This solicitation seeks wire rope services for three vessels and one barge. The Naval Undersea Warfare Center Division in Keyport, Washington requires wire rope lubrication, inspection, removal and installation services for cranes on the YTT-10 Discovery Bay, YTT-11 Discovery Bay, and the IX-536 barge. The work specifications cover annual services from 2024 through 2027 and include climbing, transportation, on-site and off-site inspections, lubrication using Dyna Guard Blue Grease, condition assessments, and reinstallation of wires. Quotes are due by the closing date listed in the solicitation. The proposed contract is 100% set aside for small businesses and has a North American Industry Classification System code of 333923 with a size standard of 1,250 employees or less.

View the file

Other files for this federal contract opportunity

Other files attached to Wire Rope, newest first.
File Type Posted
Amendment 0001.pdf PDF
Security Requirments.docx DOCX document
N0025324Q0024.pdf PDF
Kitsap County Wage Determination.txt TXT text file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to answ er vendor questions found on page tw o (2).

1. CONTRACT ID CODE PAGE OF PAGES

J 1 8

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 18-Mar-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N0025324Q0024

X 9B. DATED (SEE ITEM 11)

05-Mar-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

18-Mar-2024

CODE

NAVAL UNDERSEA WARFARE CENTER

ATTN: NAOMI MCKENZIE

NAOMI.MCKENZIE@NAVY.MIL

610 DOWELL STREET, BLDG 206

KEYPORT WA 98345

N00253 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N0025324Q0024

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been modified:

STATEMENT OF WORK

NAVAL UNDERSEA WARFARE CENTER KEYPORT

RANGE CRAFT CRANE WIRE LUBRICATION/INSPECTION

WORK SPECIFICATIONS

WORK SPEC 01

YTT-10 Discovery Bay

1. Main Crane – 1800’ 1 and 1/8” 6x36 IWRC Main Wire and 200’ ¾” 6x36 IWRC Auxiliary Wire

2. Knuckle Crane – 150’ ¾” 6x36 IWRC Wire Period of Performance: to be scheduled for the 2024 Calendar Year, at a time when the Government POC will contact the vendor to schedule the site visit. Multiple Option years requested as this will be an ongoing preventative maintenance task.

During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier, as designated by the Government Technical Representative, a portable powered line spooler and offload the vessel’s wires. Vendor will provide labor for climbing services to remove wire.

Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires.

Pressure lube of wire will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a verbal condition notification to the Governments representative. Once services are completed, vendor will return wires to KB Docks Bangor or Keyport Pier and provide labor for climbing services to re-install both wires using a portable powered line spooler to install lines under tension. Government will provide crane operator and crane crew.

REQUIREMENT Main Crane Auxiliary and Knuckle Crane wires will be removed and placed onto separate pallets, provided by the vendor. Once services completed wires will be returned on separate wooden spools, provided by the vendor, for installation on the YTT-10’s cranes. Main Crane Main wire will be removed onto a wooden spool and returned on a spool, provided by the vendor. The spools shall be adequate in strength to remove/install the wire under tension.

Labor The vendor is authorized 8 hours to remove wires, 7 business days to service wires per specifications above, and 8 hours to re-install wires.

CHECK POINT

Government representative will inspect and approve crane wire installation before service is accepted as completed.

WORK SPEC 02

YTT-11 Discovery Bay

1. Main Crane – 1800’ 1 and 1/8” 6x36 IWRC Main Wire and 200’ ¾” 6x36 IWRC Auxiliary Wire

2. Knuckle Crane – 150’ ¾” 6x36 IWRC Wire Period of Performance: to be scheduled for the 2024 Calendar Year, at a time when the Government POC will contact the vendor to schedule the site visit. Multiple Option years requested as this will be an ongoing preventative maintenance task.

During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier, as designated by the Government Technical Representative, a portable powered line spooler and offload the vessel’s wires. Vendor will provide labor for climbing services to remove wire.

Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires.

Pressure lube of wire will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a verbal condition notification to the Governments representative. Once services are completed, vendor will return wires to KB Docks Bangor or Keyport Pier and provide labor for climbing services to re-install both wires using a portable powered line spooler to install lines under tension. Government will provide crane operator and crane crew.

REQUIREMENT Main Crane Auxiliary and Knuckle Crane wires will be removed and placed onto separate pallets, provided by the vendor. Once services completed, wires will be returned on separate wooden spools, provided by the vendor, for installation on the YTT-11’s cranes. Main Crane Main wire will be removed onto a wooden spool and returned on a spool, provided by the vendor. The spools shall be adequate in strength to remove/install the wire under tension.

Labor The vendor is authorized 8 hours to remove wires, 7 business days to service wires per specifications above, and 8 hours to re-install wires.

CHECK POINT

Government representative will inspect and approve crane wire installation before service is accepted as completed.

WORK SPEC 03

IX-536 Barge:

1. Deck Crane – 400’ 1x1/8” 6x36 IWRC Main Wire and 250’ x ¾” 6x36 IWRC Auxiliary Wire

Period of Performance: to be scheduled for the 2024 Calendar Year, at a time when the Government POC will contact the vendor to schedule the site visit. Multiple Option years requested as this will be an ongoing preventative maintenance task.

During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier, as designated by the Government Technical Representative, a portable powered line spooler and offload the vessel’s wires. Vendor will provide labor for climbing services to remove wire.

Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires.

Pressure lube of wire will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a verbal condition notification to the Governments representative. Once services are completed, vendor will return wires to KB Docks Bangor or Keyport Pier and provide labor for climbing services to re-install both wires using a portable powered line spooler to install lines under tension. Government will provide crane operator and crane crew.

REQUIREMENT IX-536 Main wire will be taken off and placed onto a spool, provided by the vendor. Auxiliary wire will be placed onto a pallet and after service returned on a spool provided by the vendor. The spools shall be adequate in strength to remove/install the wire under tension.

Labor The vendor is authorized 8 hours to remove wires, 7 business days to service wires per specifications above, and 8 hours to re-install wires.

CHECK POINT

A Government representative will inspect and approve crane wire installation before service is accepted as completed.

WORK SPEC 04 / Option Years – Beginning in 2025

YTT-10

1. Main Crane – 1800’ 1 and 1/8” 6x36 IWRC Main Wire and 200’ ¾” 6x36 IWRC Auxiliary Wire

2. Knuckle Crane – 150’ ¾” 6x36 IWRC Wire During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier, as designated by the Government Technical Representative, a portable powered line spooler and offload the vessel’s wires. Vendor will provide labor for climbing services to remove wire.

Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires.

Pressure lube of wire will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a verbal condition notification to the Governments representative. Once services are completed, vendor will return wires to KB Docks Bangor or Keyport Pier and provide labor for climbing services to re-install both wires using a portable powered line spooler to install lines under tension. Government will provide crane operator and crane crew. Vendor to provide climbing services during offload and reload of wires.

CHECK POINT

Government representative will inspect and approve crane wire installation before service is accepted as completed.

WORK SPEC 05 / Option Years – Beginning in 2025

YTT-11

1. Main Crane – 1800’ 1 and 1/8” 6x36 IWRC Main Wire and 200’ ¾” 6x36 IWRC Auxiliary Wire

2. Knuckle Crane – 150’ ¾” 6x36 IWRC Wire During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier, as designated by the Government Technical Representative, a portable powered line spooler and offload the vessel’s wires. Vendor will provide labor for climbing services to remove wire.

Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires.

Pressure lube of wire will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a verbal condition notification to the Governments representative. Once services are completed, vendor will return wires to KB Docks Bangor or

Keyport Pier and provide labor for climbing services to re-install both wires using a portable crane crew. Vendor to provide climbing services during offload and reload of wires.

CHECK POINT

Government representative will inspect and approve crane wire installation before service is accepted as completed.

WORK SPEC 06/ Option Years – Beginning in 2025 IX-536 Barge:

1. Deck Crane – 400’ 1x1/8” 6x36 IWRC Main Wire and 250’ x ¾” 6x36 IWRC Auxiliary Wire

During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier, as designated by the Government Technical Representative, a portable powered line spooler and offload the vessel’s wires. Vendor will provide labor for climbing services to remove wire.

Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires.

Pressure lube of wire will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a verbal condition notification to the Governments representative. Once services are completed, vendor will return wires to KB Docks Bangor or Keyport Pier and provide labor for climbing services to re-install both wires using a portable powered line spooler to install lines under tension. Government will provide crane operator and crane crew.

CHECK POINT

Government representative will inspect and approve crane wire installation before service is accepted as completed.

WORK SPEC 07 / Option Years – Beginning in 2026

YTT-10

3. Main Crane – 1800’ 1 and 1/8” 6x36 IWRC Main Wire and 200’ ¾” 6x36 IWRC Auxiliary Wire

4. Knuckle Crane – 150’ ¾” 6x36 IWRC Wire During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier, as designated by the Government Technical Representative, a portable powered line spooler and offload the vessel’s wires. Vendor will provide labor for climbing services to remove wire.

Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires.

Pressure lube of wire will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a verbal condition notification to the Governments representative. Once services are completed, vendor will return wires to KB Docks Bangor or Keyport Pier and provide labor for climbing services to re-install both wires using a portable powered line spooler to install lines under tension. Government will provide crane operator and crane crew.

CHECK POINT

Government representative will inspect and approve crane wire installation before service is accepted as completed.

WORK SPEC 08/ Option Years – Beginning in 2026

YTT-11

3. Main Crane – 1800’ 1 and 1/8” 6x36 IWRC Main Wire and 200’ ¾” 6x36 IWRC Auxiliary Wire

4. Knuckle Crane – 150’ ¾” 6x36 IWRC Wire During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier a portable powered line spooler. Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires. The pressure lube will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a core condition report for each wire. Once service are completed vendor will return wires to KB Docks Bangor or Keyport Pier for Government personnel to install.

CHECK POINT

Government representative will inspect and approve crane wire installation before service is accepted as completed.

WORK SPEC 09 / Option Years – Beginning in 2026 IX-536 Barge:

2. Deck Crane – 400’ 1x1/8” 6x36 IWRC Main Wire and 250’ x ¾” 6x36 IWRC Auxiliary Wire

During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier, as designated by the Government Technical Representative, a portable powered line spooler and offload the vessel’s wires. Vendor will provide labor for climbing services to remove wire.

Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires.

Pressure lube of wire will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a verbal condition notification to the Governments representative. Once services are completed, vendor will return wires to KB Docks Bangor or Keyport Pier and provide labor for climbing services to re-install both wires using a portable powered line spooler to install lines under tension. Government will provide crane operator and crane crew.

CHECK POINT

Government representative will inspect and approve crane wire installation before service is accepted as completed.

WORK SPEC 10 / Option Years – Beginning in 2027

YTT-10

5. Main Crane – 1800’ 1 and 1/8” 6x36 IWRC Main Wire and 200’ ¾” 6x36 IWRC Auxiliary Wire

6. Knuckle Crane – 150’ ¾” 6x36 IWRC Wire During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier, as designated by the Government Technical Representative, a portable powered line spooler and offload the vessel’s wires. Vendor will provide labor for climbing services to remove wire.

Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires.

Pressure lube of wire will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a verbal condition notification to the Governments representative. Once services are completed, vendor will return wires to KB Docks Bangor or Keyport Pier and provide labor for climbing services to re-install both wires using a portable powered line spooler to install lines under tension. Government will provide crane operator and crane crew.

CHECK POINT

Government representative will inspect and approve crane wire installation before service is accepted as completed.

WORK SPEC 11 / Option Years – Beginning in 2027

YTT-11

5. Main Crane – 1800’ 1 and 1/8” 6x36 IWRC Main Wire and 200’ ¾” 6x36 IWRC Auxiliary Wire

6. Knuckle Crane – 150’ ¾” 6x36 IWRC Wire During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier, as designated by the Government Technical Representative, a portable powered line spooler and offload the vessel’s wires. Vendor will provide labor for climbing services to remove wire.

Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires.

Pressure lube of wire will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a verbal condition notification to the Governments representative. Once services are completed, vendor will return wires to KB Docks Bangor or Keyport Pier and provide labor for climbing services to re-install both wires using a portable powered line spooler to install lines under tension. Government will provide crane operator and crane crew.

CHECK POINT

Government representative will inspect and approve crane wire installation before service is accepted as completed.

WORK SPEC 12 / Option Years – Beginning in 2027 IX-536 Barge:

3. Deck Crane – 400’ 1x1/8” 6x36 IWRC Main Wire and 250’ x ¾” 6x36 IWRC Auxiliary Wire

During specified period of performance vendor will deliver to KB Docks Bangor or Keyport Pier, as designated by the Government Technical Representative, a portable powered line spooler and offload the vessel’s wires. Vendor will provide labor for climbing services to remove wire.

Government will provide crane operator and crane crew. Once wires are offloaded vendor will take wires offsite to scrape exterior of grease, inspect wire rope, and then pressure lube wires.

Pressure lube of wire will be performed using Dyna Guard Blue Grease (No substitutions are authorized). Vendor will provide a verbal condition notification to the Governments representative. Once services are completed, vendor will return wires to KB Docks Bangor or Keyport Pier and provide labor for climbing services to re-install both wires using a portable crane crew.

CHECK POINT

Government representative will inspect and approve crane wire installation before service is accepted as completed.

VENDOR QUESTIONS

Question One (1): Can you please provide additional information on which kind of inspection is required after the old grease has been removed?

Answer: 613-1.10.2.1 External Inspection. The external inspection criteria for general usage running rope is as follows:

a. Reduction of nominal rope diameter due to loss of core support or internal or external corrosion or wear of individual outside wires. The diameter shall be measured in a circumscribing circle in six or more places on the rope. For the correct method of measuring diameter see Figure 613–1–5.

b. Number of broken outside wires and degree of distribution or concentration of broken wires

c. Corroded, pitted, or broken wires at end connections

d. Corroded, cracked, bent, worn, or improperly applied end connections

e. Severe kinking, crushing, or distortion of rope structure

f. Evidence of heat damage from any cause

Question Two (2): Is it imperative to have a security clearance to bid on this opportunity?

If yes, Which security clearance?

Answer: No, a security clearance is not needed. Please see the “Security Requirements” attachment, for further information.

Question Three (3): Can you please confirm the following dates on the SOW pages:

Page 4 of 46 / Work Spec 03 / POP list 2020 Calendar Year Please confirm if this should be 2024.

Page 8 of 46 / Work Spec 11 Option Years - Beginning in 2025 Please confirm if this should be 2027.

Page 9 of 46 / Work Spec 12 Option Years - Beginning in 2025 Please confirm if this should be 2027.

Answer: I confirm that the years in red are correct.

Page 4 of 46 / Work Spec 03 / POP list 2020 Calendar Year Please confirm if this should be 2024. 2024

Page 8 of 46 / Work Spec 11 Option Years ‐ Beginning in 2025 Please confirm if this should be 2027. 2027

Page 9 of 46 / Work Spec 12 Option Years ‐ Beginning in 2025 Please confirm if this should be 2027.” 2027

(End of Summary of Changes)