This is a Contract Data Requirements List (CDRL) document on DD Form 1423-1 specifying four data items required under contract 4T-1355-01-580-4509-CWQC for NUWC Newport ISEA.
The four required data items are: (1) Data Item A001 – Test Procedure, a one-time submission specifying process control instructions and inspection procedures per ANSI/ASQC Q9000-2000 or equivalent, including first article and production lot quality conformance inspection procedures per DI-NDTI-80603A; (2) Data Item A002 – Test/Inspection Report (Pre-Production & Production Test), required per lot with submission within 15 days after first article test completion and within 15 days after lot acceptance testing for subsequent lots, verifying conformance to drawings, specifications, and contract requirements per DI-NDTI-80809B; (3) Data Item A003 – Failure Analysis/Corrective Action Report per DI-SESS-80255B, Section E, with frequency determined by FAT/LAT failures, requiring an interim report within 10 days of failure notification and final report within 30 days; and (4) Data Item A004 – Contractor's Progress, Status and Management Report, a monthly submission due on or before the 5th day of each month per DI-MGMT-81928. All data items require one final copy distributed to NAVSUP Weapon Systems Support, NAVSUP Ammunition Logistics Center, and Naval Surface Warfare Center, with distribution statement D marking required. The CDRL was prepared by Richard Rzomp and approved by Philip Lindley on 2/27/26, with LCDR Hardman as approver for Item A004.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N0010426rk073 CWQC Price Matrix.xlsx | XLSX spreadsheet | |
| N0010426RK073 CWQC.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT DATA REQUIREMENTS
LIST
(1 Data Item)
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 220 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0704-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A.CONTRACT LINE ITEM NO.
B.EXHIBIT
C.CATEGORY:
TDP TM OTHER
D. SYSTEM/ITEM
4T-1355-01-580-4509-CWQC
E.CONTRACT/PR NO.
F.CONTRACTOR
1.DATA ITEM NO.
A001
2.TITLE OF DATA ITEM
Test Procedure
3.SUBTITLE
17.PRICE GROUP
4.AUTHORITY (Data Acquisition Document No.) 5.CONTRACT REFERENCE
6.REQUIRING OFFICE 18.ESTIMATED
TOTAL PRICE
DI-NDTI-80603A ALL DRAWINGS NUWC Newport ISEA
7.DD250 REQ
LT
9.DIST STATEMENT
REQUIRED
10.FREQUENCY
ONE TIME
12.DATE OF FIRST
SUBMISSION
14.DISTRIBUTION
D
60 DAC
a. ADDRESSEE
b. COPIES
8.ADP CODE
A
11.AS OF DATE
13.DATE OF SUBSEQUENT
Draft
Final
Reg Repro
16.REMARKS SEE BLOCK 16 0 1 0
THE PLAN IS TO SPECIFY PROCESS CONTROL INSTRUCTIONS AND INSPECTION
PROCEDURES NEEDED TO ENSURE PRODUCT CONFORMANCE TO DRAWINGS,
SPECIFICATIONS, AND CONTRACT REQUIREMENTS IAW ANSI/ASQC Q9000-2000 OR
EQUIVALENT. THE PLAN IS TO INCLUDE FIRST ARTICLE AND PRODUCTION LOT
QUALITY CONFORMANCE INSPECTION PROCEDURES IAW DI-NDTI-80603A ALONG
WITH ALL APPLICABLE DATA ENTRY SHEETS TO BE USED TO DOCUMENT PROCESS
INSPECTIONS.
BLK 14: DISTRIBUTION ADDRESS
1. NAVSUP Weapon Systems Support
2. NAVSUP Ammunition Logistics Center
3. Naval Surface Warfare Center
POC Information: See Section H
15.TOTAL 0 1 0
G. PREPARED BY:
Richard Rzomp
H. DATE
2/27/26
I. APPROVED BY:
Philip Lindley
J. DATE
2/27/26
DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 1 of 4 Pages
(1 Data Item)
The public reporting burden for this collection of information is estimated to average 220 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0704-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
0001AA B.EXHIBIT
D. SYSTEM/ITEM
A002
2.TITLE OF DATA ITEM
Test/Inspection Report
3.SUBTITLE
Pre-Production & Production Test
DI-NDTI-80809B ALL DRAWINGS NUWC Newport ISEA
SS
REQUIRED
10.FREQUENCY
PER LOT
SEE BLOCK 16
a. ADDRESSEE
b. COPIES
8.ADP CODE
Dra ft
16.REMARKS SEE BLOCK 16 0 1 0
THE REPORT IS TO VERIFY BOTH FIRST ARTICLE AND PRODUCTION LOT
CONFORMANCE TO THE APPLICABLE DRAWINGS, SPECIFICATIONS, AND CONTRACT
REQUIREMENTS. THE REPORT CONSISTS OF THE PLAN (A001) CONTAINING ALL
REQUIRED INSPECTION RESULTS DOCUMENTED ON THE PLAN’S DATA ENTRY SHEETS.
IN ADDITION, THE REPORT IS TO INCLUDE MATERIAL CERTIFICATIONS AND ALL
OTHER PERTINENT OBJECTIVE QUALITY EVIDENCE. THE REPORT MUST BE APPROVED
BY NSWC NEWPORT BEFORE FINAL ACCEPTANCE OF THE LOT.
BLK 12: DATE OF PRE-PRODUCTION TEST REPORT SUBMISSION – NLT 15 DAYS
AFTER FIRST ARTICLE TEST COMPLETION.
BLK 13: DATE OF SUBSEQUENT SUBMISSION – NLT 15 DAYS AFTER LOT
ACCEPTANCE TESTING OF SECOND LOT AND BEYOND.
Richard Rzomp
H. DATE
2/27/26
I. APPROVED BY:
Philip Lindley
DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 2 of 4 Pages
(1 Data Item)
The public reporting burden for this collection of information is estimated to average 220 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0704-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
D. SYSTEM/ITEM
A003
2.TITLE OF DATA ITEM
Failure Analysis/Corrective Action Report
DI-SESS-80255B Section E NUWC Newport ISEA
REQUIRED
10.FREQUENCY
SEE BLOCK 16
12.DATE OF FIRST
a. ADDRESSEE
SEE BLOCK 16 Reg Repro
16.REMARKS SEE BLOCK 16 0 1 0
BLK 5: INCLUDE AND TAKE ACTION ON SECTION I IF FAT IS REQUIRED.
BLK 10: FREQUENCY - IS DETERMINED BY NUMBER OF FAT/LAT FAILURES.
BLK 12: DATE OF FIRST SUBMISSION – NLT AN INTERIM REPORT IS DUE NLT
10 DAYS AFTER NOTIFICATION OF LOT FAILURE. A FINAL REPORT IS DUE 30
DAYS AFTER NOTIFICATION OF LOT FAILURE.
BLK 13: DATE OF SUBSEQUENT SUBMISSION – NLT 10 DAYS AFTER FAT
COMPLETION OF SECOND FAILED LOT AND BEYOND.
Richard Rzomp
H. DATE
2/27/26
I. APPROVED BY:
Philip Lindley
DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 3 of 4 Pages
(1 Data Item)
The public reporting burden for this collection of information is estimated to average 220 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0704-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
D. SYSTEM/ITEM
A004
2.TITLE OF DATA ITEM
Contractor’s Progress, Status and Management Report
DI-MGMT-81928 SEE BLOCK 16 NUWC NEWPORT
REQUIRED
10.FREQUENCY
MTHLY
SEE BLOCK 16
SEE BLOCK 16
a. ADDRESSEE
16.REMARKS SEE BLOCK 16 0 1 0
BLK 12, 13: The report shall be submitted via mail or email on or before the 5th day of each month after contract award.
Richard Rzomp 2/27/26
I. APPROVED BY:
LCDR Hardman
DD Form 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED Page 4 of 4 Pages
INSTRUCTION FOR COMPLETING DD FORM 1423
(See DoD 5010.12-M for detailed instructions.)
FOR GOVERNMENT PERSONNEL
Item A. Self-explanatory
Item B. Self-explanatory
Item C. Mark (X) appropriate category: TDP - Technical Data Package; TM - Technical Manual - Other - other category of data, such as Provisioning, Configuration Management���� ���� etc.
Item D. Enter name of system/item being acquired that data will support.
Item E. Self-explanatory (to be filled in after contract award)
Item F. Self-explanatory (to be filled in after contract award)
Item G. Signature of preparer of CDRL
Item H. Date CDRL was prepared
Item I. Signature of CDRL approval authority
Item J. Date CDRL was approved
Item 1. See DoD FAR Supplement Subpart 4 71 for proper numbering.
Item 2. Enter title as it appears on data acquisition document cited in Item 4.
Item 3. Enter subtitle of data item for further definition of data item (optional entry)
Item 4. Enter Data Item Description (DID) number, military specification number, or military standard number listed in DoD 5010.12-1 (AMSDL), or one-time DID number, that defines data content and format requirements
Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g, Statement of Work paragraph number)
Item 6. Enter technical office responsible for ensuring adequacy of the data item
Item 7. Specify requirement for inspection/acceptance of the data item by the Government
Item 8. Specify requirement for approval of a draft before preparation of the final data item
Item 9. For technical data, specify requirement for contractor to mark the appropriate distribution statement on the data (ref DoDD 5230.24)
Item 10. Specify number of times data items are to be delivered
Item 11. Specify as-of date of data item, when applicable
Item 12. Specify when first submittal is required
Item 13. Specify when subsequent submittals are required, when applicable
Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee.
Explain reproducible copies it Item 16
Item 15. Enter total number of draft/final copies to be delivered
Item 16. Use of additional clarifying information for items 1 through 15. Examples are:
Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13;
Explanation of reproducible copies in Item 14; Desired medium for delivery of the data item.
FOR THE CONTRACTOR
Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423
a. Group I. Definition - Data which is not otherwise essential to the contractors performance of the primary contracted effort (production development, testing, and administration) but which is required by DD Form 1423
Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.
b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.
Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirement, and the administrative and other expenses related to reproducing and delivering such data item to the Government.
c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.
Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.
d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal
Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.
Item 18. For each data item, enter an amount equal to that portion of the total price which s estimated to be attributable to the production or development for the Government of that item of data. These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if not data were required.
The estimated data prices shall not include any amount for rights in data. The Government’s right to use the data shall be governed by the pertinent provisions of the contract
File details come from the government source that posted it. Updated .