J-8_Request_for_Spec_Clarification_WI_511a.doc
DOC document 38 KB Posted
- Attached to
- USNS HENRY J KAISER MTA Federal contract opportunity
- Solicitation number
- N32205-17-R-4008
About this file
RFC 22
View the file
Other files for this federal contract opportunity
Show all 50
USNS HENRY J KAISER MTA has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N32205-17-R-4008
USNS HENRY J. KAISER (T-AO 187)
REQUEST FOR SPECIFICATION CLARIFICATION
NAME OF CONTRACTOR:
SPECIFICATION ITEM NO.: 511
PARAGRAPH / SECTION NO: 7.23.2 and 7.23.3
TITLE: NO. 3 SSDG OVERHAUL
QUESTION:
Amendment 2 removes the requirement to remove and overhaul the turbochargers for NO.3 SSDG.
Para. “7.23.2.
Remove the exhaust piping bellows connection to the turbocharger in accordance with Sec. 6-13 of ref. 2.1.1” would be required for the R&R of the turbochargers.
Para. “7.23.3.
Upon completion of shop overhaul, reinstall using new gaskets” would also be required for the R&R of the turbochargers.
Is it the intent of the work item to remove the exhaust bellows for inspection?
What is the intent of para. 7.23.3?
ANSWER:
Exhaust Bellows will need to disconnect for removing Cylinder heads and gasket replacement. Bid as is