AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The soicitation is being amended to answ er vendor questions and provide requested documents.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 18-Feb-2022
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N0016722Q0057
X 9B. DATED (SEE ITEM 11)
10-Feb-2022
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
18-Feb-2022
CODE
NAVAL SURFACE WARFARE CENTER CARDEROCK
GEORGE DELMORAL
757-513-7194 GEORGE.DELMORAL@NAVY.MIL
904 CORPORATE LANE
CHESAPEAKE VA 23320
N00167 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N0016722Q0057
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 1449 - CONTINUATION SHEET
TABLE OF CONTENTS
The Table of Contents has changed from:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 01 A001 Health and Safety 3 Attachment 02 A001 Health and Safety
DID
Attachment 03 A002 Project Schedule 3 Attachment 04 A002 Project Schedule
DID
Attachment 05 A003 Employee Listing 3 Attachment 06 A003 Employee Listing
DID
Attachment 07 A004 Worker Qualifications
Attachment 08 A004 Worker Qualifications DID
Attachment 09 A005 Certificates of Inspection
Attachment 10 A005 Certificates of Inspection DID
Attachment 11 A006 Field Reports 3 Attachment 12 A006 Field Reports DID 8 Attachment 13 A007 Misc Close Out 3 Attachment 14 A007 Misc Close Out
DID
Attachment 15 DD Form 3150 1 Attachment 16 NAVSEA Form 6220 2 1 Attachment 17 Standard COVID 19
Screening Instructions for Contracts.JAN22 to:
Exhibit/Attachment Table of Contents
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 01 A001 Health and Safety 3 Attachment 02 A001 Health and Safety
DID
Attachment 03 A002 Project Schedule 3 Attachment 04 A002 Project Schedule
DID
Attachment 05 A003 Employee Listing 3 Attachment 06 A003 Employee Listing
DID
Attachment 07 A004 Worker Qualifications
Attachment 08 A004 Worker Qualifications DID
Attachment 09 A005 Certificates of Inspection
Attachment 10 A005 Certificates of Inspection DID
Attachment 11 A006 Field Reports 3 Attachment 12 A006 Field Reports DID 8 Attachment 13 A007 Misc Close Out 3 Attachment 14 A007 Misc Close Out
DID
Attachment 15 DD Form 3150 1 Attachment 16 NAVSEA Form 6220 2 1 Attachment 17 Standard COVID 19
Screening Instructions for Contracts.JAN22
Attachment 18 Amendment Attachment 1 of 9
Attachment 19 Amendment Attachment 2 of 9
Attachment 20 Amendment Attachment 3 of 9
Attachment 21 Amendment Attachment 4 of 9
Attachment 22 Amendment Attachment 5 of 9
Attachment 23 Amendment Attachment 6 of 9
Attachment 24 Amendment Attachment 7 of 9
Attachment 25 Amendment Attachment 8 of 9
Attachment 26 Amendment Attachment 9 of 9
The following have been added by full text:
QUESTION & ANSWERS
QUESTION 1:
Can you let us know if drawings and calculations (original certification documentation) exist for these systems?
ANSWER:
I’m not aware of any drawings or calculations previously submitted as part of the old contract.
QUESTION 2:
(Recertification) If these exist, can they be made available to bidders?
ANSWER:
The attached spreadsheet was the last list associated to the recertification’s and also attached is a handful of recent Inspection cert’s.
QUESTION 3:
Also, can you tell us when these systems were last recertified?
ANSWER:
The attached documents are all that the safety group has for recertification.
QUESTION 4:
We’d like to know which CLINs should be based around recertification, and which should be based inspection.
ANSWER:
The CLINs are not broken into separate actions, but each CLIN is for Inspection & Recertification for the designated location.
(End of Summary of Changes)