrange a kick-off meeting at an agreeable time for the purpose of reviewing the PWS requirements. Create an agenda prior to the meeting along with presenting the Plan of Action and Milestones (POA&M). Record meeting minutes and action items resulting from this meeting and provide as CDRL A002. All key personnel identified by Section 13 shall attend.
2.3 Project Schedule (CDRL A003)- Maintain POA&M in Microsoft Project. The POA&M shall be updated after the kick-off meeting, consisting of a timeline of actions, events, and delivery dates for the deliverables. The POA&M shall cover all work required under the contract. The POA&M is a living document and shall be updated and submitted to the Government on the first working day of each month and after any change is needed. The POA&M shall highlight critical path(s) as well as “not later than” dates required for each task award in order to meet the required installation schedule (as identified in Section 11).
2.4 Ship Check Plan (CDRL A005)- Prepare and submit to MSC, the Ship Check Plan by 2 weeks prior to the ship check. The plan must provide a chronological scheme of how the ship survey is to be conducted and the types of information to be acquired and recorded. The plan shall be reviewed by MSC and accepted or rejected based on the plans’ ability to successfully gather the necessary information in the allotted time with the proposed resources identified by the Contractor. The plan shall have a detailed list of expected ship check activities listed. During this ship check, the Contractor must gather information required to support the development of the design package. Key Technical Personnel must attend the ship check along with any additional support personnel necessary to gather all required information in the time provided. Ship check dates must be agreed upon by the contractor and contracting officer at least 2 weeks in advance to allow for travel planning. Should the ship check Plans require updates from MSC, incorporate MSC’s comments and resubmit revised ship check plans.
NOTE: Specific notification will be made in the ship check plans if the ADGs are to be run, run underload, or will need to be taken out of service during the ship checks. If needed, a designated time will be identified to operate the ADGs and may be outside of typical work hours.
2.5 Ship Check - Ship check the USNS Comfort in order to obtain all necessary information to perform the tasks described herein. During the ship checks, interface with the MSCREP, coordinate and consult with the crew, and anticipate and plan accordingly. Gather all information required for the tasks during the ship checks. The Government and the contractor will formalize ship checks dates at the kick-off meeting, but shall commence as early as possible. Any areas of concern found during the ship check shall be discussed with the MSCREP during the ship check and documented and forwarded in the ship check report to the MSCREP. The MSCREP will determine which minimal deficiencies may be incorporated into subject design package and incorporate corrections during the design phase of this PWS. Develop and provide the following:
2.5.1 Ship Check Notes (CDRL A006)- Take daily ship check notes throughout the duration of the ship checks. The notes shall summarize each day’s activities and highlight any incidents or deviations from the Ship check Plan. The Contractor must meet each morning with the MSCREP’s and Ship’s Force (SF) to discuss the work plan for each day. The Contractor must meet each afternoon with the MSCREP’s to discuss the work plan for the following day and to recap any issues from the day. The Contractor must provide an electronic copy of a daily log of all activities accomplished (e.g., shutdowns required, measurements calculated, drawing updates recorded, etc.). The daily notes shall list questions for MSCREPs; and explain any answers from the MSCREP or decisions required as a result of daily activities. An electronic copy of the notes and daily log shall be provided to the MSC rep within one week of the conclusion of the ship check.
2.5.2 The Contractor must conduct a meeting (CDRL A007) on the final day of the ship check to summarize the ship check events and to discuss any outstanding concerns. The Contractor must review all the Ship Check Notes with the MSC Representatives and conduct a complete walk-through of all the locations addressed in this PWS. The purpose of the walk-through is to ensure all the necessary information has been collected to develop the required work packages. It is the responsibility of the Contractor to ensure that all information needed to develop a complete work package has been gathered during the ship check. The review and monitoring by the Government does not relieve the Contractor from this responsibility.
2.5.3 Ship check Reports (CDRL A008)- After completion of each ship check, provide a Ship check Report. The Ship check Report shall summarize all activities that occurred during the ship checks.
The report shall also detail all anomalies, incidents and deviations from the Ship Check Plan. The Ship Check Report should also discuss any significant findings or issues that require MSCREP input or resolutions in support of the final deliverables. The MSC COR will review and approve each Ship Check Report.
2.5.4 Access Requirements - The Contractor, including all subcontractors, will be required to pass all applicable security requirements to obtain Base and Ship Access.
2.6 Design Package - Create a design package to facilitate the replacement of the six (6) GFM Turbochargers on the three (3) MAN Diesel Auxiliary Diesel Generators. Design Package shall include Work Items, engineering drawings, assembly drawings, and Advanced Planning Products, which include test procedures, design calculations, arrangements, schematics, and technical manuals required for the replacement the Turbochargers with MAN Diesel approved model selected above in Sections 2.1.3 and in accordance with CDRL’s A010, A011, and A014 - A016. The integration design must be Original Equipment Manufacturer (OEM) MAN Diesel approved to conform at a minimum to the manufacturer’s installation requirements for the Turbochargers and engine systems.
The design shall conform to the requirements specified in the documents listed in Section 13 below.
The design shall include all modifications to support installation of the new Turbochargers; and their integration into the ships systems including but not limited to:
Mounting brackets Intermediate pieces between turbocharger and charge air cooler Intermediate pieces between turbocharger and exhaust pipe Intermediate pieces between turbocharger and funnel Inlet and exhaust compensator Insulation/lagging Outlet casing Gage connections Drains Venting pipes Cut and modify the fuel pipes due to interference with the turbocharger installation Installation of cleaning devices Installation of speed transmitters Installation and integration of vibration or other health monitoring information Integration requirements into the ship’s machinery control and monitoring system Commissioning and matching of turbochargers Support for Class and IMO certificates
2.6.2 Not used
2.6.3 Develop a full set of structural, mechanical and electrical drawings detailing requisite modifications for turbocharger replacement and integration with the ships systems. Provide a full set of approved drawings in AutoCAD (2025 LT compatible) and electronic pdf format. PDF shall include ABS and USCG stamp of approval and be accompanied by the ABS and USCG approval letter.
2.6.4 Create Work Items for shipyard support for the installation of the ADG Turbochargers, to supplement the installation drawings. The Work Item (WI’s) shall be submitted for review as part of the Deliverables Package. Shipyard support WI’s may consist of rigging from shore to the ship and ship to shore, temporary services, cleaning, waste disposal, receiving/shipping of material, consumables, scheduling integration with other shipyard activities, power, access, supplying lay down areas (onboard or off the ship); and providing a load bank and operator if required. The WI will not include any additional labor for installation; that is the responsibility of the contractor and is subject of CLIN 0003 of the contract. Do not price the shipyard support. Shipyard support for this effort will be funded as part of the shipyard package by MSC.
2.6.5 Provide interface drawings for the integration of Turbochargers for the monitoring and control into the ship’s machinery and control system. This shall include interface schematics, signal types and ranges and connections to provide critical Turbocharger and engine operating information to the machinery control system. This information shall include at a minimum;
Turbocharger speed, boost pressure, oil pressure and intake/exhaust temperatures, pump pressures and temperatures; and other OEM recommended monitoring/control points. The integration of the data points and controls from the turbocharger interface panel/locations back to the machinery control system will be coordinated by Contractor with the ship’s machinery control and monitoring system, which the OEM is TMS. It is the duty of the Contractor to sub-contract and directly interface with TMS and provide all associated costs as part of this contract.
2.6.6 The Contractor is responsible for all calculations and equipment certification required to obtain ABS and USCG approval. Further, the Contractor is responsible for developing engineering solutions for any technical design problems related to the installation for the replacement Turbochargers and associated equipment and hardware.
2.6.7 Develop test procedures for both the new Turbochargers. All test procedures will be approved by MSC/ABS/USCG.
2.6.8 Provide updates to be incorporated in documents for Operation (changes in operating parameters between new and replaced Turbochargers), Preventative Maintenance (PM), and test procedures affected by the modifications required for the new Turbochargers for future testing on the ADGs
– for example alarm set points for temperatures, pressures and over speeds.
2.6.9 Existing ADG Technical Manual’s shall be updated (to include the new Turbochargers and parts) and all affected sheets provided. Redlining is not an acceptable form of updating. Technical Manual updates shall provide a parts breakdown and OEM recommended spare parts components for five years of both corrective and preventative maintenance based on approximately 3,000 hours of operation a year.
This list shall be provided to the MSCREP. Parts shall be priced individually . The list shall contain:
2.6.9.1 Make and model of the new Turbochargers
Maintenance equipment Maintenance Material and vendor cut sheets.
Special Tools Spare parts
2.6.9.2 Not used.
2.6.9.3 Component level details for ordering replacement parts to include Make Model/Part Number Material danielle.grisson Line danielle.grisson Line
2.6.10 Host design review (CDRL A012) meetings after the submittal of each round of Deliverables.
The Contractor is to provide hard copies of the work items and drawings and shall be prepared to record action items and mark up a set of work items and drawings as the master copy during the design review meetings. Provide design review meeting minutes (A013). Incorporate all agreed upon changes as discussed in the design review meeting into the subsequent deliverables. Key personnel are required to attend the design review meetings.
2.6.11 Create an electronic copy of meeting minutes, which will be due two (2) business days after each design review meeting and provide to the COR and Contracting Officer.
2.6.12 Be responsible for pickup and delivery of documentation and technical references at MSC N7 offices, (Building N-19 Naval Station Norfolk, Norfolk VA). Scheduling pick up requires 24 hours business day notice to ensure an MSC rep is available to meet the need.
2.6.13 Not used.
2.7 Progress Reports (CDRL A004) – Electronic Monthly Progress Reports Progress Reports shall be submitted to the COR and Contracting Officer and shall provide the status of each item included in the POA&M. Any issues requiring the MSCREP’s input shall be presented as part of the Progress Report.
Progress reports shall continue through the Procurement.
3. OPTION CLIN 0002 – PROCUREMENT
3.1 Procure three (3) sets (total six (6)) Turbochargers integration components (CDRL B001). The Turbochargers integration components shall be crated in internationally approved shipping containers and preserved for storage until installation in an environmentally secure storage. Specific packaging techniques shall be approved by the MSCREP. Contractor shall store the turbocharger components until ready for installation and ship them directly to the shipyard.
3.2 Not used.
3.3 Procure all equipment and material as required by the installation package developed into Section 2.1 above for replacing the Auxiliary Diesel Generator Turbochargers (CDRL B001). This includes any specialty tools, automation components, lagging/insulation, and equipment for installation and testing that has not already been procured by the government.
3.4 Provide Factory Acceptance Test (FAT) signed off by ABS/USCG that also demonstrates the turbochargers were balanced before shipping (B002). If they were not, it shall be the contractor’s responsibility to provide all shipping and regulatory body testing approvals.
3.5 Provide the certification of the testing and inspection results meeting the requirements of the test plans from section 1.3.1. and all completed test and inspection results will be documented electronically and the results provided to MSC (B003). MSC and regulatory bodies will be given the option to attend any testing with a minimum of 3 weeks’ notice.
3.6 Track, store and deliver the equipment for the ADG Turbocharger parts, equipment and tools to the shipyards (B005). Tracking information should be sent to the COR and Contracting Officer. Price delivery to a location for the USNS COMFORT on the East Coast or Gulf Coast of the United States, whichever is more expensive.
danielle.grisson Line
3.7 Not used.
3.7.1 Individual spare parts, tools or maintenance material procured under this contract will be provided to the ship and must be independently marked, affixed to the part itself and sealed to protect from the high humidity shipboard environment.
3.8 Packaging for parts, tools and material shall be in accordance with ASTM D3951-10. All packages containing equipment, parts and materials shall be labeled with weatherproof labels inside and out with the contract number, requisition number, complete parts list in the packaging and vessel name (B004).
Labels will be identified with “USNS COMFORT ADG (Number) TURBOCHARGER REPLACEMENT”. Provide confirmation to the MSCREP, COR and Contracting Officer when in receipt of all material.
4. OPTION CLIN 0003 – INSTALLATION AND TESTING
4.1 The installation shall take place within a 90-day window during a Shipyard availability in 2028 for the USNS COMFORT. A 45-day notice will be given to the Contractor prior to installation. For estimating the installation cost, shipping and travel, use either East Coast or Gulf Coast; whichever is higher, for cost estimating. (CDRL C009)
4.2 Once the shipyard and location of the installations have been determined, develop a schedule for the turbocharger replacements. Determine an installation timeline so as to integrate with the crew’s work, shipyard work and support; and any external contractors supporting the installation. Prepare a schedule of events and submit to the MSCREP and applicable shipyard before work onboard begins
(CDRL C002).
4.3 Provide labor, parts, materials, tools, storage, and shipping to perform the installations of the ADG Turbochargers.
4.4 Provide a qualified installation team (CDRL C008). The installation team shall be key personnel and must have the demonstrated ability to accomplish the installation. The installation team must have the manpower and technical ability to perform all the requirements necessary to replace the Turbochargers. Installation team must be certified by MAN.
4.5 Perform all work and provide all materials necessary to replace the ADG Turbochargers identified in the deliverables and components identified in Sections 2.1 (CDRL C009). The Contractor is responsible for resolving any technical design problems related to the installation. The installation, testing, tuning, and commissioning shall take place in a shipyard period within a 90-day window on the USNS COMFORT. Coordinate with the shipyard working together to avoid conflict and scheduling delays. The installation window shall be determined during the Kick-Off meeting with the Shipyard POC and MSCREP. Be available to support any Calendar day within the shipyard availability and should plan for 3 trips; 1 for installation, 1 for testing/dock trials, and one for sea trials for both ships. (CDRL C010 & C011)
4.6 TEST AND INSPECTION REPORTS (CDRL C004) - Record all Test Data into the Test Procedures developed during the execution of this PWS and provide to the Onsite Management Team (OMT) final Test Procedures with MAN Diesel, ABS, USCG, Chief Engineer, and MSCREP signatures and Approvals. The Contractor is required to develop Test and Inspection Reports that contain:
4.6.1 The completed test plan.
4.6.2 All objective test data obtained during testing and inspection.
4.6.3 The corresponding design data and conclusions as to the condition of the equipment.
4.6.4 System or structure based on comparison of design data to actual data.
4.6.5 Recommendations to correct any deficiencies.
4.7 Coordinate a Kick-Off Meeting (CDRL C001) on day one of the Shipyard Availability when the turbochargers will be replaced, with the MSCREP and the Shipyard POC (Shipyard TBD). Be required to work with the Shipyard POC and is responsible for coordinating all work and testing for this item with the complete Shipyard Package, MSC REP, and Shipyard POC. Work to mitigate delay and disruption.
Provide an up-to-date copy of the POA&M at this meeting.
4.8 Progress Reports shall be electronically submitted weekly during shipyard installation and shall provide the status of each item included in the POA&M (CDRL C003). Any issues requiring the MSCREP’s input shall be presented as part of the Progress Report.
4.9 Conduct an operational test of existing units to observe and record existing running condition of all three diesel engines and all associated components, record all running conditions, and submit an “As-Found” condition report to MSCREP, with recommendations including approximate cost to repair all discrepancies found (CDRL C005). Request Chief Engineer to take baseline vibration readings with Ships vibration monitoring equipment prior to the start of any work. This work shall be completed prior to shut down and should be arranged ahead of time with the Chief Engineer.
4.10 Alleviate potential delays by reviewing the production schedule for the ROHDD to ensure work under this contract does not create disruption to the ROHDD contract and vice versa. Conflicting scheduling work should be worked out with the prime contractor to avoid delays for any work.
4.11 Uncrate and examine new turbochargers for any damage incurred during transit prior to uninstalling old turbocharger.
4.12 Prior to the start of any work, ensure all material shipped to the site has been received, no missing parts, and all received items are in good condition before beginning, disassembly. Inform MSCREP with the list of discrepancies if any (CDRL C006).
4.13 Consult with the vessel’s Chief Engineer, shipyard, and MSCREP prior to starting any work, for coordinating the sequence of work between the three engines.
4.14 Disable only one generator engine at a time, unless otherwise approved by the MSC MSCREP.
4.15 Submit an electronic detailed condition report on any findings requiring further consideration with a solution and price to correct (CDRL C007).
4.16 Remove all interferences required for accomplishing this work. Label, mark, protect and store all items removed in an environmentally safe place.
4.17 TAG-Out and secure all auxiliary systems. All system operation, securing, Tag-Out/Tag-In shall be accomplished by ship’s force. Confirm all systems are secured and tagged out in compliance with their own companies’ and the prime contractor of the ROHDD’s procedures and regulations.
4.18 Perform replacement of Auxiliary Diesel Generator turbochargers as identified in design deliverables in Section 2 above.
4.19 Clean all intercoolers, examine for defect, and inform MSCREP for any additional repairs deemed necessary.
4.20 Replace the turbocharger inlet and exhaust compensator to match the turbocharger to include all gaskets, flanges, expansion pieces, insulation, labor, and shipping. Contractor to properly dispose of any Asbestos material found during removal in accordance with the prime contractors asbestos policy.
4.21 Contractor to utilize OEM (TMS) of the ADG Panels to make software modifications in accordance with drawings developed in CLIN 0001. OEM to program Panels and Auxiliary Switchboard room to show panel displays and alarms for the three ADG’s. Provide all wiring, material, and labor for modifications.
4.22 Remove and replace with new, the exhaust manifold lagging.
4.23 Cut and modify the fuel pipes due to interference with the turbocharger installation.
4.24 Open, clean, and close the fuel tank in preparation for hydro testing and then hydro test.
4.25 Plan to replace up to 5-cylinder heads with ship’s spares, overhaul them, and then return them to the ship as spares when complete. Provide written and signed documents of who received the items returned to the ship.
4.26 Plan to replace up to 10 injectors with ships spares and overhaul them along with another 20 injectors and return them to the ship as spares when complete.
4.27 Contractor to Check and adjust valve clearance and timing on all three ADG’s.
4.28 Contractor to balance all 3 ADG’s.
4.29 Have appropriately sized nozzle rings readily available during commissioning and matching.
4.30 Reinstall and restore all previously removed interferences to as found condition or better, upon completion work.
4.31 Upon completion of all new installations, modifications, and assembly of all piping, tubing, ducting, exhaust and intake transition pieces, and reconnecting all instrument wiring, inform the Chief engineer to replenish engine oil or other mediums and remove the tags in accordance with the vessel and prime contractors tagout procedures in preparation for operational test.
4.32 Successfully test run and tune completed engine prior to the subsequent start of work on the next engine.
Perform operational test of each diesel as per test procedure developed in Section 2.6.7.
4.33 Tune or match each newly installed turbocharger with their respected diesel engine through a range of engine speed and various load condition, to achieve smooth operation and meet desired conditions.
4.34 Continuously record all diesel engine and turbocharger performance parameters throughout each test for each engine.
4.35 Final acceptance for each engine shall be signed off by MAN diesel representative, MSCREP, ABS and USCG surveyors and copies of the signoff provided to the MSCREP (CDRL C012).
4.36 Be aware of and observe any OEM requirements for commissioning newly installed turbochargers.
4.37 Repair and/or replace all disturbed and damaged insulation.
4.38 Prime and coat all new and disturbed surfaces in accordance with Reference 13.8.
4.39 Submit to MSCREP a detailed service report for each engine including all as found conditions and requisite modifications or corrections, material used, reports of inspection by ABS, MSC Rep, and Chief Engineer, and operational parameters taken during test run. (CDRL C013)
4.40 Attend sea-trials and address any issues noted.
4.41 AS BUILT DOCUMENTS (CDRL C014):
4.41.1 Redline all installation drawings provided as part of the base task. Also update all shipboard documents, test procedures, and technical manuals relating to the turbocharger replacement. Create As-Built drawings in AutoCAD (2025 LT compatible) based off of the redline mark ups. Red line mark ups and As-Built drawings shall be provided to the MSCREP and reviewed. All MSC drawing comments shall be incorporated into the final As-Built drawings delivered to MSC. All drawings, test procedures, and technical manuals shall retain their existing level of detail at a minimum.
Coordinate all final ABS/USCG approvals.
4.41.2 Update the ADG Tech Manual to reflect the new turbocharger configuration. Redlines will not be acceptable. Sheets shall be updated and replaced in their entirety.
5. PLACE OF PERFORMANCE: Work is to be performed on board the USNS COMFORT at the contractor’s facility, located at Naval Station Norfolk, or a shipyard facility located on the East, or Gulf Coast.
6. PERIOD OF PERFORMANCE: The period of performance for the contract is on award, and shall be completed by December 31, 2028. The Design requirement under CLIN 0001 shall be completed within one calendar year from award date. The installation shall take place in a 90-day window shipyard availability in 2028 for the USNS COMFORT .
7. DELIVERABLES:
7.1 Delivery of Documents: All deliverables shall be submitted to the MSCREP. The Contractor shall be responsible for pickup and delivery of documentation and technical references at MSC N7 offices, (Building N-19 Norfolk Naval Base, VA) at the Contractor’s expense. All comments shall be incorporated into each round of the deliverables as required by Section 8.2.
7.2 CLIN 0001 Deliverables –Design:
7.2.1 Kickoff meeting minutes with action items as required by Section 2.2.
7.2.2 Plan of Action and Milestones (POA&M) in MS Project and PDF as required by Section 2.3.
7.2.3 Shipcheck Plan, Notes, and Report as required by Section 2.5
7.2.4 Monthly Progress Reports as required by Section 2.7.
7.2.5 Recommended spare parts, special tools, and maintenance equipment with pricing information as required by Section 2.6.13.
7.2.6 Design Packages: Electronically delivered and 1 hard copy for each ship, to include Drawings, Work Items, Shipboard Test Procedures, Calculations, entire Technical Manuals for all new or modified equipment, as required by Section 2.6.
7.2.6.1 The Preliminary Copy will be marked as Preliminary 1 (P1) and will be reviewed by MSC.
The MSCREP and Contractor Key Personnel shall meet to discuss and MSC comments. The Contractor shall incorporate all comments developed by this review into the Review Copy.
7.2.6.2 The Review Copy will be marked as P2 and will be reviewed by MSC. The Contractor shall incorporate all MSC comments into the Final Copy.
7.2.6.3. After MSC has approved P2, all preliminary revision marks and revision notes shall be removed from the drawings and the Final Copy shall be labeled as “Rev-”. The Contractor will then submit the required deliverables to MSC for final approval and then to ABS/USCG for approval.
7.2.7 Design review meeting minutes and actions items as required by Section 2.6.10.
7.2.8 Pickup and delivery of documentation as required by Section 2.6.12
7.3 OPTION CLIN 0002- Procurement Deliverables:
7.3.1 Procure material as required by Section 3. Provide confirmation once all material is procured.
7.3.2 Test turbochargers as required by Section 3.4 – 3.7.
7.4 OPTION CLIN 0003– Installation:
7.4.1 Fully installed, functional, tested, and regulatory body approved Auxiliary Diesel Generator turbocharger installations as required by Section 4.
7.4.2 Conditions Found Report as required by Section 4.15.
7.4.3 Full set of as-built drawings as required by Section 4.41.
7.4.4 Test reports from installation as required by Section 2.6.7.
7.4.5 Final approval letters and signatures from ABS, USCG, and MSCREP.
7.5 TASK DELIVERABLE FORMATS:
7.5.1 Copies of all reports, work packages, studies and other text documents shall be submitted to the MSCREP in electronic form (Microsoft Office Products, Adobe products, and AutoCAD 2025 LT compatible respectively) and three (3) Hard Copies (8 ½ x 11 for all reports/technical manuals and 11x17 for all drawings).
7.5.2 Software and Software Development Tools. The Contractor shall maintain compatibility with the following MSC software: AutoCAD (2025 LT compatible), Microsoft Office 2010 suites, Windows 7, Windows 10, Citrix, SYBASE, JAVA, Sharepoint, and Microsoft.(dot)NET.
7.5.3 Regulatory Body Approvals. The Contractor shall provide Regulatory review and approval. The contractor shall provide two (2) full size hard copies, two (2) AutoCAD (2025 LT compatible) copies, and two (2) PDF copies of each deliverable, including USCG and ABS stamp and/or letter as applicable certifying approval, if required, on CD/DVD. All CD/DVD(s) shall be labeled, at a minimum with the date of delivery, Contract Number/Description, name of the MSCREP, and list of documents on CD/DVD (include drawing numbers, work items, and technical manual numbers as applicable).
8. PERFORMANCE STANDARDS: This is a Performance Based Contract in accordance with FAR 37.6.
The PWS provides specific requirements to accomplish the work. Evaluation of performance will be based on ability to provide quality, and deliverables to include parts, installation, and required documents in an efficient and timely manner. The Government shall monitor the Contractor’s performance under this contract using the Quality Assurance Surveillance Plan (QASP) developed by the Government.
9. Review Process - All deliverables described in this PWS must be submitted in accordance with the following process:
9.1 The Contractor must submit P1 (A010) deliverables for MSC review and. The P1 deliverables must be complete, technically correct, and properly formatted with no reservations, errors or omissions.
The P1 deliverables must be reviewed by the Contractor’s Quality Assurance personnel as identified in Section 14 prior to submission to the COR. MSC review is not to be used as the Contractor’s Quality Assurance (QA) review. If P1 deliverables are submitted with reservations, omissions or are unacceptable per the Performance Requirements Summary (PRS) the P1 deliverables will be rejected and returned to the contractor as unacceptable and updated P1 deliverables must be resubmitted to MSC. This process must continue until MSC accepts the P1 deliverables. Each new revision of P1 deliverables must be marked with a subsequent letter starting with P1A, P1B, P1C, etc. until P1 deliverables are accepted by MSC. An updated POAM must be submitted within 2 business days of receiving the rejection from COR.
9.2 The Contractor must adjudicate and/or incorporate all comments from the P1 deliverables review to create the P2 (A011) deliverables. The P2 deliverables must be complete, technically correct, and properly formatted with no reservations, errors or omissions. The P2 deliverables must be reviewed by the Contractor’s Quality Assurance personnel as identified in (2025 LT compatible) prior to submission to the COR. MSC review is not to be used as the Contractor’s Quality Assurance (QA) review. The P2 deliverables must be submitted with a listing of all P1 comments (or later revision, if required) and their resolution status. The listing should also include explanation for any comments not thoroughly incorporated, and responses to any design questions. The Contractor’s Quality Assurance personnel must ensure all P1 (or later revision, if required) comments have satisfactorily been addressed prior to submission to the COR. If P2 deliverables are submitted with reservations, omissions or are unacceptable per the PRS the deliverable will be rejected and returned to the contractor as unacceptable and updated Preliminary Copy (P2) must be submitted to MSC. This process must continue until MSC accepts the P2 deliverables. Each new revision of P2 must be marked with a subsequent letter starting with P2A, P2B, P2C, etc. until P2 deliverables are accepted by MSC. An updated POAM must be submitted within 2 business days of receiving the rejection from COR. MSC reserves the right to make new comments during P2 review.
9.3 After P2 deliverables have been accepted by the COR, all preliminary revision marks and revision notes must be removed from the drawings and they must be labeled as “Rev –” (A014) or the most up to date revision. The “Rev –” deliverables must be reviewed by the Contractor’s Quality Assurance personnel prior to submission to the COR. If Rev- is submitted with reservations, omissions or is unacceptable per the PRS, the deliverable will be rejected and returned to the contractor as unacceptable and an updated Rev - must be submitted to MSC. This process must continue until MSC accepts the Rev - deliverable. Each new revision of Rev - must be marked with the submittal date on both the file name and in the revision notes section for document control. For any deliverables that do not require regulatory approval, this deliverable will become the Final Copy after MSC’s comments are incorporated and Rev – is accepted.
9.4 After the “Rev –” deliverables are approved by MSC, the Contractor must submit the approved “Rev –” final deliverables to ABS for review via ABS website (www.eagle.org) and to the USCG at msc@uscg.mil. When submitting to ABS (see GFI 8.10), and USCG the Contractor must include the COR in the Notification List with both Submission and Approval rights. When completing form 8.12, Contractor should provide it to their COR in accordance with Reference 8.9 for ABS Services to be processed. The Contractor is responsible for addressing any technical comments from ABS and USCG (CDRL A015) including all required calculations to obtain ABS/USCG approvals. Prior to uploading any technical comment responses to ABS and the USCG, the Contractor must first submit the responses to the COR. Upon approval from the COR, technical comment responses must be officially uploaded to the ABS website and submitted to the USCG. MSC must be copied on all information submitted to ABS/USCG and all ABS/USCG responses. The Contractor is responsible for following up with ABS/USCG to ensure Final Deliverables are received on time from ABS/USCG to meet MSC Final Delivery dates. The Contractor must be responsible for delivering all ABS/USCG stamped plans and corresponding approval letters from ABS/USCG to the COR. Documents must be submitted directly to the COR from the Contractor; the COR downloading plans and letters from the ABS website does not meet this requirement. All items must be returned stamped ABS “APPROVED” or “REVIEWED” and with a letter of approval from USCG or ABS Stamped “APPROVED BY ABS ON BEHALF OF USCG” (CDRL A016) in accordance with the NVIC 10-92 review procedures as outlined in References 10.3.5 respectively.
10. APPLICABLE SPECIFICATIONS:
10.1 Design, review, construction, and installation shall be in accordance with the specifications, standards, and all requirements incorporated within the documents found in Section 10.3.
10.2 The upgrade project shall meet all applicable ABS, USCG, SOLAS rules and regulations, and IEEE and
MSC requirements.
10.3 In the event of a conflict between specification requirements, the following precedence shall be invoked.
Any specification conflicts shall be brought to the attention of MSC.
10.3.1 United States Coast Guard (USCG) Regulations
10.3.2 American Bureau of Shipping (ABS) Marine Vessel Rules (MVR)
10.3.3 MARPOL
10.3.4 International Convention for the Safety of Life at Sea (SOLAS)
10.3.5 NVIC 10-92
10.3.6 This Technical and Performance Specification (i.e. The Contract)
10.3.7 MSC Drawing Standard 7080803 – Preparation of Computer Aided Designed (CAD) Drawings
10.3.8 MSC General Technical Requirements (GTRs)
11. DELIVERY SCHEDULE:
No. ACTIVITY DEADLINE
CLIN 0001 – DESIGN
Kickoff Meeting
Within one (1) week of effective date of the Contract
2 Kick-off meeting minutes One (1) week after kick-off meeting
POA&M
One (1) week after kick-off meeting. Updated on the 1st of every month until contract completion.
Monthly Progress Reports
One (1) month after effective date of the Contract (Monthly thereafter)
5 Ship check Plan Two (2) weeks prior to start of ship check
6 Ship check Notes Daily during Ship check
7 Ship check Final Day Meeting Held on final day of Ship check
8 Ship check Report Two (2) weeks after completion of ship check.
Spares List Four (4) weeks after effective date of the
Contract
11 Preliminary copy of design packages (P1) Four (4) weeks after effective date of the Contract
MSC Review of P1 design packages
Comments to be provided to contractor within ten
(10) working days of submittal to MSC.
13 Review copy (P2) of design packages to MSC Two (2) weeks after ship check
14 Design Review Meeting Within one (1) week of submitting P2 to MSC
15 Design Review Meeting Minutes Two (2) days after design review meeting
16 Submit final copy of design packages to MSC, once approved, send to ABS
Within two (2) weeks of design review meeting
17 Respond to ABS Comments Within one (1) week of receiving comments from ABS
18 Final ABS Approved design packages to MSC Within ten (10) weeks of first submittal to ABS or upon receipt from ABS
CLIN 0002 – PROCUREMENT
19 Provide Receipt of Material Six (6) weeks after CLIN 0002 is exercised 20 Provide Signed Factory Acceptance Test Six (6) weeks after CLIN 0002 is exercised
21 Provide certification of testing and inspection results Six (6) weeks after CLIN 0002 is exercised
22 Package parts, tools, and material Six (6) weeks after CLIN 0002 is exercised.
23 Provide Tracking Information Eight (8) weeks after CLIN 0002 is exercised
CLIN 0003 - INSTALLATION
25 Kick Off Meeting 1st day of shipyard availability
26 Project Schedule (POA&M) 1st day of shipyard availability
27 Progress Reports Weekly throughout installation
28 Test Procedures and Inspection Reports Completed prior to shut down
29 As Found Condition Report Completed prior to shut down
30 List of Discrepancies Completed prior to shut down
31 Detailed Condition Report Completed prior to shut down
32 Provide Qualified Installation Team Completed prior to shut down
33 Installation of new turbochargers Contractor will have 90 days to complete installation on COMFORT. Installation window within availability period TBD with 45 days’ notice.
34 Dock Trials Dock Trials TBD after end of availability period with 7 days’ notice.
35 Sea Trials Sea Trials TBD after end of availability period with 7 days’ notice.
36 Provide Signed Final Acceptance Documents Within one (1) month of the completion of sea trials
37 Submit Detailed Service Report Within one (1) month of the completion of sea trials
Final Documentation including tech manual inserts, tech manuals, as-built drawings, test reports, condition found reports and final ABS approvals
Within one (1) month of the completion of sea trials or by December 31, 2028, whichever is earlier.
12. GOVERNMENT FURNISHED INFORMATION (GFI)
No. Doc Number Title Revision Format
1 8387635 General Arrangement and Profile - PDF
2 5981915 General Arrangement Inboard Profile G PDF
3 5980081 Diesel & Incinerator Exhaust System B PDF
4 T6270-AF-MMC-010 Diesel Engines Operating Manual - PDF
5 390-205-003 Diesel Generator Exhaust Piping Plan, Sect., Elev. & L/M - PDF
6 T6270-AF-MMC-030
2000 KW Auxiliary Diesel Generator Volume 3 Spare Parts Catalogue Diesel Engine - PDF
Insulation Schedule Machinery and Ventilation
Insulation Schedule Machinery and Ventilation - PDF
8 631-5981321 Paint Schedule - PDF 9 7081123 MSC General Technical Requirements - PDF
10 - ABS Engineering Manager Help Manual - PDF
11 T6270-AF-MMC-020
Diesel Engines Operating Manual (Gen, Install, Maintenance) -
12 T6270-AF-MMC-040
Diesel Engines Operating Manual (Gen, and Operating Instructions) -
13 - REPORT, No. 2 Engine Overhaul, Feb 2012 - PDF
14 - REPORT, No. 1 Engine Performance data, Sep 16 - PDF
15 - Alert Safety Bulletin, ASB2011/12/09 MAN Diesel/Turbo
13. KEY PERSONNEL AND SUBSTITUTION OF KEY PERSONNEL
13.1 General Provision – The Contractor agrees to assign to this Contract the persons whose resumes are submitted with its proposal and who have been identified in the Contractor’s key personnel. No substitutions shall be made except in accordance with this clause. The following positions/individuals are considered as Key Personnel:
Position Employee
Project Manager
Lead Design Engineer
QA Engineer
Lead Installation Technician
Installation Team Members
13.2 Request for substitution – All requests for substitutions must provide a detailed explanation of the circumstances necessitating the proposed substitution, a resume for the proposed substitute, and any other information as requested by the Contracting Officer. All proposed substitutes must have qualifications equal to or higher than the qualifications of the person being replaced. The Contracting Officer or his/her authorized representative will evaluate such requests and promptly notify the Contractor of his/her approval or disapproval thereof.
14. TRAVEL
14.1 Travel. Travel shall be included with offer as this is a firm fixed price contract. Assume East or Gulf Coast for ship check on USNS COMFORT and assume East or Gulf Coast in 2028 for installation at a private shipyard.
15. DATA RIGHTS
15.1 All work performed by the Contractor under the Contract shall become the exclusive property of MSC in which the Government shall have unlimited rights. The Contractor shall not deliver or otherwise provide to the Government technical data, turbocharger design, or computer software, to include the deliverables under the Contract, with restrictions, including those as to use, modification, reproduction, and transfer, or with restrictive markings.
15.2 At any and all times, the Contractor agrees to promptly provide to the Government at no additional cost such documents, codes or other materials and information that are necessary to permit the Government’s full enjoyment of its rights in the deliverables as described above. This term shall survive the expiration of the Contract.
16. COR DESIGNATION - The person named below is the COR for this Contract:
NAME: Zachary Mauer/Michael Downs
CODE: N712
PHONE: 757-341-5570/
The COR shall represent the Contracting Officer in the administration of technical details within the scope of this Contract and will perform inspection and acceptance of all deliverables. The COR is not otherwise authorized to make any representations or commitments of any kind on behalf of the Contracting Officer or the Government. The COR does not have the authority to alter the Contractor’s obligations or change the specifications in the Contract or issue Task Orders. If, as a result of technical discussions, it is desirable to alter Contract obligation or statements of work, a modification must be issued in writing and signed by the Contracting Officer. The COR is responsible for reviewing the invoices submitted by the Contractor and informing the Contracting Officer of areas where exceptions are to be taken. The COR authority is non-delegable. The COR may be personally liable for unauthorized acts.
The Technical Point of Contact (TPOC) for this contract is:
NAME: Danielle Grisson
CODE: N72
PHONE: 757-341-5995 // 757-617-3761
EMAIL: danielle.n.grisson.civ@us.navy.mil
17. AUTHORIZED CHANGES BY THE CONTRACTING OFFICER
17.1 Except as specified in subparagraph 3 below, no order, statement, or conduct of Government personnel who visit the Contractor’s facilities or in any other manner communicate with Contractor personnel during the performance of this Contract shall constitute a change under the Changes clause of this Contract.
17.2 Do not comply with any order, direction or request of Government personnel unless it is issued in writing and signed by the Contracting Officer, or is pursuant to specific authority otherwise included as a part of this Order.
17.3 The Contracting Officer is the only person authorized to approve changes in any of the requirements of this Contract and notwithstanding provisions contained elsewhere in this Contract, said authority remains solely the Contracting Officer’s. In the event the Contractor effects any change at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority and no adjustment will be made in the Contract price to cover any increase incurred as a result thereof. The address and telephone number of the Contracting Officer is:
17.3.1 NAME: TBD
17.3.2 ADDRESS: Building SP64, East C Street, Norfolk, VA 23511
17.3.3 TELEPHONE: TBD