This document is a Contract Data Requirements List (DD Form 1423-1) for a federal contract involving a system with the item number 4T-1355-00-433-3214-TA68. The document outlines five distinct data items that the contractor must submit: (1) Test Procedure, (2) Test/Inspection Report, (3) Failure Analysis/Corrective Action Report, (4) Contractor's Progress, Status and Management Report, and (5) Certificate of Compliance. The contract requires detailed reporting on production lot quality, testing procedures, potential failures, monthly progress updates, and compliance certifications.
The primary federal agencies involved are NAVSUP WSS Contracting Officer, NAVSUP ALC, and NUWC-Keyport. Key submission requirements include a preliminary test procedure within 60 days after contract award, monthly progress reports by the 5th day of each month, and certificates of compliance with each delivery. The documents emphasize quality control, adherence to specifications, and rigorous documentation of production processes, with distribution limited to DoD and U.S. DoD contractors due to critical technology and export control considerations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0704-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address.
Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT
C. CATEGORY:
TDP ☐ TM ☐ OTHER ☐
D. SYSTEM/ITEM
4T-1355-00-433-3214-TA68
E. CONTRACT/PR NO.
F. CONTRACTOR
1. DATA ITEM NO.
A001
2. TITLE OF DATA ITEM
Test Procedure
3. SUBTITLE
17. PRICE GROUP
4. AUTHORITY (Data Acquisition Document No.)
DI-NDTI 80603A
5. CONTRACT REFERENCE
ALL DRAWINGS
6. REQUIREING OFFICE
KEYPORT
18. ESTIMATED TOTAL
PRICE
7. DD 250 REQ
SD
9. DIST STATEMENT
REQUIRED
D
10. FREQUENCY
ONE TIME
12. DATE OF FIRST SUBMISSION
60 DADC
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. ADP CODE
A
11. AS OF DATE
13. DATE OF SUBSEQUENT SUBMISSION
Draft
Final
Reg Repro
16. REMARKS
THE PLAN IS TO SPECIFY PROCESS CONTROL INSTRUCTIONS AND INSPECTION
PROCEDURES NEEDED TO ENSURE PRODUCT CONFORMANCE TO DRAWINGS,
SPECIFICATIONS, AND CONTRACT REQUIREMENTS IAW ASQ-Q9001-2008
OR EQUIVALENT. THE PLAN IS TO INCLUDE FIRST ARTICLE AND PRODUCTION
LOT QUALITY CONFORMANCE INSPECTION PROCEDURES IAW DID-80603 ALONG
WITH ALL APPLICABLE DATA ENTRY SHEETS TO BE USED TO DOCUMENT PROCESS
INSPECTIONS.
BLK 10 & 12: VENDOR SHALL PROVIDE PRELIMINARY TEST PROCEDURE WITHIN
60 DAYS AFTER CONTRACT AWARD. GOVERNMENT WILL PROVIDE RESPONSE
WITHIN 10 DAYS. VENDOR SHALL PROVIDE FINAL TEST PROCEDURE WITHIN 10
DAYS UPON GOVERNMENT APPROVAL OF DRAFT.
BLK 14: Distribution List
1. NAVSUP WSS Contracting Officer N772
2. NAVSUP ALC, Code A151
3. NUWC-Keyport Code N323 See section H for distribution POC’s and their emails.
Contract Officer 1 1 0
Program Analyst 1 1 0
Engineer 1 1 0
15. TOTAL 3 3 0
G. PREPARED BY
Robert Kovach
H. DATE
28 August 2025
I. APPROVED BY
John Knecht
J. DATE
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 1 of 5 Pages
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0704-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address.
Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
D. SYSTEM/ITEM
A002
Test/Inspection Report
3. SUBTITLE
Pre-Production & Production Test
DI-NDTI 80809B
ALL DRAWINGS
SD
PER LOT
SEE BLOCK 16
Reg Repro
16.REMARKS
THE REPORT IS TO VERIFY PRODUCTION LOT CONFORMANCE TO THE APPLICABLE
DRAWINGS, SPECIFICATIONS, AND CONTRACT REQUIREMENTS. THE REPORT
CONSISTS OF THE PLAN (A001) CONTAINING ALL REQUIRED INSPECTION
RESULTS DOCUMENTED ON THE PLAN’S DATA ENTRY SHEETS. IN ADDITION, THE
REPORT IS TO INCLUDE MATERIAL CERTIFICATIONS AND ALL OTHER PERTINENT
OBJECTIVE QUALITY EVIDENCE. THE REPORT MUST BE APPROVED BY NAVSUP
WSS CONTRACTING OFFICER BEFORE FINAL ACCEPTANCE OF THE LOT.
BLK 12: DATE OF PRE-PRODUCTION TEST REPORT SUBMISSION – NLT 15 DAYS
AFTER FIRST ARTICLE TEST COMPLETION.
BLK 13: DATE OF SUBSEQUENT SUBMISSION – NLT 15 DAYS AFTER LOT
ACCEPTANCE TESTING OF SECOND LOT AND BEYOND.
BLK 14: Distribution List
1. NAVSUP WSS Contracting Officer N772
2. NAVSUP ALC, Code A151
Contract Officer 1 1 0
Program Analyst 1 1 0
Engineer 1 1 0
15. TOTAL 3 3 0
Robert Kovach
H. DATE
28 August 2025
I. APPROVED BY
John Knecht
J. DATE
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 2 of 5 Pages
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0704-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address.
Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
D. SYSTEM/ITEM
A003
Failure Analysis/Corrective Action Report
DI-SESS-80255B
Section E
LT
Reg Repro
16. Remarks
BLK 5: INCLUDE AND TAKE ACTION ON SECTION I IF FAT IS REQUIRED.
BLK 10: FREQUENCY - IS DETERMINED BY NUMBER OF FAT/LAT FAILURES.
BLK 12: DATE OF FIRST SUBMISSION – NLT AN INTERIM REPORT IS DUE NLT
10 DAYS AFTER NOTIFICATION OF LOT FAILURE. A FINAL REPORT IS DUE 30
DAYS AFTER NOTIFICATION OF LOT FAILURE.
BLK 13: DATE OF SUBSEQUENT SUBMISSION – NLT 10 DAYS AFTER FAT
COMPLETION OF SECOND FAILED LOT AND BEYOND.
BLK 14: Distribution List
1. NAVSUP WSS Contracting Officer N772
2. NAVSUP ALC, Code A151
Contract Officer 0 1 0
Program Analyst 0 1 0
Engineer 0 1 0
15. TOTAL 0 3 0
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 3 of 5 Pages
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0704-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address.
Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
D. SYSTEM/ITEM
A004
Contractor’s Progress, Status and Management Report
DI-MGMT-81928
MNTHLY
Reg Repro
16. REMARKS
BLK 11, 12,14: THE DD-375 REPORT SHALL BE SUBMITTED VIA MAIL OR EMAIL ON OR BEFORE THE 5TH DAY OF EAC
MONTH AFTER CONTRACT AWARD.
BLK 14: Distribution List
1. NAVSUP WSS Contracting Officer N772
2. NAVSUP ALC, Code A151
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 4 of 5 Pages
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Department of Defense, Washington Headquarters Services, Directorate for Information Operations and Reports (0704-0188), 1215 Jefferson Davis Highway, Suite 1204, Arlington, VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please DO NOT RETURN your form to the above address. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
D. SYSTEM/ITEM
A005
Certificate of Compliance
3. SUBTITLE
Certificate of Compliance
DI-MISC-81356
13. DATE OF SUBSEQUENT
SUBMISSION
Reg Repro
16.REMARKS
BLK 5: ENSURE COMPLIANCE IAW DWG 1300711 REV M. CERTIFICATES
OF COMPLIANCE (COC) ARE TO BE PROVIDED TO SHOW CONFORMANCE TO ALL
ASSOCIATED DRAWINGS, NOTICES OF REVISION, SPECIFICATIONS, AND
CONTRACT REQUIREMENTS AS PROVIDED IN TECHNICAL DATA PACKAGE.
BLK 9: DISTRIBUTION STATEMENT "D" - DISTRIBUTION AUTHORIZED TO
DOD AND U.S. DOD CONTRACTORS ONLY; CRITICAL TECHNOLOGY, EXPORT
CONTROLLED (8/25/2016). OTHER REQUESTS SHALL BE REFERRED TO
PEO-SUBS (PMS404).
"WARNING" THIS DOCUMENT CONTAINS TECHNICAL DATA WHOSE EXPORT
IS RESTRICTED BY THE ARMS EXPORT CONTROL ACT (TITLE 22, U.S.C. SEC.
2751 ET. SEQ.) OR THE EXPORT ADMINISTRATION ACT OF 1979, AS AMENDED,
TITLE 50, U.S.C. APP. 2401 ET. SEQ. VIOLATORS OF THESE EXPORT LAWS
ARE SUBJECT TO SEVERE CRIMINAL PENALTIES. DISSEMINATE PER THE
PROVISIONS OF DOD DIRECTIVE 5230.25.
DESTRUCTION NOTICE - FOR UNCLASSIFIED, LIMITED DOCUMENTS,
DESTROY BY ANY METHOD THAT WILL PREVENT DISCLOSURE OF
CONTENTS OR RECONSTRUCTION OF THE DOCUMENT.
BLKS 10-13: COC SHALL BE SUBMITTED WITH EACH DELIVERY, INCLUDING
FIRST ARTICLE DELIVERY.
BLK 14: Distribution List
1. NAVSUP WSS Contracting Officer N772
2. NAVSUP ALC, Code A151
Robert Kovach
H. DATE
28 August 2025
I. APPROVED BY
John Knecht
J. DATE
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page 5 of 5 Pages
File details come from the government source that posted it. Updated .