BISMARCK_Amendment_N3220518R4101-0009.docx

DOCX document 40 KB Posted

Attached to
USNS CITY OF BISMARCK PSA/DD
Solicitation number
N3220518R4101
Issued by

About this file

USNS BISMARCK (T-EPF 9) AMENDMENT N3220518R4101-0009

View the file

Other files

File Type Posted
BISMARCK_Amendment_N3220518R4101-0008.docx DOCX document
BISMARCK_PSA-DD_Amendment_N3220518R4101-0007.docx DOCX document
BISMARCK_Amendment_N3220518R4101-0006.docx DOCX document
BISMARCK_Amendment_N32205-18-R-4101-0005.docx DOCX document
Amendment_N32205-18-R-4101-0004.docx DOCX document
Q&A_11_-_15.doc DOC document
Amendment_N32205-18-R-4101-0003.docx DOCX document
RFP_Q&A_5,_7_-_9.doc DOC document
Amendment_N32205-18-R-4101-0002.docx DOCX document
RFP-_Q_&_A_1_-_4_&_6.docx DOCX document
J_-_1_Work_Item_Index_Rev_1.pdf PDF
Amendment_N32205-18-R-4101-0001_BISMARCK.docx DOCX document
JA_N32205-18-R-4101BISMARCK_PSA_(Posted).pdf PDF
J_-_Attachments.zip ZIP file
Solicitation_-_CITY_OF_BISMARCK_N32205-18-R-4101.docx DOCX document
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N3220518R4101

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION F - DELIVERIES OR PERFORMANCE

The following Delivery Schedule item for SUBCLIN 0001AA has been changed from:

DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE

POP 15-OCT-2018 TO

13-JAN-2019

N/A
N/A

FOB: Destination

To:

DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE

POP 07-JAN-2019 TO

06-APR-2019

N/A
N/A

The following Delivery Schedule for SUBCLIN 0001AB has been added:

DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE

POP 07-JAN-2019 TO

N/A
N/A

FOB: N/A

The following Delivery Schedule item for SUBCLIN 0002AA has been changed from:

DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE

POP 15-OCT-2018 TO

N/A
N/A
DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE

POP 07-JAN-2019 TO

N/A
N/A

The following Delivery Schedule item for CLIN 0004 has been changed from:

DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE

POP 15-OCT-2018 TO

N/A
N/A
DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE

POP 07-JAN-2019 TO

N/A
N/A

The following Delivery Schedule item for CLIN 0005 has been changed from:

DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE

POP 15-OCT-2018 TO

N/A
N/A
DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE

POP 07-JAN-2019 TO

N/A
N/A

The following Delivery Schedule item for CLIN 0006 has been changed from:

DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE

POP 15-OCT-2018 TO

N/A
N/A
DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE

POP 07-JAN-2019 TO

N/A
N/A

The following Delivery Schedule item for CLIN 0007 has been changed from:

DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE

POP 15-OCT-2018 TO

N/A
N/A
DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE

POP 07-JAN-2019 TO

N/A
N/A

The following Delivery Schedule item for CLIN 0008 has been changed from:

DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE

POP 15-OCT-2018 TO

N/A
N/A
DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE

POP 07-JAN-2019 TO

N/A
N/A

The following Delivery Schedule item for CLIN 0009 has been changed from:

DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE

POP 15-OCT-2018 TO

N/A
N/A
DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE

POP 07-JAN-2019 TO

N/A
N/A

The following Delivery Schedule item for CLIN 0010 has been changed from:

DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE

POP 15-OCT-2018 TO

N/A
N/A
DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE

POP 07-JAN-2019 TO

N/A
N/A

The following Delivery Schedule item for CLIN 0011 has been changed from:

DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE

POP 15-OCT-2018 TO

N/A
N/A
DELIVERY DATE
QUANTITY
SHIP TO ADDRESS
DODAAC / CAGE

POP 07-JAN-2019 TO

N/A
N/A

The following have been modified:

F-1 SHIP AVAILABILITY PERIOD

It is anticipated that ship will arrive at Contractor’s yard on or about 7 January 2019. All work shall be completed in no more than 90 calendar days from actual start date designated by the Government at time of contract award.

(End of Summary of Changes) image1.wmf