AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is the follow ing:
1. Provide answ ers to questions asked.
2. Although FAR 52.212-1(c) and FAR 52.212-1(c) DEVIATION 2018-O0018 state 30 days, this amendment is to change that from 30 to 90 days.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 20-Jul-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N0016420RWP46
X 9B. DATED (SEE ITEM 11)
05-May-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
20-Jul-2020
CODE
NAVAL SURFACE WARFARE CENTER CRANE DIV
S. ECKERLE (812-854-6538)
BLDG 121
300 HWY 361
CRANE IN 47522-5001
N00164 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N0016420RWP46
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SECTION 4.0 - CLAUSES & OTHER FULL TEXT INFORMATION
SUMMARY OF CHANGES
SECTION 4.0 - CLAUSES & OTHER FULL TEXT INFORMATION
The following have been modified:
QUESTIONS AND ANSWERS
QUESTION #1: Will the NAVY ship the product to the vendor to another state, for example at its own cost and pay for the vendor to ship it back or does Crane want the vendor to pick up the part at Crane and deliver, where all transportation cost is vendor’s expense?
ANSWER #1: The Government will ship items to the contractor for repair, and the contractor will be responsible for shipping the items back to Crane after repair.
QUESTION #2: Is the maximum contract amount of approximately $3.5 million for the entire contract or per year?
ANSWER #2: The maximum contract amount is for the entire contract.
QUESTION #3: Are there any drawings or motor information for SPS 55A or SPQ-9B? Do you have any motor data on either of these?
ANSWER #3: Drawing #411763 (Attachment 9) applies to SPS-55A. There is no manual for SPS-55A. There is no drawing for SPQ-9B. The manual for SPS-Q9B (Attachment 16) has been attached.
QUESTION #4: Will NSWC be supplying a repair kit for each motor to include bearings seals, sleeves, o-rings, etc.?
ANSWER #4: NSWC Crane will not be supplying repair kits for the motors.
QUESTION #5: When does the solicitation close?
ANSWER #5: N0016420RWP46 closes at 4:00 p.m. on 07/27/2020.
QUESTION #6: When a machine is disassembled and evaluated and something is not to specification, emergent work surfaces. Therefore, in the CLIN system of fixed pricing, how does one lineate or cost between services needed. As an example, a shaft has two bearing surfaces and two output areas. Verbiage overhaul/replacement can mean fix only one small section or a more detailed process of pressing out, manufacturing, installing. A second example is bell housings. Are we repairing one or two?
ANSWER #6: There are supplemental repair CLINs for anything not included in the other repair CLINs. The supplemental CLINs will be negotiated at time of order.
QUESTION #7: What is a Supplemental Repair.
ANSWER #7: Supplemental repairs require processes, materials, and/or parts not already addressed in existing overhaul Contract Line Item Numbers (CLINs). (CDRL A001). Supplemental repairs shall include additional labor and material data in order for the Government to make a BER determination.
QUESTION #8: Are the motors for closed couple pump/motor assemblies? If so do we need to include the replacement consumable parts, (seals, gasket, packing and hardware), for the pump or will this be as a change order?
ANSWER #8: These are not closed couple motors.