This amendment to solicitation N0016719R0019 updates the SOW, provides answers to questions, and extends the date for submission of questions to 05/29/19 at 10:00 AM EST and the submission of proposals to 06/12/19 at 10:00 AM EST.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N0016719R0019

1300779454

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment to solicitation is to provide an updated SOW, provide answ ers to questions presented, and to extend the date for submission of questions and proposals.

All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 24-May-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N0016719R0019

X 9B. DATED (SEE ITEM 11)

03-May-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

24-May-2019

CODE

NAVAL SURFACE WARFARE CENTER CARDEROCK

CODE 0225, PATRICIA VARA

301-227-5497, PATRICIA.VARA@NAVY.MIL

9500 MACARTHUR BLVD

WEST BETHESDA MD 20817

N00167 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

SOLICITATION/CONTRACT FORM

The required response date/time has changed from 28-May-2019 10:00 AM to 12-Jun-2019 10:00 AM.

The following have been added by full text:

QUESTIONS & ANSWERS

1. Please provide drawings or specific dimensions for hydraulic cylinder to be repaired (drawings provided)

2. Please provide drawings or specific dimensions of hydraulic pump to be reused (no drawings available)

3. What is flow rate requirement of the system? (flow rate of current pump is unknown; will estimate nominal speeds for gantry frame travel and actuator for lifting & lowering tank head)

4. What is the operating pressure of the system? (3000 psi)

5. Are there schematics/drawings of the existing system available? (Yes, drawings provided)

6. If not, please identify the size and type of the hydraulic connections so we can verify specs.

7. Is there a schematic available for the desired new system configuration? (none)

8. Are there any environmental requirements for the hydraulic and electrical components? (i.e.: corrosion resistance, NEMA rating, etc.) (none)

9. What is the power available to the new control system? (460 V, 60 A, 3 phase)

10. Are there any Mil. Specs or standards we need to take into consideration? (none)

All questions are due by 10:00 AM EST on 29 May 2019!

The following have been modified:

STATEMENT OF WORK

Statement of Work Cyclops Gantry Crane Hydraulic

System

1 SCOPE

1.1 This Statement of Work establishes the requirements for replacement of the Cyclops Gantry Crane hydraulic system in the 10ft Diameter Pressure Vessel Facility.

2 BACKGROUND

2.1 The 10ft diameter spherical pressure vessel is critical to facility operations in Bldg. 19, as it provides the

Navy and other maritime industries the capability to test submarines and other submersible structures under deep sea conditions. The vessel is operated by a 100-ton Cyclops Gantry Crane hydraulic system used to lift the top half of the pressure vessel and drive it to another location via a rail network. This facilitates the unobstructed use of the lower portion of the spherical pressure vessel for installing test articles. The hydraulic system has been in place since the 1960’s and many of the components are obsolete. A loud “banging” noise can be heard when operating the lifting cylinder, which may have been damaged from a prior lifting operation. To ensure continuous use of the equipment, a number of repairs and upgrades are required

3 REQUIREMENTS

3.1 The contractor shall remove and dispose of existing components of the hydraulic pressure unit. The following replacement components shall be provided and installed:

i. 15HP electric motor 1.

RPM

2. 460 Volts

3. 60 Amps

4. 3 Phase A/C

ii. 50 Gallon reservoir to allow easy maintenance and service of pump and motor

iii. 10µ in-line pressure filter and 10µ tank mount return filtration

iv. 1 kW in-tank heater with temperature switch, dual level float switches, and switch monitored suction valve.

v. Drive motor rebuild/replacement, with addition of gear type flow divider to ensure equal flow to each gantry drive motors

3.2 The contractor shall refurbish existing wheel motor gearbox

3.3 The contractor shall remove and dispose of the current hydraulic safety manifold. Replacement components for the safety for hydraulic oil shall be provided and installed, with individual switches to perform the following functions:

1. Low Level 1 Warning

2. Low Level 2 Shut Down

3. Temperature 1

4. Temperature 2

5. Pressure Filter Dirty

6. Brake Pressure Released

3.4 The contractor shall remove and dispose of the current system used for gantry crane head travel. Replacement solenoid and valves shall be provided and installed, to perform the following functions for gantry crane/tank head travel.

1. Gantry Travel Direction A

2. Gantry Travel Direction B

3. Brake release

4. Ram Down A

5. Ram Up B

6. Ram Down Creep Speed

3.5 The contractor shall remove and dispose of all current remote panels. Replacement components shall be provided and installed for new remote panels which include:

i. Top level control panel with individual push buttons for the following functions:

1. Hydraulics On

2. Hydraulics Off

3. Ram Down

4. Ram Up

5. Ram Down Creep Speed

6. Gantry Travel + Direction

7. Gantry Travel – Direction

ii. Top level diagnostic panel with individual indicators lamps showing gantry status:

1. Hydraulics On

2. Oil Temp High

3. Oil Level Warning

4. Oil Level Shut Down

5. Pressure Filter Dirty

6. Ram Brake Release

7. Ram Down Energized

8. Ram Up Energized

9. Ram Down Creep Speed Energized

10. Gantry Travel + Direction Energized

11. Gantry Travel – Direction Energized

12. Available Spare

13. Available Spare

14. Available Spare

iii. A crane pendant with individual inputs to perform the following functions:

1. Hydraulics On

2. Hydraulics Off

3. Ram Down

4. Ram Up

5. Ram Down Creep Speed

6. Gantry Travel + Direction

7. Gantry Travel – Direction

8. Cylinder Ok For Gantry Movement

9. Return Filter Dirty

10. Additional switches for the following functions:

(a) Return Filter Dirty

(b) Suction Valve Open

iv. An additional remote diagnostic panel shall be mounted down at operator/floor level with individual indicators lamps showing gantry status:

1. Hydraulics On

2. Oil Temp High

3. Oil Level Warning

4. Oil Level Shut Off

5. Pressure Filter Dirty

6. Ram Brake Release

7. Ram Down Energized

8. Ram Up Energized

9. Ram Down Creep

10. Gantry Travel + Direction

11. Gantry Travel – Direction

3.6 The contractor shall perform a cylinder rebuild on the system. This includes the barrel, rod, and brake.

The cylinder shall be tested and painted after installation. Specifications of the cylinder are below:

i. American Machining and Foundry Bear-Loc Hydraulic Cylinder

1. 100-ton capacity at 3000 psi

2. Full stroke = 7 ft.

3.7 The contractor shall dispose of old hydraulic lines and provide replacement soft hydraulic lines, matching the following specifications.

i. -8 and -12 hose sizes

ii. Rating - 5000 psi

iii. Tough Cover

4 GOVERNMENT FURNISHED EQUIPMENT

4.1 Cyclops Gantry Crane hydraulic system of the 10ft. diameter spherical pressure vessel

5 DELIVERY DATE

5.1 The Period of Performance for repair and upgrade work must be completed prior to 27 September 2019.

(End of Summary of Changes)