Sources Sought N00421-17-R-0014 Questions & Answers: Part I
| 1 |
| Is this a new requirement? |
| No |
| 2 |
| What is the current contract number? |
| N68335-16-C-0328 |
| 3 |
| Does Government intent to release the PMA-281 Systems Lifecycle Support RFP as an OASIS’s Task Order RFP (TORFP)? |
No
| 4 |
| What is the NAICS Code? |
| 541512 |
| 5 |
| When will the RFP be released? |
| We are estimating a late March 2017 release. |
| 6 |
| Will PMA-201 be participating in the requirements? |
| PMA-201 is not currently considered in the SOW requirements; however, PMA-201 and PMA-281may be coordinating efforts in the future. |
| 7 |
| Is the security/clearance requirement correct on the RFI? |
| Security/clearance requirement is correct in SOW; TS/SCI eligible. Please notify NAVAIR if there is conflicting information. |
| 8 |
| Will Original Equipment Manufacturer (OEM) be able to submit a proposal? |
| A conflict of interest clause will be applied to the RFP/Contract. |