This is a solicitation from the Naval Sea Systems Command seeking wire rope services. The solicitation requires wire rope lubrication, inspection, and installation services for three vessels: the YTT-10 Discovery Bay, the YTT-11 Discovery Bay, and the IX-536 Barge. Services include removing existing wire ropes, transporting them for cleaning and lubrication, inspecting them, and reinstalling them. The work specifications provide details on the wire ropes for each vessel and the period of performance. The solicitation includes fixed-price line items for the initial requirements as well as option line items to extend the services for additional years. Offerors are required to submit pricing for all line items. The solicitation provides instructions on submitting offers and the evaluation process.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 0002.pdf | ||
| Amendment 0001.pdf | ||
| Security Requirments.docx | DOCX document | |
| Kitsap County Wage Determination.txt | TXT text file |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE ADDENDUM
(No Collect Calls)
N0025324Q0024 05-Mar-2024
b. TELEPHONE NUMBER
360-315-8930
8. OFFER DUE DATE/LOCAL TIME
01:00 PM 18 Mar 2024
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
N002539. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
NAOMI NI MCKENZIE
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED OR X
SMALL BUSINESSX
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
NAVAL UNDERSEA WARFARE CENTER
ATTN: NAOMI MCKENZIE
NAOMI.MCKENZIE@NAVY.MIL
610 DOWELL STREET, BLDG 206
KEYPORT WA 98345
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS AX
13b. RATING
DO-C9
CODE15. DELIVER TO CODE N00253 16. ADMINISTERED BY
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
NAVAL UNDERSEA WARFARE CENTER
RECEIVING OFFICER
ATTN: DIVISION KEYPORT SUPPLY OFFICER
BLDG 893
610 DOWELL STREET
KEYPORT WA 98345-7610
TEL: 360 396-2760 FAX:
FAX:
TEL: 360-315-8930 SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
1,250
NAICS:
333923
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF46
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
N0025324Q0024
Section SF 30 - BLOCK 14 CONTINUATION PAGE
STATEMENT OF WORK
NAVAL UNDERSEA WARFARE CENTER KEYPORT
RANGE CRAFT CRANE WIRE LUBRICATION/INSPECTION
WORK SPECIFICATIONS
WORK SPEC 01
YTT-10 Discovery Bay
1. Main Crane – 1800’ 1 and 1/8” 6x36 IWRC Main Wire and 200’ ¾” 6x36 IWRC Auxiliary Wire
2. Knuckle Crane – 150’ ¾” 6x36 IWRC Wire Period of Performance: to be scheduled for the 2024 Calendar Year, at a time when the Government POC will contact the vendor to schedule the site visit. Multiple Option years requested as this will be an ongoing preventative maintenance task.
During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier, as designated by the Government Technical Representative, a portable powered line spooler and offload the vessel’s wires. Vendor will provide labor for climbing services to remove wire.
Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires.
Pressure lube of wire will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a verbal condition notification to the Governments representative. Once services are completed, vendor will return wires to KB Docks Bangor or Keyport Pier and provide labor for climbing services to re-install both wires using a portable powered line spooler to install lines under tension. Government will provide crane operator and crane crew.
REQUIREMENT Main Crane Auxiliary and Knuckle Crane wires will be removed and placed onto separate pallets, provided by the vendor. Once services completed wires will be returned on separate wooden spools, provided by the vendor, for installation on the YTT-10’s cranes. Main Crane Main wire will be removed onto a wooden spool and returned on a spool, provided by the vendor. The spools shall be adequate in strength to remove/install the wire under tension.
Labor The vendor is authorized 8 hours to remove wires, 7 business days to service wires per specifications above, and 8 hours to re-install wires.
CHECK POINT
Government representative will inspect and approve crane wire installation before service is accepted as completed.
WORK SPEC 02
YTT-11 Discovery Bay
1. Main Crane – 1800’ 1 and 1/8” 6x36 IWRC Main Wire and 200’ ¾” 6x36 IWRC Auxiliary Wire
2. Knuckle Crane – 150’ ¾” 6x36 IWRC Wire
Period of Performance: to be scheduled for the 2024 Calendar Year, at a time when the Government POC will contact the vendor to schedule the site visit. Multiple Option years requested as this will be an ongoing preventative maintenance task.
During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier, as designated by the Government Technical Representative, a portable powered line spooler and offload the vessel’s wires. Vendor will provide labor for climbing services to remove wire.
Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires.
Pressure lube of wire will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a verbal condition notification to the Governments representative. Once services are completed, vendor will return wires to KB Docks Bangor or Keyport Pier and provide labor for climbing services to re-install both wires using a portable powered line spooler to install lines under tension. Government will provide crane operator and crane crew.
REQUIREMENT Main Crane Auxiliary and Knuckle Crane wires will be removed and placed onto separate pallets, provided by the vendor. Once services completed, wires will be returned on separate wooden spools, provided by the vendor, for installation on the YTT-11’s cranes. Main Crane Main wire will be removed onto a wooden spool and returned on a spool, provided by the vendor. The spools shall be adequate in strength to remove/install the wire under tension.
Labor The vendor is authorized 8 hours to remove wires, 7 business days to service wires per specifications above, and 8 hours to re-install wires.
CHECK POINT
Government representative will inspect and approve crane wire installation before service is accepted as completed.
WORK SPEC 03
IX-536 Barge:
1. Deck Crane – 400’ 1x1/8” 6x36 IWRC Main Wire and 250’ x ¾” 6x36 IWRC Auxiliary Wire
Period of Performance: to be scheduled for the 2020 Calendar Year, at a time when the Government POC will contact the vendor to schedule the site visit. Multiple Option years requested as this will be an ongoing preventative maintenance task.
During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier, as designated by the Government Technical Representative, a portable powered line spooler and offload the vessel’s wires. Vendor will provide labor for climbing services to remove wire.
Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires.
Pressure lube of wire will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a verbal condition notification to the Governments representative. Once services are completed, vendor will return wires to KB Docks Bangor or
Keyport Pier and provide labor for climbing services to re-install both wires using a portable powered line spooler to install lines under tension. Government will provide crane operator and crane crew.
REQUIREMENT IX-536 Main wire will be taken off and placed onto a spool, provided by the vendor. Auxiliary wire will be placed onto a pallet and after service returned on a spool provided by the vendor. The spools shall be adequate in strength to remove/install the wire under tension.
Labor The vendor is authorized 8 hours to remove wires, 7 business days to service wires per specifications above, and 8 hours to re-install wires.
CHECK POINT
A Government representative will inspect and approve crane wire installation before service is accepted as completed.
WORK SPEC 04 / Option Years – Beginning in 2025
YTT-10
1. Main Crane – 1800’ 1 and 1/8” 6x36 IWRC Main Wire and 200’ ¾” 6x36 IWRC Auxiliary Wire
2. Knuckle Crane – 150’ ¾” 6x36 IWRC Wire During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier, as designated by the Government Technical Representative, a portable powered line spooler and offload the vessel’s wires. Vendor will provide labor for climbing services to remove wire.
Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires.
Pressure lube of wire will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a verbal condition notification to the Governments representative. Once services are completed, vendor will return wires to KB Docks Bangor or Keyport Pier and provide labor for climbing services to re-install both wires using a portable powered line spooler to install lines under tension. Government will provide crane operator and crane crew. Vendor to provide climbing services during offload and reload of wires.
CHECK POINT
Government representative will inspect and approve crane wire installation before service is accepted as completed.
WORK SPEC 05 / Option Years – Beginning in 2025
YTT-11
1. Main Crane – 1800’ 1 and 1/8” 6x36 IWRC Main Wire and 200’ ¾” 6x36 IWRC Auxiliary Wire
2. Knuckle Crane – 150’ ¾” 6x36 IWRC Wire During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier, as designated by the Government Technical Representative, a portable powered line spooler and offload the vessel’s wires. Vendor will provide labor for climbing services to remove wire.
Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires.
Pressure lube of wire will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a verbal condition notification to the Governments representative. Once services are completed, vendor will return wires to KB Docks Bangor or Keyport Pier and provide labor for climbing services to re-install both wires using a portable powered line spooler to install lines under tension. Government will provide crane operator and crane crew. Vendor to provide climbing services during offload and reload of wires.
CHECK POINT
Government representative will inspect and approve crane wire installation before service is accepted as completed.
WORK SPEC 06/ Option Years – Beginning in 2025 IX-536 Barge:
1. Deck Crane – 400’ 1x1/8” 6x36 IWRC Main Wire and 250’ x ¾” 6x36 IWRC Auxiliary Wire
During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier, as designated by the Government Technical Representative, a portable powered line spooler and offload the vessel’s wires. Vendor will provide labor for climbing services to remove wire.
Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires.
Pressure lube of wire will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a verbal condition notification to the Governments representative. Once services are completed, vendor will return wires to KB Docks Bangor or Keyport Pier and provide labor for climbing services to re-install both wires using a portable powered line spooler to install lines under tension. Government will provide crane operator and crane crew.
CHECK POINT
Government representative will inspect and approve crane wire installation before service is accepted as completed.
WORK SPEC 07 / Option Years – Beginning in 2026
YTT-10
3. Main Crane – 1800’ 1 and 1/8” 6x36 IWRC Main Wire and 200’ ¾” 6x36 IWRC Auxiliary Wire
4. Knuckle Crane – 150’ ¾” 6x36 IWRC Wire During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier, as designated by the Government Technical Representative, a portable powered line spooler and offload the vessel’s wires. Vendor will provide labor for climbing services to remove wire.
Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires.
Pressure lube of wire will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a verbal condition notification to the Governments representative. Once services are completed, vendor will return wires to KB Docks Bangor or Keyport Pier and provide labor for climbing services to re-install both wires using a portable powered line spooler to install lines under tension. Government will provide crane operator and crane crew.
CHECK POINT
Government representative will inspect and approve crane wire installation before service is accepted as completed.
WORK SPEC 08/ Option Years – Beginning in 2026
YTT-11
3. Main Crane – 1800’ 1 and 1/8” 6x36 IWRC Main Wire and 200’ ¾” 6x36 IWRC Auxiliary Wire
4. Knuckle Crane – 150’ ¾” 6x36 IWRC Wire During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier a portable powered line spooler. Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires. The pressure lube will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a core condition report for each wire. Once service are completed vendor will return wires to KB Docks Bangor or Keyport Pier for Government personnel to install.
CHECK POINT
Government representative will inspect and approve crane wire installation before service is accepted as completed.
WORK SPEC 09 / Option Years – Beginning in 2026 IX-536 Barge:
2. Deck Crane – 400’ 1x1/8” 6x36 IWRC Main Wire and 250’ x ¾” 6x36 IWRC Auxiliary Wire
During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier, as designated by the Government Technical Representative, a portable powered line spooler and offload the vessel’s wires. Vendor will provide labor for climbing services to remove wire.
Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires.
Pressure lube of wire will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a verbal condition notification to the Governments representative. Once services are completed, vendor will return wires to KB Docks Bangor or Keyport Pier and provide labor for climbing services to re-install both wires using a portable powered line spooler to install lines under tension. Government will provide crane operator and crane crew.
CHECK POINT
Government representative will inspect and approve crane wire installation before service is accepted as completed.
WORK SPEC 10 / Option Years – Beginning in 2027
YTT-10
5. Main Crane – 1800’ 1 and 1/8” 6x36 IWRC Main Wire and 200’ ¾” 6x36 IWRC Auxiliary Wire
6. Knuckle Crane – 150’ ¾” 6x36 IWRC Wire During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier, as designated by the Government Technical Representative, a portable powered line spooler and offload the vessel’s wires. Vendor will provide labor for climbing services to remove wire.
Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires.
Pressure lube of wire will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a verbal condition notification to the Governments representative. Once services are completed, vendor will return wires to KB Docks Bangor or Keyport Pier and provide labor for climbing services to re-install both wires using a portable powered line spooler to install lines under tension. Government will provide crane operator and crane crew.
CHECK POINT
Government representative will inspect and approve crane wire installation before service is accepted as completed.
WORK SPEC 11 / Option Years – Beginning in 2025
YTT-11
5. Main Crane – 1800’ 1 and 1/8” 6x36 IWRC Main Wire and 200’ ¾” 6x36 IWRC Auxiliary Wire
6. Knuckle Crane – 150’ ¾” 6x36 IWRC Wire During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier, as designated by the Government Technical Representative, a portable powered line spooler and offload the vessel’s wires. Vendor will provide labor for climbing services to remove wire.
Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires.
Pressure lube of wire will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a verbal condition notification to the Governments representative. Once services are completed, vendor will return wires to KB Docks Bangor or Keyport Pier and provide labor for climbing services to re-install both wires using a portable powered line spooler to install lines under tension. Government will provide crane operator and crane crew.
CHECK POINT
accepted as completed.
WORK SPEC 12 / Option Years – Beginning in 2025 IX-536 Barge:
3. Deck Crane – 400’ 1x1/8” 6x36 IWRC Main Wire and 250’ x ¾” 6x36 IWRC Auxiliary Wire
During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier, as designated by the Government Technical Representative, a portable powered line spooler and offload the vessel’s wires. Vendor will provide labor for climbing services to remove wire.
Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires.
Pressure lube of wire will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a verbal condition notification to the Governments representative. Once services are completed, vendor will return wires to KB Docks Bangor or Keyport Pier and provide labor for climbing services to re-install both wires using a portable powered line spooler to install lines under tension. Government will provide crane operator and crane crew.
CHECK POINT
accepted as completed.
Section SF 1449 - CONTINUATION SHEET
ATTACHMENTS VIA INTERNET
1. NAVSEA NUWC Division Keyport, OPSEC Guide for Defense Contractor, Rev May 2016
2. Safety - Requirements for Contractors & Subcontractors,
3. Contractor’s Guide to Environmental Compliance (Items 1-3 are incorporated by reference. Documents can be downloaded from http://www.navsea.navy.mil/Home/Warfare-Centers/NUWC-Keyport/Resources )
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Lot YTT-10 Discovery Bay
FFP
Service for YTT-10 Discovery Bay in accordance with (IAW) Work Spec 01, located in the statement of work (SOW). Pricing is to include all parts, material, labor, and travel costs.
Period of performance (POP): 7 months from date of award.
FOB: Destination
PSC CD: H961
NET AMT
0002 1 Lot YTT-11 Discovery Bay
FFP
Service for YTT-11 Discovery Bay in accordance with (IAW) Work Spec 02, located in the statement of work (SOW). Pricing is to include all parts, material, labor, and travel costs.
Period of performance (POP): 7 months from date of award.
0003 1 Lot IX-536 Barge
FFP
Service for IX-536 Barge in accordance with (IAW) Work Spec 03, located in the statement of work (SOW). Pricing is to include all parts, material, labor, and travel costs.
Period of performance (POP): 7 months from date of award.
1001 1 Lot OPTION YTT-10 Discovery Bay
FFP
Service for YTT-10 Discovery Bay in accordance with (IAW) Work Spec 04, located in the statement of work (SOW). Pricing is to include all parts, material, labor, and travel costs.
This is an Option Item only and in no way are purchased or guaranteed under the resulting contract. Work cannot be started or performed under the Option Items without Option Exercise by the Contracting Officer in accordance with FAR Clause 52.217-7 VAR 1.
1002 1 Lot OPTION YTT-11 Discovery Bay
FFP
Service for YTT-11 Discovery Bay in accordance with (IAW) Work Spec 05, located in the statement of work (SOW). Pricing is to include all parts, material, labor, and travel costs.
This is an Option Item only and in no way are purchased or guaranteed under the resulting contract. Work cannot be started or performed under the Option Items without Option Exercise by the Contracting Officer in accordance with FAR Clause 52.217-7 VAR 1.
1003 1 Lot OPTION IX-536 Barge
FFP
Service for IX-536 Barge in accordance with (IAW) Work Spec 06, located in the statement of work (SOW). Pricing is to include all parts, material, labor, and travel costs.
This is an Option Item only and in no way are purchased or guaranteed under the resulting contract. Work cannot be started or performed under the Option Items without Option Exercise by the Contracting Officer in accordance with FAR Clause 52.217-7 VAR 1.
2001 1 Lot OPTION YTT-10 Discovery Bay
FFP
Service for YTT-10 Discovery Bay in accordance with (IAW) Work Spec 07, located in the statement of work (SOW). Pricing is to include all parts, material, labor, and travel costs.
This is an Option Item only and in no way are purchased or guaranteed under the resulting contract. Work cannot be started or performed under the Option Items without Option Exercise by the Contracting Officer in accordance with FAR Clause 52.217-7 VAR 1.
2002 1 Lot OPTION YTT-11 Discovery Bay
FFP
Service for YTT-11 Discovery Bay in accordance with (IAW) Work Spec 08, located in the statement of work (SOW). Pricing is to include all parts, material, labor, and travel costs.
This is an Option Item only and in no way are purchased or guaranteed under the resulting contract. Work cannot be started or performed under the Option Items without Option Exercise by the Contracting Officer in accordance with FAR Clause 52.217-7 VAR 1.
2003 1 Lot OPTION IX-536 Barge
FFP
Service for IX-536 Barge in accordance with (IAW) Work Spec 09, located in the statement of work (SOW). Pricing is to include all parts, material, labor, and travel costs.
This is an Option Item only and in no way are purchased or guaranteed under the resulting contract. Work cannot be started or performed under the Option Items without Option Exercise by the Contracting Officer in accordance with FAR Clause 52.217-7 VAR 1.
3001 1 Lot OPTION YTT-10 Discovery Bay
FFP
Service for YTT-10 Discovery Bay in accordance with (IAW) Work Spec 10, located in the statement of work (SOW). Pricing is to include all parts, material, labor, and travel costs.
This is an Option Item only and in no way are purchased or guaranteed under the resulting contract. Work cannot be started or performed under the Option Items without Option Exercise by the Contracting Officer in accordance with FAR Clause 52.217-7 VAR 1.
3002 1 Lot OPTION YTT-11 Discovery Bay
FFP
Service for YTT-11 Discovery Bay in accordance with (IAW) Work Spec 11, located in the statement of work (SOW). Pricing is to include all parts, material, labor, and travel costs.
This is an Option Item only and in no way are purchased or guaranteed under the resulting contract. Work cannot be started or performed under the Option Items without Option Exercise by the Contracting Officer in accordance with FAR Clause 52.217-7 VAR 1.
3003 1 Lot OPTION IX-536 Barge
FFP
Service for IX-536 Barge in accordance with (IAW) Work Spec 12, located in the statement of work (SOW). Pricing is to include all parts, material, labor, and travel costs.
This is an Option Item only and in no way are purchased or guaranteed under the resulting contract. Work cannot be started or performed under the Option Items without Option Exercise by the Contracting Officer in accordance with FAR Clause 52.217-7 VAR 1.
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 Destination Government Destination Government 0002 Destination Government Destination Government 0003 Destination Government Destination Government 1001 Destination Government Destination Government 1002 Destination Government Destination Government 1003 Destination Government Destination Government 2001 Destination Government Destination Government 2002 Destination Government Destination Government 2003 Destination Government Destination Government 3001 Destination Government Destination Government 3002 Destination Government Destination Government 3003 Destination Government Destination Government
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 7 mths. ADC 1 NAVAL UNDERSEA WARFARE CENTER
RECEIVING OFFICER
ATTN: DIVISION KEYPORT SUPPLY
OFFICER
BLDG 893
610 DOWELL STREET
KEYPORT WA 98345-7610
360 396-2760
N00253
0002 7 mths. ADC 1 (SAME AS PREVIOUS LOCATION)
0003 7 mths. ADC 1 (SAME AS PREVIOUS LOCATION)
1001 7 mths. AOE 1 (SAME AS PREVIOUS LOCATION)
1002 7 mths. AOE 1 (SAME AS PREVIOUS LOCATION)
1003 7 mths. AOE 1 (SAME AS PREVIOUS LOCATION)
2001 7 mths. AOE 1 (SAME AS PREVIOUS LOCATION)
2002 7 mths. AOE 1 (SAME AS PREVIOUS LOCATION)
2003 7 mths. AOE 1 (SAME AS PREVIOUS LOCATION)
3001 7 mths. AOE 1 (SAME AS PREVIOUS LOCATION)
3002 7 mths. AOE 1 (SAME AS PREVIOUS LOCATION)
3003 7 mths. AOE 1 (SAME AS PREVIOUS LOCATION)
CLAUSES INCORPORATED BY REFERENCE
52.204-7 System for Award Management OCT 2018 52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier
Subcontract Awards
JUN 2020
52.204-13 System for Award Management Maintenance OCT 2018 52.204-16 Commercial and Government Entity Code Reporting AUG 2020 52.204-18 Commercial and Government Entity Code Maintenance AUG 2020 52.204-21 Basic Safeguarding of Covered Contractor Information
Systems
NOV 2021
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment
NOV 2021
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.211-15 Defense Priority And Allocation Requirements APR 2008 52.212-1 Instructions to Offerors--Commercial Products and
Commercial Services
SEP 2023
52.212-3 Alt I Offeror Representations and Certifications--Commercial Products and Commercial Services (NOV 2023) Alternate I
OCT 2014
52.212-4 Contract Terms and Conditions--Commercial Products and Commercial Services
NOV 2023
52.217-5 Evaluation Of Options JUL 1990 52.219-6 Notice Of Total Small Business Set-Aside NOV 2020 52.219-28 Post-Award Small Business Program Rerepresentation SEP 2023 52.222-3 Convict Labor JUN 2003 52.223-18 Encouraging Contractor Policies To Ban Text Messaging
While Driving
JUN 2020
52.232-33 Payment by Electronic Funds Transfer--System for Award Management
OCT 2018
52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.237-2 Protection Of Government Buildings, Equipment, And
Vegetation
APR 1984
52.242-15 Stop-Work Order AUG 1989 52.242-17 Government Delay Of Work APR 1984 52.246-4 Inspection Of Services--Fixed Price AUG 1996 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7002 Requirement to Inform Employees of Whistleblower Rights DEC 2022 252.203-7005 Representation Relating to Compensation of Former DoD
Officials
SEP 2022
252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7004 Antiterrorism Awareness Training for Contractors JAN 2023 252.204-7008 Compliance With Safeguarding Covered Defense Information
Controls
OCT 2016
252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support
JAN 2023
252.204-7016 Covered Defense Telecommunications Equipment or Services -- Representation
DEC 2019
252.204-7017 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services -- Representation
MAY 2021
252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services
JAN 2023
252.204-7019 Notice of NIST SP 800-171 DoD Assessment Requirements NOV 2023 252.204-7020 NIST SP 800-171 DoD Assessment Requirements NOV 2023 252.204-7024 Notice on the Use of the Supplier Performance Risk System MAR 2023 252.211-7003 Item Unique Identification and Valuation JAN 2023 252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or
Hazardous Materials
SEP 2014
252.223-7008 Prohibition of Hexavalent Chromium JAN 2023 252.225-7001 Buy American And Balance Of Payments Program--Basic JAN 2023 252.225-7048 Export-Controlled Items JUN 2013 252.225-7055 Representation Regarding Business Operations with the
Maduro Regime
MAY 2022
252.225-7056 Prohibition Regarding Business Operations with the Maduro Regime
JAN 2023
252.225-7972 (Dev) Prohibition on the Procurement of Foreign-Made Unmanned Aircraft Systems (DEVIATION 2020-O0015)
MAY 2020
252.225-7973 (Dev) Prohibition on the Procurement of Foreign-Made Unmanned Aircraft Systems - Representation (DEVIATION 2020- O0015)
MAY 2020
252.232-7003 Electronic Submission of Payment Requests and Receiving Reports
DEC 2018
252.232-7010 Levies on Contract Payments DEC 2006 252.237-7010 Prohibition on Interrogation of Detainees by Contractor
Personnel
JAN 2023
252.244-7000 Subcontracts for Commercial Products or Commercial Services
NOV 2023
252.247-7023 Transportation of Supplies by Sea JAN 2023
CLAUSES INCORPORATED BY FULL TEXT
52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO
SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)
The Offeror shall not complete the representation at paragraph (d)(1) of this provision if the Offeror has represented that it "does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument" in paragraph (c)(1) in the provision at 52.204-26, Covered Telecommunications Equipment or Services-- Representation, or in paragraph (v)(2)(i) of the provision at 52.212-3, Offeror Representations and Certifications- Commercial Products and Commercial Services. The Offeror shall not complete the representation in paragraph (d)(2) of this provision if the Offeror has represented that it "does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services" in paragraph (c)(2) of the provision at 52.204-26, or in paragraph (v)(2)(ii) of the provision at 52.212-3.
(a) Definitions. As used in this provision-
Backhaul, covered telecommunications equipment or services, critical technology, interconnection arrangements, reasonable inquiry, roaming, and substantial or essential component have the meanings provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.
(b) Prohibition.
(1) Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.
115-232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. Nothing in the prohibition shall be construed to--
(i) Prohibit the head of an executive agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or
(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.
(2) Section 889(a)(1)(B) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.
115-232) prohibits the head of an executive agency on or after August 13, 2020, from entering into a contract or extending or renewing a contract with an entity that uses any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. This prohibition applies to the use of covered telecommunications equipment or services, regardless of whether that use is in performance of work under a Federal contract. Nothing in the prohibition shall be construed to--
(i) Prohibit the head of an executive agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or
(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.
(c) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for "covered telecommunications equipment or services."
(d) Representations. The Offeror represents that--
(1) It [ ___ ] will, [ ___ ] will not provide covered telecommunications equipment or services to the Government in the performance of any contract, subcontract or other contractual instrument resulting from this solicitation. The Offeror shall provide the additional disclosure information required at paragraph (e)(1) of this section if the Offeror responds "will" in paragraph (d)(1) of this section; and
(2) After conducting a reasonable inquiry, for purposes of this representation, the Offeror represents that--
It [ ___ ] does, [ ___ ] does not use covered telecommunications equipment or services, or use any equipment, system, or service that uses covered telecommunications equipment or services. The Offeror shall provide the additional disclosure information required at paragraph (e)(2) of this section if the Offeror responds "does" in paragraph (d)(2) of this section.
(e) Disclosures.
(1) Disclosure for the representation in paragraph (d)(1) of this provision. If the Offeror has responded "will" in the representation in paragraph (d)(1) of this provision, the Offeror shall provide the following information as part of the offer:
(i) For covered equipment--
(A) The entity that produced the covered telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the original equipment manufacturer (OEM) or a distributor, if known);
(B) A description of all covered telecommunications equipment offered (include brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); and
(C) Explanation of the proposed use of covered telecommunications equipment and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(1) of this provision.
(ii) For covered services--
(A) If the service is related to item maintenance: A description of all covered telecommunications services offered (include on the item being maintained: Brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); or
(B) If not associated with maintenance, the Product Service Code (PSC) of the service being provided; and explanation of the proposed use of covered telecommunications services and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(1) of this provision.
(2) Disclosure for the representation in paragraph (d)(2) of this provision. If the Offeror has responded "does" in the representation in paragraph (d)(2) of this provision, the Offeror shall provide the following information as part of the offer:
(i) For covered equipment--
(A) The entity that produced the covered telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the OEM or a distributor, if known);
(B) A description of all covered telecommunications equipment offered (include brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); and
(C) Explanation of the proposed use of covered telecommunications equipment and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(2) of this provision.
(ii) For covered services--
(A) If the service is related to item maintenance: A description of all covered telecommunications services offered (include on the item being maintained: Brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); or
(B) If not associated with maintenance, the PSC of the service being provided; and explanation of the proposed use of covered telecommunications services and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(2) of this provision.
(End of provision)
52.211-14 NOTICE OF PRIORITY RATING FOR NATIONAL DEFENSE, EMERGENCY PREPAREDNESS, AND ENERGY PROGRAM USE (APR 2008)
Any contract awarded as a result of this solicitation will be DX rated order; X DO rated order certified for national defense, emergency preparedness, and energy program use under the Defense Priorities and Allocations System (DPAS) (15 CFR 700), and the Contractor will be required to follow all of the requirements of this regulation.
52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR
EXECUTIVE ORDERS—COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (DEVIATION 2024-
O0002) (JAN 2024)
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:
(1) 52.203–19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L.
113–235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).
(2) 52.204–23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (NOV 2021) (Section 1634 of Pub. L. 115–91).
(3) 52.204–25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (NOV 2021) (Section 889(a)(1)(A) of Pub. L. 115–232).
(4) 52.209–10, Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015).
(5) 52.232–40, Providing Accelerated Payments to Small Business Subcontractors (MAR 2023) (31 U.S.C. 3903 and 10 U.S.C. 3801).
(6) 52.233–3, Protest After Award (AUG 1996) (31 U.S.C. 3553).
(7) 52.233–4, Applicable Law for Breach of Contract Claim (OCT 2004) (Public Laws 108–77 and 108–78 (19 U.S.C. 3805 note)).
(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services: [Contracting Officer check as appropriate.]
___ (1) 52.203–6, Restrictions on Subcontractor Sales to the Government (JUN 2020), with Alternate I (NOV 2021) (41 U.S.C. 4704 and 10 U.S.C. 4655)
___ (2) 52.203–13, Contractor Code of Business Ethics and Conduct (NOV 2021) (41 U.S.C. 3509).
___ (3) 52.203–15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (JUN 2010) (Section 1553 of Pub. L. 111–5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)
___ (4) 52.203–17, Contractor Employee Whistleblower Rights (NOV 2023) (41 U.S.C. 4712); this clause does not apply to contracts of DoD, NASA, the Coast Guard, or applicable elements of the intelligence community—see FAR 3.900(a).
X (5) 52.204–10, Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020) (Pub. L.
109–282) (31 U.S.C. 6101 note).
___ (6) [Reserved]
___ (7) 52.204–14, Service Contract Reporting Requirements (OCT 2016) (Pub. L. 111–117, section 743 of Div.
C).
___ (8) 52.204–15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts (OCT 2016) (Pub.
L. 111–117, section 743 of Div. C).
X (9) 52.204–27, Prohibition on a ByteDance Covered Application (JUN 2023) (Section 102 of Division R of Pub.
L. 117–328).
X (10) 52.209–6, Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (NOV 2021) (31 U.S.C. 6101 note).
___ (11) 52.209–9, Updates of Publicly Available Information Regarding Responsibility Matters (OCT 2018) (41 U.S.C. 2313).
___ (12) [Reserved]
___ (13) 52.219–3, Notice of HUBZone Set-Aside or Sole-Source Award (OCT 2022) (15 U.S.C. 657a).
___ (14) 52.219–4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (OCT 2022) (if the offeror elects to waive the preference, it shall so indicate in its offer) (15 U.S.C. 657a).
___ (15) [Reserved]
X (16)(i) 52.219–6, Notice of Total Small Business Set-Aside (NOV 2020) (15 U.S.C. 644).
___ (ii) Alternate I (MAR 2020) of 52.219–6.
___ (17)(i) 52.219–7, Notice of Partial Small Business Set-Aside (NOV 2020) (15 U.S.C. 644).
___ (ii) Alternate I (MAR 2020) of 52.219–7.
___ (18) 52.219–8, Utilization of Small Business Concerns (DEVIATION 2024-O0002) (JAN 2024) (15 U.S.C.
637(d)(2) and (3)).
___ (19)(i) 52.219–9, Small Business Subcontracting Plan (SEP 2023) (15 U.S.C. 637(d)(4)).
___ (ii) Alternate I (NOV 2016) of 52.219–9.
___ (iii) Alternate II (NOV 2016) of 52.219–9.
___ (iv) Alternate III (JUN 2020) of 52.219–9.
___ (v) Alternate IV (SEP 2023) of 52.219–9.
___ (20)(i) 52.219–13, Notice of Set-Aside of Orders (MAR 2020) (15 U.S.C. 644(r)).
___ (ii) Alternate I (MAR 2020) of 52.219–13.
___ (21) 52.219–14, Limitations on Subcontracting (OCT 2022) (15 U.S.C. 657s).
___ (22) 52.219–16, Liquidated Damages—Subcontracting Plan (SEP 2021) (15 U.S.C. 637(d)(4)(F)(i)).
___ (23) 52.219–27, Notice of Set-Aside for, or Sole-Source Award to, Service-Disabled Veteran-Owned Small Business (SDVOSB) Concerns Eligible Under the Service-Disabled Veteran-Owned Small Business Program
(DEVIATION 2024-O0002) (JAN 2024) (15 U.S.C.
657f).
X (24)(i) 52.219–28, Post-Award Small Business Program Rerepresentation (DEVIATION 2024-O0002) (JAN 2024) (15 U.S.C. 632(a)(2)).
___ (ii) Alternate I (MAR 2020) of 52.219–28.
___ (25) 52.219–29, Notice of Set-Aside for, or Sole-Source Award to, Economically Disadvantaged Women- Owned Small Business Concerns (OCT 2022) (15 U.S.C. 637(m)).
___ (26) 52.219–30, Notice of Set-Aside for, or Sole-Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program (OCT 2022) (15 U.S.C. 637(m)).
___ (27) 52.219–32, Orders Issued Directly Under Small Business Reserves (MAR 2020) (15 U.S.C. 644(r)).
___ (28) 52.219–33, Nonmanufacturer Rule (SEP 2021) (15 U.S.C. 657s).
X (29) 52.222–3, Convict Labor (JUN 2003) (E.O. 11755).
___ (30) 52.222–19, Child Labor—Cooperation with Authorities and Remedies (DEC 2022) (E.O. 13126).
X (31) 52.222–21, Prohibition of Segregated Facilities (APR 2015).
X (32)(i) 52.222–26, Equal Opportunity (SEP 2016) (E.O. 11246).
___ (ii) Alternate I (FEB 1999) of 52.222–26.
___ (33)(i) 52.222–35, Equal Opportunity for Veterans (JUN 2020) (38 U.S.C. 4212).
___ (ii) Alternate I (JUL 2014) of 52.222–35.
X (34)(i) 52.222–36, Equal Opportunity for Workers with Disabilities (JUN 2020) (29 U.S.C. 793).
___ (ii) Alternate I (JUL 2014) of 52.222–36.
___ (35) 52.222–37, Employment Reports on Veterans (JUN 2020) (38 U.S.C. 4212).
___ (36) 52.222–40, Notification of Employee Rights Under the National Labor Relations Act (DEC 2010) (E.O.
13496).
X (37)(i) 52.222–50, Combating Trafficking in Persons (NOV 2021) (22 U.S.C. chapter 78 and E.O. 13627).
___ (ii) Alternate I (MAR 2015) of 52.222–50 (22 U.S.C. chapter 78 and E.O. 13627).
___ (38) 52.222–54, Employment Eligibility Verification (MAY 2022). (E. O. 12989). (Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial products or commercial services as prescribed in FAR 22.1803.)
___ (39)(i) 52.223–9, Estimate of Percentage of Recovered Material Content for EPA-Designated Items (MAY 2008) (42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
___ (ii) Alternate I (MAY 2008) of 52.223–9 (42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
___ (40) 52.223–11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (JUN 2016) (E.O. 13693).
___ (41) 52.223–12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners
(JUN 2016) (E.O. 13693).
___ (42)(i) 52.223–13, Acquisition of EPEAT®-Registered Imaging Equipment (JUN 2014) (E.O.s 13423 and 13514).
___ (ii) Alternate I (OCT 2015) of 52.223–13.
___ (43)(i) 52.223–14, Acquisition of EPEAT®-Registered Televisions (JUN 2014) (E.O.s 13423 and 13514).
___ (ii) Alternate I (JUN 2014) of 52.223–14.
___ (44) 52.223–15, Energy Efficiency in Energy-Consuming Products (MAY 2020) (42 U.S.C. 8259b).
___ (45)(i) 52.223–16, Acquisition of EPEAT®-Registered Personal Computer Products (OCT 2015) (E.O.s 13423 and 13514).
___ (ii) Alternate I (JUN 2014) of 52.223–16.
X (46) 52.223–18, Encouraging Contractor Policies to Ban Text Messaging While Driving (JUN 2020) (E.O.
13513).
X (47) 52.223–20, Aerosols (JUN 2016) (E.O. 13693).
___ (48) 52.223–21, Foams (JUN 2016) (E.O. 13693).
X (49)(i) 52.224–3, Privacy Training (JAN 2017) (5 U.S.C. 552a).
___ (ii) Alternate I (JAN 2017) of 52.224–3.
___ (50)(i) 52.225–1, Buy American—Supplies (OCT 2022)) (41 U.S.C. chapter 83).
___ (ii) Alternate I (OCT 2022) of 52.225–1.
___ (51)(i) 52.225–3, Buy American—Free Trade Agreements—Israeli Trade Act (DEC 2022) (19 U.S.C. 3301 note, 19 U.S.C. 2112 note, 19 U.S.C. 3805 note, 19 U.S.C. 4001 note, 19 U.S.C. chapter 29 (sections 4501–4732), Public Law 103–182, 108–77, 108–78, 108–286, 108–302, 109–53, 109–169, 109–283, 110–138, 112–41, 112–42, and 112–43.
___ (ii) Alternate I [Reserved].
___ (iii) Alternate II (DEC 2022) of 52.225–3.
___ (iv) Alternate III (JAN 2021) of 52.225–3.
___ (v) Alternate IV (OCT 2022) of 52.225–3.
___ (52) 52.225–5, Trade Agreements (DEC 2022) (19 U.S.C. 2501, et seq., 19 U.S.C. 3301 note).
___ (53) 52.225–13, Restrictions on Certain Foreign Purchases (FEB 2021) (E.O.'s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).
___ (54) 52.225–26, Contractors Performing Private Security Functions Outside the United States (OCT 2016) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. Subtitle A, Part V, Subpart G Note).
___ (55) 52.226–4, Notice of Disaster or Emergency Area Set-Aside (NOV 2007) (42 U.S.C. 5150).
___ (56) 52.226–5, Restrictions on Subcontracting Outside Disaster or Emergency Area (NOV 2007) (42 U.S.C.
5150).
___ (57) 52.229–12, Tax on Certain Foreign Procurements (FEB 2021).
___ (58) 52.232–29, Terms for Financing of Purchases of Commercial…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .