Solicitation Amendment N0018926QL1330001 SF 30.pdf

PDF 590 KB Posted

Attached to
INDIG Village Demolition
Solicitation number
N0018926QL133
Issued by

About this file

This document is a Standard Form 30 Amendment to Solicitation N0018926QL133, issued by the Naval Supply Fleet Logistics Center Norfolk on 15 June 2026. The amendment extends the response due date from 18 June 2026 to 22 June 2026 and modifies the period of performance from 18 June 2026 to 30 September 2026 to 22 June 2026 to 30 September 2026. The solicitation is administered by NAVSUP Fleet Logistics Center Norfolk (Contracting Officer: Sherell Brown, Norfolk, VA 23511-3392) and addresses questions received during the question and answer period, revises the Performance Work Statement based on clarifications from a site visit, and updates FAR 52.222-42 regarding wage determinations.

The Performance Work Statement requires a contractor to complete demolition, debris removal, and site preparation at Fort Story, Virginia Beach, VA 23459 (INDIG Village). The contractor must demolish 23 wood and steel training buildings and 6 wall sections down to ground level; extract all foundation elements, footings, and anchoring systems; remove and transport all debris off-site to licensed facilities; and execute comprehensive grading of the entire designated area to 2,500 pounds per square foot of barring capacity to prepare for subsequent Phase 2 construction. The contract includes a mandatory site visit on 8 June 2026 at 10:00 AM EST at the Pass and ID Office in Virginia Beach (limited to three representatives per vendor, U.S. Citizens only), and requires contractor personnel to maintain required documentation for military base access at time of award. The wage determination for Heavy Equipment Operators is established at $23.97 under Wage Determination No. 2015-4341 Revision No. 34 (dated 5/14/2026). Two attachments—a Questions and Responses document and a Site Map—were added to the solicitation.

View the file

Other files

File Type Posted
Questions and Responses.pdf PDF
Site Map Attachment.pptx PPTX presentation
Solicitation - N0018926QL133.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Block 14 (Description of Amendment/Modification): The purpose of this Amendment 0001 is to:

1. Address questions received during the questions and answers period.

2. Revise the PWS based on clarifications after site visit.

3. Update FAR 52.222-42.

2. Extend the closing date from 18 June 2026 to 22 June 2026.

All other terms and conditions remain unchanged.

Solicitation/Contract Form Continuation

The following changes have been made:

INFORMATION FROM TO

Response Due Date 18 Jun 2026 22 Jun 2026

N0018926QL1330001

Continuation of Description

Miscellaneous text in this section has been modified to:

Performance Work Statement

1. Background: The existing structures within INDIG Village have surpassed their operational lifespan, requiring a systemic refresh to uphold safety and training standards. To mitigate operational impact and ensure project manageability, the replacement is structured into incremental phases. This phased approach facilitates uninterrupted training delivery, which is fundamental to TEU2's capacity to fulfill mission-essential objectives. Comprehensive site preparation, encompassing the removal of existing infrastructure and necessary terrain grading, must be finalized before commencing construction on the replacement target buildings.

2. Scope: The Contractor shall provide all labor, materials, heavy equipment, and supervision necessary to complete the demolition, debris removal, and comprehensive grading of the designated project area.

Contractor shall:

1. Conduct a joint site walk with government/command representatives to identify the 23 buildings and 6 wall sections designated for demolition.

2. If using a crane, must submit a crane package to EODTEU2 for NAVFAC approval.

3. Systematically demolish twenty-three (23) training buildings, comprising exclusively of wood and steel structures with wood flooring, down to ground level.

4. Demolish and remove six (6) distinct sections of walls currently enclosing sub-compounds within the training site.

5. Extract all foundation elements, footings, and anchoring systems associated with the demolished structures.

6. Load and transport all resulting demolition debris (wood, steel, fasteners, footings, etc.) off the installation.

7. Ensure no debris is left staged on-site that could impede subsequent grading operations.

8. Following complete structural and debris removal, execute comprehensive grading of the designated training entire area. Grading needs to be level to current grade and compaction requirements at 2,500 lbs. per sq. ft. of barring capacity.

9. Level the site to resolve any depressions left by foundational removal and establish proper drainage gradients to prevent water pooling.

10. Prepare and compact the soil sub-base across the entire cleared area to 2,500 lbs. per sq. ft. of barring capacity for the subsequent installation of the new Phase 2 multi-level target complexes.

3. Requirements: The primary requirement of this phase is the complete site clearance and comprehensive preparation of the designated INDIG Village area, which shall serve as a strict prerequisite prior to the construction of the new target facilities. The Contractor is required to systematically demolish twenty-three legacy wood-structured buildings and six enclosing wall sections down to ground level, ensuring the extraction of all associated foundational elements. Following demolition, the Contractor must remove all resulting debris from the installation and dispose of it at licensed off-site facilities in accordance with all applicable environmental regulations. Upon clearance of all debris, the Contractor is required to execute comprehensive grading across the entire designated training area, leveling the site to resolve depressions, establishing proper drainage gradients, and compacting the soil sub-base to 2,500 lbs. per sq. ft. of barring capacity to prepare the footprint for subsequent construction. Throughout this effort, the Contractor must coordinate closely with TEU2 site managers to minimize disruption to adjacent active training zones, employing necessary noise, dust, and traffic mitigation strategies. Final acceptance of the project requires a joint inspection verifying the total removal of the specified structures, the complete absence of debris, and the successful leveling and grading of the entire project area, rendering it fully prepared for the installation of the new multi-level target complexes.

4. Period of Performance: From Date of Award to - 60 Days After Award

5. Place of Performance: Fort Story, Virginia Beach, VA 23459 - INDIG Village

ACCESS TO THE BASE: Contractor Personnel/Vendor shall maintain all required documentation to access base.

Contractors shall be eligible to receive base access at time of award.

ADDENDUM TO 52.237-1 SITE VISIT INSTRUCTIONS

A MANDATORY site visit is scheduled for 08 June 2026 at 10:00 AM (EST). On 08 June 2026 at 10:00 AM, all attending the site visit will meet Mr. Ryan Caldwell at the Pass and ID Office (9031 Atlantic Ave, Virginia Beach VA 23451) with a real ID or passport. There is a three (3) person limit for each interested vendor. Vendors not present for the site visit will not be considered eligible for award. Provide yourself adequate time to arrive to the site visit location on time.

Site visit will normally take no more than one hour.

- Base visitors must be U.S. Citizens

- No additional site visits will be scheduled

All vendors interested in attending the site visit must provide names of attendees in advance by emailing Contracting Officer Sherell Brown at sherell.g.brown.civ@us.navy.mil NO LATER THAN 12:00 PM (EST), 04 June 2026:

Please provide the following for each individual attending:

1. Name

2. Company Name

3. CAGE Code

Clarifications of the Performance Work Statement may be asked at the site visit. All other questions must be submitted in writing by email NO LATER THAN 08:00 AM EST, 09 June 2025. All questions after the site visit will be answered in writing and posted with the solicitation.

Continuation of Deliveries or Performance

The delivery information for the following CLIN(s) / SLIN(s) / ELIN(s) were modified:

INFORMATION FROM TO

Period of Performance 18 Jun 2026 to 30 Sep 2026 22 Jun 2026 to 30 Sep 2026

Contract Clauses

Additional Information/Notes

The following clauses were modified:

52.222-42 Statement of Equivalent Rates for Federal Hires. May 2014 hereby reads as follows:

Statement of Equivalent Rates for Federal Hires (May 2014)

In compliance with the Service Contract Labor Standards statute and the regulations of the Secretary of Labor ( ), this clause identifies 29 CFR Part 4 the classes of service employees expected to be employed under the contract and states the wages and fringe benefits payable to each if they were employed by the contracting agency subject to the provisions of 5 U.S.C.5341 or 5332.

This Statement is for Information Only: It is not a Wage Determination

23440 - Heavy Equipment Operator $23.97

Wage Determination No 2015-4341 Revision No 34 Dated 5/14/2026 is incorporated into this contract.

(End of clause)

List of Contract Documents, Exhibits, or Attachments

The following attachments were added:

Questions and Responses Site Map Attachment

IDCode: J
Page: 1
Pages: 7
AmendNo: 0001
EffDate: 15 Jun 2026
ReqNo: See Continuation Sheet
ProjNo:
IssCode: N00189
AdmCode:
IssuedBy: NAVSUP FLT LOG CTR NORFOLK

ATTENTION CODE 301, 1968 GILBERT STREET SUITE 600

NORFOLK, VA 23511-3392

UNITED STATES

Sherell Brown, Email: sherell.g.brown.civ@us.navy.mil Telephone: 771-229-3524 AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: N0018926QL133
SolDate: 27 May 2026
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: 1
OffrNoEx: Off
NoCopies: 1
ApprData: See Continuation
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: See Schedule
ContNameTitle:
CoNameTitle: Sherell Brown
ContDate:
CODate: 15 Jun 2026