Q and A Responses 1.docx
DOCX document 121 KB Posted
- Attached to
- Worldwide Paint Program Federal contract opportunity
- Solicitation number
- N3220524R4094
About this file
This document is a set of Questions and Answers related to Solicitation N3220524R4094 issued by the Department of the Navy's Military Sealift Command (MSC) for a Worldwide Paint Program. The solicitation is for paint, coatings, solvents, preservation products, and engineering/technical services for the MSC Fleet Paint Program. The original solicitation due date of September 20, 2024 has been extended to October 4, 2024, and the deadline to submit questions has been extended to September 13, 2024. Clarifications were provided regarding the Exhibit A pricing spreadsheet, the inclusion of Exhibit B Contract Data Requirements List, and the minimum and maximum contract values. Technical requirements were also clarified, such as the definition of "shut down" and the need for a writable version of Attachment F. Overall, this document addresses various questions received from offerors to provide additional details and make updates to the solicitation as necessary.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Q and A Responses 2.docx | DOCX document | |
| Q and A Responses 3.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MILITARY SEALIFT COMMAND
N3220524R4094
QUESTIONS AND ANSWERS #1
QUESTION #1
SOLICITATION SECTION: Main Contract, N3220524R4094
PARAGRAPH / SECTION NO: Block 8, Due Date of September 20, 2024, 4:00 pm EST
TITLE: Offer Due Date/Local Time
QUESTION: Solicitation posted 8/20/2024 with a due date of 9/20/24. Given the scope and magnitude of the contract, both from a global set of requirements and dollar commitment, 30 days is not sufficient time. Also, the current contract was extended until June 13, 2025 (close to 9 months remaining).
REQUEST: Please extend the solicitation due date until December 9th. This will provide sufficient planning and proposal generation time. As of December 9th there will be over 6 months left on the remaining contract extension.
ANSWER: The solicitation due date has been extended until 04 October 2024, 4:00PM EDT. In addition, the opportunity to submit questions has been extended until 13 September 2024, 4:00PM EDT.
QUESTION #2
SOLICITATION SECTION: Exhibit A
PARAGRAPH / SECTION NO: Various Lines & Sections
TITLE: Calculations
QUESTION: The spread sheet provided as Exhibit A is not calculating data we enter accurately; there are at least two (2) lines that don’t calculate volume at all (line 22 & 25); all line items do not extend accurately; there also seems to be a disparity in volume calculated; can a more accurate Exhibit A be provided; lack of accuracy on Exhibit A is delaying our ability to accurately complete Attachment F.
ANSWER:
A revised Exhibit A has been provided under Amendment 00001 of the solicitation.
QUESTION #3
SOLICITATION SECTION: Exhibit A
PARAGRAPH / SECTION NO: Various Lines & Sections
TITLE: Overall Volume
QUESTION: Please confirm that volume on Exhibit A is representative of 5/year projected volume?
ANSWER: Exhibit A represents the Government’s estimated volume for (5) years. The Government’s estimates are not contractually binding.
QUESTION #4
SOLICITATION SECTION: Exhibit B – CDRL’s
PARAGRAPH / SECTION NO: N/A
TITLE: CDRL’s
QUESTION: There is no Exhibit B posted for offeror’s to execute. Please provide?
ANSWER: Exhibit B has been provided under Amendment 00001 of the solicitation.
QUESTION #5
SOLICITATION SECTION: Section SF 1449 – Continuation Sheet
PARAGRAPH / SECTION NO: Page 3; Last sentence before ‘end of text’
TITLE: Contract Minimum & Maximum
QUESTION: Why does this sentence establish minimum / maximum values for a one-year ordering period when all other references are for a five-year ordering period?
ANSWER: Contract Minimum & Maximum section of solicitation has been corrected. Changes are in red font of amendment 00001.
QUESTION #6
SOLICITATION SECTION: 12.6 Economic Price Adjustment (EPA)
PARAGRAPH / SECTION NO: 12.6.4
TITLE: Notification
QUESTION: Please define ‘fiscal year’? Is this referring to the Government fiscal or the contract fiscal?
ANSWER: Section 12.6.4 is referring to the contract fiscal year.
QUESTION #7
SOLICITATION SECTION: Page 50, Technical Factor 1 – Paint Products
PARAGRAPH / SECTION NO: Statement ‘O’
TITLE: Confirmation Statements
QUESTION: Please define your meaning of ‘shut down’
ANSWER: Any scheduled breaks or closures during which operations will cease or be significantly reduced, potentially impacting timelines, staffing levels, or service availability (e.g., warehouse maintenance or other facility-related downtimes)
QUESTION #8
SOLICITATION SECTION: Page 51, Technical Factor 3 – Delivery & Distribution Approach
PARAGRAPH / SECTION NO: First Paragraph on the page
TITLE: Attachment F
QUESTION: The Attachment F provided is not a writable file; can you please provide a writable version of that file?
ANSWER: Attachment F has been provided in an Excel format.
QUESTION #9
SOLICITATION SECTION: Section SF 1449 - CONTINUATION SHEET
PARAGRAPH / SECTION NO: Page 3/ CONTRACT MINIMUM AND MAXIMUM
TITLE: Maximum Amount
QUESTION: On page 3 of the solicitation document, it states the minimum amount but no maximum amount is mentioned. Please see screenshot below. May you please assist with this?
ANSWER: Contract Minimum & Maximum section of solicitation has been corrected. Changes are in red font of amendment 00001.