Questions_&_Answers_-_Part_I.docx

DOCX document 15 KB Posted

Attached to
PMA-281 Systems Lifecycle Support
Solicitation number
N00421-17-R-0014
Issued by

About this file

Not Listed

View the file

Other files

File Type Posted
Responses_To_Questions_-_Part_III.docx DOCX document
Questions_&_Answers-Part_II_.docx DOCX document
Attachment_2_-_Estimated_Labor_Hours.xlsx XLSX spreadsheet
Attachment_3_-_Questionnaire.doc DOC document
Attachment_1__-_Draft_Statement_of_Work.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sources Sought N00421-17-R-0014 Questions & Answers: Part I

#
Questions
Answers
1
Is this a new requirement?
No
2
What is the current contract number?
N68335-16-C-0328
3
Does Government intent to release the PMA-281 Systems Lifecycle Support RFP as an OASIS’s Task Order RFP (TORFP)?

No

4
What is the NAICS Code?
541512
5
When will the RFP be released?
We are estimating a late March 2017 release.
6
Will PMA-201 be participating in the requirements?
PMA-201 is not currently considered in the SOW requirements; however, PMA-201 and PMA-281may be coordinating efforts in the future.
7
Is the security/clearance requirement correct on the RFI?
Security/clearance requirement is correct in SOW; TS/SCI eligible. Please notify NAVAIR if there is conflicting information.
8
Will Original Equipment Manufacturer (OEM) be able to submit a proposal?
A conflict of interest clause will be applied to the RFP/Contract.